Other: ML20082E320, ML20093M745, ML20093M749, ML20094A277, ML20100C247, ML20101C284, ML20116G049, ML20198A027, ML20204E694, ML20204E706, ML20205B056, ML20205B071, ML20214R856, ML20214R871, ML20235Z262, ML20236H257, ML20262E589, ML20262E593, ML20262E597, ML20262E601, ML20262E606, ML20262E611, ML20262E615, ML20262E619, ML20262E624, ML20262E629, ML20266F484, ML20266F489, ML20266F494, ML20266F498
|
MONTHYEARML20266F4841983-04-28028 April 1983 Ft St Vrain 2500 Kva Xfmr Foundations & Details. Sheet 1 of 2.No Rev Date Project stage: Other ML20266F4891983-05-0202 May 1983 Ft St Vrain 2500 Kva Xfmr Foundations & Details. Sheet 2 of 2 Project stage: Other ML20266F4981983-06-17017 June 1983 480V Transformer Fire Protection Sys Project stage: Other ML20082E3201983-11-0909 November 1983 Responds to Notice of Deviation Noted in IE Insp on 830801-31.Corrective Actions:Concrete Samples Taken at End of Concrete Pump Discharge Line,Addl Lighting Installed & Number of Concrete Vibrators Increased Project stage: Other ML20262E6241984-01-0404 January 1984 Building 10 Walk-Over Structure Roof Plan & Details, as-built Project stage: Other ML20262E6291984-01-0404 January 1984 Building 10 Walkover Structure Steel Elevation, as-built Project stage: Other ML20262E6191984-01-0404 January 1984 Building 10 Walk-Thru Structure Floor Plans, as-built Project stage: Other ML20262E6151984-01-0404 January 1984 Building 10 Steel Framing Plans, as-built Project stage: Other ML20262E6111984-01-0404 January 1984 Building 10 Concrete Sections & Details, as-built.Sheet 3 Project stage: Other ML20262E5971984-01-0505 January 1984 Building 10 Architectural Elevations & Details, as-built Project stage: Other ML20262E6011984-01-0505 January 1984 Building 10 Concrete Floor Plans, as-built Project stage: Other ML20093M7491984-01-22022 January 1984 Rept of Changes,Test & Experiments Not Requiring Prior Commission Approval Per 10CFR50.59(a) for 840101-22 Project stage: Other ML20093M7451984-07-20020 July 1984 Forwards Rept of Changes,Tests & Experiments Not Requiring Prior Commission Approval for 840101-22.Anniversary Date of Rept Changed to Correspond W/Submittal of Annual Update to Fsar.Future Annual Repts Will Cover Jan 23 - Jan 22 Project stage: Other ML20094A2771984-07-25025 July 1984 Responds to NRC 840625 Concerns Re Bldg 10 Const.Concept of Bldg 10 Finalized to Relieve Crowding Conditions & to Accommodate Equipment Replacements Being Planned.Bldg 10 Constitutes Mod Not Requiring Amend to OL Project stage: Other ML20262E5931984-09-21021 September 1984 Building 10 Site Plan & Caisson Details Project stage: Other ML20262E6061984-09-27027 September 1984 Building 10 Concrete Sections & Details, as-built.Sheet 1 Project stage: Other ML20101C2841984-11-29029 November 1984 Forwards Hl Brey for Redistribution Due to Error in Ltr Date.Correct Date Should Be 831101 Project stage: Other ML20100C2471985-03-11011 March 1985 Advises That Attachments A,B,C & D Re Diesel Generator Loading,Battery Sizing,Listing of Encl Drawings & Partial one-line Diagram Forwarded to J Miller,Per 850227 Telcon Request Project stage: Other ML20116G0491985-04-12012 April 1985 Informs That Listed Electrical Sys Drawings Sent to J Miller of NRR for Review,Per 840410 & 12 Requests.Copy of Logic Diagrams Being Prepared by I Ahmed Requested Project stage: Other ML20133A4141985-07-23023 July 1985 Forwards Request for Addl Info Re Const of Bldg 10 & Associated Walkover Structure,Including Engineering Drawings,Walkover Structure