ML20198H642

From kanterella
Jump to navigation Jump to search
SALP Repts 50-454/86-01 & 50-455/86-01 for May 1984 - Oct 1985
ML20198H642
Person / Time
Site: Byron  Constellation icon.png
Issue date: 01/27/1986
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20198H597 List:
References
50-454-86-01, 50-454-86-1, 50-455-86-01, 50-455-86-1, NUDOCS 8601310070
Download: ML20198H642 (52)


See also: IR 05000454/1986001

Text

SALP 5

SALP BOARD REPORT

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

SYSTEMATIC ASSESSMENT OF LICENSEE PERFORMANCE

50-454/86001; 50-455/86001

Inspection Report Nos.

Commonwealth Edison Company

Name of licensee

Byron Nuclear Station, Units 1 & 2

Name of Facility

May 1, 1984 through October 31, 1985

Assessment Period

,

l

0601310070

PDH 060127ADOCK 05000404

PDR

o

I. INTRODUCTION

The Systematic Assessment of Licensee Performance (SALP) program is an

integrated NRC staff effort to collect available observations and data on

a periodic basis and to evaluate licensee performance based upon this

information. The SALP program is supplemental to normal regulatory

processes used to ensure compliance to NRC rules and regulations. The

SALP program is intended to be sufficiently diagnostic to provide a

rational basis for allocating NRC resources and to provide meaningful

guidance to the licensee's management to promote quality and safety of

plant construction and operation.

An NRC SALP Board, composed of staff members listed below, met on

December 11, 1985, to review the collection of performance observations

and data to assess licensee performance in accordance with the guidance

in NRC Manual Chapter 0516, " Systematic Assessment of Licensee Performance."

A summary of the guidance and evaluation criteria is provided in Section II

of this report.

This report is the SALP Board's assessment of the licensee's safety

performance at Byron Nuclear Station, Units 1 and 2, for the period

May 1, 1984 through October 31, 1985. Licensee activities over the

assessment period include Unit 1 preoperational, startup, and operational

phases and also Unit 2 construction and preoperational phases. For the

purposes of evaluation, the functional areas fall into three general

categories. The first category addresses Unit 1 as an operating facility

and covers the period of October 31, 1984 through October 31, 1985.

Functional areas A., and C. through E. in Section III of this report

identify the areas evaluated in this category. The second category

addresses Unit 1 and Unit 2 preoperational and startup functional

areas which are common to both Unit 1 and Unit 2 and covers the entire

assessment period. Functional areas B. and F. through K. in Section III

of this report identify these areas. Unit 1 and Unit 2 functional areas

for construction are addressed in the third category identified by

functional areas L. through Q. in.Section III of this report. The

evaluations of these areas also spans the entire assessment period.

SALP Board for Byron Station, Units 1 and 2:

Name Title

C. E. Norelius Director, DRP

J. A. Hind Director, DRSS

L. A. Reyes Branch Chief, DRS '

W. D. Shafer Branch Chief, DRSS

W. L. Axelson Branch Chief, DRSS

R. F. Warnick Branch Chief, DRP  !

W. L. Forney Section Chief, DRP l

M. A. Ring Section Chief, DRS  !

L. R. Greger Section Chief, DRSS

-

M. Schumacher Section Chief, DRSS

M. P. Phillips Section Chief, DRSS

I L. N. 01shan Project Manager, NRR

J. M. Hinds Jr. Senior Resident Inspector, DRP

P. G. Brochman Resident Inspector, DRP

R. M. Lerch Project Inspector, DRP

J. L. Belanger Reactor Inspector, DRSS

C. A. VanDenburgh Reactor Inspector, DRS

N. A. Nicholson Reactor Inspector, DRSS

T. J. Ploski Reactor Inspector, DRSS

K. R. Ridgway Reactor Inspector, DRP

!

!

!

!

!

!

!

,

!

i

i

2

1

L

- . _ - _ . _ _ _ - . . - - - _ - _ - - _ _ - . _. _

- - - -

L

II. CRITERIA

The licensee's performance is assessed in selected functional areas,

depending upon whether the facility is in a construction, preoperational,

or operating phase. Functional areas normally represent areas significant

to nuclear safety and the environment. Some functional areas may not be

assessed because of little or no licensee activities, or lack of meaningful

observations. Special areas may be added to highlight significant

observations.

One or more of the following evaluation criteria were used to assess each

functional area.

1. Management involvement and control in assuring quality

2. Approach to the resolution of technical issues from a safety

standpoint

3. Responsiveness to NRC initiatives

l

4. Enforcement history

1

5. Operational and Construction events (including response to, analyses

of, and corrective actions for) '

6. Staffing (including management)

7. Training effectiveness and qualification

However, the SALP Board is not limited to these criteria and others may

have been used where appropriate.

I

Based upon the SALP Board assessment, each functional area evaluated is

'

classified into one of three performance categories. The definitions of

these performance categories are:

Category 1: Reduced NRC attention may be appropriate. Licensee management

i attention and involvement are aggressive and oriented toward nuclear safety;

licensee resources are ample and effectively used so that a high level of

performance with respect to operational safety and construction quality is l

being achieved.

Category 2: NRC attention should be maintained at normal levels. Licensee

management attention and involvement are evident and are concerned with

nuclear safety; licensee resources are adequate and are reasonably l

l effective such that satisfactory performance with respect to operational l

l safety and construction quality is being achieved.

i

Category 3: Both NRC and licensee attention should be increased.

Licensee management attention or involvement is acceptable and considers

nuclear safety, but weaknesses are evident; licensee resources appear to

i

l

3

E

I

l

be strained or not effectively used so that minimally satisfactory

performance with respect to operational safety and construction is being

achieved.

Trend: The SALP Board has also categorized the performance trend in

each functional area rated over the course of the SALP assessment period.

The categorization describes the general or prevailing tendency (the

performance gradient) during the SALP period. The performance trends

are defined as follows:

Improved: Licensee performance has generally improved over the course of

the SALP assessment period.

Same: Licensee performance has remained essentially constant over the

course of the SALP assessment period.

l

l Declined: Licensee performance has generally declined over the course of

l the SALP assessment period.

!

l

I

l

4

. . _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

. - . - . . _ . - _ - _ _ - .-

!

III. SUMMARY OF RESULTS  :

,

Byron SALP 5 incompasses activities in 17 functional areas during all, or ,

part, of the 18 month assessment period. The licensee's performance was -

acceptable in the construction activities which continued from the previous

assessment period. However, performance in functional areas involving Unit 1

operations demonstrates significant weaknesses. Although the licensee

is considered capable, continued management action is needed in order

to assure acceptable performance.

Rating Last Rating This

Functional Areas _

Period Period Trend

A. Plant Operations NR 3 None*

B. Radiological Controls 2 3 Same

C. Maintenance NR 2 Same i

'

D. Surveillance NR 3 Declined

E. Initial Fuel Loading NR 1 N/A i

F. Preoperational Testing 3 2 Same  ;

and Startup Testing '

G. Fire Protection 3 2 Improved

!

H. Emergency Preparedness 2 1 Improved

I. Security 2 3 Declined

J. Quality Programs and 2 2 Same

Administrative Controls

K. Licensing Activities 2 2 Same

L. Containment and 2 2 Same  !

Other Safety-Related

Structures

l

M. Piping Systems 2 2 Same i

and Supports

l

N. Safety-Related 2 2 Same

Components  !

0. Support Systems 2 NR N/A

P. Electrical Power Supply 2 2 Same

and Distribution

,

i

i

- _ -

l

Q. Instrumentation and 2 2 Same

l Control System

l

NR = Not rated because of limited work or inspection activity.

  • Discernable improvement was observed since the end of the

summer of 1985.

6

.

IV. PERFORMANCE ANALYSIS

A. Plant Operations

1. Analysis

l Licensee activities in this functional area were observed in

33 inspections. Two inspections were conducted by region based

inspectors to determine the adequacy of the test and experiments

program. The test and experiments program was defined by

documented procedures for control of activities; however, no

work had been performed in this area at the time of these

inspections. Thirty-one inspections were conducted by resident

I inspectors. The inspectors observed control room operation;

! reviewed applicable logs; conducted discussions with control

room operators; ascertained that the operators were alert,

cognizant of plant conditions, attentive to changes in those

conditions, and took prompt action when appropriate; verified

the operability of selected emergency systems; reviewed tagout

records; verified proper return to service of components; toured

the plant to observe plant equipment conditions, including

potential fire hazards, fluid leaks, excessive vibration, and

to verify that maintenance requests had been initiated for

maintenance; verified by observation and interviews that the

physical security plan was being implemented; observed plant

housekeeping / cleanliness conditions; verified implementation

of radiation protection controls; and witnessed portions of the

radioactive waste system controls associated wit 1 radwaste

shipments and barreling. These reviews and observations were

conducted to verify that facility operations were in accordance

with the requirements established by Technical Specifications,

the Code of Federal Regulations and administrative procedures.

Nine violations were identified:

a. Severity Level IV - Both ECCS subsystems were rendered

inoperable as a result of a procedural violation involving

valvealignment(ReportNo. 454/85002).

b. Severity Level IV - Overtemperature Delta T and Overpower

Delta T channels inoperable in Mode 2 due to NTC circuit

cardsnotbeingseismicallyqualified(ReportNo. 454/85002).

c. Severity Level V - Failure to follow administrative

p(rocedures for controlling overtime (four examples)

Report No. 454/85009),

d. Severity Level IV - Failure to implement the required

procedures upon entry into a LCO and failure to de energize

the PORV block valves in the closed position within one

hour (ReportNo. 454/85016).

7

e. Severity Level IV - Failure to follow operating and

administrative procedures iesulting in the Refueling

Water Storage Tank being inoperable for four hours

(ReportNo. 454/85030).

f. Severity Level IV - Failure to monitor the indicated Axial

Flux Difference (AFD) hourly for ten hours following the

restoration to OPERABLE status of the AFD Monitor Alarm

(ReportNo. 454/85039),

g. Severity Level III - Operation of the Emergency Core

Cooling System such that a portion could not have

performed its intended safety function and failure to

follow the applicable Technical Specification Action

Requirements (Report No. 454/85042),

h. Severity Level III - Failure of management controls

necessary to assure compliance with the Technical

Specifications (fourexamples)(ReportNos.454f85042

454/85043).

1. Severity Level IV - Inadequate procedure utilized for

calculating the reactor core thermal power (Report

Nos. 454/85042; 454/85056).

The above violations directly involved plant operation; however,

other violations which indicate direct or indirect involvement

by plant operations are discussed in other functional areas of

this report.

An enforcement conference was held after the closure of the

assessment period to discuss the facts and significance of

violations g., h., and 1. NRC enforcement action is presently

under review.

InreviewingtheLicenseeEventReports(LERs)issuedoverthe

assessment period it has been determined that plant operations

have been subject to numerous personnel errors, and other

Technical Specification violations. Over the period, the

licensee was involved in 137 events for which LERs were required,

resulting in a monthly average of approximately 11.5 which is

considered excessive.

