|
---|
Category:SAFETY EVALUATION REPORT--LICENSING & RELATED ISSUES
MONTHYEARML20212K9781999-09-30030 September 1999 Safety Evaluation Accepting USI A-46 Implementation Program ML20209H8281999-07-15015 July 1999 Safety Evaluation Accepting GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Cooper Nuclear Station ML20206P0481999-05-12012 May 1999 Safety Evaluation Concluding That NPP Established Acceptable Program to Verify Periodically design-basis Capability of safety-related MOVs at CNS & Adequately Addressed Actions Requested in GL 96-05 ML20204B3701999-03-11011 March 1999 SER Accepting Third 10-year Interval Inservice Insp Plan Requests for Relief for RI-17,Rev 1 and RI-25,Rev 0.Request for Relief RI-13,Rev 2 Involving Snubber Testing & Is Being Evaluated in Separate Report ML20196J9641998-12-0707 December 1998 Safety Evaluation Accepting Licensee Third 10-yr Interval Inservice Insp Plan Request for Relief RI-27,rev 1 ML20196A2861998-11-23023 November 1998 SER Re Core Spray Piping Weld for Cooper Nuclear Station. Staff Concluded That Operation During Cycle 19 Acceptable with Indication re-examined During RFO 18 ML20196A5241998-11-23023 November 1998 Safety Evaluation Accepting Proposed Alternative to Use UT Techniques Qualified to Objectives of App Viil as Implemented by PDI Program in Performing RPV Shell Weld & Shell to Flange Weld Examinations ML20196A5061998-11-23023 November 1998 Safety Evaluation Re Flaw Indication Found in Main Steam Nozzle to Shell Weld NVE-BD-N3A at Cns.Plant Can Be Safely Operated for at Least One Fuel Cycle with Indication in as-is Condition ML20195H1761998-11-17017 November 1998 SER Authorizing Proposed Alternative in Relief Requests RV-06,RV-07,RV-09,RV-11,RV-12 & RV-15 Pursuant to 10CFR50.55a(a)(3)(ii).RV-08 Granted Pursuant to 10CFR50.55a(f)(6)(i) & RV-13 Acceptable Under OM-10 ML20151Z6141998-09-16016 September 1998 SER Accepting Util Responses to NRC Bulletin 95-002 for Cooper Nuclear Station ML20236R9131998-07-20020 July 1998 SER Accepting Rev 13 to Quality Assurance Program for Operation Policy Document for Plant ML20203K0351998-02-26026 February 1998 SER Approving Third ten-year Interval Inservice Inspection Program Plan,Request for Relief PR-10 for Cooper Nuclear Station.Technical Ltr Rept on Request Relief PR-10 Also Encl ML20212E0811997-10-23023 October 1997 SER Accepting Third 10-yr Interval Insp Program Plan & Associated Requests for Relief for Plant ML20217E6141997-09-23023 September 1997 Safety Evaluation Accepting Util Proposed Changes to Licensing Basis for Plant to Reflect Incorporation of Safer/Gestr Methodology for LOCA Analysis ML20199F7411997-08-14014 August 1997 Safety Evaluation Rept Accepting Design of torus-to-reactor Bldg Vacuum Breakers at Plant ML20210J5731997-08-13013 August 1997 Safety Evaluation Denying Relief Request for Plant Third 10-yr Interval Program for Inservice Testing of Pumps. Request Not in Sufficient Detail to Justify Proposed Alternative ML20148H2381997-06-0606 June 1997 Safety Evaluation Granting Licensee Relief Requests for 10-yr Interval Inservice Insp Program Plan for Plant,Unit 1 ML20138K0241997-05-0707 May 1997 Safety Evaluation Supporting Proposed Rev to RPV Surveillance Capsule Withdrawal Schedule ML20134N6911997-02-19019 February 1997 Safety Evaluation Related to Third ten-year Interval Inservice Testing Program Nebraska Public Power District Cooper Nuclear Station ML20198E1091992-11-25025 November 1992 Safety Evaluation Accepting Licensee 920921 120-day Response to GL 87-02, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors,Usi A-46 ML20127N3741992-11-19019 November 1992 Supplemental SE Accepting Analysis & Results in Response to SBO rule,10CFR50.63 ML20128C2911992-11-19019 November 1992 Safety Evaluation Accepting Revised ACAD Sys Into Nitrogen Containment Atmosphere Dilution,Eliminating Potential post-accident Oxygen Source ML20059E2781990-08-31031 August 1990 Safety Evaluation Granting Licensee 900525 Relief Requests RP-14 & RP-15 from