Layout & Spatial Relationship W/Surrounding Bldgs Project stage: RAI ML20262E5891985-08-0808 August 1985 Ft St Vrain Plot Plan. Sheet 1 of 1.Drawing Consists of Two Aperture Cards Project stage: Other ML20137C4011985-11-21021 November 1985 Requests Addl Info Re Bldg 10,including CN-1255 & CN-1332 for Sys 92 & CN-1294 for Sys 92/45.For Each Cn,Safety Evaluation & Design Criteria & Analysis Required.Info Requested within 30 Days of Ltr Receipt Project stage: Approval ML20138P0791985-12-17017 December 1985 Forwards Legible Copy of Safety Evaluation Design Criteria & Design Analysis for Change Notices CN-1255,CN-1332, CN-1294 & CN-1391,per NRC 851121 Request for Addl Info. Future Changes to CN-1391 Cover nonsafety-related Battery Project stage: Request ML20205B0711985-12-31031 December 1985 Rev 0 to Evaluation of Structure-Soil-Structure Interaction Effect Between Bldg 10/Walkover Structure & Main Plant Project stage: Other ML20153H0731986-02-19019 February 1986 Safety Evaluation Supporting Bldg 10 & Walkover Structure Design,Per FSAR Requirements for Category 1 Bldgs.Lack of Clearance Between Structures Should Be Addressed by Util Project stage: Approval ML20153H0571986-02-19019 February 1986 Forwards Safety Evaluation Re 850828 Submittal Concerning Bldg 10 & Walkover Structure.Designs Acceptable,Per FSAR Requirements for Category 1 Bldgs.Confirmatory Analysis, Addressing Lack of Clearance Between Structures,Requested Project stage: Approval ML20266F4941986-03-15015 March 1986 Bus Duct Layout and Location of Bus Duct Supports Project stage: Other ML20204A2161986-05-0101 May 1986 Forwards Request for Addl Info Re Bldg 10 Electrical Mods, Including Confirmation That All Class 1E Power,Control & Instrumentation Cables in Bldg 10 Qualified for Environ of 120 F Project stage: RAI ML20197F6541986-05-0707 May 1986 Summary of 860423-24 Meetings W/Util,Ga Technologies & S&W at Site Re Fuel Block Cracking,Bldg 10 Const,Seismic Instrumentation,Pcrv Tendons & Integrated Leak Rate Testing. Attendance List & Viewgraphs Encl Project stage: Meeting ML20198A0271986-05-12012 May 1986 Responds to NRC 860219 Questions Re Bldg 10 & Walkover Structure.Walkover Structure & Bldg 10 Designed Such That Structural Elements Will Not Impact on Adjacent Bldgs During Seismic Event Project stage: Other ML20204E7061986-06-19019 June 1986 Forwards Addl Info Re Bldg 10 Electrical Mods & Essential Power Bus Upgrades,Per NRC 860501 Request Project stage: Other ML20199J0261986-06-25025 June 1986 Requests Addl Info Re Structural Evaluation of Bldg 10 & Walkover Structure,Discussed at 860423 & 24 Meetings.Ltr Inadequately Addressed NRC Concerns Project stage: Meeting ML20204E6941986-07-25025 July 1986 Forwards Resubmittal of Addl Info Re Bldg 10 Electrical Mods & Essential Power Bus Upgrades to Include Attachments Not Received by NRC Project stage: Other ML20205B0561986-07-28028 July 1986 Forwards Addl Info Re Structural Analysis of Bldg 10 & Walkover Structure,Per 860625 Request,Including Seismic Model Used for Bldg & Rev 0 to SAD-481, Evaluation of Structure-Soil-Structure.. Project stage: Other ML20214R8561987-03-0606 March 1987 Forwards EGG-NTA-7607, Technical Evaluation Rept Evaluation of Bldg 10 Electrical Mods Fort St Vrain Nuclear Generating Station, Informal Rept Project stage: Other ML20205R1561987-03-31031 March 1987 Forwards Request for Addl Info Re Seismic Design of Bldg 10, for Nrc/Bnl Review.Site Visit to Review Response to Encl Questions,To Insp Bldg 10 & to Audit Supporting