|
---|
Category:SAFETY EVALUATION REPORT--LICENSING & RELATED ISSUES
MONTHYEARML20212K9781999-09-30030 September 1999 Safety Evaluation Accepting USI A-46 Implementation Program ML20209H8281999-07-15015 July 1999 Safety Evaluation Accepting GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Cooper Nuclear Station ML20206P0481999-05-12012 May 1999 Safety Evaluation Concluding That NPP Established Acceptable Program to Verify Periodically design-basis Capability of safety-related MOVs at CNS & Adequately Addressed Actions Requested in GL 96-05 ML20204B3701999-03-11011 March 1999 SER Accepting Third 10-year Interval Inservice Insp Plan Requests for Relief for RI-17,Rev 1 and RI-25,Rev 0.Request for Relief RI-13,Rev 2 Involving Snubber Testing & Is Being Evaluated in Separate Report ML20196J9641998-12-0707 December 1998 Safety Evaluation Accepting Licensee Third 10-yr Interval Inservice Insp Plan Request for Relief RI-27,rev 1 ML20196A2861998-11-23023 November 1998 SER Re Core Spray Piping Weld for Cooper Nuclear Station. Staff Concluded That Operation During Cycle 19 Acceptable with Indication re-examined During RFO 18 ML20196A5241998-11-23023 November 1998 Safety Evaluation Accepting Proposed Alternative to Use UT Techniques Qualified to Objectives of App Viil as Implemented by PDI Program in Performing RPV Shell Weld & Shell to Flange Weld Examinations ML20196A5061998-11-23023 November 1998 Safety Evaluation Re Flaw Indication Found in Main Steam Nozzle to Shell Weld NVE-BD-N3A at Cns.Plant Can Be Safely Operated for at Least One Fuel Cycle with Indication in as-is Condition ML20195H1761998-11-17017 November 1998 SER Authorizing Proposed Alternative in Relief Requests RV-06,RV-07,RV-09,RV-11,RV-12 & RV-15 Pursuant to 10CFR50.55a(a)(3)(ii).RV-08 Granted Pursuant to 10CFR50.55a(f)(6)(i) & RV-13 Acceptable Under OM-10 ML20151Z6141998-09-16016 September 1998 SER Accepting Util Responses to NRC Bulletin 95-002 for Cooper Nuclear Station ML20236R9131998-07-20020 July 1998 SER Accepting Rev 13 to Quality Assurance Program for Operation Policy Document for Plant ML20203K0351998-02-26026 February 1998 SER Approving Third ten-year Interval Inservice Inspection Program Plan,Request for Relief PR-10 for Cooper Nuclear Station.Technical Ltr Rept on Request Relief PR-10 Also Encl ML20212E0811997-10-23023 October 1997 SER Accepting Third 10-yr Interval Insp Program Plan & Associated Requests for Relief for Plant ML20217E6141997-09-23023 September 1997 Safety Evaluation Accepting Util Proposed Changes to Licensing Basis for Plant to Reflect Incorporation of Safer/Gestr Methodology for LOCA Analysis ML20199F7411997-08-14014 August 1997 Safety Evaluation Rept Accepting Design of torus-to-reactor Bldg Vacuum Breakers at Plant ML20210J5731997-08-13013 August 1997 Safety Evaluation Denying Relief Request for Plant Third 10-yr Interval Program for Inservice Testing of Pumps. Request Not in Sufficient Detail to Justify Proposed Alternative ML20148H2381997-06-0606 June 1997 Safety Evaluation Granting Licensee Relief Requests for 10-yr Interval Inservice Insp Program Plan for Plant,Unit 1 ML20138K0241997-05-0707 May 1997 Safety Evaluation Supporting Proposed Rev to RPV Surveillance Capsule Withdrawal Schedule ML20134N6911997-02-19019 February 1997 Safety Evaluation Related to Third ten-year Interval Inservice Testing Program Nebraska Public Power District Cooper Nuclear Station ML20198E1091992-11-25025 November 1992 Safety Evaluation Accepting Licensee 920921 120-day Response to GL 87-02, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors,Usi A-46 ML20127N3741992-11-19019 November 1992 Supplemental SE Accepting Analysis & Results in Response to SBO rule,10CFR50.63 ML20128C2911992-11-19019 November 1992 Safety Evaluation Accepting Revised ACAD Sys Into Nitrogen Containment Atmosphere Dilution,Eliminating