An assessment of a sample of LERs found them to be generally of

acceptable quality based on the requirements of 10 CFR 50.73.

It appears, however, that the large number of personnel

involved in preparing LERs results in a wide diversity in

quality. The low quality in some LERs reduced the assessment

of LERs to an overall quality that was average.

! Anexcessivenumberofreactortrips(31)wasrecordedduring

l the assestment period. Of these, four were planned as part of

l

the startup test program engineering tests, eight were attributed

!

8

- - - -_ ____ --_- -- - - - - _ _ __ .

l

l

l to personnel errors, four were the result of procedural

deficiencies, seven were related to design / manufacturing /

installation, two were attributed to external / natural phenomena,

and for six, the cause was not identified.

Based on Region III management's concern with of the licensee's

performance immediately following issuance of the operating

license, Region III management began to meet with Byron Station

managers to review licensee performance and NRC findings and

observations of plant operations. The management meetings were

held on a monthly basis beginning in December 1984 and continued

through the end of the assessment period. These management

meetings centered on the licensee's performance and corrective

actions to reduce personnel errors, reactor trips, and missed or

unsatisfactory surveillances. Surveillances are discussed as a

functional area in Section IV.D of this report. A number of

violations listed in the functional area of Surveillance also

involve plant operations personnel and are also applicable to this

functional area.

In response to the NRC concerns expressed in the monthly

management meetings, the licensee developed and implemented the

" Conduct of 0)eration Improvement Program" for the Byron Station.

Features of t1e program include imnroved communication and

awareness of trends and problem areas thrcugh production of a

Monthly Plant Status Report; " Increased Shift Overview

Superintendent (505) Involvement." " Technical Staff System

Interaction with Operations," and " Increased Awareness Of

Personnel To Day-To-Day Activities;" actions to reduce the

number of LERs and DVRs; controls to eliminate missed surveill-

ances; and improved housekeeping. The NRC has noted licensee

management's increased responsiveness to this NRC initiative

(monthly meetings) and involvement, as the assessment period ,

progressed, in efforts to identify problem areas and secure

needed improvements in the Plant Operations functional area.

A review of the indicators of management involvement in assuring l

quality indicates that in the area of reportable events, as

documented in LERs the 1985 average stands at nine per month

and although the trend over the period

hasbeendownoverall(13,10,4,5 from July)through

respectively , continuedOctober l

nanagement attention in thir, area must )e maintained to ensure

that LERs reach minimum achievable levels. Personnel errors l

shcwn  :

have been excessively high over the period and have only(9, 6, I '

an improving)

respectively trend over the

. Managenent August

attention must- October

continuetime frame

to be focuse:t  ;

in this area to bring personnel errors to the level expected of -

a good performing plant. As discussed in Section IV.D. of this

report, missed or incorrectly performed surveillances involving l

plant operations and operating personnel continue to be a high

percentage of reportable events and will require continued

management attention to bring them under control.

1

9

During the appraisal period, the licensee's administrative

controls over control room activities were challenged by the

increased testing activity, the complexity of activities being

added daily to the operator's shift routine, and the evolution

from piecemeal system / component testing to integrated plant

operation. The licensee's administrative controls for

, maintaining control room discipline have proven to be adequate

'

to this point in plant operations. Personnel access controls

,

were established for the control room, center desk, and unit .

I

licensed operator control console area and have proven  !

effective in minimizing licensed operator distraction. Station

management has thoroughly indoctrinated licensed operators

through implementation of corporate directives and plant

procedures which include NRC regulations and guidance on

maintaining order in the control room, the authority and

responsibility of licensed personnel, and the need for

'

professional attitudes and conduct at all times. The

effectiveness of station management presence in the operations

control areas is demonstrated, for the most part, by the

absence of distracting or prohibited activity in the control

room or other watch stations. Another indicator of the

atmosphere of professionalism existing in Byron managers and

licensed operators is the willingness to employ a color coded

work uniform program from the station superintendent to the

equipment attendants. The uniforms project a professional air

and thus promote greater professional conduct of operations.

Although the licensed operators of the Byron Station plant

operations staff have been both directly and indirectly

involved in reportable events, the NRC recognizes the high

level of professionalism demonstrated by the conduct of control

room activities related to plant operations and considers the

licensed operator staff to be well trained, highly motivated,

and of the highest quality.

Staffing continues to be a licensee strength. The staff is

stable and well organized with no significant turnover to date,

other than internal promotions and transfers among departments.

Qualifications, education, and experience levels within the staff

are good and should improve with additional experience,

requalification activities, and continued operation. Staffing

levels are high by design to ensure a qualified and experienced

cadre in preparation for Unit 2 integrated plant operations.

During the assessment period, license examinations were

administered to two different groups of candidates. The July

1984 group consisted of 8 senior operator and 6 reactor

operator candidates. The overall pass rate for the group was

78%, which is comparable to the national average of 80% and

indicated an upward trend compared to previous examination

groups.

The Octobe" 1985 group of 8 senior operator and 10 reactor operator

candidates had an overall pass rate of 61%. This is below the

national average and is considered unsatisfactory, and indicated

10

that improvement achieved early in the assessment period has not

continued. The licensee should focus more attention to the

screening of candidates to assure that marginal candidates are

not submitted to take the NRC examination.

The licensee generally exhibited a conservative approach to

technical safety issues penalizing unit production on some

occasions to assure compliance to a conservative interpretation

of Technical Specification requirements. Responsiveness to

issues and/or concerns raised by the NRC was, for the most

part, thorough and showed overall a cooperative attitude.

2. Conclusion

The licensee is rated Category 3 in this area based on inspection

findings of high numbers of reportable events, reactor trips,

missed and inadequate surveillances, and personnel errors in

plant operations. The licensee was not rated in this functional

area in the last assessment period.

3. Board Recommendations

NRC and licensee management should continue to focus attention

on the progress of the licensee's programs implemented

to improve regulatory performance and reactor operations.

B. Radiological Controls

1. Analysis

Nine inspections were conducted during this assessment period

by region based inspectors. These inspections included radiation

protection, radioactive waste management, TMI Action Plan Items,

environmental protection, chemistry and radiochemistry, and

confirmatory measurements. Six inspections were conducted while

Unit I was in the preoperational modes, and three operational

inspections were conducted subsequent to fuel load. Unit 2

remained in a preoperational status throughout the assessment

period. The resident inspectors also reviewed this area during

routine inspections.

Seven violations were identified as follows:

a. Severity Level IV - Failure to report air filtration

and absorption unit test nonconformances in accordance

withlicenseequalityassuranceprocedures(Report

No. 454/84066).

b. Severity Level (*) - Inadequate procedures or failure to

follow radiation protection procedures for: (1) restricting

personnel entry into containment while the incore detectors

were withdrawn, (2) providing continual radiation / chemistry

technician (RCT) atten# nce during an emergency containment

entry. (3) providing continual RCT attendance as specified

11

_

on the radiation work permit, (4) exiting a high radiation

area when exceeding administrative doses (two occasions),

(5) adherence to general contamination controls and

personal decontamination methods by workers involved in

work on a contaminated CVCS valve, and (6) providing

positive controls to prevent personnel exiting the station

following activation of portal monitor. alarms (Report

No. 454/85022).

c. Severity Level (*) - Failure to provide adequate

instructions regarding radiological conditions and

precautions to two workers who entered containment for

work on a stuck incore detector (Report No. 454/85022).

d. Severity Level (*) - Failure to make an evaluation of

radiological hazards associated with work on a contaminated

CVCS valve (Report No. 454/85022).

e. Severity Level IV - Failure to have an authorized

procedure addressing a valve lineup to transfer diluted

reactor water from the recycle holdup tanks to the Unit 2

condensate sump. As a result, the sump overflowed (Report

No. 454/85022).

f. Severity Level IV - Failure to follow liquid radwaste

release procedures to positively verify that the required

dilution flow was available (Report No. 454/85038).

g. Severity Level IV - Failure to take timely action when the

Technical Specification Limiting Condition for Operation

(LC0) for liquid radioactive release was exceeded (Report

. No. 454/85038).

  • Three violations (b., c., and d.) were classified collectively

as Severity Level III.

These violations appear indicative of programmatic and managerial

failures in radiological evaluations, procedural controls,

training, and effluent release controls. A civil penalty of

$50,000 was proposed for violations, classified collectively as

a Severity Level III problem, involving three separate incidents

which included numerous failings concerning radiological procedure

adherence, procedure adequacy, and evaluation of working conditions.

The enforcement meetings for these incidents stressed a need for

improved supervisory adherence to the licensee's established

radiological control program and improved instructions to

radiation workers. Licensee corrective actions have generally

been timely.

12

-

_ _ _ _ __

Inadequate management attention to and involvement in

radiological activities was evident during this assessment period

as indicated by: (1) management's untimely recognition of

potentially serious problems identified during the incore motor

drive repair and at power containment entry incidents,

(2) numerous examples of poor adherence to radiation protection

procedures and good health physics practices by first line

supervisors and professional / technical staff, and (3) management's

initially inadequate investigation into radiologically

significant incidents. Management weaknesses regarding

timeliness in identification and resolution of potential problems

with TMI action items were also evident' An improving trend of

.

positive management involvement was observed subsequent to the

enforcement conferences, including higher priority given to

investigating poor performance reports, staff emphasis on

procedural adherence, and increased disciplinary action taken for

flagrant procedural violations. In addition, licensee management

requested an audit of the radiation protection program by

non-station CECO health physics representatives to identify

operational and functional weaknesses. Licensee representatives

began implementing corrective actions for these weaknesses late

in the assessment period. Corporate management involvement,

limited during initial operational phases, also improved during

the period as evidenced by a commitment to investigate

significant radiological occurrences.

Staffing has generally improved during this assessment period.

Startup and operational activities for Unit 1 increased the

workload for the RCT staff, resulting in significant overtime

to meet programmatic needs. In an attempt to supplement the

staff, licensee management directed an additional class of

seven RCTs be trained; this has helped ease the shortage. The

staff has been fairly stable during the assessment period, with

promotions and transfers being the principal reason for personnel

losses. Qualifications meet current industry standards; however,

, the radiation protection staff's operational experience levels

are low as is generally the case at new plants. In accordance

with a generic CECO plant organization change, two intermediate

management positions between the Radiation Protection Manager

(RPM) and Plant Manager were created toward the end of the

assessment period. This is generally considered a weakness

because of the communication barriers it creates between the

RPM and the plant manager.