Structural Matl Recommended within 60 Days of Ltr Receipt Project stage: RAI ML20214R8711987-03-31031 March 1987 Technical Evaluation Rept Evaluation of Bldg 10 Electrical Mods Fort St Vrain Nuclear Generating Station, Informal Rept Project stage: Other ML20215F9631987-05-29029 May 1987 Forwards Response to NRC 870331 Request for Addl Info Re Bldg 10,per 870527 Telcon.Supporting Matl for Bldg 10 Structural Analyses Available in Util Ofc for Review Project stage: Request ML20235Z2621987-07-0808 July 1987 Requests Addl Info from Util Re Bldg 10 Seismic Design, Including Descriptive Matl for PILAY2 Computer Code & Sketches or Drawings Showing Caisson/Slab/Wall Configurations Project stage: Other ML20236H2571987-07-28028 July 1987 Requests Addl Info Re Seismic Design of Bldg 10,based on Util 870529 Submittal.Response Requested within 45 Days of Ltr Date Project stage: Other ML20234D8091987-09-0909 September 1987 Responds to NRC 870728 Request for Addl Info Re Bldg 10, Including Descriptive Matl for PILAY2 Computer Code & Sketches or Drawings of Caisson/Slab/Wall Configurations. Sketch of Configuration & Wall Stiffness Calculation Encl Project stage: Request ML20150C4541988-03-10010 March 1988 Safety Evaluation Concluding That Seismic Analysis Methods for Bldg 10 & Walkover Structure Conservative.Gaps Provided Adequate to Accommodate Relative Motions Which Occur Between Subj Structures & Walkover Structure & Turbine Bldg Project stage: Approval ML20150C4441988-03-10010 March 1988 Forwards Safety Evaluation Re Seismic Analysis of Bldg 10 & Walkover Structure.Seismic Analysis Methods Used Conservative Relative to FSAR & Acceptable Project stage: Approval 1985-07-23
[Table View] |
Text
_ _.
March 31, 1987 Docket No. 50-267 Mr. R. O. Williams, Jr.
Vice President, Nuclear Operations Public Service Company of Colorado Post Office Box 840 Denver, Colorado 80201-0840
Dear Mr. Williams:
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION ON FORT ST. VRAIN - BUILDING 10 The staff and it's consultant, Brookhaven National Laboratory, are continuing their review of your submittals concerning the seismic design of Building 10 at Fort St. Vrain. We request that you provide certain additional information as indicated in the enclosure. This information is requested to aid in the completion of this review.
To facilitate a timely resolution of this issue, we recommend that you prepare the responses to these questions, and make the supporting material for all Building 10 structural analyses available for audit. The staff and its consultants would then meet with you at the site to review the responses, inspect Building 10 and audit the supporting material. This site visit should be conducted no later than 60 days from the date of this letter.
The information requested in this letter affects fewer than 10 respondents; therefore, OMB clearance is not required under P.L.96-511.
Sincerely, original signed by Kenneth L. Heitner, Project Manager Standardization and Special Projects Directorate Division of PWR Licensing-B-Office of Nuclear Reactor Regulation
Enclosure:
As stated cc w/ enclosure:
See next page 8704060242 870331 PDR ADOCK 05000267 DISTRIBUTION:
G PDR
- Docket:F11eg" PNoonan NRC PDR'
KHeitner Local PDR 0 Lynch PBSS Reading HBerkow PBSS BSS PBSh ah KHeitner:ac Linch H8e 03/3l /87 03/3[/87 03h\\/87 03 8) /87
kBKfCp E(
UNITED STATES NUCLEAR REGULATORY COMMISSION 4
"[
WASHINGTON, D. C. 20555
%,..... /
March 31, 1987 Docket No. 50-267 Mr. R. O. Williams, Jr.