Requirements to Measure Pump Inlet Pressure & Instrument Ranges,Respectively ML20246B2501989-05-31031 May 1989 Safety Evaluation on Generic Ltr 83-28,Item 4.5.3 Re Reactor Trip Sys Reliability for All Domestic Operating Reactors. Intervals for on-line Functional Testing Consistent W/ Achieving High Reactor Trip Sys Availability at Reactors ML20247A4241989-03-20020 March 1989 Safety Evaluation Accepting Revised Process Control Program Re General Methods of Sampling,Processing,Analysis & Waste Formulation During Solidification of Radwaste ML20205S2031988-11-0303 November 1988 Safety Evaluation Supporting Interim Operability of Piping Sys ML20147B5161988-02-23023 February 1988 Safety Evaluation Supporting Amend 117 to License DPR-46 ML20148C9591988-01-13013 January 1988 Safety Evaluation Concluding That Inservice Testing Program Submitted w/860730 Ltr as Modified in Subj Safety Evaluation Will Provide Reasonable Assurance of Operational Readiness of safety-related Pumps & Valves ML20238C4001987-12-23023 December 1987 Safety Evaluation Supporting Proposed Mod to 10CFR50.62, ATWS Rule ML20237E3261987-12-21021 December 1987 Safety Evalution Supporting Amend 113 to License DPR-46 ML20236B8901987-10-20020 October 1987 Sser Re Alternate Rod Insertion (ARI) Sys.Util Plans for Relocating ARI Position Indication Out of Control Room to Another Location in Control Bldg Acceptable ML20235H0351987-09-23023 September 1987 Safety Evaluation Re Alternate Rod Injection & Recirculating Pump Trip Sys ML20235N4581987-07-10010 July 1987 Safety Evaluation Supporting Util 810707,820623,0730 & 831215 Submittals Re Valve Operability Info for 24-inch Isolation Valves in Purge & Vent Sys.Nrc Conclusion Subj to Valves Being Modified to Have Torque Readjustments ML20214S8741987-05-21021 May 1987 Supplemental Safety Evaluation Re Dcrdr.Listed Activities Must Be Finished in Order to Satisfy Dcrdr Requirements in Suppl 1 to NUREG-0737 ML20212Q9721987-04-16016 April 1987 Safety Evaluation Accepting Util 831104 & 870121 Responses to Generic Ltr 83-28,Items 3.2.1 & 3.2.2, Post-Maint Verification Testing ML20212L1751987-03-0606 March 1987 Safety Evaluation Supporting Util Methodology in Standby Gas Treatment Suction Analysis & Interim Operation for Fuel Cycle 11 Only ML20209A7001987-01-30030 January 1987 Safety Evaluation Accepting Util Response to Vendor Recommended Reliability Verification Testing Per Generic Ltr 83-28,Item 4.5.1 Re Reactor Trip Sys Reliability (Sys Functional Testing) ML20215M5021986-10-27027 October 1986 Safety Evaluation Accepting Util Response to Generic Ltr 82-33 Re Conformance to Rev 2 to Reg Guide 1.97,except for Instrumentation Associated W/Neutron Flux Variable ML20210K2491986-09-25025 September 1986 Safety Evaluation Supporting Analytical Method Used by Licensee to Evaluate Critical Stresses ML20141E9291986-04-10010 April 1986 Safety Evaluation Supporting Amend 98 to License DPR-46 ML20151Y2541986-01-27027 January 1986 Safety Evaluation Re Requests for Relief from Inservice Insp Requirements.Relief Not Granted for Surface & Volumetric Exam of Drywell Piping Spray Welds Since Requirements Not Impractical ML20140C5761986-01-17017 January 1986 Safety Evaluation Supporting 831104 Response to Generic Ltr 83-28,Items 3.1.1 & 3.1.2 Concerning post-maint Testing Verification of Reactor Trip Sys Components ML20134J6301985-08-21021 August 1985 Safety Evaluation Accepting Proposed Mods as Ensuring Safe Shutdown Capability in Event of Fire in Areas of Concern in Accordance W/Requirements of 10CFR50,App R ML20127E7281985-06-10010 June 1985 Safety Evaluation Supporting Response to Generic Ltr 83-28, Item 1.2 Re post-trip Review Data & Info Capability ML20127E1051985-05-0606 May 1985 Safety Evaluation Re Util 831104 Response to Generic Ltr 83-28,Item 1.1 Concerning post-trip Review Program & Procedure ML20148N2351978-11-0101 November 1978 Safety Eval Rept of Main Stream Isolation Valve Test Results. Util Request for Continuing CNS in Present Fuel Cycle for Addl mid-cycle