The licensee has formal training / qualification programs for

RCTs, plant workers, and visitors. Improvements are needed in

the areas of plant systems training for RCTs and procedural

adherence for all plant workers. These weaknesses were clearly

indicated by the RCT staff's lack of awareness of radiological

hazards associated with reactor systems, such as the incore

detectors, and by the repeated procedural violations by the

plant staff during this assessment period.

i

13 l

The licensee's responsiveness to NRC initiatives has been

inconsistent during this period. Licensee actions have been

acceptable in the areas of radiation seal qualification,

radiation monitor, and ventilation system concerns. The

licensee has resolved most of the TMI Action Item probiems

identified during this assessment period and has proposed

corrective actions for the remainder, although action to resolve

some of the issues was slow. The licensee's reporting of

incidents to the NRC exceeded requirements. Weaknesses

concerning the radiological environmental monitoring program

(REMP) problems which were identified during the previous

assessment period went uncorrected until a few weeks before fuel

load in August 1984. Licensee (corporate) responsiveness to

REMP issues improved considerably following a special NRC REMP

inspection in April 1985 of the licensee's corporate

environmental group. The corporate environmental group was

instructed to place more emphasis on REMP managerent to avoid

problems in the future. In response to NRC concerns regarding

low level licensed material shipped offsite to ncn-licensees,

timely action was taken to recover all material and implement

positive controls to prevent recurrence. The effectiveness of

licensee corrective actions for problems addressed in the civil

penalty could not be ascertained during this assessment period

due to their recent implementation.

The licensee's approach to resolution of radiological technical

issues has been adequate. Personal radiation exposures for the

first eight months operation were approximately 43 person-rems,

reflecting adequate exposure control program design and

implementation. Based on a design analysis, licensee

representatives plan to shield neutron streaming from the

cavity to minimize dose levels near the personnel hatch.

Interim shielding attempts during this assessment period

have not been successful.

Although the operational liquid and airborne effluent programs ,

were not specifically inspected this assessment period, five

unplanned or improper radioactive releases were reported. All

were quantitatively minor, but three were noteworthy because of

-

the errors which contributed to the releases. Additional problems

'

in this area include inoperability of both the boric acid and

radwaste evaporators and the resin cleanup system until sometime

about early September 1985 when the resin cleanup system became

fully operational and the evaporators became operational

'

intermittently, resulting in significant reduction in liquid

, effluent activity. The licensee anticipates elimination of

remaining problems with the evaporators during the current

outage. Use of a vendor resin cleanup system hos been

discontinued but a vendor resin solidification system is still in

use. The licensee unintentionally released low level contaminated

,

4

14

. _ -- _ _ _ _ . _ _ __ _ - _ ___ ___ _ - _ _ _ _ _ _ __

resins to two offsite vendors because the resins were not

adequately monitored before release from the site. All affected

resins were recovered by the licensee and returned to the site

after the problem was identified by the licensee.

Licensee's chemistry / radiochemistry performance was generally

satisfactory during the period. The licensee's policy of

rotating radiation-chemistry technicians (RCTs) between chemistry

and health physics, with resulting long intervals between

laboratory assignments, is a weakness that may limit technician

performance and will require strong management oversight to avoid

performance problems. A full complement of RCTs has satisfactorily

completed an on-the-job certification program in numerous areas

in chemistry and a formal training program, including a water

chemistry control training program. The licensee has issued a

comprehensive water chemistry control directive which directs

each station to develop site specific water chemistry control

parameters. The Chemistry Department is making good progress in

implementing this directive by preparing an extensive list of 54

administrative procedures (BAPs) describing all facets of water

chemistry control to avoid corrosion of the plant. The licensee,

however, had difficulty in maintaining desired secondary chemistry,

particularly during power transients, and has had to impose an

action described in BAP 599-39 requiring reduction in power to

30% within specified time periods. The licensee had developed

plans to make a number of modifications to the secondary system

during a plant outage to resolve some of the problems encountered

and has had to use excessive amounts of hydrazine to remove the

organics present in secondary water systems. Progress in

reducing organics in the secondary systems has been made.

The licensee also has established an adequate QA/QC program

providing RCTs with blind samples of nonradiological chemical

species but has not yet included a similar program for

radiochemistry as discussed in the previous SALP report. The

licensee analyzes radioactive samples from the Zion Nuclear

Plant; results reviewed appeared satisfactory.

2. Conclusion

The licensee is rated Category 3 in this area. This is a lower

rating than was given in the previous assessment period. This

rating is based primarily on the licensee's performance

subsequent to fuel load. During this period, the licensee's

performance in the areas of enforcement, management, radiological

controls, and training were primarily responsible for the

Category 3 rating. Improvements initiated by the licensee near

the completion of this assessment period should improve licensee

performance. Licensee performance has remained the same during

the assessment period.

15

3. Board Recommendations

Increase inspection attention in this area.

C. Maintenance

1. Analysis

Activities in this functional area were examined by four

inspections conducted by region based inspectors and portions

of nine inspections by resident inspectors.

Activities covered included the program and implementation

review of maintenance and supporting activities including

calibration, control of test and measuring equipment, design

changes, and modifications. Station maintenance activities of

safety related systems and components were observed and

reviewed to ascertain that they were conducted in accordance

with approved procedures, regulatory guides, industry codes

and standards, and in conformance with technical specifications.

Several weaknesses were identified in the program review in

these areas. The licensee took prompt action to correct the

weaknesses. Activities were performed to approved documented

procedures and procedures were rarely violated. The limiting

conditions for operation were met while components or systems

were removed from service; approvals were obtained prior to

initiating the work; functional testing and/or calibrations

were performed prior to returning components or systems to

service; quality control records were maintained; activities

were accomplished by qualified personnel; parts and materials

used were properly certified; radiological controls were

implemented; and, fire prevention controls were implemented.

Work requests were reviewed to determine the status of

outstanding jobs and to assure that priority is assigned to

safety-related equipment maintenance which may affect system

performance.

Two violations were identified:

a. Severity Level V - Failure to provide appropriate

acceptance limits in instructions, procedures, or drawings

utilized to accomplish battery cell-to-rack end stringer

gaps (Report No. 455/85006).

b. Severity Level IV - Failure to adequately document a

deviation in the operation of the Rod Control System

(Report No. 454/85033).

Work performed was generally technically sound, thorough and

timely. Records were generally complete, well maintained and

available. However, the NRC is concerned that appropriate

management attention and accurate, timely resolution of

maintenance items which have been identified as having minimal

16

safety significance may be a weakness. As evidenced by item b.

above, inadequate documentation and management review of an

operational problem on a nonsafety-related system subsequently

delayed the timely correction of an equipment deficiency which

resulted in the occurrence of multiple rod drops and contributed

to the dissemination of inaccurate information to the NRC.

Aggressive management attention and rigorous evaluation of all

technical issues is required to ensure acceptable equipment

performance.

Although there has been some cross-over between construction

incidents and operational reportable events, the number of LERs

and violations in this area have not been excessive and

management involvement in assuring quality in this area has

been adequate over the period. Upon identifying an area

requiring additional management oversight, the licensee har

provided technically sound resolution with good consideration

of the safety issues involved.

A review of the maintenance organization reveals adequate

manning in all positions with well-trained, moderately

experienced personnel who demonstrate a degree of pride in

their workmanship.

Inspections in the overall maintenance area have provided a

reasonable level of confidence in the administration of a sound

program with adequately documented procedures and records;

however, the effectiveness and timeliness of maintenance

activities could be improved by greater involvement in the

day-to-day inner departmental problems and delays by the upper

levels of managers at the shop head, general foreman, and

foreman levels, thereby enhancing the communication of maintenance

problems at the intra-departmental level. Examples of this

weakness are: (1) two identical cases of reactor trip due to

dropped rods on March 29, 1985 and April 10, 1985; (2) exceeding

the administrative radiation exposure limits for workers while

performing incore detector repairs; (3) reactor trip due to low

lube oil reservoir level; (4) three incidents of dropping the

identical control rod resulting in 2 reactor shutdowns during

startup and one reactor trip from power; and (5) an unusual

event resulting from both trains of control room ventilation

being inoperable.

2. Conclusion

The licensee is rated Category 2 in this area. The licensee

was not rated in this functional area in the previous

assessment period. Licensee performance has remained the

same during the assessment period.

17

3. Board Recommendations

None.

D. Surveillance

1. Analysis

This functional area was examined in two inspections conducted

by region based inspectors and portions of ten inspections

conducted by resident inspectors.

The inspections included a review of the program for the

control and evaluation of surveillance testing including

inservice inspections. Problems were identified in procedures

regarding independent verifications during surveillance

testing. Procedures were revised in an attempt to correct these

probl ems.- Implementation of the surveillance program was also

reviewed and inspectors verified that testing was performed in

accordance with approved procedures, that test instrumentation

was calibrated, that limiting conditions for operation were

met, that removal and restoration of the affected components

were accomplished, that test results conformed with technical

specifications and procedure requirements and were reviewed by

personnel other than the individual directing the test, and

that any deficiencies identified during the testing were reviewed

and resolved by appropriate management personnel. Work was

generally timely, thorough, and technically sound. Records

were generally complete, well maintained, and available.

Six violations were identified:

a. Severity Level IV - Failure to perform inservice tests

of Unit 1 RHR pumps within the required surveillance

interval; inservice testing to establish pump and/or

system operability using inadequate instrumentation

(Report No. 454/84079).

b. Severity Level IV - Failure to follow surveillance

procedures (Report No. 454/85009).

c. Severity Level IV - Failure to perform a surveillance as

required prior to entry into the applicable operational

mode; failure to perform surveillances prior to returning

components to service; and failure to perform a surveillance

within the required time interval (Report No. 454/85016).

d. Severity Level IV - Failure to perform a surveillance ,

within the required time interval; failure to collect,and ,

analyze reactor coolant sample within the time rsquir?ments .

of Technical Specifications (Report No. 454/850Fh.). '

!

'

18

.-. .-.

e. Severity Level IV - Failure to perform surveillance within

the required time interval; failure to perform surveillance

as required (Report No. 454/85025).

f. Severity Level IV - The Reactor Coolant System water

inventory balance was not performed within the required

surveillance interval (Report No. 454/85039).

Violation "a" involved two discrepancies: (1) failure to i

ensure Residual Heat Removal (RHR) pump operability by

performance of inservice testing within the required

surveillance interval prior to entering Modes 6 and 5; and (2)

use of inadequate instrumentation which exceeded the maximum

allowable range requirements of the licensee's inservice test

program during inservice tests to establish operability prior

to entry into Modes 6 and 5. These two incidents resulted in

operation in Modes 6 and 5 without properly establishing the

OPERABILITY of the RHR pump.

Violation "b" involved two discrepancies: (1) failure to

follow prerequisite steps of a surveillance procedure based on

ad-hoc advice from Westinghouse personnel resulting in a

turbine trip and reactor trip at power; and (2) use of a

surveillance procedure to investigate a turbine impulse

pressure channel indication in a prohibited mode during a

reactor startup which resulted in an additional reactor trip.

These two incidents resulted in two unwarranted reactor trips

due to the failure to observe and follow the stated

prerequisite steps of approved surveillance procedures.

Violation "c" involved three discrepancies: (1) failure to

observe and implement the Technical Specification Action

Statement for six hours in Mode 5 while the emergency power

source for the operable Centrifugal Charging Pump was

out-of-service; (2) failure to de-energize the Pressurizer

Power Operated Relief Valve Block Valves in the closed position

for 1.8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> in Mode 3 as required by the Technical

Specifications; and (3) failure to place the main Control Room

Ventilation System Train in the makeup mode exceeding time

limits in Mode 5 upon taking radiation monitoring

instrumentation out-of-service for maintenance as required by

the Technical Specifications. These three incidents resulted

in systems / components not being placed in the Action Statement

s required conditions in excess of the time requirements of the

Technical Specifications as a result of failure to observe and

implement the Technical Specification Action Statements.