Vice President, Nuclear Operations Public Service Company of Colorado Post Office Box 840 Denver, Colorado 80201-0840
Dear Mr. Williams:
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION ON FORT ST. VRAIN - BUILDING 10 The staff and it's consultant, Brookhaven National Laboratory, are continuing their review of your submittals concerning the seismic design of Building 10 at Fort St. Vrain. We request that you provide certain additional infonnation as indicated in the enclosure. This information is requested to aid in the completion of this review.
l To facilitate a timely resolution of this issue, we recommend that you prepare the responses to these questions, and make the supporting material for all Building 10 structural analyses available for audit. The staff and its consultants would then meet with you at the site to review the responses, inspect Building 10 and audit the supporting material. This site visit should be conducted no later than 60 days from the date of this letter.
The information requested in this letter affects fewer than 10 respondents; therefore, OMB clearance is not required under P.L.96-511.
Sincerely, Kenneth L. Heitner, Project Manager Standardization and Special Projects Directorate Division of PWR Licensing-B Office of Nuclear Reactor Regulation
Enclosure:
1 As stated
{
1 cc w/ enclosure:
See next page
1 e
f
'l Mr. R. O. Williams Public Service Company of Colorado Fort St. Vrain cc:
Mr. D. W. Warembcurg, Manager Albert J. Hazle, Director Nuclear Engineering Division Radiation Control Division Public Service Company Department of Health of Colorado 4210 East lith Avenue P. O. Box 840 Denver, Colorado 80220 Denver, Colorado 802C1 Mr. David Alberstein, 14/159A Mr. R. O. Williams, Acting Manager GA Technologies, Inc.
Nuclear Production Division Post Office Box 85608 Public Service Company of Colorado San Diego, California 92138 16805 Weld County Road 19-1/2 Platteville, Colorado 80651 Mr. H. L. Brey, Manager Nuclear Licensing and Fuel Division Mr. P. F. Tomlinson, Manager Public Service Company of Colorado Quality Assurance Division P. O. Box 840 Public Service Company of Colorado Denver, Colorado 80201 16805 Weld County Road 19-1/2 Platteville, Colorado 80651 Senior Resident Inspector U.S. Nuclear Regulatory Commission Mr. R. F. Walker P. 0. Box 840 Public Service Company of Colorado Platteville, Colorado 80651 Post Office Box 840 Denver, Colorado 80201-0840 Kelley, Stansfield & 0'Donnell Public Service Company Building Commitment Control Program Room 900 Coordinator 550 15th Street Public Service Company of Colorado Denver, Colorado 80202 2420 W. 26th Ave. Suite 100-D Denver, Colorado 80211 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 l
Arlington, Texas 76011 Chaiman, Board of County Commissioners of Weld County, Colorado Greeley, Colorado 80631 Regional Representative Radiation Programs Environmental Protection Agency 1 Denver Place 999 18th Street, Suite 1300 Denver, Colorado 80202-2413
.4 I
Enclosure Request For Additional Information Fort St. Vrain Building 10 1.
In the analysis of the Building 10 caissons, two foundation moduli valaes were considered.
It should be demonstrated that these two cases bound the actual condition, where a stiff layer is sandwiched between two soft layers. Consideration should be given to both the equivalent interaction springs and dampers.
2.
The rocking interaction parameters were developed based on the assumption that the foundation is rigid in flexure relative to the axial stiffness of the caisson. Provide information so that the validity of this assumption may be reviewed.
3.
The seismic input ground motion used for Building 10 and the turbine building are different.
Information describing and justifying the use of two different inputs should be provided.
4.
The license's submittal includes spectra labeled " Isolated" and
" Coupled." It is not clear whether the " coupled" spectra are the spectra of the turbine building basemat motion, or spectra of the response of Building 10 to an input motion due to the turbine building basemat motion.
If the first is the case, then information should be provided demonstrating that this solution bounds the structure / soil / structure interaction situation.
If the latter is true, information describing the model used and the input motion should be provided.
5.
The basis for the displacements of the turbine building and Building 10 used to determine the relative building displacements should be provided.
i l