Msltv Leak Test Is Approved ML20147D3101978-09-29029 September 1978 Safety Evaluation Rept Supporting Amend 52 to Facil Oper Lic DPR-46 Concludes That Installation & Use of New Fuel Racks Can Be Accomplished Safety & Health & Safety of Pub Will Not Be Endangered ML20235F1591968-04-0404 April 1968 Safety Evaluation Re Facility 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217A9931999-09-30030 September 1999 NRC Regulatory Assessment & Oversight Pilot Program, Performance Indicator Data ML20217G7461999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Cooper Nuclear Station ML20212K9781999-09-30030 September 1999 Safety Evaluation Accepting USI A-46 Implementation Program ML20217A1691999-09-22022 September 1999 Part 21 Rept Re Engine Sys,Inc Controllers,Manufactured Between Dec 1997 & May 1999,that May Have Questionable Soldering Workmanship.Caused by Inadequate Personnel Training.Sent Rept to All Nuclear Customers ML20212C5001999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Cooper Nuclear Station ML20211D6491999-08-25025 August 1999 Part 21 Rept Re Nonconformance within LCR-25 safety-related Lead Acid Battery Cells Manufactured by C&D.Analysis of Cells Completed.Analysis of Positive Grid Matl Shows Nonconforming Levels of Calcium within Positive Grid Alloy ML20210R0381999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Cooper Nuclear Station ML20210J2921999-07-29029 July 1999 Special Rept:On 990406,OG TS & Associated Charcoal Absorbers Were Removed from Svc.Caused by Scheduled Maint on Hpci. Evaluation of Offsite Effluent Release Dose Effects Was Performed to Ensure Plant Remained in Compliance ML20209H8281999-07-15015 July 1999 Safety Evaluation Accepting GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Cooper Nuclear Station ML20211A9981999-07-12012 July 1999 Draft,Probabilistic Safety Assessment, Risk Info Matrix, Risk Ranking of Systems by Importance Measure ML20196H8621999-06-30030 June 1999 NRC Regulatory Assessment & Oversight Pilot Program, Performance Indicator Data, June 1999 Rept ML20209E1061999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Cns.With ML20196B3851999-06-17017 June 1999 Summary Rept of Facility Changes,Test & Experiments,Per 10CFR50.59 for Period 970901-990331.Summary of Commitment Changes Made During Same Time Period Also Encl ML20195K2851999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Cooper Nuclear Station.With ML20206P0481999-05-12012 May 1999 Safety Evaluation Concluding That NPP Established Acceptable Program to Verify Periodically design-basis Capability of safety-related MOVs at CNS & Adequately Addressed Actions Requested in GL 96-05 ML20206J0811999-05-0404 May 1999 Rev 14 to CNS QA Program for Operation ML20206P9751999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Cooper Nuclear Station ML20205Q0891999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Cooper Nuclear Station.With ML20204G8951999-03-15015 March 1999 CNS Inservice Insp Summary Rept Fall 1998 Refueling Outage (RFO-18) ML20207M9231999-03-12012 March 1999 Amended Part 21 Rept Re Cooper-Bessemer Ksv EDG Power Piston Failure.Total of 198 or More Pistons Have Been Measured at Seven Different Sites.All Potentially Defective Pistons Have Been Removed from Svc Based on Encl Results ML20204B3701999-03-11011 March 1999 SER Accepting Third 10-year Interval Inservice Insp Plan Requests for Relief for RI-17,Rev 1 and RI-25,Rev 0.Request for Relief RI-13,Rev 2 Involving Snubber Testing & Is Being Evaluated in Separate Report ML20204C9751999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Cooper Nuclear Station ML20199E6751999-01-14014 January 1999 Monthly Operating Rept for Dec 1998 for Cooper Nuclear Station ML20195B9191998-12-31031 December 1998 1998 NPPD Annual Rept. with ML20196J9641998-12-0707 December 1998 Safety Evaluation Accepting Licensee Third 10-yr Interval Inservice Insp Plan Request for Relief RI-27,rev 1 ML20198D2471998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Cooper Nuclear