Letter Sequence Approval |
---|
|
|
MONTHYEARML20198E1091992-11-25025 November 1992 Safety Evaluation Accepting Licensee 920921 120-day Response to GL 87-02, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors,Usi A-46 Project stage: Approval ML20198E0951992-11-25025 November 1992 Forwards Safety Evaluation Accepting 920921 120-day Response to Suppl 1 to GL 87-02, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors,Usi A-46 Project stage: Approval ML20151U6881998-09-0808 September 1998 Forwards Request for Addl Info Re Unresolved Safety Issue A-46, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors, in Response to Util 960613 Submittal of Summary Rept Project stage: RAI ML20154F8371998-10-0707 October 1998 Forwards Request for Addl Info Related to Unresolved Safety Issue A-46, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors, for Plant. Response Requested within 90 Days of Receipt of Ltr Project stage: RAI ML20212K9661999-09-30030 September 1999 Forwards Safety Evaluation Accepting plant-specific Safety Evaluation Rept for USI A-46 Program Implementation at Cooper Nuclear Station Project stage: Approval 1998-10-07
[Table View] |
|
---|
Category:SAFETY EVALUATION REPORT--LICENSING & RELATED ISSUES
MONTHYEARML20212K9781999-09-30030 September 1999 Safety Evaluation Accepting USI A-46 Implementation Program ML20209H8281999-07-15015 July 1999 Safety Evaluation Accepting GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Cooper Nuclear Station ML20206P0481999-05-12012 May 1999 Safety Evaluation Concluding That NPP Established Acceptable Program to Verify Periodically design-basis Capability of safety-related MOVs at CNS & Adequately Addressed Actions Requested in GL 96-05 ML20204B3701999-03-11011 March 1999 SER Accepting Third 10-year Interval Inservice Insp Plan Requests for Relief for RI-17,Rev 1 and RI-25,Rev 0.Request for Relief RI-13,Rev 2 Involving Snubber Testing & Is Being Evaluated in Separate Report ML20196J9641998-12-0707 December 1998 Safety Evaluation Accepting Licensee Third 10-yr Interval Inservice Insp Plan Request for Relief RI-27,rev 1 ML20196A2861998-11-23023 November 1998 SER Re Core Spray Piping Weld for Cooper Nuclear Station. Staff Concluded That Operation During Cycle 19 Acceptable with Indication re-examined During RFO 18 ML20196A5241998-11-23023 November 1998 Safety Evaluation Accepting Proposed Alternative to Use UT Techniques Qualified to Objectives of App Viil as Implemented by PDI Program in Performing RPV Shell Weld & Shell to Flange Weld Examinations ML20196A5061998-11-23023 November 1998 Safety Evaluation Re Flaw Indication Found in Main Steam Nozzle to Shell Weld NVE-BD-N3A at Cns.Plant Can Be Safely Operated for at Least One Fuel Cycle with Indication in as-is Condition ML20195H1761998-11-17017 November 1998 SER Authorizing Proposed Alternative in Relief Requests RV-06,RV-07,RV-09,RV-11,RV-12 & RV-15 Pursuant to 10CFR50.55a(a)(3)(ii).RV-08 Granted Pursuant to 10CFR50.55a(f)(6)(i) & RV-13 Acceptable Under OM-10 ML20151Z6141998-09-16016 September 1998 SER Accepting Util Responses to NRC Bulletin 95-002 for Cooper Nuclear Station ML20236R9131998-07-20020 July 1998 SER Accepting Rev 13 to Quality Assurance Program for Operation Policy Document for Plant ML20203K0351998-02-26026 February 1998 SER Approving Third ten-year Interval Inservice Inspection Program Plan,Request for Relief PR-10 for Cooper Nuclear Station.Technical Ltr Rept on Request Relief PR-10 Also Encl ML20212E0811997-10-23023 October 1997 SER Accepting Third 10-yr Interval Insp Program Plan & Associated Requests for Relief for Plant ML20217E6141997-09-23023 September 1997 Safety Evaluation Accepting