Potential post-accident Oxygen Source ML20059E2781990-08-31031 August 1990 Safety Evaluation Granting Licensee 900525 Relief Requests RP-14 & RP-15 from Requirements to Measure Pump Inlet Pressure & Instrument Ranges,Respectively ML20246B2501989-05-31031 May 1989 Safety Evaluation on Generic Ltr 83-28,Item 4.5.3 Re Reactor Trip Sys Reliability for All Domestic Operating Reactors. Intervals for on-line Functional Testing Consistent W/ Achieving High Reactor Trip Sys Availability at Reactors ML20247A4241989-03-20020 March 1989 Safety Evaluation Accepting Revised Process Control Program Re General Methods of Sampling,Processing,Analysis & Waste Formulation During Solidification of Radwaste ML20205S2031988-11-0303 November 1988 Safety Evaluation Supporting Interim Operability of Piping Sys ML20147B5161988-02-23023 February 1988 Safety Evaluation Supporting Amend 117 to License DPR-46 ML20148C9591988-01-13013 January 1988 Safety Evaluation Concluding That Inservice Testing Program Submitted w/860730 Ltr as Modified in Subj Safety Evaluation Will Provide Reasonable Assurance of Operational Readiness of safety-related Pumps & Valves ML20238C4001987-12-23023 December 1987 Safety Evaluation Supporting Proposed Mod to 10CFR50.62, ATWS Rule ML20237E3261987-12-21021 December 1987 Safety Evalution Supporting Amend 113 to License DPR-46 ML20236B8901987-10-20020 October 1987 Sser Re Alternate Rod Insertion (ARI) Sys.Util Plans for Relocating ARI Position Indication Out of Control Room to Another Location in Control Bldg Acceptable ML20235H0351987-09-23023 September 1987 Safety Evaluation Re Alternate Rod Injection & Recirculating Pump Trip Sys ML20235N4581987-07-10010 July 1987 Safety Evaluation Supporting Util 810707,820623,0730 & 831215 Submittals Re Valve Operability Info for 24-inch Isolation Valves in Purge & Vent Sys.Nrc Conclusion Subj to Valves Being Modified to Have Torque Readjustments ML20214S8741987-05-21021 May 1987 Supplemental Safety Evaluation Re Dcrdr.Listed Activities Must Be Finished in Order to Satisfy Dcrdr Requirements in Suppl 1 to NUREG-0737 ML20212Q9721987-04-16016 April 1987 Safety Evaluation Accepting Util 831104 & 870121 Responses to Generic Ltr 83-28,Items 3.2.1 & 3.2.2, Post-Maint Verification Testing ML20212L1751987-03-0606 March 1987 Safety Evaluation Supporting Util Methodology in Standby Gas Treatment Suction Analysis & Interim Operation for Fuel Cycle 11 Only ML20209A7001987-01-30030 January 1987 Safety Evaluation Accepting Util Response to Vendor Recommended Reliability Verification Testing Per Generic Ltr 83-28,Item 4.5.1 Re Reactor Trip Sys Reliability (Sys Functional Testing) ML20215M5021986-10-27027 October 1986 Safety Evaluation Accepting Util Response to Generic Ltr 82-33 Re Conformance to Rev 2 to Reg Guide 1.97,except for Instrumentation Associated W/Neutron Flux Variable ML20210K2491986-09-25025 September 1986 Safety Evaluation Supporting Analytical Method Used by Licensee to Evaluate Critical Stresses ML20141E9291986-04-10010 April 1986 Safety Evaluation Supporting Amend 98 to License DPR-46 ML20151Y2541986-01-27027 January 1986 Safety Evaluation Re Requests for Relief from Inservice Insp Requirements.Relief Not Granted for Surface & Volumetric Exam of Drywell Piping Spray Welds Since Requirements Not Impractical ML20140C5761986-01-17017 January 1986 Safety Evaluation Supporting 831104 Response to Generic Ltr 83-28,Items 3.1.1 & 3.1.2 Concerning post-maint Testing Verification of Reactor Trip Sys Components ML20134J6301985-08-21021 August 1985 Safety Evaluation Accepting Proposed Mods as Ensuring Safe Shutdown Capability in Event of Fire in Areas of Concern in Accordance W/Requirements of 10CFR50,App R ML20127E7281985-06-10010 June 1985 Safety Evaluation Supporting Response to Generic Ltr 83-28, Item 1.2 Re post-trip Review Data & Info Capability