Station.With ML20196A5241998-11-23023 November 1998 Safety Evaluation Accepting Proposed Alternative to Use UT Techniques Qualified to Objectives of App Viil as Implemented by PDI Program in Performing RPV Shell Weld & Shell to Flange Weld Examinations ML20196A5061998-11-23023 November 1998 Safety Evaluation Re Flaw Indication Found in Main Steam Nozzle to Shell Weld NVE-BD-N3A at Cns.Plant Can Be Safely Operated for at Least One Fuel Cycle with Indication in as-is Condition ML20196A2861998-11-23023 November 1998 SER Re Core Spray Piping Weld for Cooper Nuclear Station. Staff Concluded That Operation During Cycle 19 Acceptable with Indication re-examined During RFO 18 ML20196C4241998-11-20020 November 1998 Rev 1 to Cooper Nuclear Station COLR Cycle 19 ML20195H1761998-11-17017 November 1998 SER Authorizing Proposed Alternative in Relief Requests RV-06,RV-07,RV-09,RV-11,RV-12 & RV-15 Pursuant to 10CFR50.55a(a)(3)(ii).RV-08 Granted Pursuant to 10CFR50.55a(f)(6)(i) & RV-13 Acceptable Under OM-10 ML20155D9961998-10-31031 October 1998 Rev 0 to GE-NE-B13-01980-24, Fracture Mechanics Evaluation on Observed Indication at N3A Steam Outlet Nozzle to Shell Weld at Cooper Nuclear Station ML20195F8601998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Cooper Nuclear Station.With ML20154Q5661998-10-0505 October 1998 Rev 0 to CNS COLR Cycle 19 ML20154L5381998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Cooper Nuclear Station.With ML20151Z6141998-09-16016 September 1998 SER Accepting Util Responses to NRC Bulletin 95-002 for Cooper Nuclear Station ML20154F7931998-08-31031 August 1998 Rev 0 to J11-03354-10, Supplemental Reload Licensing Rept for CNS Reload 18,Cycle 19 ML20153B1101998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Cooper Nuclear Station ML20237E7771998-08-20020 August 1998 Revised COLR Cycle 18 for Cooper Nuclear Station ML20151Q1211998-08-14014 August 1998 Rev 0 to Control of Hazard Barriers ML20237C0591998-07-31031 July 1998 Monthly Operating Rept for Jul 1998 for Cooper Nuclear Station ML20236R9131998-07-20020 July 1998 SER Accepting Rev 13 to Quality Assurance Program for Operation Policy Document for Plant ML20236P2971998-07-0707 July 1998 Rev 2 to NPPD CNS Strategy for Achieving Engineering Excellence ML20236R0931998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Cooper Nuclear Station ML20249A7701998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Cooper Nuclear Station ML20247G6131998-05-13013 May 1998 Part 21 Rept Re Defect Contained in Automatic Switch Co, Solenoid Valves,Purchased Under Purchase Order (Po) 970161. Caused by Presence of Brass Strands.Replaced Defective Valves ML20247G0951998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Cooper Nuclear Station ML20237B6861998-04-24024 April 1998 Vols I & II to CNS 1998 Biennial Emergency Exercise Scenario, Scheduled for 980609 ML20217A1531998-04-16016 April 1998 Closure to Interim Part 21 Rept Submitted to NRC on 970929. New Date Established for Completion of Level I & 2 Setpoint Project Committed to in .Final Approval of Setpoint Calculations Will Be Completed by 980531 ML20216G5331998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Cooper Nuclear Station 1999-09-30
[Table view] |
Text
,
/[ g UNITED STATES g g NUCLEAR REGULATORY COMMISSION ,
5 e WASHINGTON, D. C 20666 s ,
- .... t ENCLOSURE SAFETY EVALUATION BY THE OFFICE OF hUCLEAR REACTOR REGULATION RELATING TO THE INTERIM OPERABil.lTY OF PIPING SYSTEMS NEBRASKAPUBLICPOWERDISTRig 4
COOPER NUCLEAR STATION DOCKET NO. 50-298
- 1. INTRODUCTION ,
On January 19, 1988, a flonconfornance Report, NCR No.88-019, was issued by Nebraska Public Power District (NPPD) to document that pipe support RF-H53 did not conform with the requirements of the Code of Record for the plant. This i,
was discovered when an NPPD consultant (CYGNA) was designing a 1" drain and ,
vent line connection to the 14" High Pressure Coolant Inspection (HPCI) system I piping and checked the structural adequacy of supports near the connection.