Util Proposed Changes to Licensing Basis for Plant to Reflect Incorporation of Safer/Gestr Methodology for LOCA Analysis ML20199F7411997-08-14014 August 1997 Safety Evaluation Rept Accepting Design of torus-to-reactor Bldg Vacuum Breakers at Plant ML20210J5731997-08-13013 August 1997 Safety Evaluation Denying Relief Request for Plant Third 10-yr Interval Program for Inservice Testing of Pumps. Request Not in Sufficient Detail to Justify Proposed Alternative ML20148H2381997-06-0606 June 1997 Safety Evaluation Granting Licensee Relief Requests for 10-yr Interval Inservice Insp Program Plan for Plant,Unit 1 ML20138K0241997-05-0707 May 1997 Safety Evaluation Supporting Proposed Rev to RPV Surveillance Capsule Withdrawal Schedule ML20134N6911997-02-19019 February 1997 Safety Evaluation Related to Third ten-year Interval Inservice Testing Program Nebraska Public Power District Cooper Nuclear Station ML20198E1091992-11-25025 November 1992 Safety Evaluation Accepting Licensee 920921 120-day Response to GL 87-02, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors,Usi A-46 ML20127N3741992-11-19019 November 1992 Supplemental SE Accepting Analysis & Results in Response to SBO rule,10CFR50.63 ML20128C2911992-11-19019 November 1992 Safety Evaluation Accepting Revised ACAD Sys Into Nitrogen Containment Atmosphere Dilution,Eliminating Potential post-accident Oxygen Source ML20059E2781990-08-31031 August 1990 Safety Evaluation Granting Licensee 900525 Relief Requests RP-14 & RP-15 from Requirements to Measure Pump Inlet Pressure & Instrument Ranges,Respectively ML20246B2501989-05-31031 May 1989 Safety Evaluation on Generic Ltr 83-28,Item 4.5.3 Re Reactor Trip Sys Reliability for All Domestic Operating Reactors. Intervals for on-line Functional Testing Consistent W/ Achieving High Reactor Trip Sys Availability at Reactors ML20247A4241989-03-20020 March 1989 Safety Evaluation Accepting Revised Process Control Program Re General Methods of Sampling,Processing,Analysis & Waste Formulation During Solidification of Radwaste ML20205S2031988-11-0303 November 1988 Safety Evaluation Supporting Interim Operability of Piping Sys ML20147B5161988-02-23023 February 1988 Safety Evaluation Supporting Amend 117 to License DPR-46 ML20148C9591988-01-13013 January 1988 Safety Evaluation Concluding That Inservice Testing Program Submitted w/860730 Ltr as Modified in Subj Safety Evaluation Will Provide Reasonable Assurance of Operational Readiness of safety-related Pumps & Valves ML20238C4001987-12-23023 December 1987 Safety Evaluation Supporting Proposed Mod to 10CFR50.62, ATWS Rule ML20237E3261987-12-21021 December 1987 Safety Evalution Supporting Amend 113 to License DPR-46 ML20236B8901987-10-20020 October 1987 Sser Re Alternate Rod Insertion (ARI) Sys.Util Plans for Relocating ARI Position Indication Out of Control Room to Another Location in Control Bldg Acceptable ML20235H0351987-09-23023 September 1987 Safety Evaluation Re Alternate Rod Injection & Recirculating Pump Trip Sys ML20235N4581987-07-10010 July 1987 Safety Evaluation Supporting Util 810707,820623,0730 & 831215 Submittals Re Valve Operability Info for 24-inch Isolation Valves in Purge & Vent Sys.Nrc Conclusion Subj to Valves Being Modified to Have Torque Readjustments ML20214S8741987-05-21021 May 1987 Supplemental Safety Evaluation Re Dcrdr.Listed Activities Must Be Finished in Order to Satisfy Dcrdr Requirements in Suppl 1 to NUREG-0737 ML20212Q9721987-04-16016 April 1987 Safety Evaluation Accepting Util 831104 & 870121 Responses to Generic Ltr 83-28,Items 3.2.1 & 3.2.2, Post-Maint Verification Testing ML20212L1751987-03-0606 March 1987 Safety Evaluation Supporting Util