ML20127E1051985-05-0606 May 1985 Safety Evaluation Re Util 831104 Response to Generic Ltr 83-28,Item 1.1 Concerning post-trip Review Program & Procedure ML20148N2351978-11-0101 November 1978 Safety Eval Rept of Main Stream Isolation Valve Test Results. Util Request for Continuing CNS in Present Fuel Cycle for Addl mid-cycle Msltv Leak Test Is Approved ML20147D3101978-09-29029 September 1978 Safety Evaluation Rept Supporting Amend 52 to Facil Oper Lic DPR-46 Concludes That Installation & Use of New Fuel Racks Can Be Accomplished Safety & Health & Safety of Pub Will Not Be Endangered ML20235F1591968-04-0404 April 1968 Safety Evaluation Re Facility 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20212K9781999-09-30030 September 1999 Safety Evaluation Accepting USI A-46 Implementation Program ML20217A9931999-09-30030 September 1999 NRC Regulatory Assessment & Oversight Pilot Program, Performance Indicator Data ML20217G7461999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Cooper Nuclear Station ML20217A1691999-09-22022 September 1999 Part 21 Rept Re Engine Sys,Inc Controllers,Manufactured Between Dec 1997 & May 1999,that May Have Questionable Soldering Workmanship.Caused by Inadequate Personnel Training.Sent Rept to All Nuclear Customers ML20212C5001999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Cooper Nuclear Station ML20211D6491999-08-25025 August 1999 Part 21 Rept Re Nonconformance within LCR-25 safety-related Lead Acid Battery Cells Manufactured by C&D.Analysis of Cells Completed.Analysis of Positive Grid Matl Shows Nonconforming Levels of Calcium within Positive Grid Alloy ML20210R0381999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Cooper Nuclear Station ML20210J2921999-07-29029 July 1999 Special Rept:On 990406,OG TS & Associated Charcoal Absorbers Were Removed from Svc.Caused by Scheduled Maint on Hpci. Evaluation of Offsite Effluent Release Dose Effects Was Performed to Ensure Plant Remained in Compliance ML20209H8281999-07-15015 July 1999 Safety Evaluation Accepting GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Cooper Nuclear Station ML20211A9981999-07-12012 July 1999 Draft,Probabilistic Safety Assessment, Risk Info Matrix, Risk Ranking of Systems by Importance Measure ML20196H8621999-06-30030 June 1999 NRC Regulatory Assessment & Oversight Pilot Program, Performance Indicator Data, June 1999 Rept ML20209E1061999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Cns.With ML20196B3851999-06-17017 June 1999 Summary Rept of Facility Changes,Test & Experiments,Per 10CFR50.59 for Period 970901-990331.Summary of Commitment Changes Made During Same Time Period Also Encl ML20195K2851999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Cooper Nuclear Station.With ML20206P0481999-05-12012 May 1999 Safety Evaluation Concluding That NPP Established Acceptable Program to Verify Periodically design-basis Capability of safety-related MOVs at CNS & Adequately Addressed Actions Requested in GL 96-05 ML20206J0811999-05-0404 May 1999 Rev 14 to CNS QA Program for Operation ML20206P9751999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Cooper Nuclear Station ML20205Q0891999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Cooper Nuclear Station.With ML20204G8951999-03-15015 March 1999 CNS Inservice Insp Summary Rept Fall 1998 Refueling Outage (RFO-18) ML20207M9231999-03-12012 March 1999 Amended Part 21 Rept Re Cooper-Bessemer Ksv EDG Power Piston Failure.Total of 198 or More Pistons Have Been Measured at Seven Different Sites.All Potentially Defective Pistons Have Been Removed from Svc Based on Encl Results ML20204B3701999-03-11011 March 1999 SER Accepting Third 10-year Interval Inservice Insp Plan Requests for Relief for RI-17,Rev 1 and RI-25,Rev 0.Request for Relief RI-13,Rev 2 Involving Snubber Testing & Is Being Evaluated in Separate Report