As a result of this NCR, the other supports on the HPCI system were evaluated and 17 out of 33 were identified as not meeting code allowables for the existing ,
- design loadings. This nonconformance was reported by NPPD on April 28, 1988 in ;
NCR No.88-119. In response to this NCR, the HPCI system was evaluated on an "operability" basis and c plant-wide assessment was made of all pipe supports ,
on safety-related systems. Since from the outset it was NPPD's intention to '
bring all deficient supports te full compliance with the original design basis, the purpose of the reviews were to scope the problem plant wide and to develop I 4
a basis to justify operation in t.'e interim before full corpliance is achieved. ,
Brookhaven National Laboratory (ENL) provided the NPC with technical assistance in the review of the licensee's efforts to assess the operability status of the l Cooper Station piping systems. The BNL effort included attendance at meetings with the licensee and staff on May 18, May 31, and June 24, 1988 at the staff offices in White Flint, Maryland and participation with the staff in an audit :
- of NPPD activities at the Cooper Nuclear Station (CNS) on May 23-26, 1988. The j adequacy of the overall operability evaluation was assessed from a review of >
the documents provided in the NPPD June 12 subnittal, references 1-3, and their earlier drafts. The evaluation of analysis rethodology was based on the review i of selected calculations from the operability evaluation, references 4-7. This l report provides a sunnary description of the review activity and the staff /BNL '
evaluation. l 4 ,
l l
i
)
i G311100290 631103
- HEW ADOCK 050002$$
PDG
2 2.0 EVALUATION 2.1 Su w.ary Desc i tion Fo11twing the discovery of the underdesigned surport in the HPCI systtm NPPD, usig its consultant CYGNA, performed a review cf other supports in the HPCI piping system and additional nonconforming pipe supports were identified.
j Given that result, NPPD took the following actions:
- Modified the affected HPCI discharge piping system supports to l
obtain full code qualification,
- Performed an operability evaluation of the as-found HPCI discharge piping system; and, Reviewed other essential piping systems to ascertain whether the HPCI nonconferming supports were an isolated occurrence.
The evaluations of the HPCI system were more detailed than the original calcula-tions in that actual support stiffnesses and realistic thermal conditions were used. The results of these analyses indicated that the piping system was operable in accordance with the requirerents of CNS Technical Specifications in the as-found condition. This detailed evaluation is prosented in the CYGNA report Doc. No. TR-88037A-2 Peference 2, included as attachnent 1 to the NPPD l subrittal dated June 12, 1988, titled Justification for Interim Operation, Reference 1.
The review of other essential systems indicated that other nonconforming supports existad. These were all found to be associated with the original design and construction at CNS. Dele;ing from revicw systems which had under-gene design and analysis subsequent to original design, a review and evaluation of all supports on essential piping system wes undertaken (1157 supports in 11 sy s tems) . In inis effort all Class IN supports were analyzed and modified, as necessary, to enNre full code qualification. Operability of all other supports were analyzed on a sampling basis (satole of 170 from 1157) in accordance with an interir operability criteria and the results corpared with the results of th6 HPCI operability evaluations. As a result of this methodology, all existing emntial supports at CNS were found to be enveloped by the HPCI results, except certain deadweight supports and welded pipe support anchors which had unique attributes. One hundred percent of these deadweight supports and welded pipe support anchors were then reviewed leading to the redification of seventeen deadwe.ight supports and the need for modification of four welded aachors. The detailed evaluation supporting the operability status of existing essential piping system other than the HPCI system is presented in the CYGNA report Doc.