Methodology in Standby Gas Treatment Suction Analysis & Interim Operation for Fuel Cycle 11 Only ML20209A7001987-01-30030 January 1987 Safety Evaluation Accepting Util Response to Vendor Recommended Reliability Verification Testing Per Generic Ltr 83-28,Item 4.5.1 Re Reactor Trip Sys Reliability (Sys Functional Testing) ML20215M5021986-10-27027 October 1986 Safety Evaluation Accepting Util Response to Generic Ltr 82-33 Re Conformance to Rev 2 to Reg Guide 1.97,except for Instrumentation Associated W/Neutron Flux Variable ML20210K2491986-09-25025 September 1986 Safety Evaluation Supporting Analytical Method Used by Licensee to Evaluate Critical Stresses ML20141E9291986-04-10010 April 1986 Safety Evaluation Supporting Amend 98 to License DPR-46 ML20151Y2541986-01-27027 January 1986 Safety Evaluation Re Requests for Relief from Inservice Insp Requirements.Relief Not Granted for Surface & Volumetric Exam of Drywell Piping Spray Welds Since Requirements Not Impractical ML20140C5761986-01-17017 January 1986 Safety Evaluation Supporting 831104 Response to Generic Ltr 83-28,Items 3.1.1 & 3.1.2 Concerning post-maint Testing Verification of Reactor Trip Sys Components ML20134J6301985-08-21021 August 1985 Safety Evaluation Accepting Proposed Mods as Ensuring Safe Shutdown Capability in Event of Fire in Areas of Concern in Accordance W/Requirements of 10CFR50,App R ML20127E7281985-06-10010 June 1985 Safety Evaluation Supporting Response to Generic Ltr 83-28, Item 1.2 Re post-trip Review Data & Info Capability ML20127E1051985-05-0606 May 1985 Safety Evaluation Re Util 831104 Response to Generic Ltr 83-28,Item 1.1 Concerning post-trip Review Program & Procedure ML20148N2351978-11-0101 November 1978 Safety Eval Rept of Main Stream Isolation Valve Test Results. Util Request for Continuing CNS in Present Fuel Cycle for Addl mid-cycle Msltv Leak Test Is Approved ML20147D3101978-09-29029 September 1978 Safety Evaluation Rept Supporting Amend 52 to Facil Oper Lic DPR-46 Concludes That Installation & Use of New Fuel Racks Can Be Accomplished Safety & Health & Safety of Pub Will Not Be Endangered ML20235F1591968-04-0404 April 1968 Safety Evaluation Re Facility 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20212K9781999-09-30030 September 1999 Safety Evaluation Accepting USI A-46 Implementation Program ML20217A9931999-09-30030 September 1999 NRC Regulatory Assessment & Oversight Pilot Program, Performance Indicator Data ML20217G7461999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Cooper Nuclear Station ML20217A1691999-09-22022 September 1999 Part 21 Rept Re Engine Sys,Inc Controllers,Manufactured Between Dec 1997 & May 1999,that May Have Questionable Soldering Workmanship.Caused by Inadequate Personnel Training.Sent Rept to All Nuclear Customers ML20212C5001999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Cooper Nuclear Station ML20211D6491999-08-25025 August 1999 Part 21 Rept Re Nonconformance within LCR-25 safety-related Lead Acid Battery Cells Manufactured by C&D.Analysis of Cells Completed.Analysis of Positive Grid Matl Shows Nonconforming Levels of Calcium within Positive Grid Alloy ML20210R0381999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Cooper Nuclear Station ML20210J2921999-07-29029 July 1999 Special Rept:On 990406,OG TS & Associated Charcoal Absorbers Were Removed from Svc.Caused by Scheduled Maint on Hpci. Evaluation of Offsite Effluent Release Dose Effects Was Performed to Ensure Plant Remained in Compliance ML20209H8281999-07-15015 July 1999 Safety Evaluation Accepting GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Cooper Nuclear Station ML20211A9981999-07-12012 July 1999 Draft,Probabilistic