ML20204C9751999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Cooper Nuclear Station ML20199E6751999-01-14014 January 1999 Monthly Operating Rept for Dec 1998 for Cooper Nuclear Station ML20195B9191998-12-31031 December 1998 1998 NPPD Annual Rept. with ML20196J9641998-12-0707 December 1998 Safety Evaluation Accepting Licensee Third 10-yr Interval Inservice Insp Plan Request for Relief RI-27,rev 1 ML20198D2471998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Cooper Nuclear Station.With ML20196A2861998-11-23023 November 1998 SER Re Core Spray Piping Weld for Cooper Nuclear Station. Staff Concluded That Operation During Cycle 19 Acceptable with Indication re-examined During RFO 18 ML20196A5241998-11-23023 November 1998 Safety Evaluation Accepting Proposed Alternative to Use UT Techniques Qualified to Objectives of App Viil as Implemented by PDI Program in Performing RPV Shell Weld & Shell to Flange Weld Examinations ML20196A5061998-11-23023 November 1998 Safety Evaluation Re Flaw Indication Found in Main Steam Nozzle to Shell Weld NVE-BD-N3A at Cns.Plant Can Be Safely Operated for at Least One Fuel Cycle with Indication in as-is Condition ML20196C4241998-11-20020 November 1998 Rev 1 to Cooper Nuclear Station COLR Cycle 19 ML20195H1761998-11-17017 November 1998 SER Authorizing Proposed Alternative in Relief Requests RV-06,RV-07,RV-09,RV-11,RV-12 & RV-15 Pursuant to 10CFR50.55a(a)(3)(ii).RV-08 Granted Pursuant to 10CFR50.55a(f)(6)(i) & RV-13 Acceptable Under OM-10 ML20195F8601998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Cooper Nuclear Station.With ML20155D9961998-10-31031 October 1998 Rev 0 to GE-NE-B13-01980-24, Fracture Mechanics Evaluation on Observed Indication at N3A Steam Outlet Nozzle to Shell Weld at Cooper Nuclear Station ML20154Q5661998-10-0505 October 1998 Rev 0 to CNS COLR Cycle 19 ML20154L5381998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Cooper Nuclear Station.With ML20151Z6141998-09-16016 September 1998 SER Accepting Util Responses to NRC Bulletin 95-002 for Cooper Nuclear Station ML20154F7931998-08-31031 August 1998 Rev 0 to J11-03354-10, Supplemental Reload Licensing Rept for CNS Reload 18,Cycle 19 ML20153B1101998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Cooper Nuclear Station ML20237E7771998-08-20020 August 1998 Revised COLR Cycle 18 for Cooper Nuclear Station ML20151Q1211998-08-14014 August 1998 Rev 0 to Control of Hazard Barriers ML20237C0591998-07-31031 July 1998 Monthly Operating Rept for Jul 1998 for Cooper Nuclear Station ML20236R9131998-07-20020 July 1998 SER Accepting Rev 13 to Quality Assurance Program for Operation Policy Document for Plant ML20236P2971998-07-0707 July 1998 Rev 2 to NPPD CNS Strategy for Achieving Engineering Excellence ML20236R0931998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Cooper Nuclear Station ML20249A7701998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Cooper Nuclear Station ML20247G6131998-05-13013 May 1998 Part 21 Rept Re Defect Contained in Automatic Switch Co, Solenoid Valves,Purchased Under Purchase Order (Po) 970161. Caused by Presence of Brass Strands.Replaced Defective Valves ML20247G0951998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Cooper Nuclear Station ML20237B6861998-04-24024 April 1998 Vols I & II to CNS 1998 Biennial Emergency Exercise Scenario, Scheduled for 980609 ML20217A1531998-04-16016 April 1998 Closure to Interim Part 21 Rept Submitted to NRC on 970929. New Date Established for Completion of Level I & 2 Setpoint Project Committed to in .Final Approval of Setpoint Calculations Will Be Completed by 980531 ML20216G5331998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Cooper Nuclear Station 1999-09-30
[Table view] |
Text
{{#Wiki_filter:- - _ _ - - - . _ _ _ - _ _ _ _ _ _ _ _ - _ _ _ _
4
.,., ENCLOSURE 1
./,p m\ UNITED sT ATEs
! c f ?g NUCLEAR REGULATORY COMMISSION