Violation "c" also involved eight discrepancies which included:

(1) failure to establish an hourly fire watch in Mode 6 from

October 1984 to December 1985, while a replacement ultraviolet

fire detector in the Fuel Handling Building remained untested

to atsure operability by surveillance performance; (2) failure

to perform inservice inspection visual examinations on seven

19

_ _

valves and components prior to returning them to service in

Mode 6; (3) failure to perform required surveillance position

indication testing on a safety injection valve prior to entry

into Mode 3 from January 10 to January 24, 1985; (4) failure to

demonstrate operability of remaining offsite electrical

circuits while one offsite electrical circuit was

out-of-service for maintenance by exceeding the specified time

limits for the initial and subsequent verification while in

Mode 3; (5) failure to demonstrate the capability of 2A Diesel

Generator to supply power to Bus 141 daily in excess of time

limits in Mode 3; (6) failure to perform the quarterly test on

a Containment Isolation Valve in excess of the time limits in

Mode 3; (7) failure to perform the required 31 day operability

test of the Lower Cable Spreading Room CO2 Systet in the months

of January and February, 1985 while in Modes 5 through 1;

(8) failure to perform a Turbine Emergency Trip Header Low

Pressure Reactor Trip Surveillance prior to entry into Mode 2.

These eight incidents resulted in equipment, components and/or

system operability not being certified for periods of time from a

few hours to a few months and resulted from failure to observe,

recognize and implement the Technical Specification Surveillance

requirements.

Violation "d" involved two discrepancies: (1) failure to

perform the isolation time surveillance on 1PR066 while in

Mode 1; and (2) failure tu sample the primary system in excess

of the time limitations following a power level change. These

two incidents resulted in operation in Mode 1 with the operability

of a containment isolation valve not ve. * fied and, exceeding the

time limitations to verify that no reactor coolant radio-chemistry

limits had been exceeded.

Violation "e" involved two discrepancies: (1) failure to

verify that Indicated Reactor Coolant System Average

Temperature and Indicated Pressurizer Pressure were within

specified limits at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> from March 27 to

May 5,1985, while in Mode 1; and (2) failure to verify the

above parameters within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> prior to entry into Mode 1 on

5 occasions. These two variations of a.like problem resulted

in lengthy operation in Mode 1 during which time certain key

plant parameters were not being verified as being within the

specified limits as required by Technical Specifications and

were a result of failure to process, review and control a

revision to the applicable surveillance procedure coupled with

the failure to be aware of and implement the appropriate

Technical Specification surveillance requirements prior to

entry into and during operations in Mode 1.

20

- _ - .

"f" involved one discrepancy which resulted in the

~

Violation

failure to perform a Reactor Coolant System Water inventory

balance once per 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> (+25%) from August 16 at 1214 to

August 20, 1985, at 0900. This incident resulted in operations

in Mode 1 for a period of time exceeding the Technical

Specification limits while reactor coolant system leakage went

unmonitored and was a result of a management decision to defer

performance of the surveillance due to interference with a

startup test.

During this assessment period the licensee reported 18 incidents

of missed or inadequately performed surveillances. Of these,

13 were attributed to personnel error, one to design,

manufacturing, construction / installation, and 4 to defective

procedures. Many of these reportable events have resulted in

violation of License Conditions, Technical Specifications, or

NRC Regulations. The NRC recognizes that the licensee's program

encompasses hundreds of surveillance procedure requirements.

Performance of this function has shown a significant increase in

total incident occurrences during the last three months of the

SALP period. Although the rate has been improving, the numbers

of surveillance incidents is considered excessive.

Management involvement in the surveillance function peaked

about two-thirds through the period when the licensee developed

and implemented the Conduct of Operations Improvement Program

(COIP). A feature of the COIP was designed to eliminate missed

surveillances. Based on the findings of NRC inspections over

the last three months of the assessment period it appears that,

although the program is technically sound and has provided

acceptable technical resolutions from a safety standpoint,

management involvement in reducing the numbers of surveillance

incidents, has demonstrated a low level of effectiveness.

The licensee has indicated a willingness to address this issme

in response to NRC concerns expressed in the monthly management

meetings discussed in Section V.E of this report and is devoting

resources to the resolution of the problem through efforts in

the areas of monitoring the surveillance system records,

increasing awareness of the operating staff in the area of

surveillance scheduling requirements, increasing surveillance

scheduling requirements, increasing technical staff awareness

and interaction with the operating staff, and continuing to

monitor and improve the corrective action items designed to

eliminate the problem. However, a review of the recent events

indicates that these changes are apparently slow in being

effective and this indicates a weakness in the program.

2. Conclusion

The licensee is rated Category 3 in this area. The licensee

was not rated in this functional area in the previous SALP.

A significant group of Violations occurred earlier in this

assessment period and another significant group occurred at the

21

__

_

'

1

I

end of this period, in each case demonstrating unacceptable

performance requiring corrective action. Licensee performance

has declined during the assessment period, despite several

Regulatory Performance Improvement Program activities which

were targeted to reducing procedural and personnel errors.

3. Board Recommendations

The licensee should continue to concentrate a high level of

management attention to this functional area to reduce the

number of missed and inadequately performed surveillances.

E. Initial Fuel Loading

1. Analysis

The initial Unit 1 core was loaded between November 2, 1984

and November 27, 1984. The core loading activities, conducted

between November 2 and November 5, 1984, were inspected on a

24 hour-a-day coverage basis by region based inspectors and

resident inspectors. Fuel loading activities between

November 6 and November 27, 1984, were inspected on a routine

basis.

The licensee's fuel loading crew demonstrated a high degree of

training and experience in the performance of their duties

resulting in few NRC observations related to documentation,

preparation, and execution of the fuel load procedures.

No violations or deviations were identif ed in this area.

Delays encountered in the fuel load sequence resulted from

equipment malfunctions including the fuel transfer cart drive

shear pin failures and source range nuclear instrument noise

spiking.

Management involvement in these two problems resulted in

technically sound and thorough resolutions in a timely

fashion employing a high degree of conservatism for the safety

significance in each case. Throughout the NRC inspection of

the fuel load activities, the licensee provided technically

sound and thorough responses to NRC observations resulting in

acceptable resolutions to technical issues brought to their

attention.

2. Conclusion

The licensee is rated Category 1 in this area based on the

overall quality of performance during the fuel loading

sequence. The licensee was not rated in this functional

area in the previous assessment period. Since initial fuel

load is a single evolution, no trend has been established.

22

_ _ _ _ -

3. Board Recommendations

None.

F. Preoperational Testing and Startup Testing

1. Analysis

The preoperational testing and startup testing inspection effort

for Unit 1 consisted of 13 inspections conducted by region based

inspectors, and a portion of 16 inspections by resident inspectors.

The inspections consisted of observations of licensee performance

in implementing administrative controls; in-depth procedure

review, verification, witnessing, and test results review and

verification for both preoperational and startup test procedures;

and observations of corrective actions for problems identified.

There were no violations identified for the Unit 2 preoperational

test program. The preoperational testing inspection effort for

Unit 2 consisted of four inspections by regional based inspectors

and portions of five inspections by resident inspectors. This

is considered very little inspection effort. The startup test

program for Unit 2 has not yet commenced.

Six violations on Unit 1 were identified as follows:

a. Severity Level IV - Failure to adequately test and

evaluate Emergency Core Cooling System (ECCS) remote

valve position indications in the preoperationai test

program (Report No. 454/84055).

b. Severity Level V - Failure to adequately evaluate

the leakage test results of Safety Injection-ECCS

check valves in the preoperational test program

(Report No. 454/84073).

c. Severity Level V - Failure to adequately evaluate

the pump curves of the Boric Acid transfer pumps in

the preoperational test program (Report No. 454/84073).

d. Severity Level V - Failure to adequately test the Diesel

Generator Fuel Oil System in the preoperational test

program (Report No. 454/84073).

e. Severity Level IV - Failure to adequately test the

Auxiliary Power System electrical distribution system

voltages in the preoperational test program (Report

No. 454/85002).

f. Severity Level IV - Failure to adequately evaluate and

document the test results of four separate tests in the

startup test program (Report No. 454/85008).

23

1

A concern with the preoperational test program results review

identified late in the SALP 4 rating period resulted in an

overall assessment of the licensee's performance as Category 3.

Although improvements from the previous SALP period were

initially noted, similar concerns on the adequacy of the

results evaluation of the test program were also noted in this

SALP period as evidenced by items a., b., c. and f. above. An

enforcement conference was held on April 29, 1985, to discuss,

in part, these concerns. Violations a. through f. above,

occurred prior to the enforcement conference. Subsequent to the

enforcement conference, licensee performance in the area of

startup test performance improved as evidenced by three full and

six partial inspections in the startup test area with no violations

noted. It should be noted, however, that subsequent to the

enforcement conference, the startup program was completed on

September 10, 1985 and the fewer violations are, in part, due to

the decreased level of activity in the development of the

preoperational and startup test programs. Continued high

priority and management attention are warranted to assure

attention to detail and rigorous analysis during the

preoperational and startup test programs for Unit 2.

In the SALP 3 rating period, 10 violations consisting of 7

Severity Level IV and 3 Severity Level V items t re identified

over a rating period of 12 months. In the SALP 4 rating

period,15 violations consisting of 4 Severity Level IV and

11 Severity Level V items were identified over a period of

16 months. In the SALP 5 rating period, 6 violations consisting

of 3 Severity Level IV and 3 Severity Level V items were

identified over a period of 18 months. Considering the longer

period for this SALP and the decrease in the number of

violations identified, the licensee's performance has improved.

Staffing (including management) appears to be adequate and the

licensee remains responsive to NRC concerns and initiatives.

Training effectiveness and the qualification of test personnel

was satisfactory and showed a marked improvement over the

previous SALP rating period. The effectiveness of staffing,

training and the qualification of personnel remains to be

demonstrated during the preoperational test program of Unit 2.

New personnel will be involved in this test program and the

effectiveness of the transfer of knowledge and experience must

be closely monitored to ensure continued satisfactory

performance in these areas.

The licensee's resolutions and management involvement in

technical issues identified in the course of the performance of

the startup program placed sufficient emphasis on the safety

significance of issues identified in the performance and review

of test results.

24

2. Conclusion

The licensee is rated Category 2 in this area. This is a

higher rating than was given in the previous rating period.

Although significant improvements were not noted in the

performance of test results evaluations, fewer violations were

identified following the enforcement conference of April 29,

1985. This is, in part, due to the decreased level of activity

in the development and performance of the preoperational and

startup test programs.

3. Board Recommendations

Continued licensee attention is warranted to insure the

transfer of expertise and experience in the upcoming

performance of the Unit 2 preoperational and startup test

programs.

