ML20202J223

From kanterella
Jump to navigation Jump to search
Summary of 860204 Meeting W/Util,Sargent & Lundy & Carboline Co in Bethesda,Md Re Mods to Containment Liner Coating Sys. Util Will Submit Test Repts Supporting Conclusion That Sys Meets ANSI Stds.W/O Stated Encls
ML20202J223
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 04/04/1986
From: Stevens J
Office of Nuclear Reactor Regulation
To:
Office of Nuclear Reactor Regulation
References
NUDOCS 8604150587
Download: ML20202J223 (2)


Text

.

f APR 4y Docket Nos.:

STN 50-456 and STN 50-457 APPLICANT: Comonwealth Edison Company FACILITY:

Braidwood Station, Units 1 and 2

SUBJECT:

MEETING

SUMMARY

- CONTAINMENT LINER C0ATING SYSTEM On February 4,1986, a meeting was held in Bethesda, Maryland between members of the NRC staff, Commonwealth Edison Company (the applicant),

Sargent and I. undy (the architect / engineer), and Carboline Company (paint coatings manufacturer). A list of the meeting attendees is given in.

The viewgraphs used during the presentation are given in.

~

The applicant, together with its architect / engineer and paint coatings manufacturer, gave a presentation covering modifications made to the safety-related containment liner coating system at Braidwood Station, Units 1 and 2.

During the presentation, Mr. J. Montle (Carboline Company) indicated that the footnote in the paint manufacturer's recomendations-for recoating operations should be interpreted as follows:

In order to maintain a 3 mils dry film thickness of the final paint coating, as much as 50% thinning of the paint may be necessary; use of lesser thinning ratios would not constitute a deviation from the paint manufacturer's recomendations as long as the final coating had a dry film thickness of 3 mils. Mr. J. Montle made a comitment to revise l

this footnote in order to incorporate the clarification as stated i

above. The staff requested that the applicant submit four test reports l

which were used to support their conclusion that the coating system as installed satisfies the ANSI 101.2 and ANSI 5.12 standards, including

}

the DBA testing requirement.

((For b

J.A. Stevens, Project Manager PWR Project Directorate No. 5 Division of PWR licensing-A 4

Enclusures:

1.

List of Meeting Attendees 2.

Viewgraphs Used During Presentation cc:

J. Wing, NRR W. Little, RIII PM:PD#5 DIR:PD#5 JStevens:js V. Noonan

'4/ 4 /85 4/

/86 0FFICIAI. RECORD COPY 8604150587 860404 PDR ADOCK 05000456 A

PDR 4

p+

~

~

i -

Meeting Suninary Distribution

^

er Central File NRC Participants

. g Local'PDR V. Nerses PD#5 Reading File R. Ballard J. Partlow (Emergency Preparedness only)

S. Chan V.-Noonan D. Jeng Project Manager V. Nerses D. Ruscitto OELD A. Cerne E. Jordan B. Grimes ACRS (10)

M. Rushbrook cc: Licensee and Plant Service List b

m m

m.

m'

.