$ . "'/ j_ W ASHINGTON, D. C. 20555 jl SAFETY EVALUATION ON COOPER NUCLEAR STATION COMPLIANCE WITH ATWS RULE 10CFR50.62 RELATING TO ALTERNATE R00 INJECTION (ARI) AND RECIRCULATING PUMPS TRIP (RPT) SYSTEMS DOCKET NO. 50-298
1.0 INTRODUCTION
On July 26, 1984, the Code of Federal Regulations (CFR) was amended to include Section 10CFR50.62, " Requirements for Reduction of Risk from AnticipatedTransientsWithoutScram(ATWS)EventsforLight-Water-Cooled Nuclear Power Plants" (known as the "ATWS Rule"). An ATWS is an expected operational transient (such as loss of feedwater, loss of condenser vacuum, or loss of offsite power) which is accompanied by a failure of the reactor trip system (RTS) to shutdown the reactor. The ATWS Rule requires specific improvements in the design and operation of commercial nuclear power facilities to reduce the likelihood of failure to shutdown the reactor following anticipated transients, and to mitigate the consequences of an ATWS event.
For each boiling water reactor, three systems are required to mitigate the consequences of an ATWS event.
- 1. It must have an alternate rod injection (ARI) system that is diverse (from the reactor trip system) from sensor output to the final actuation devices. The ARI system must have redundant scram air header exhaust valves. The ARI system must be designed to perform its function in a reliable manner and be independent (from the existing reactor trip system) from sensor output to the final actuation device. l 8709300341 870923 PDR ADDCK0500,g8 I
h
-.2 -
y
- 2. It must have a standby liquid control system (SLCS) with a minimum flow capacity and boron content equivalent in control capacity to 86 gallons per. minute of 13 weight percent sodium pentaborate solution.
The SCLS and its injection location must be designed to perform its function in a reliable manner.
- 3. It must have equipment to trip the reactor coolant recirculating pumps automatically under conditions indicative of an ATWS. This
. equipment must be designed to perform its function in a reliable manner.
By letters dated October 14,1985 (Ref.1) and April 8, August 4,1987 (Ref. 2 & 3), Nebraska Public Power District '(the Licensee) provided information to comply with the ATWS Rule. This safety evaluation report addressestheARIsystem(Item 1)andtheATWS/RPTsystem(Item 3). The SLCS (Item 2) will be addressed in a separate document.
2.0 REVIEW CRITERIA i
The systems and equipment required by 10CFR50.62 do not have to meet all of the stringent requirements nonnally applied to safety-related equipment. However, this equipment is part of the broader class of structures, systems, and components important to safety defined in the introduction to 10CFR50, Appendix A General Design Criteria (GDC).
GDC-1 requires that " structures, systems, and components important to safety shall be designed, fabricated, erected, and tested to quality standards commensurate with the importance of the safety functions to be perfonned." Generic Letter 85-06 " Quality Assurance Guidance for ATWS Equipment that is not Safety Related" details the quality assurance that must be applied to this equipment.
In general, the equipment to be installed in accordance with the ATWS Rule is required to be diverse from the existing RTS, and must be testable 1
i t
w____--__ ._
o-at power. This equipment is intended to provide needed diversity (where only minimal diversity currently exists in the RTS) to reduce the potential for comon mode failures that could result in an ATWS leading to unacceptable plant conditions.
The criteria used in evaluating the licensee's submittal include 10CFR50.62 " Rule Considerations Regarding Systems and Equipment Criteria" published in Federal Register Volume 49, No.124 dated June 26, 1984 and Generic Letter 85-06 " Quality Assurance Guidance for ATWS Equipment that is not Safety Related."