G. Fire Protection

1. Analysis

During this assessment period, one routine and five special

team safety inspections were conducted by region based

inspectors to assess conformance of the as-built plant fire

protection features, fire protection program implementation

and post-fire safe shutdown capability. In addition, portions

of 31 inspections by resident inspectors were made to assess

housekeeping and the care and preservation of equipment.

Three violations were identified as follows:

a. Severity Level V - The licensee failed to implement

procedures to verify the quality of fire barrier

penetration seals (Report No. 454/84076).

b. Severity Level V - The licensee failed to provide

instructions, procedures or drawings which ensured

timely review of radiation seal substitutions

(Report No. 454/84076).

c. Severity Level V - The licensee failed to provide and

maintain three aspects of the fire protection program

(Report No. 454/84082).

Subsequent follow-up inspections and meetings with the licensee

resulted in the licensee taking appropriate corrective actions

for all of the identified violations. Most of the unresolved

and open items that were identified have been closed out.

25

During the previous assessment period, the licensee was rated

Category 3 in this functional area. As noted in the cover

letter which transmitted that assessment, the Category 3 rating

reflected the Region III view that there was a lack of concerted

management attention to the development and implementation of the

fire protection program. Further, there was no evidence that the

licensee had undertaken a comprehensive evaluation of their fire

protection program to establish their degree of conformance with

FSAR commitments. As noted in the assessment itself, these

problems were compounded by a lack of technical expertise by the

plant staff in fire protection.

In response to Region III's expressed concerns in this area,

the licensee brought additional technical expertise to bear in

fire protection, increased the level of management attention

devoted to fire protection and undertook a self-evaluation of

their degree of conformance to their commitments. 'The actions

resulted in a measurable improvement in performance in the fire

protection area.

While problems continue to be identified as noted above, they

are of a more isolated nature and are generally dispositioned

better than in the past.

Routine housekeeping inspection tours of Unit 1 indicate that the

licensee has developed and implemented programs to supplement

the on going effort in the areas of plant cleanliness and care

and preservation of safety-related equipment. In addition,

special cleaning / preservation teams were formed and employed on

a full time basis in the areas of component / pipe ending

coverings and a wide spread and growing problem of graffiti

cleanup. The licensee expended considerable resources in

upgrading plant cleanliness and care and preservation of

safety-related components during the transition period from

construction to operation. The most noticeable effects of this

effort were observed in the months immediately preceding

issuance of the operating license on October 31, 1984. Limited

work activities still in progress in plant-common and Unit 1

areas have afforded the cleaning teams opportunity to gain

control of the graffiti problem; however, additional management

attention is still required to maintain the cleanliness levels

achieved. Resident Inspector tours conducted since OL have not

discovered housekeeping problems detrimental to safety-related

equipment indicating management involvement is adequate.

Routine housekeeping tours of Unit 2 indicate that while the

licensee has developed and implemented houskeeping programs,

they have not been effective in maintaining an adequate level

of cleanliness for the level of construction activity.

Additional management attention is required to achieve and

maintain adequate cleanliness.

26

2. Conclusion

The licensee is rated a Category 2 in this area. This is a

higher rating than was given in the previous assessment period

and is based on appropriate corrective actions that have been

taken and generally adequate management responses to concerns

raised by the NRC. Noted improvements in this area provide

assurance that the quality of installed fire protection

features will be maintained to accommodate post-fire safe

shutdown given a fire in any area of the plant. Licensee

performance has remained the same during the assessment period.

3. Board Recommendations

None.

H. Emergency Preparedness

1. Analysis

Six inspections were conducted during the period by region

based inspectors to evaluate the following aspects of the

licensee's emergency preparedness program: (1) emergency

detection and classification, (2) protective action decision

making, (3) emergency notifications, (4) emergency communications,

(5) shift augmentation provisions, (6) emergency preparedness

training, (7) offsite dose assessment. (8) independent audits of

emergency preparedness, (9) implementat. ion of changes to the

program, and (10) followup on items identified during the

December 1983 Emergency Preparedness Implementation Appraisal.

Three inspections were appraisal followup inspections; another

involved an allegation regarding provisions for the assembly,

accountability, and evacuation of contractors; another was the

observation of the annual exercise; and the sixth was a routine

inspection of the emergency preparedness program.

One violation was identified:

Severity Level IV - During a five month period, the

licensee failed to complete quarterly inventories of

emergency supplies located in two emergency response

facilities (Report Nos. 454/85038; 455/85034).

Appropriate corrective actions for the violation were initiated

  • prior to the end of the inspection. This violation is not

considered indicative of a programmatic breakdown in conducting

periodic inventories of emergency supplies.

Independent audits of the emergency preparedness program were

ad a nte in scope, depth, and frequency. Audit records were

complete and well maintained. Administrative procedures were

adhered to regarding the preparation, review, and distribution

of the emergency plan and its implementing procedures.

27

_ ___

.-

Revisions to the Byron Annex of the generic emergency plan,

and implementing procedure revisions were consistent and did

not degrade their effectiveness. An effective system had been

utilized to track and document corrective actions on items

identified during drills, audits, and NRC inspections.

As evident from the followup inspections on items identified

during the appraisal, the licensee had a clear understanding

of the staff's concerns. Initial corrective actions were

appropriate in almost all cases. Closure of the items was

generally timely, with few remaining open beyond August 1984.

These items were closed in December 1984. The licensee's

responsiveness to all items identified subsequent to the

appraisal followup inspections has been very good. Required

responses were received by the established deadlines. All

corrective actions were technically sound, thorough, promptly

initiated, and were either complete or were being completed

on schedule.

Records associated with six actual emergency plan activations

through August 1985 indicated that all situations had been

properly classified. The NRC and State of Illinois were

initially notified of these emergency declarations in a timely

manner. Detailed records of notification messages to the NRC

and State of Illinois were complete and readily available.

The licensee has maintained a prioritized roster of adequate

numbers of qualified personnel to fill well-defined, key

positions in the emergency organization. Semi-annual,

off-hours drills have been conducted to successfully

demonstrate the capability to augment on-shift personnel

in a timely manner.

Proficiency of persons assigned to the onsite emergency

organization has largely been maintained through annual

training on the generic emergency plan, Byron Annex, relevant

implementing procedures, and by participation in drills and

exercises. In addition, operating shift personnel have been

kept informed of emergency plan implementing procedure changes

through a periodic required reading program administered by

the Station's Training Department. Based on walkthroughs

and observations of participants in the annual exercise,

persons assigned to the emergency organization have adequately

demonstrated their capabilities to perform their emergency

duties.

2. Conclusion

The licensee is rated Category 1 in this area. This is a

higher rating than was given in the previous assessment

period. Licensee performance has improved during the

assessment period, particularly in regards to responsiveness

to NRC concerns. The rating is based on the following: the

28

strength of the emergency preparedness training program, as

evidenced during walkthroughs and exercises; the licensee's

ability to monitor its own activities and take timely,

appropriate corrective actions; and the timely and accurate

reporting of emergency plan activations to the NRC and State

agencies.

3. Board Recommendations

None.

I. Security

1. Analysis

During this assessment period, eight inspections were conducted

by region based inspectors. Three routine preoperational

inspections were conducted by regional based prior to license

issuance. Two routine and three special inspections were

conducted subsequent to license issuance. The assessment in

this functional area was divided into two phases - those issues

of the security program required to be completed prior to fuel

load, and the full implementation of the security plan after ,

license issuance.

Three violations, subsequent to the issuance of the license were

identified as follows:

Severity Level IV - Adequate protected and vital area

'

a.

access controls in the form of physical barriers were

not provided (Report No. 454/84085).

b. Severity Level III - The locked status of vital area

doors was not properly verified following a computer

outage, resulting in two unlocked doors for approximately

4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> (Report No. 454/84085).

c. Severity Level IV - Failure to provide adequate access

controls to two vital areas because of inadequate physical

barriers (Report No. 454/85046).

Violation a. represented a significant breakdown in the

security system that occurred prior to initial reactor startup.

Due to the status of the plant, an act of radiological sabotage

was not possible; consequently, enforcement actions were not

escalated. Violation b. represented a personnel error that

led to the inadequacy of two of the three elements of access

control for the affected vital area. A proposed imposition of

civil penalty in the amount of $25,000 was issued. At the

close of the assessment period, the NRC was evaluating the

licensee's response to the Notice of Violation. Violation c.

represented a disregard for security procedures by both

station and contractor employees. These three violations were

29

_ _

_ __ _ . _ _ _ _ _ _ _ - _ .

l

!

indicative of a significant programmatic breakdown. Corrective

actions, although prompt, were not successful in preventing

recurrence. The continuation of similar types of problems

necessitated the formulation of a Performance Improvement  !

Program with the goal of precluding recurrence. The results

of this program will be evaluated during the next assessment

period.

During the preoperational phase, in anticipation of initial

activation of the program needed at license issuance, the

corporate nuclear security office conducted an extensive audit

which established priorities for implementation and problem

areas. Th3 Quality Assurance audit program on the other hand,

is neither as comprehensive nor as effective in identifying

causes of problems.

Communications between the site and the corporate nuclear

security office were improved during the assessment period

through the establishment of the " Senior Nuclear Security

Administrator" position onsite. The licensee should consider

an increased oversight by the corporate organization in

the decision making and operation of the security system.

The licensee's approach to the resolution of technical issues

has been viable and generally sound, with the exception of the

security computer reliability issue which has involved both

software and hardware problems. The issue of security system

reliability has not been resolved to date.

Security event reports, under 10 CFR 73.71(c) were accurately

identified, but some analyses were marginal. For example, in

the initial event involving inadequately protected and vital

area access controls, the initial evaluation approach showed

a lack of understanding of the issue, resulting in incomplete

compensatory measures.

Staffing problems were noted in the security force contract

overview, both onsite and in the contractor's branch and

corporate offices. Personnel in key management positions

changed frequently, contributing to low morale and poor

administrative support. Only within the latter portion of

the assessment period did the licensee address this issue

and require the contract agency to maka necessary changes

to improve its performance.

The security training and qualification contributed to an

adequate understanding of work and fair adherence to

procedures with a modest number of personnel errors. However,

the Severity Level III violation, involving inadequately

implemented compensatory measures, was in large part due

to deficiencies in the guard and firewatch training programs.

Our review has shown that despite the identified individual

30

- . - --

--

,

areas of needed improvement, the security and guard force

organizations have made steady improvement. The continuing

vital area access control problems do not appear not to be caused

by major deficiencies in security organization performance.

The licensee has taken several actions to improve their

performance in the area of vital area access control. These

actions have been logical and efficiently implemented but did

not achieve the ultimate results of preventing continued similar

problems from occurring.

2. Conclusion

The licensee is rated Category 3 in this area. This is a

lower rating than was given in the previous assessment period.

This rating is based primarily on the licensee's performance

subsequent to the issuance of the license. Licensee's overall

performance in this functional area has not demonstrated an

adequate understanding of the fundamental security issue of

protected and vital area access controls and has declined

during the assessment period.

3. Board Recommendations

Licensee management should place major emphasis on implementation

of a corformance improvement program.