Safety Assessment, Risk Info Matrix, Risk Ranking of Systems by Importance Measure ML20196H8621999-06-30030 June 1999 NRC Regulatory Assessment & Oversight Pilot Program, Performance Indicator Data, June 1999 Rept ML20209E1061999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Cns.With ML20196B3851999-06-17017 June 1999 Summary Rept of Facility Changes,Test & Experiments,Per 10CFR50.59 for Period 970901-990331.Summary of Commitment Changes Made During Same Time Period Also Encl ML20195K2851999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Cooper Nuclear Station.With ML20206P0481999-05-12012 May 1999 Safety Evaluation Concluding That NPP Established Acceptable Program to Verify Periodically design-basis Capability of safety-related MOVs at CNS & Adequately Addressed Actions Requested in GL 96-05 ML20206J0811999-05-0404 May 1999 Rev 14 to CNS QA Program for Operation ML20206P9751999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Cooper Nuclear Station ML20205Q0891999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Cooper Nuclear Station.With ML20204G8951999-03-15015 March 1999 CNS Inservice Insp Summary Rept Fall 1998 Refueling Outage (RFO-18) ML20207M9231999-03-12012 March 1999 Amended Part 21 Rept Re Cooper-Bessemer Ksv EDG Power Piston Failure.Total of 198 or More Pistons Have Been Measured at Seven Different Sites.All Potentially Defective Pistons Have Been Removed from Svc Based on Encl Results ML20204B3701999-03-11011 March 1999 SER Accepting Third 10-year Interval Inservice Insp Plan Requests for Relief for RI-17,Rev 1 and RI-25,Rev 0.Request for Relief RI-13,Rev 2 Involving Snubber Testing & Is Being Evaluated in Separate Report ML20204C9751999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Cooper Nuclear Station ML20199E6751999-01-14014 January 1999 Monthly Operating Rept for Dec 1998 for Cooper Nuclear Station ML20195B9191998-12-31031 December 1998 1998 NPPD Annual Rept. with ML20196J9641998-12-0707 December 1998 Safety Evaluation Accepting Licensee Third 10-yr Interval Inservice Insp Plan Request for Relief RI-27,rev 1 ML20198D2471998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Cooper Nuclear Station.With ML20196A2861998-11-23023 November 1998 SER Re Core Spray Piping Weld for Cooper Nuclear Station. Staff Concluded That Operation During Cycle 19 Acceptable with Indication re-examined During RFO 18 ML20196A5241998-11-23023 November 1998 Safety Evaluation Accepting Proposed Alternative to Use UT Techniques Qualified to Objectives of App Viil as Implemented by PDI Program in Performing RPV Shell Weld & Shell to Flange Weld Examinations ML20196A5061998-11-23023 November 1998 Safety Evaluation Re Flaw Indication Found in Main Steam Nozzle to Shell Weld NVE-BD-N3A at Cns.Plant Can Be Safely Operated for at Least One Fuel Cycle with Indication in as-is Condition ML20196C4241998-11-20020 November 1998 Rev 1 to Cooper Nuclear Station COLR Cycle 19 ML20195H1761998-11-17017 November 1998 SER Authorizing Proposed Alternative in Relief Requests RV-06,RV-07,RV-09,RV-11,RV-12 & RV-15 Pursuant to 10CFR50.55a(a)(3)(ii).RV-08 Granted Pursuant to 10CFR50.55a(f)(6)(i) & RV-13 Acceptable Under OM-10 ML20195F8601998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Cooper Nuclear Station.With ML20155D9961998-10-31031 October 1998 Rev 0 to GE-NE-B13-01980-24, Fracture Mechanics Evaluation on Observed Indication at N3A Steam Outlet Nozzle to Shell Weld at Cooper Nuclear Station ML20154Q5661998-10-0505 October 1998 Rev 0 to CNS COLR Cycle 19 ML20154L5381998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Cooper Nuclear Station.With ML20151Z6141998-09-16016 September 1998 SER Accepting