No. TR 88037A-3, Reference 3 included as Attachrent 2 to the NPPD June 12, 1988, submittal. ,
5 r
i 2.2 N, PPD,0perabilityleviewCriteria D
The CNS Code of Record for Class IN/15 piping is ANSI B31.1 "Power Piping",
1967 Edition. Piping support design is also in accordance with ANSI B31.1, ,
1967 and the AISC code allowables. In perforcing the operability assessments for essential piping and supports the allowables from the code of record were used for piping while the following operability criteria was used for supports:
Support Allowable Component Ovel Reference Structural Normal Stress - S y AISC, 7th Edition Merbers Shear .57xS y j Welds Weld .45 S T
AISC, 7th Edition with Base .47 S y 1.5 increase Vender Level D, or As listed in vendor Hardware Fr ellow catalogue ;
i Base plates S y
AISC, 7th Edition Concrete Wedge Type: SF=2.0 NRC !E Bulletin i Anchor Bolts Shell Type: SF=2.5 79-04 and S = yield stress, S = tensile strength and Sp = safety factor applied tu !
ancho bolt ultirate 1 ad I In the HPCI operability evaluation the operability criteria were used in +
conjunction with new assessrents of system stresses and loads. In making i' these new assessrents, efforts were made to eiinimize the conservathe:s inherent in piping system design as used in the original design. Examples of analysis refinerentsincludetheuseofCodeCaseN-411darping,themodelingofsupport stiffnesses e.9d the use of realistic rather than enve oping definitions of therral conditions, i t
In the operability review of other essential piping systems the sare acceptance ;
c-iteria for operability was used. In that review, hcwever, the sampled I su,70rts were assessed for the loads shown on the latest revisions of the i support drawings. Specifically a load case consisting of the cortination i of deadweight, thermal and twice the seismic OBE loads were considered. [
23 LPff.ppyab,1,1,1,ty= Review Results As a result of the operability reviews NPPD concluded in their June 12, 1988 submittal that the status of the essential piping systems at CNS is: ;
All pipe supports associated with the reactor coolant pressure ;
boundary are fully code qualified. !
i i
(
l
i 4
All piping supports associated with the HPCI discharge line are fully code qualified.
- Alldeadweightsupports(17)experiencingupliftduringdesignbasis seismic events have been modified to acconnodate such loads.
All we'ved pipe anchors ( O that werd overstressed will be modified prior '..s startup.
All pipe supports designed subsequent to the initial CNS design were previously analyzed and documented, resulting in a conclusion that they are not within the scope of the identified nonconforming condition.
All other essential supports have been statistically evaluated on the basis of the HPCI Pump Discharge System Operability Evaluation.
With Statisti,. certainty, the essential piping systems are considered to be operable.
Based on these findings, NPPD submitted the June 12, 1988, "Justificatien for -
Interim Operation". In that submittal, NPPD coccitted to have all nonconforming supports modified to neet the design basis prior to startup from the 1990 refueling outage. A detailed plan to ac w nlish the redifications will be provided by August 15, 1988.
At the time of the site audit, NPPD and its consultant CYGNA were actively engaged in performing the operability evaluations. At that stage the analysis procedures and acceptance criteria could be characterized as aggressive in that current era analysis practices were being coupled with liberal definitions for lotds and allowables. The audit teani focused its efforts in a review of analysis procedures, load definition, acceptance criteria and statistical sanpling methods. A description of the audit team activities and findings are presented in the audit trip report, reference 8. The significant findings and observations were discussed with NPPD at the audit exit meeting. The following is a listing of these items:
a) There are no further concerns with the HPCI sys'.em since all supports nave been breeght into code compliance, b) Concerns with CYGNA criteria were expressed by SpSS is not acceptable.
- 1. Coebination of two earthquake components by SRSS is not acceptable.
- 2. High values of dar9tr.) with original response spectra is not acceptable,.
- 3. Vertical floor response (2/3 of ground horizontal) is acceptable if all other pertinent FSAR costnitrents are adhered to.
4 PPCI system design temperature of 120'F is p vbably acceptable.
- 5. Strain criteria are not acceptable.
e O
s ,
5-c) Result of sampling of plant supports (i.e. 125 supports) does not support the CYGNA contention that all safety-related supports are satisfactory for interim operation.
d) We snderstand that all Class IN supports are going to be analyzed and brought into code corplianci before start-up.
e) Assuming that all concerns regarding pipe support operability are
- atisfied, NPDD is to develop a long-range plan to analyze each support
! for code compliance and modify where required. The plan should be I
presented before restarting the plant and should contain the methodology for performing the analysis, criteria for judging acceptability and a schedule for completing the work.
i
! The auJit team also recomended that before CNS is permitted to return to
- power operation
- 1. All class IN supports be brought into code compliance, j 2. NPPO demonstrate that all essential system supports when evaluated for i
original design loads will meet "operability" criteria acceptable to the NRC.
i 3. The "operability" assessment should be based on "as-built" data.