[ NOTE: In the first month following and conclusion of this

assessment period, another potential Severity Level III

violation, involving a degraded, unmonitored vital area

barrier for 26 consecutive days, was identified by the

licensee. Escalated enforcement action is pending.]

J. Quality Programs and Administrative Controls

1. Analysis

Ten inspections by region based inspectors and one inspection

by resident inspectors examined activities in this functional

area. Activities inspected included quality assurance program

review and administration; procurement control; receipt, storage

and handling of material; QA records program; document control;

the offsite review committee; audit program; offsite support

staff; followup of the licensee contracted Independent Design

Review (IDR); and review of Systems Control Corporation (SCC)

procurement activities. In addition, meetings were held monthly

between NRC staff and plant management to assess operation of

the plant.

Twelve violations were identified:

31

- _ --

l

I

!

a. Severity Level III - A material false statement regarding

SCC source inspections. (Report Nos. 454/84032; 455/84025).

b. Severity Level IV - Failure to maintain records of

nonconforming items (Report Nos. 454/84032; 455/84025),

c. Severity Level IV - Failure to include SCC on the Approved

Bidders List (Report Nos. 454/84032; 455/84025).

d. Severity Level IV - Failure to take timely and

effective corrective actions regarding SCC supplied

equipment (Report Nos. 454/84032; 455/84025).

.

'

e. Severity Level IV - Six examples of QA audit program and

implementation deficiencies (Report No. 454/84040).

f. Severity Level IV - Improper implementation of disposition

on nonconforming material (Report No. 454/84044).

g. Severity Level V - Two examples of improper material

storage (Report No. 454/84044).

h. Severity Level IV - Changes made to facility which

involved an unreviewed safety ~ question without prior

Commission approval (Report No. 454/85002).

i. Severity Level V - Failure to control design documents

to ensure use of latest revision (Report Nos. 454/85019;

455/85012).

j. Severity Level IV - Failure to translate regulatory

requirements and design basis into appropriate procedures

and design documents (three examples) (Report No. 455/85027).

k. Severity Level IV - Failure to assure that purchased

equipment and services conform to procurement documents

(numerous examples) (Report No. 455/85027).

1. Severity Level IV - Failure to establish and execute an

effective inspection program to verify conformance with

instructions, procedures, and drawings (three basic

examples) (Report No. 455/85027).

Four violations, a., b., c., and d. resulted from followup

inspections of SCC supplied equipment $ssues originally iden-

tified in Inspection Reports No. 454/80004; 455/80004. The

violations identified failures by the licensee in dealing with

deficient SCC products. The licensee's response was reviewed

and determined to be adequate. Followup inspections of the

licensee's corrective actions found them to be satisfactory.

.

32

_ . ,- .- .. - . - . ._ _ _ __

r

!

!

l Followup review of the Integrated Design Inspection (IDI)

findings was also completed in this assessment period. The

resolution of the remaining 29 of 96 issues was accomplished

with extensive NRC staff / licensee information exchange and

review. The complexity of the issues required significant

effort from the staff and licensee.

l

! Violations f., g., and i. resulted from QA program inspections

l and appeared to document isolated instances rather than program

! breakdowns. Items f. and g. were identified early in the

j assessment period and subsequent inspections indicated proper

i correction and acceptable performance. Action on item i. was

completed during the inspection and appeared to be an isolated

case.

Violation e. identified significant problems in the

documentation and implementation of the quality assurance

audit program. These problems along with several program

l weaknesses documented as open and unresolved items were

l

'

identified early in the assessment period. The licensee

took immediate action to address the identified problems

and weaknesses. Prompt and adequate action was taken and

subsequent inspections indicated acceptable performance in

this area.

Violation h. involved a failure of licensee administration to

identify and appropriately evaluate a temporary alteration of

a protection system, based on an interpretation of a justifi-

cation for interim operation that was less conservative than the

NRC staff interpretation. The licensee subsequently adopted the

staff interpretation and took prompt and thorough corrective

action.

Prior to licensing, an independent design review (IDR) of the

Byron Station was performed by the Bechtel Power Corporation

(Bechtel) to provide an assessment by an outside party of the

adequacy of the design activities performed by Sargent and

Lundy Engineers. One inspection was conducted by regional

based inspectors to evaluate the acceptability of Bechtel's

effort. Areas reviewed included a review of the program and

procedures, the indoctrination and training of engineering

personnel performing reviews, reviewing monitoring / audit

documents, and evaluating potential observations and Bechtel's

approach to resolving the safety significance of these

observations. For the areas of the IDR examined, the inspectors

determined that activities were controlled through the use of

well stated and defined procedures. Reviews were thorough,

technically sound and performed by experienced reviewers.

Records and evaluations were found to be generally complete,

well maintained, and available. The program procedures dealing

with the dispositioning of the observations were functioning

properly. No violations or deviations were identified.

,

33

The Construction Assessment Team (CAT) inspected a wide

spectrum of Unit 2 construction activities late in the

assessment period. Violations j., k., and 1. were identified in

the CAT inspection. These violations are not representative of

any programatic breakdown. The licensee's response and

corrective actions will be reviewed in subsequent inspections.

The examples cited in these violations are referenced in the

appropriate functional areas.

Programatic inspections noted problems early in the assessment

period. Actions taken to correct the problems were adequate

and program performance appeared to be consistently acceptable

for the balance of the period.

2. Conclusion

The licensee is rated a Category 2 in this area. This is

the same rating as was given in the previous assessment period.

Licensee performance has remained the same during the

assessment period.

3. Board Recommendations

None.

K. Licensing Activities

1. Analysis

During the evaluation period there was a significant level

of activity. The low power license for Byron 1 was issued

on October 31, 1984, and the full power license was issued

on February 14, 1985. Supplemental SERs were issued along

with each of these licenses. Technical Specifications for

Byron 1 were issued with the low power license. The Technical

Specifications issued with the full power license were made

applicable to both Units.

The licensee's decision making is usually at a level that

ensures adequate management review. The submittals needed to

support licensing were generally timely, thorough and

technically sound. Upper management was available to resolve

concerns and took an active role on certain actions, such as

the Technical Specifications and staffing for operation of the

volume reduction system. The licensee understands the

technical issues and responses are generally sound and

thorough. Conservatism is generally exhibited and approaches

are viable. In several instances, the licensee challenged

staff positions, but only when it believed safety would not

be compromised. In the weeks prior to issuance of the low

power and full power licenses, the licensee had to respond

to many NRC initiatives in a short time. The licensee

responses were generally timely, sound, and thorough. Events

34

i

__. _.. _ _ _ _ _ _ _ . _ _ _

at Byron 1 appear to have been reported promptly and

accurately. Key positions are clearly identified and

responsibilities and authorities are well defined. The need

for operators on shift with previous operating experience was

a relatively recent requirement at the time of our review to

support issuance of the low power license. The licensee

responded by selecting several qualified individuals to act as

Shift Advisors on those shift crews that did not meet the

requirement. The trainiiig of shift advisors is acceptable

and on a par with other recently licensed plants.

2. Conclusion

The licensee is rated Category 2 in this area. This is the

same rating as was given in the previous assessment period.

Licensee performance has remained the same during the

assessment period.

3. Board Recommendations

None.

L Containment and Other Safety-Related Structures

1. Analysis

The work activities in this area were essentially complete.

Consequently, examinations of this functional area were limited

to seven inspections by regional based inspectors and a portion

of the NRC CAT inspection observing completed work and

reviewing installation records and associated documentation.

An as-built walkdown and a document review were performed for i

selected areas of Unit 1 and 2 containment structural framing,

steam generator bolting and supports, main steam support ,

structures, reactor coolant pump support column modifications, t

and containment electrical penetrations. Other selected,

safety-related, structural welding records were also examined.

One inspection examined concrete drilling and coring activities, ,

containment structural integrity testing, modifications, and t

licensee action on a related IE Bulletin and IE Circular. The  !

results of a statistical sampling plan, established to reinspect  !

high strength bolted connections which were reported as a '

10 CFR 50.55(e) deficiency, and allegations were also examined.  ;

'

For the areas examined, the inspectors determined that the

10 CFR 50.55(e) deficiency was reported in a timely manner, ,

and was accurately identified and that the resulting reviews

were effective and technically sound. The installation records l

and associated documentation were generally complete, well

maintained, and available. Observations during the walkdown

'

indicate personnel have an adequate understanding of work

practices and have adhered to drawings and procedures. A large .

/

a

35 f

- -_ _ - -

portion of inspection resources in this functional area and in

Piping Systems and Supports was used in six inspections by

regional based inspectors to conduct reviews of allegations and

concerns expressed by an expert witness who appeared on behalf

of the Intervenors during the remanded ASLB hearing for Byron.

Three violations were identified:

a. Severity Level V - Failure to assure welding was

performed in accordance with the applicable AWS

D1.1 Code (Report Nos. 454/84050; 455/84034).

b. Severity Level IV - Failure to maintain retrievable

design basis documents (Report Nos. 454/84071;

455/84049).

c. Severity Level V - Failure to specify appropriate

code provisions (Report Nos. 454/84071; 455/84049).

The licensee's response and corrective actions related to

these violations were reviewed and found to be acceptable.

One example in a violation identified by the CAT inspection

(see Section J.) concerns structural steel bolts with torque

tension below that specified. The licensee has initiated

corrective actions which will be inspected in a future

inspection. In addition to the violations, a number of design

practices were found to be in need of improvement. During the

inspection appropriata corrective actions were taken by the

architect engineer to effect the needed improvements in the

design process.

The licensee's actions in response to the concerns forwarded to

them for review were timely, thorough, and technically sound.

A positive attitude was exhibited by the licensee and its

architect / engineer toward the prompt resolution of all issues

and implementation of improvements in the design process.

2. Ccnclusion

The licensee is rated Category 2 in this area. This is the

same rating as was given in the previous assessment period.

Licensee performance has remained the same during the assessment

period.

3. Board Recommendations

- None.

36

l

,

M. Piping Systems and Supports

1. Analysis

l

The work activities in this area were essentially complete.

Examination of this functional area consisted of seven

inspections by regional based inspectors and a portion of

the NRC CAT inspection. Areas examined included: (1) attend

periodic exit meetings conducted by the National Board of Boiler

and Pressure Vessel Inspectors to present their findings and the

progress of their comprehensive independent audit of ASME Code

l construction and related activities; (2) examine activities

l as they relate to the preservice inspection (PSI) of piping

l and systems, including a review of the PSI program and

,

procedures, equipment and material certifications, personnel

l qualifications, selected records of nondestructive examinations,

and observation of several liquid peustrant examinations;

,

(3) observe completed work and review installation records

1 and associated documentation for reactor coolant pressure

l boundary and other safety-related piping, including welder

l qualifications, weld repairs, visual examination of completed

'

welds, and review of radiographs of field pipe welds;

(4) evaluate the design, fabrication, and installation of

energy absorbing material used for pipe whip restraints;

,

(5) examine IE Bulletin 79-14 as-built walkdown inspection

i and design review, including a review of procedures, inspection

criteria, inspection measurements, and engineering analyses and

evaluations; (6) followup on licensee actions related to previous

l

inspection findings, 10 CFR 50.55(e) deficiency reports and

other IE Bulletins; (7) examine allegations; and (8) conduct

reviews of concerns expressed by an expert witness who

appeared on behalf of the Intervenors during the remanded ASLB

l

hearing for Byron.