Util Responses to NRC Bulletin 95-002 for Cooper Nuclear Station ML20154F7931998-08-31031 August 1998 Rev 0 to J11-03354-10, Supplemental Reload Licensing Rept for CNS Reload 18,Cycle 19 ML20153B1101998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Cooper Nuclear Station ML20237E7771998-08-20020 August 1998 Revised COLR Cycle 18 for Cooper Nuclear Station ML20151Q1211998-08-14014 August 1998 Rev 0 to Control of Hazard Barriers ML20237C0591998-07-31031 July 1998 Monthly Operating Rept for Jul 1998 for Cooper Nuclear Station ML20236R9131998-07-20020 July 1998 SER Accepting Rev 13 to Quality Assurance Program for Operation Policy Document for Plant ML20236P2971998-07-0707 July 1998 Rev 2 to NPPD CNS Strategy for Achieving Engineering Excellence ML20236R0931998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Cooper Nuclear Station ML20249A7701998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Cooper Nuclear Station ML20247G6131998-05-13013 May 1998 Part 21 Rept Re Defect Contained in Automatic Switch Co, Solenoid Valves,Purchased Under Purchase Order (Po) 970161. Caused by Presence of Brass Strands.Replaced Defective Valves ML20247G0951998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Cooper Nuclear Station ML20237B6861998-04-24024 April 1998 Vols I & II to CNS 1998 Biennial Emergency Exercise Scenario, Scheduled for 980609 ML20217A1531998-04-16016 April 1998 Closure to Interim Part 21 Rept Submitted to NRC on 970929. New Date Established for Completion of Level I & 2 Setpoint Project Committed to in .Final Approval of Setpoint Calculations Will Be Completed by 980531 ML20216G5331998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Cooper Nuclear Station 1999-09-30
[Table view] |
Text
. ..
Enclosure 1
- p oog'o,,
UNITED STATES l' - 'n NUCLEAR REGULATORY COMMISSION t, -y WASHINGTON. D. C. 20555 j
\...../
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION EVALUATION OF NEBRASKA PUBLIC POWER DISTRICT'S 110-DAY RESPONSE TO SUPPLEMENT NO. 1 TO GENERIC LETTER 8J-32 FOR COOPER NUCLEAR STATION DOCKET NO. 50-E93 TAC NO. M69439 INTRODUCTION On May 22, 1992, the NRC staff issued Supplement No. I to Generic Letter (GL) 87-02, " Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Rcettors, Unresolved Safety Issue (JSI) A-46." In this supplement, the staff requested that licensees submit the following information within 120 days of the issue date of the supplement:
I. A statement whether you cor.ait to use both the Seismic Qualification Utility Group (SQUG) commitments and the implementation guidance provided in the Generic Implementation Procedure, Revision 2 (GIP-2) as supplemented by the staff's Supplemental Safety Evaluation Report No. 2 (SSER-2) for the resolution of USI A-46. In this case, any deviation from GIP-2, as supplemented by the SSER-2, must be identified, justified, and documented. If you do not make such a commitment, you must provide youi alternative for responding to GL 87-02.
- 2. A plant-specific schedule for the implementation of the GIP-2 and submission of a report to the staff that summarizes the results of the USI A-46 review, if you are committing to implement GIP-2. This schedule shall be such that each affected plant will complete its implementetion and submit the summary report within 3 years after the issuance of SSER-2, unless otherwise justified.
- 3. The detailed information as to what procedures and criteria were used to generate the in-structure response spectra to be used for USI A-46 as requested in SSER-2. The licensee's in-structure response spectra are considered acceptable for USI A-46 unless the staff indicates otherwise during a 60-day review period.