3.0 EVALUATION OF ARI SYSTEM The licensee is participating in the BWR Owners' Group ATWS implementation alternatives program. The BWR Owners' Group submitted a licensing topical report NEDE-31096-P " Anticipated Transients Without Scram, Response to NRC ATWS Rule 10CFR50.62" (Ref. 4) for staff review. The staff accepted the licensing topical report NEDE-31096-P in Reference 5. Reference 2 summarizes the licensee's compliance with the ATWS Rule. The staff's evaluation is addressed in the following section.
3.1 ARI SYSTEM FUNCTION TIME The licensee stated that the size of the ARI solenoid valves has been selected, based on actual plant configuration, to allow the insertion of all control rods to begin within 15 seconds of initiation of the ATWS signal. All control rods will reach their full-in position within 25 seconds of the ARI initiation signal. This will be verified by tests following installation of the ARI system. The staff finds this acceptable.
.. r
. m r
3.2 SAFETY-RELATED REQUIREMEN E
~The ATWS Rule does not require the ARI system to be safety grade, but the
~
implementation must be such that the existing protection system continues to meet all applicable safety related criteria.
' The licensee stated that the Cooper ARI will utilize the existing sensors from the Recirculation Pump Trip (RPT) system which are independent from the existing reactor protection system. The ARI will maintain the present separation criteria' that exists between safety-related systems and the RPT
~
system.- The ARI logic will not violate the existing separation criteria of the Reactor Protection System (RPS)*. Since the ARI does not interface with any safety-related system, isolation devices will not be used. The staff finds this acceptable. (*RPSinlicensee'ste'rminologyissameas RTS in ATWS Rule) 3.3 REDUNDANCY The licensee stated that the ARI system has redundant valves at the scram air header. The'ARI system performs a function redundant to the backup scram system and the RPS. The staff finds this acceptable.
3.4 DIVERSITY FROM THE EXISTING RTS The licensee stated that the ARI system controls, instrumentation, and solenoid valves are de powered with the solenoid valves energized to open.
The ARI solenoid valves are separated from the backup scram valves. All instrument channel components including the sensors will be diverse from the existing RTS components. The staff finds this acceptable.
3.5 - ELECTRICAL INDEPENDENCE FROM THE EXISTING RTS The licensee stated that electrical independence from the RPS will be provided from sensor output to final actuation devices (ARI solenoid
~
e valves). The ARI actuation logic is separated from the RTS logic. The staff finds this acceptable.
3.6 PHYSICAL SEPARATION FROM THE EXISTING RTS,_
The licensee stated that the ARI system is physically separated from the RPS by the following means:
- 1. ARI initiation signals are transmitted from different sensing instrumentation than that of RPS.
- 2. - ARI wiring and cables will be routed in separate conduits from either RPS Division I or Division 11 wiring.
- 3. ARI instrumentation and control in the Control Room will be physically separated from their RPS counterparts.
- 4. The ARI actuating solenoid valves on the scram air header are different than those used by the RPS.
The staff finds this acceptable.
3.7 ENVIRONMENTAL QUALIFICATION Th'e licensee stated that all hardware required for the ARI to function !
properly will be environmentally qualified to conditions that occur during an anticipated operational occurrence. Qualification of new equipment will be to temperature, pressure, humidity, and radiation levels associated with an ATWS event up to the time the ARI function is complete. The staff finds this acceptable.
3.8 QUALITY ASSURANCE The licensee has committed to comply with Generic Letter 85-06, " Quality Assurance Guidance for ATWS Equipment that is not Safety Related." The ,
staff finds this acceptable. !
4 3.9 SAFETY-RELATED p0WER SUPPLY The licensee stated that the ARI will use'nondivisional de power that is independent from RPS power. A noninterruptible power source will be provided to allow the ARI to perform its intended function during any loss of offsite power event. The staff finds this acceptable.