Four violations were identified:

l

a. Severity Level V - Failure to follow procedures

during inspection (Report Nos. 454/84051; 455/84035).

b. Severity Level IV - Four examples of failure to

control design activities (Report Nos. 454/84051;

455/84035).

c. Severity Level V - Two examples of failure to have

,

adequate procedures (Report Nos. 454/84051; 455/84035).

i d. Severity Level V - Failure to identify as-built

l

dimension deviations during inspection (Report

Nos. 454/84051; 455/84035).

l

l

37

-. ..

The licensee efforts to resolve these violations were reviewed

during the course of the inspection and found acceptable prior

to the issuance of the full power license. The above violations

are not repetitive of violations identified during the previous

assessment period and they do not appear to indicate a programmatic

breakdown. One example in a violation identified by the CAT

inspection (see section J.) concerns concrete expansion anchor

embedment depth. The licensee has initiated corrective actions

which will be reviewed in a future inspection.

For tne areas examined, the inspectors concluded that with the

exceptions noted above, activities were generally controlled

through the use of well stated and defined procedures that were

adhered to. The approach used to evaluate IE Bulletin 79-14

findings was generally conservative, technically sound, and

thorough. Records were found to be generally complete, well

maintained, and available. The records also indicate that

preservice inspection equipment and material certifications

were current and complete and the personnel performing

nondestructive examinations were trained and certified. Review

of deficiency reports and IE Bulletin actions indicates that the

licensee understood the issues and their reviews were generally

timely, thorough, and technically sound.

2. Conclusion

The licensee is rated Category 2 in this area. This is the

same rating as was given in the previous assessment period.

Licensee performance has remained the same during the

assessment period.

3. Board Recommendations

None.

N. Safety-Relatad Components

1. Analysis

The work activities in this area were essentially complete.

Examination of this functional area consisted of six

inspections by regional based inspectors and a portion of

the NRC CAT inspection. Areas examined included: (1) evaluate

the qualification testing performed to confirm the

functionability of the as received Boeing steam generator

snubbers; (2) evaluate the modified snubber design, installation,

and qualification testing of the Paul Monroe Hydraulic (PMH)

snubbers procured to replace the Boeing snubbers on the Byron

Unit 1 steam generators; (3) review installation procedures,

observe the installation, and review installation documentation

for the PMH steam generator snubbers; (4) evaluate the redesign,

modification, and qualification testing of the ITT-Grinnell

38

-

modified Boeing steam generator snubbers; (5) review records

and associated documentation related to the welding of the

internals installed in the reactor vessels for both Unit 1

and 2; (6) evaluate the dispositicn and repair of indications

identified during preservice inspection of the Unit 2 steam

generators ~and pressurizer; and (7) followup on licensee

actions related to previous inspection findings, 50.55(e)

deficiency reports and IE Bulletins.

One violation was identified:

Severity Level V - Failure to conduct steam generator

snubber testing in accordance with approved procedures

(Report No. 455/85004).

In addition, one example from violation c. of Section M. cited

a lack of approved procedures to conduct steam generator

snubber tests. The licensee's written response to these

violations and corrective actions were reviewed and found to be

acceptable. These violations are not repetitive of violations

identified during the previous assessment period, and they do not

appear to indicate a programatic breakdown. A violation

identified by the CAT inspection (cee Section J. violation k.)

related to deficiencies in vendor supplied components. The

licensee has initiated corrective actions which will be

examined in a future inspection.

For the areas examined, the inspectors determined that

activities were controlled through the use of well stated and

defined procedures. With the exceptions noted above, these

procedures were adhered to. The approach used to evaluate,

design, test, and install snubbers was generally conservative,

technically sound, and thorough. Records and test data were

found to be generally complete, well maintained, and available.

Review of the deficiency reports and IE Bulletin actions

indicate that the licensee understood the issues and their

reviews were generally timely, thorough, and technically sound.

2. Conclusion

The licensee is rated Category 2 in this area. This is the

same rating as was given in the previous assessment period.

Licensee performance has remained essentially constant over

the course of the SALP assessment period.

3. Board Recommendations

None.

39

_ - _ _ - _ __ _

_____ _ _ __ _ _ - _ _ _ _ _ _ _

0. Support Systems Heating, Ventilating and Air Conditioning (HVAC)

1. Analysis

The work activities in this area were essentially complete.

Examination of this functional area was limited to one

inspection by regional based inspectors to review numerous

allegations relating to the quality of HVAC construction.

Two violations were identified:

a. Severity Level IV - Failure to control special processes and

personnel qualifications (Inspection Report No. 454/85011).

b. Severity Level IV - Failure to promptly identify and

correct conditions adverse to quality (Inspection Report

No. 454/85011).

The licensee's written response to these violations has been

reviewed and found to be acceptable. An inspection of

corrective actions will be made in a subsequent inspection at

the site.

2. Conclusions

The licensee was not rated in this area due to the limited

nature of the inspection. This area was rated category 2 in

the previous assessment period.

3. Board Recommendations

None.

P. Electrical Power Supply and Distribution

1. Analysis

Examination of this functional area consisted of ten inspections

by region based inspectors, portions of seven resident inspections

and a portion of the NRC CAT inspection. Areac examined included:

(1) review of previous inspection findings; (2) observations of

raceway and equipment installations; (3) observations of electrical

cable installations and terminations; (4) equipment storage and

maintenance activities; (5) conductor butt splice reinspection

program; (6) as-built drawing walkdown; and (7) tr:ining and

qualification of personnel.

Three violations identified by the CAT inspection (see Section

J. violations j., k., and 1.) relate to this functional area and

also Section Q. Several of the examples of violations were

repetitive of violations identified during the previous SALP

assessment period, although they are not interpreted to be

serious programatic breakdowns. The licensee has initiated

40

_ . ._ . _ _ _ _ _ _ __ _

corrective actions on these violations and the actions taken

will be reviewed during subsequent inspections. In the first

violation, one of the three examples identified is electrical.

This example identifies that the licensee was splicing Class 1E

wire inside of panels contrary to the requirements of IEEE

Standard 420 which is an FSAR commitment. The second violation

identifies numerous equipment assembly / mounting bolts, for

certain electrical and mechanical equipment, that were found to

be unmarked thus making the quality of these bolts indeterminate.

In the third violation, example 1 identifies that 4160V switchgear

units 2AP05E and 2AP06E and 125V DC fuse panel 2DC11J were not

installed in accordance with the requireirents for seismic

mounting of Class 1E equipment in that the mounting weld

configuration did not match the details shown on approved design

drawings. With respect to the 4160V switchgear, similar

deficiencies were previously identified on Unit 1 equipment;

however, the impact on relevant Unit 2 equipment was not reviewed.

Example 2 identified that some Class IE electrical raceways have

not been installed in accordance with FSAR commitments for

separation. Separation violations were also identified in the

previous SALP assessment period. Example 3 identified that 5 of

7 motor operated valves inspected contained two or more termination

errors that had been accepted by first line QC inspectors. The

licensee was responsive to NRC concerns and took appropriate

corrective actions to resolve the specific issues from a technical

and safety standpoint. However, the licensee was not always

aggressive in assessing potential problem areas. The violations

identified above represent examples wherein the licensee's

management attention should have been more effective.

2. Conclusion

The licensee is rated Category 2 in this area. This is the

same rating as was given in the previous assessment period.

Licensee performance has remained the same during the

assessment period.

3. Board Recommendations

None.

Q. Instrument and Control Systems

1. Analysis

Examination of this functional area consisted of significant

portions of ten region based inspections, portions of

four resident inspections, and a portion of the NRC CAT

inspection. Areas examined included: (1) review of previous

inspection findings; (2) observation of raceway and equipment

installations; (3) observation of electrical cable installations

and terminations; (4) equipment storage and maintenance activities;

41

_ ._ . _ _ . _ . - -

. . . - . -. _ . . - -. . ._--

(5) observation of instrument sensing line installations; (6)

conductor butt splice reinspection program; (7) as-built drawing

2

walkdown; (8) training and qualification of personnel; and also,

for certain equipment supplied by Systems Control Corporation,

(9) observing reinspection of certain welds; (10) visually

examining discrepant hanger welds, (11) attending formal

j classroom training to certify walkdown personnel in the

inspection of welds; and (12) reviewing the engineering analysis

and evaluations performed to demonstrate the structural adequacy

of the discrepant welds.

!

Due to the overlap between the this area and the electrical

area, Section P. of this report, the violations identified by

the CAT inspection and discussed in the electrical area are also

applicable to this functional area.

For the areas examined the inspectors determined that

activities were controlled through the use of well stated and

defined procedures. The personnel performing the inspections

were trained and certified. Reviews were thorough, technically

sound, and performed by experienced reviewers. The procedures

dealing with the performance of these analyses were functioning

properly. The structural adequacy of the Systems Control

Corporation supplied components was demonstrated.

The licensee was responsive to NRC concerns and took appropriate

corrective actions to resolve the specific issues from a technical

and safety standpoint. However, as discussed in Section P, the

,

licensee was not always aggressive in assessing potential

problem areas.

2. Conclusion

The licensee is rated Category 2 in this area. This is the

same rating as was given in the previous assessment period.

Licensee performance has remained the same during the

assessment period.

3. Board Recommendations

,

None.

f

d

42

. . _ __ _ _ .._ . _ _ __ _ _ _ _ _ . _ . . _ _ _ . ___ _ _ . _ _ ,. _ _ _ _ . _ _ _ _ _

V. SUPPORTING DATA AND SUPMARIES

A. Licensee Activities

During this SALP period, the following activities of interest

occurred:

1. October 31, 1984 - Licensee was issued Low Power (five percent)

Operating License No. NFF-23.

2. November 2 through November 27, 1984 - Initial Fuel Loading.

3. February 2,1985 - Initial Criticality.

4. February 4,1985 - Licensee was issued Full Power Operating

License No. NPF-37.

5. February 24, 1985 - Mode 1 (commenced Power Ascension Testing).

6. June 10 through June 13, 1985 - Byron Nuclear Generating

Station's Emergency Preparedness exercise.

7. September 16, 1985 - Power Ascension Testing completed, unit

turned over to Load Dispatching.

8. October 25, 1985 - Scheduled maintenance outage.

B. hspectionActivities

1. Inspection Data

a. Facility Name: Byron Unit 1 Docket No.: 50-454

Inspection Report Nos.: 84025 and 84026

84028 through 84080

84082 and 84083

84085 through 84088

85001 through 85017

85019 through 85031

85033 through 85044

85046

b. Facility Name: Byron Unit 2 Docket No.: 50-455

Inspection Report Nos.: 84018

84020 through 84039

84041 through 84057

85001 through 85004

43

__

85006 through 85010

85012 through 85015

85017 through 85025

85027 through 85029

85038 and 85040

85042 and 85043

2. Inspection Summary

The inspection programs at Byron during the evaluation period

were conducted by the NRC using resident and region based

inspectors, inspection teams and consultants. An NRC

Construction Appraisal Team (CAT) inspection was conducted on

August 19-30 and September 9-20, 1985, and is documented in

Inspection Report No. (50-455/85027). In addition, a Region I

Non-destructive Examination (NDE) van team inspection was conducted

on Unit 2 from October 28 through November 8, 1985; the results

will be reviewed in the next SALP assessment.