In addition, the staff requested in SSER-2 that each licensee inform the staff, in its 120-day response, if it intends to change its licensing basis to reflect a commitment to the USI A-46 (GIP-2) methodolcgy for verifying the 9212040129 921125 8 DR ADOCK 0500
4 seismic adequacy of mechanical and electrical equipment, prior to receipt of the staff's plant-specific safety evaluation resolving USI A-46.
By letter dated September 21, 1992, the Nebraska Public Power District (the licensee for Cooner Nuclear Station) submitted its response to Supplement No. I to Gener c Letter (GL) 87-02.
i EVALUATION Implementation of SOUG and GIP-2 commitments With regard to Item 1, the licensee stated that it "... commits to the SQUG commitments set forth in the GIP in their entirety, including the clarifications, interpretations, and exceptions identified in the SSER-2 as clarified by the August 21, 1992, SQUG
, letter responding to SSER-2." The licensee also stated that it "... generally will be guided by the remaining (non-commitment) sections of the GIP, i.e.,
GIP implementation guidance, which comprises suggested methods for implementing the applicable comitments."
The licensee's response is unclear as te whether or not the licensee intends to implement both the SQUG commitments and the implementation guidance. In accepting GIP-2 as a method for resolving USI A-46, it was the staff's understanding that the SQUG members who chose to implement GIP-2 would '
essentially use the entire procedure, including the SQUG commitments, which contain the general programmatic objectives and goals, and the implementation guidance, which contains the specific criteria and procedures to be used for the resolution of USI A-46. This understanding was the basis for the staff's position, wt.ich was stated in SSER-2, that if the licensee commits to use GIP-2 for the impicnentation of USI A-46, it must commit to both the SQUG commitments and the use of the entire implementation guidance provided in GIP-2, un'less otherwise justified to the staff. In order to allow some flexibility in implementing GIP-2, the staff acknowledged in the supplement to GL 87-02 that SQUG members wno commit to GIP-2 (both the SQUG commitments and the implementation guidance) may deviate from it provided that such deviations are identified, documented and justified. However, it was also indicated in SSER-2 that if a licensee uses methods that deviate from the criteria and procedures described in the SQUG commitments and in the implementation guidance of GIP-2 without prior NRC approval, the staff may find the use of such methods unacceptable with regard to satisfying the provisions of GL 87-02.
In light of the above, the staff interprets the licensee's response to Supplement No, I to GL 87-02 as a commitment to the entire GIP-2 including both the SQUG commitments and the implementation guidance, and therefore considers it acceptable. If the staff's interpretation is incorrect, then in accordance with Supplement No. 1 to GL 87-02, the licensee should provide for staff review, as soon as practicable prior to implementation, its alternative criteria and proc.dures for responding to GL 87-02.
. In addition, Enclosure 2 provides the staff's response, dated October 2, 1992, to the August 21, 1992, SQUG letter. The staff does not concur with all of the SQUG's clarifications and positions stated in that letter, and thus, the licensee should not use the August 21, 1992, letter as guidance in responding to Supplement No. I to GL 87-02. The licensee should refer to the NRC staff's October 2,1992 letter (see Enclosure 2) for the staff's position on the SQUG letter.
Imolementation schedule With regard to Item 2, the licensco stated that it I will submit a summary report to the NRC summarizing the results of the ;
USI A-46 program at Cooper Nuclear Station by May 22, 1995. This submittal !
date is within the 3-year response period requested by the staff and is therefore acceptable.
In-structure response spectra With regard to Item 3, the NRC staff has reviewed the licensee's in-structure response spectra to be used for USI A-46 evaluations. Specifically, the staff has reviewed the licensee's response with the objective of assessing the acceptability of the response to item 11.4.2.3 of SSER-2.
The plant SSE peak ground acceleration (PGA) is 0.209 The licensee has developed 'in-structure response spectra (IRS) utilizing the N69W component of the July 1952 Taft, California, earthquake records normalized to 0.20g PGA.