4 In cases where integral attachrent loads lead to excessive local pipe f stresses NDE should be performed to assure that no damage has occurred. [
- 5. A long-range plan, acceptable to NRC, be developed by NPPD to brirs all i supporte into code compliance.
(
Following the site audit, NPPD and its contractor attended a eeeting at the i i staff offices on May 31, 1988. At that meeting, NPPD was advised that interir ,
j operation would only be considered af ter items 1 thru 4 of the aucit team '
reconcendation list above were complied with.
l In its June 12, 1988 submittal to the staff NPPD provided justification for interim operation of the Cooper Nuclear Station. As detailed in that submittal,
{ full code qualification of all supports associated with reactor coolant piping was ensured the operability of all essential supports were verified with a l statisticadysalidsarple,allsupportswithuniqueattributesproneto deficiencies were reviewed and a lo.1 term plan was in preparation and will t>e provided by August 15, 1988.
A review of the June 12 submittal le.' to the conclusion that the NPFu etions essentially complied with the staff's requests. In performing the rev h v however, additional concerns were raised. These were expressed as eight written questions, five requiring resolution prior to the restart and three requiring response subsequent to restart, docunented in a June 16, 1968 remorandun to the Project Manager, reference 9. The questions were addressed by the licensee curing a conference call on June 16, 1988 and at the meeting at the staff offices on June 24, 1988. Based on the licensee's responses the staff concluded:
l 1
l 6-a) the allowable stresses used to demonstrate operabilit3 are accepta'.le b) the analysis options deemed unacceptable to the staff werc not used by ;
the licensee to demonstrate the operability of the essential systems c) all supports which had operability stress ratios greater than 1.0 were or i will be modified prior *o interim operation 3.0 CONCLOSIONS, The licensee's effora to scope, characterize and remedy the support problems !
at the Cooper Nuclear Station have been comprehensise, timely and aggressive. !
through these dforts the licensee has, a) restored all HpCI supports to full code compliance b) restored all supports associated with the reactor coo' ant pressure !
boundary to full code compliance P
c) demonstrated with a statistically acceptable sarple the operability cf l 4 essential piping systems Based on these actions and the June 24, 1988 connitments by the licensee to f bring all supports to full code con:pliance prior to start-up in 1989, the restart ar.d operation of the plant in the interim period is deened acceptable.
r Principal Contributors: P. T. Kuo l P. O'Connor l
Dated: Nosember 3,1988 l
i i
I l
l
i .. ,
n .
4 REFERENCES ,
- 1. Letter from G. A. Trevors, NPPD to NRC dated June 12, 1988 l
- 2. "Operability Evaluation of the HPC1 Pump Discharge System", CYGNA report Doc. No. TR-88037A-2, Rev. 1 1
- 3. "Ope,* ability Evtluation of Essential Piping Systems". CYGNA report Dec.
No. TR-88037A-3, Rev.1 :
4 "NPPD Functionality Analysis of Essential Systems, Statistical Analysis",
CYGNA Cal'c No. 88037A/8/F, May 6, 1988
- 5. CNS hPCI, Pipe Stress, CYGNA Cal'c No. 88037A/a/F, STR-1, April 19,1988 '
, l
- 6. Ct:5 HPCI, Pipe Stress, CYGNA Cal'c No. 88037A/7/F, STR-4, Pay 23,1988 '
- 7. "Essential Systems Support Furectionality Evaluation", CYGNA Cal'c No. ;
88027A/6/F, May 1988
(
I
- 8. "Trip Report - Site Audit of Safety Related Pipe Supports at Cooper l Nuclear Station, May 23-26, 1988", from P.T. Kuo to L.B. Marsh, June 8, '
1988 ;
f
, 9. Memoranda from L.B. l'arsh, Chief HE8 to W.O. Long, Project Manager, ;
Projer.t Directorate IV, June 16,19B8 ,
, 1 i
i i
r
. i I.
t 4
i l
i
[
1 i t l
i
- I L -- - - . . _ _ _. . - - - -_ - - - .