TABLE 1

ENFORCEMENT ACTIVITY

,

No. of Violations in Each Severity Level

Functional Unit 1 Unit 2 Site

i Areas III IV V III IV V III IV V

l

A. Plant Operations 2 6 1

B. Radiological Controls 1* 3 1

C. Maintenance 1 1

D. Surveillance 6

E. Initial Fuel Loading

F. Preoperational Testing 3 3

and Startup Testing

i

G. Fire Protection 3

i

H. Emergency Preparedness 1

I. Security 1 2

J. Quality Programs and

Administrative 3 1 3 1 3 1

Controls Affecting

Quality

f 44

. _ _ _ _ _ _ _ _ _ _ - - - -, __ __ __ , _ _ __ __ _ _ _ . -

.- _. --.

l

Functional Unit 1 Unit 2 Site

Areas III IV V III IV V III IV V

K. Licensing Activities

L. Containment, and ,

Other Safety-Related 1 2

Structures

,

M. Piping Systems & 1 3

Supports

N. Safety-Related Components 1

0. Support Systems 2

P. Electrical Power Supply

and Distribution

Q. Instruments & Control

Systems

TOTALS

4 26 8 0 3 2 1 7 6

i

  • Three violations were combined into one citation

C. Investigations and Allegation Review

There were 22 allegation cases initiated during this assessment

period. All have been reviewed; substantiated issues are documented

in inspection reports and followed to resolution. Violations

resulting from inspections of allegations are included in the

appropriate functional area section of this SALP report.

One, very extensive allegation case was initiated from the

concerns expressed by the expert witnesses for the Intervenors

which related to the QC Inspector Reinspection Program, Sargent

and Lundy Engineers' (the licensee's architect-engineer) design

criteria and calculations, computer programs, and several other

areas. Most of the concerns originated from the expert witness'

examination of documents during the discovery process for the

remanded hearing and from observations made by the expert

witnesses during a tour of the Byron facility with the Licensing

Board and hearing parties.

Region III arranged for other NRC offices to review some of the

concerns, forwarded many of them to the licensee for review, and

retained the remainder of Region III action, Although the concerns

were never expressed'to the NRC as allegations, the concerns were

nevertheless processed as allegations to assure a complete NRC review.

The Region III action of requiring the licensee to review many of the

concerns was an action consistent with the Commission policy on review

of allegations received near the licensing decision date.

45

D. Escalated Enforceinent Action

1. Civil Penalties

There were three civil penalties assessed during the SALP period

and operational violations identified near the end of the SALP

period that may result in another civil penalty.

a. Inspection Report Nos. 454/84-32, 455/84-25 assessed a

Civil Penalty of $40,000 based on statements made by the

licensee regarding inspections of products from Systems

Control Corporation.

b. Inspection Report No. 454/85012 imposed a civil penalty of

$25,000 for inadequate control of access in a vital area.

c. Inspection Report Nos. 454/85022, 455/85020 assesses a

civil penalty of $50,000 for three radiological protection

problems collectively.

2. Orders

No orders relating to enforcement were issued to the licensee

during the assessment period.

E. Licensee Conferences Held During Appraisal Period

Meetings

1. June 6, 1984, an enforcement conference to discuss licensee

submittals to the NRC relating to Systems Control Corporation

equipment.

2. July 19, 1984, Management meeting with Vice President and other ,

CECO management representatives in the Lombard, Illinois Holiday

Inn to review the systematic assessment of the licensee performance

'SALP 4) of the Byron Nuclear Station.

3. August 14, 1984, a public meeting was held to discuss matters

related to the integrated design inspection (IE, RIII, NRSS,

and CECO attended).

4. September 7, 1984, Management meeting with Commonwealth Edison

Company corporate staff to discuss the status of their

regulatory performance improvement program.

5. March 7, 1985, Management meeting with representatives to Ceco

to discuss the licensee's regulatory improvement program status.

6. March 27, 1985, Management meeting to discuss the progress of

the Byron startup program.

46

_- ._ . .. - - _ __

7. April 2, 1985, an enforcement conference to discuss vital area

access control relating to the door alarm system.

8. April 29, 1985, an enforcement conference to discuss the

operation of Unit I with certain protection system components

not seismically qualified, and the adequacy of the technical

review of test results.

i

9. June 24, 1985, Management meeting aimed at improving licensee

regulatory performance and enhancing communications between the

NRC and CECO. Meeting included an update of actions initiated

.

by CECO as a result of past meetings and involved discussion

regarding the effectiveness of the program, particularly in the

area of individual plant improvements.

10. June 27, 1985, Enforcement Conference to discuss exposure of

personnel above administrative limits and other radiation

protection problems associated with a May 1, 1985 incore

detector incident.

11. July 22, 1985, Enforcement Conference to discuss continuing

radiation protection problems since the June 27, 1985,

Enforcement Conference.

12. November 22, 1985, an enforcement conference to discuss the

inoperable condition of both RHR trains of ECCS and other

failures to follow technical specifications.

In addition, meetings were held between NRC staff and licensee plant

management on a monthly basis to assess overall facility status

through the various phases of licensing. After issuance of the

license, the meetings were continued in order to assess plant

operations.

F. Confirmatory Action Letters

'

A Confirmatory Action Letter was issued on March 15, 1985, regarding

the failure of the 1A and 10 Main Steamline Isolation Valves (MSIVs)

to close and other plant responses during the loss of offsite power

test.

G. Review of Licensee Event Reports, Construction Deficiency Reports

and 10 CFR 21 Reports Submitted by the Licensee

1. Licensee Event Reports (LERs)

'

The licensee has held a full power license for Byron Unit 1

since February 14, 1985. Unit 2 is still under construction.

During this time the licensee reported 64 non-security events

to the NRC Operations Center. One of these events was considered

significant by the staff and was followed up and reviewed in

detail. This event involved air check valves leaking which

resulted in two MSIVs failing to close on March 14, 1985.

47

.

The licensee issued 91 LERs during the assessment period in

1985. Forty-three LERs were issued during 1984 from the date

the Byron plant received its low power license (October 31,

1984) until the end of the calendar year 1984.

The following is the number of LERs classified with each cause,

issued during the assessment period:

Number of LERs Cause

, 65 Personnel Error

26 Design, Manufacturing,

and Construction /

Installation

7

'

External Cause

15 Defective Procedure

2 Management / Quality

Assurance Deficiency

19 Other(cannotbe

identified or assigned

to another

classification)

  • Cause is assigned by the licensee according to NUREG - 0161,

" Instructions for preparation of Data Entry Sheets for Licensee

Event Report (LER) File," nr NUREG - -1022, " Licensee Event

Report System."

Twenty-three of the events reported for 1985 have involved reactor

trips. This represents a rate which is significantly higher

than average for new plants (average about 12-15 trips per year)

and well above the rate for more mature facilities (about 5-6

trips per year).

Reviews of operating experience at Byron 1 for the fuel load /

low power license period (October 31, 1984 to February 14,

1985) indicate that Byron 1 had a higher frequency of reportable

events than other recently licensed plants for similar periods

of operation. This higher frequency was primarily the result

of two factors: recurring inadvertent actuations of the

control room ventilation isolation system; and actuations of

the baron dilution prevention system. Both of these problems

appear to have been substantially corrected before the end of

the SALP period.

The frequency of all events in the period is somewhat higher than

is typical for new plants. However, the frequency of reactor

trips is significantly higher than normal.

48

2. Construction Deficiency Reports (CDR)s: 10 CFR 50.55(e)s

During this SALP performance 9 CDRs were submitted by the

licensee under the requirements of 10 CFR 50.55(e). The

content of these reports was acceptable.

a. Containment spray pumps identification confused between

pumps with differing outlet pressure capacity.

b. Acceptability of electrical cable butt splices

indeterminate based on inspection results from other sites.

c. Spot weld connection on Westinghouse 480V breaker

connection found questionable,

d. Boeing steam generator snubbers failed to meet test

criteria.

e. Steam generator snubber under ultrasonic testing revealed

material lamination around the piston rod end,

f. Energy absorbing material had lower than specified crush

strength,

g. Westinghouse motor control centers circuit breakers AMP

fault current capability too low.

h. Seismic qualification of containment floor drain valves.

i. Environmental effects on High Energy Line Break (HELB) in

Auxiliary Building.

3. Part 21 Reports

Two 10 CFR Part 21 reports were submitted by the licensee during

this assessment period.

a. Airline check valves manufactured by Parker-Hannafin,

supplied by Anchor-Darling Valve Co. fail to reseat on slow

bleed off of supply side air pressure.

b. Degradation of diesel RPM reading giving indication in the

standby mode due to power supply noise

H. Licensing Actions-

1. NRR Site and Corporate Office Visits

August 23, 1984, Audit of river screenhouse analyses at Sargent

& Lundy

49

_. . . _ ._. . _ _ - . _ _ _ _ _ _ _ _ _ _ . -

October 2, ?984, Management site visit to determine readiness

for fLe1 load.

September 20, 1985, Site visit for CAT exit meeting.

2. Commission Briefing

February 12, 1985, Favorable' Commission vote to authorize full

power operation.

3. Schedular Extension Granted

None.

4. Relief Granted

October 1984, Supplement No. 5 to SER grants relief for preservice

inspection and inservice testing of pumps and valves.

February 1985, Supplement No. 6 to SER grants relief in

inservice testing of pumps and valves.

August 30, 1985, Emergency relief from preservice inspection

requirements granted.

September 24, 1985, Second relief granted (on August 30, 1985,

request) from preservice inspection requirements.

5. Exemption Granted

October 31, 1984, Exemptions to Appendices A and J granted with

low power license for Byron 1.

February 14, 1984, Exemptions to Appendices A, E and J granted

with full power license for Byron 1.

August 27, 1985, Exemption granted to Section 50.71(e)(3)(1) to

defer submittal of updated FSAR for Byron 1 and 2.

October 28, 1985, Schedular exemption from GDC 4 on

leak-before-break for Byron 2.

6. License Amendments Issued

Amendment No. 1 to Low Power License, issued January 28, 1985,

adds footnote to table of containment isolation valves that

allows certain valves to be opened on an intermittent basis

under administrative controls.

Amendment No. I to Full Power License, issued October 1, 1985,

i relates to administrative controls for access to high radiation

areas during certain emergencies.

'

50

7. Emergency / Exigent Technical Specification

January 18, 1985, Emergency Technical Specification authorized

by telephone call from Assistant Director for Licensing.

Formal change issued January 28, 1985 (see Item 6 above).

8. Orders Issued

None

9. NRR/ Licensee Management Conference

None.

51

. .

___ _ - - ___-___- ___-