The 7% damped design response spectrum is the Housner spectral shape with amplifications determined by approximately averaging the peaks and valleys of the Taft spectrum. The licensee states that the IRS should be considered as the " conservative design" spectra for verifying the plant equipment. However, the staff does not agree. The parameters that are not in favor of such acceptance are: non-conservative input spectrum, Regulatory Guide 1.61 type damping, and soil-property variations not according to the Standard Review-Plan. The applicat* ef the design motion at the foundation level and some unspecified broadening of IRS peaks can be considered as conserotive considerations. Overall, a review of the IRS provided by the liensee (if at 1/2% or 1% damping as stated on page 6 of the licensee':, submittal) does not lend itself to such an acceptance.
Based on our review of the licensee response and the staff positions l delineated in the SSER-2, we conclude that the licensee response is adequate i
and acceptable, but the IRS developed by the licensee should be considered as
" median centered" in-structure response spectra, rather than " conservative design" spectra. This conclusion is based on the assumption that the stateme-ts made in the submittal,-including the procedures used in generation of the IRS, correctly reflect the FSAR and other licensing basis. The staff may audit the process by which the in-structure response spectra were j generated.
i It is noted that the licensee did not indicate in its submittal that it
! intended to change its licensing basis to reflect a commitment to the USI A-46 l methodology prior to receipt of the staff's plant-specific SER.
l l
4 a
i
- CONCLUSIONS i The staff interprets the licensee's response to Supplement No. I to GL 87-02 as a commitment to the entire GIP-2, including both the SQUG commitments and i the implementation gridance, and therefore considers it acceptable. If this 1 interpretation is incorrect, and the licensee does not commit to implement the entire GIP-R, then in accordance with Supplement No. I to GL 87-02, the 1
licensee'should provide _ for staff review, as soon as practicable prior to.
{ implementation, its alternative criteria and procedures for responding to
! GL 87-02. Additionally the licensee should not merely follow the August 21,
! 1992, SQUG letter for implementing GIP-2, but should refer to the staff's j October 2,1992 respor.se to the- SQUG letter (see Enclosure 2).
1 The implementation schedule proposed by the licensee is within the 3-year .
{ response period requested by-the staff in Supplement No, I to GL 87-02 and is j therefore acceptable.
i l The in-structure response spectra developed by the licensee is adequate and acceptable, but should be considered as " median centered" in-structure -
- response sis;tra, rather than " conservative design" spectra, i- - Principal Contributors
- H. Ashar 4
P.'Chen M. McBrearty i_ Date: November 25, 1992 i
?
l-l-
i L
i i' ,.
l:
I l
_ . ~ . _.- _ . . , - _ _ , , , . _
ENCLOSURE 2
. ff, % UNITED STATES P "t ,, , * ,% NUCLEAR REGULATORY COMMISSION 2 I wassisvorow o.c. roses
'9, N s, o . . . . /
OCT 0 2 W l 1
4 Mr. Neil Smith, Chairman Seismic Qualification Utility Group l
c/o EPRI 3 1019 19th Street, N.W.
Washington, DC 20036 )
1 4
SUBJECT:
NRC RESPONSE TO SEISMIC QUALIFICATION UTILITY GROUP (SQUG)
Re: Letter, N. Smith, EPRI, To J. Partlow, NRR, datad August 21, 1992, !
concerning USI A-46 Issues, j
Dear Mr. Smith:
This is to acknowledge the receipt of the SQUG response to Supplement No. I to Generic Letter (GL) 87-02, and Supplemental Safety Evaluation (SSER) No. 2, on the SQUG Generic Implementation Procedure for Seismic Verification of Nuclear Plant Equipment, Revision 2, as corrected February 14, 1992 (GIP-2). The NRC staff believes thr.t successful implementation of the. entire GIP-2,' supple-mented by the staff's SSER No. 2, by each SQUG licensee will result in cost-4 effective plant safety enhancement for their USI A-46 plants.