3.10 TESTABILITY AT POWER The licensee stated that the ARI system will be testable up to, and including, the final actuating devices while the reactor is at power. A 3-way ARI solenoid will be installed in the scram air header supply as close as possible to the Hydraulic Control Units (HCUs) to block the air supply pressure leading to the HCU and SDV and to depressurize this portion of the air header upon ARI initiation. A separate solenoid valve will be installed downstream of the vent portion of the 3-way valve to prevent inadvertent header depressurization. A 2-way solenoid ARI valve will be installed in parallel with the 3-way solenoid valve to allow continued air supply to the header during plant operation surveillance testing of the 3-way solenoid valve. The other three ARI air header vent paths contain an inboard and outboard ARI solenoid valve in series. During surveillance testing, all inboard and outboard valve groupings will be tested I separately. The ARI system utilizes no bypass features for testing. The staff finds this acceptable. ,
1 I
3.11 INADVERTENT ACTION 1 The licensee stated that the ARI design will utilize coincident logic.
Both channels must be tripped in order to initiate the mitigative actions. The ARI actuation setpoints will not challenge scram setpoints. The staff finds this acceptable.
l l
l i
(' I
_ __ I
j 3.12 MANUAL INITIATION The licensee stated that the manual initiation capability will be provided.
The staff finds this acceptable.
3.13.INFORMATION READ 0UT The licensee stated that all ARI solenoid valves will provide an open/
closed position indication in the Control Room. Indication will a' Iso ce !
provided to indicate when the system is in test or out of service. Two annunciators will be provided for ARI initiation. They are:
- 1. ARI Channel 1 or 2 Initiated
- 2. ARI Initiated (either manual or automatic)
The staff finds this acceptable.
3.14 COMPLETION OF PROTECTIVE ACTION ONCE IT IS INITIATED j The licensee stated that the ARI design will have a seal-in feature for ;
30 to 35 seconds to ensure the completion of protective action once it is f
initiated. After initial conditions return to nortral, deliberate operator action is required to reset the safety system logic to normal. The staff
]
finds this acceptable. -{
3.15 CONCLUSION ON ARI SYSTEM As stated in Reference 4, the staff SER on GE Topical Report NEDE-31096-P, l
the staff does not' intend to repeat its review of the design information !
described in the GE Topical Report and found acceptable when the report appears as a reference in a specific license application. Reference 2 summarizes the licensee's compliance with the ATMS Rule. The staff finds I
l i
)
1
d 8
that the Cooper Station AR1 design is in general compliance with the ATWS Rule,10CFR50.62 paragraph (C)(3).
3.16 ARI TECHNICAL SPECIFICATIONS The equipment required by the ATWS Rule to reduce the risk associated.with an ATWS event must be desigr.ed to perform its function in a reliable manner. A method acceptable to the staff for demonstrating that the equipment satisfies the reliability requirements of the ATWS Rule is to provide ARI Technical Specifications which include operability and surveillance requirements. The staff will provide guidance on a generic basis regarding Technical Specification requirements for ARI at~ a later date.
4.0 EVALUATION OF A_TWS/ PPT SYSTEM By. letter dated April 8,1987, the licensee stated that the present RPT system at Cooper will be upgraded to the "Monticello" design which is described in NEDE-31096-P. The licensee will install redundant trip coils on the field breakers of the recirculation system motor-generator sets and will use a redundant two-out-of-two initiation logic.
As stated in Reference 4, the staff SER on GE Topical Report NEDE-31096-P, the Monticello design is an acceptable reference ATWS/RPT design. The staff concludes that the Cooper's ATWS/RPT design is in compliance with the ATWS Rule,10CFR50.62 paragraph (C)(5), and therefore is acceptable.
,t .
~ ~
4,.
5.0 REFERENCE (1) Nebraska Public Power District letter J. M. Pilant to
'H. L. Thompson, Jr. , dated October 14, 1985.
(2) Nebraska Public Power District letter G. A. Trevors to NRC Docunent Control Desk, dated April 8,1987.
(3)' Nebraska Public Power district telex copy from G. Smith to.NRC Project Manager W. Long, dated August 4,1987.
(4) GE Topical Report NEDE-31096-P " Anticipated Transients Without Scram;-Response to NRC ATWS Rule 10CFR50.62,"
dated December, 1985.
1 (5) Staff SEP on GE Topical Report NEDE-31096-P. Letter from Gus Lainas (NRC) to Terry A. Pickens (BWR Owners' Group Chairman), dated October 21, 1986.
1 i
j l
_ _ _ _ _ _ _ _ I}}