The staff also believes that the positions delineated in Supplement No. I to
- Gl. 87-02 and SSER No. 2 are clear and correct, and should not be misinterpret-ed. The staff's comments on SQUG's August 21, 1992, letter and attachment are provided in the enclosure to this letter. If you need further clarification concerning our response, please contact Mr. James Norberg at 504-3288.
1 Sincerely, r
I
% dit James G. Cartlow
. As'sociate Director for Projects Office of Nuclear Reactor Regulation
Enclosure:
As stated ,
9LiOO903L5 3ff Y&
i ,. * -s ENCLOSURE I
- !. NRC's Coments on the SOUG Letter of Auaust 21. 1992
- .
- 1. In regard to the issue of seismic qualification, the staff
-reiterates the position stated in the SSER No. 2, in that the GIP-2 methodology is not considered to be a seismic qualification j method, rather, it is an= acceptable evaluation method for US! A-46 plants only, to verify the seismic adequacy of the safe-shutdown equipment and to ensure that the pertinent equipment.
seismic requirements of General Design Criterion 2 and the pur
'of the NRC regulations relevant-to equipment seismic adequacy pose including 10 CFR Part 100 are satisfied.-
( 2. The second paragraph on page 2 of your letter addressed the issue
- of timing of staff response to additional information requested i from a licensee. Although you ar~e correct in your. statement l regarding the sixty-day. period for response to initial. submittal
- of in-structure response spectra (ISRS) information, we do not
! agree that_the same concept applies to a licensee's submittal of i additional information received following a rejection or a
! question from-the staff. To eliminate any potential misunder-I standing in this regard, the staff has determined that it will respond to any submittal of additional information received from a licensee within 60 days. However, in this response, the staff l will either state.its approvP (or rejection) of the information--
i' provided, or indicate the tt Juration needed for the review-of such information, prior to'h , Amitting a follow-up response of i acceptance-(or rejection) to~the licensee. This time duration i will vary depending on the complexity of the submittal. .
3.
Regarding the EBAC and ANCHOR computer. codes, the_ staff's
[ evaluations and concerns stated in the SSER No.:2 are correct.and i valid. The ANCHOR code does not consider the effects of base t
plate flexibility on the ' anchorage capacity,
- 4. With respect to transfer of knowledge regarding major problems- '
l identified, and lessons--learned, in the USl A-46 plant walkdowns L and third-party reviews, we request that you include the NRC in l the distribution of written communications to all member utilities in this regard, and infore the NRC staff of any planned workshops on A-46_ implementation for possible staff participation.
_ NRC's Coments on th' e Procedure for Reviewina- the GIP -
II.
- 1. _The staff supports SQUG's establishment of a; Peer Review Panel composed of. seismic experts since it should serve to enhance the-
. review process.of substantive changes to-the technical-
! requirements in the GIP,. prior to-its submittal to NRC for approval. However, since the NRC no longer intends to help-t finance a Peer Review Panel, the staff does not believe it=
4 4
., ,,_,-,,m.., ,,.,,,,-,,,_,_.__,m.,.A,....m_,,,,_..... , ,,. m , , , , . . , . ~. ,
4 4
is appropriate to participate in the selection of the Peer Review members, who will be financed by SQUG/EPRI. We would like to.
emphasize-that staff's review of a proposed GIP change will j receive thorough independent NRC evaluation and will be assessed '
on its merits.
- 2. With respect to the NRC review and approval of the changes to the 'I
! GIP (Item 5, page 3 of the procedure), the staff's position on the l 15pte of-its response timing is identical.to that delineated in i the response to a licensee submittal of additional information (refer to item 2 of NRC's Comments on the SQUG letter in this
! enclosure). This comment also applies to the section " LICENSING l l CONSIDERATIONS" on page 5 of the Attachment to-the SQUG letter, f
- 3. With respect to item 4, " Additional Restrictions," the text should
. be expanded to reflect that new information which indicates that existing GIP criteria and guidelines may be unconservative should
- be evaluated for potential 10 CFR Part 21 implications.
l I
4 l
l i
s f
f
. . . . . , ... .- ,, .. . --.,-.-.., .