|
---|
Category:Inspection Report
MONTHYEARIR 05000395/20230042024-01-31031 January 2024 Integrated Inspection Report 05000395/2023004 IR 05000395/20240112024-01-17017 January 2024 Notification of VC Summer Station Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000395/2024011 IR 05000395/20230912023-12-21021 December 2023 Final Significance Determination of a White Finding and Notice of Violation and Assessment Followup Letternrc Inspection Report 05000395/2023091 IR 05000395/20234032023-11-0101 November 2023 Material Control and Accounting Program Inspection Report 05000395/2023403 Cover IR 05000395/20230032023-11-0101 November 2023 Integrated Inspection Report 05000395/2023003 IR 05000395/20230902023-10-0404 October 2023 NRC Inspection Report 05000395/2023090 and Preliminary Yellow Finding and Apparent Violation IR 05000395/20230112023-09-27027 September 2023 Focused Engineering Inspection Report 05000395/2023011 IR 05000395/20234012023-08-30030 August 2023 Security Baseline Inspection Report 05000395/2023401 IR 05000395/20230052023-08-23023 August 2023 Updated Inspection Plan for Virgil C. Summer Nuclear Station (Report 05000395 2023005) IR 05000395/20230022023-08-14014 August 2023 Integrated Inspection Report - Integrated Inspection Report 05000395/2023002 and Apparent Violation IR 05000395/20230102023-08-12012 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000395/2023010 IR 05000395/20234412023-07-17017 July 2023 95001 Supplemental Inspection Report 05000395/2023441 and Follow Up Assessment Letter ML23131A3512023-05-12012 May 2023 Integrated Inspection Report 05000395/2023001 IR 05000395/20230012023-05-12012 May 2023 Integrated Inspection Report 05000395/2023001 IR 05000395/20230402023-05-0101 May 2023 95001 Supplemental Inspection Supplemental Report 05000395/2023040 and Follow-Up Assessment Letter ML23075A1702023-03-21021 March 2023 Security Baseline Inspection Report 05000395/2023420 IR 05000395/20234202023-03-21021 March 2023 Letter - Virgil C. Summer Nuclear Station, Unit 1 Security Baseline Inspection Report 05000395/2023420 IR 05000395/20220062023-03-0101 March 2023 Annual Assessment Letter for Virgil C. Summer Nuclear Station (Report 05000395/2022006) IR 05000395/20220042023-02-10010 February 2023 Integrated Inspection Report 05000395/2022004 IR 05000395/20234402023-02-0202 February 2023 Final Significance Determination for a Security-Related Greater than Green Finding, Notice of Violation and Assessment Follow-up Letter, NRC Security Inspection Report 05000395/2023440 ML22314A1832022-11-14014 November 2022 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000395/ 2022012 IR 05000395/20220032022-10-31031 October 2022 Integrated Inspection Report 05000395/2022003 IR 05000395/20220912022-10-18018 October 2022 Final Significance Determination of a White Finding and Notice of Violation and Assessment Follow-up Letter; NRC Inspection Report 05000395/2022091 IR 05000395/20220112022-09-29029 September 2022 Fire Protection Team Inspection Report 05000395/2022011, Summer Report Final IR 05000395/20220052022-08-26026 August 2022 Updated Inspection Plan for Virgil C. Summer - Report 05000395/2022005 IR 05000395/20224012022-08-23023 August 2022 V. C. Summer Nuclear Station Cyber Security Inspection Report 05000395 2022401 - Cover ML22216A1202022-08-0404 August 2022 IR2022002 Summer for Workflow IR 05000395/20220902022-07-14014 July 2022 NRC Inspection Report 05000395/2022090 and Preliminary White Finding and Apparent Violation IR 05000395/20220012022-05-12012 May 2022 Integrated Inspection Report 05000395/2022001 and Apparent Violation IR 05000395/20220102022-03-10010 March 2022 NRC Inspection Report 05000395 2022010 IR 05000395/20210062022-03-0202 March 2022 Annual Assessment Letter for Virgil C. Summer Unit 1 (Report No 05000395/2021006) IR 05000395/20224022022-02-15015 February 2022 Security Baseline Inspection Report 05000395/2022402 IR 05000395/20210042022-01-21021 January 2022 Integrated Inspection Report 05000395/2021004 IR 05000395/20213012021-11-0303 November 2021 NRC Operator License Exam Report 05000395/2021301 IR 05000395/20210032021-10-28028 October 2021 Integrated Inspection Report 05000395/2021003 IR 05000395/20210052021-08-24024 August 2021 Updated Inspection Plan for Virgil C.Summer Nuclear Station, Unit 1 (Report 05000395/2021005) IR 05000395/20214022021-08-0505 August 2021 Security Baseline Inspection Report 05000395/2021402 IR 05000395/20210022021-08-0404 August 2021 Integrated Inspection Report 05000395/2021002 IR 05000395/20210102021-08-0202 August 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000395/2021010 IR 05000395/20214032021-07-0808 July 2021 Target Set Inspection Report 05000395/2021403 IR 05000395/20210112021-06-0101 June 2021 Biennial Problem Identification and Resolution Inspection Report 05000395/2021011 IR 05000395/20210012021-05-12012 May 2021 Integrated Inspection Report 05000395/2021001 IR 05000395/20214012021-04-16016 April 2021 Security Baseline Inspection Report 05000395/2021401 IR 05000395/20200062021-03-0303 March 2021 Annual Assessment Letter for Virgil C. Summer Station, Unit 1 Report 05000395/2020006 IR 05000395/20200042021-02-0909 February 2021 Integrated Inspection Report 05000395/2020004 and Independent Spent Fuel Storage Installation (ISFSI) Inspection 07201038/2020002 IR 05000395/20200102020-12-21021 December 2020 NRC Design Bases Assurance Inspection (Team) Report 05000395/2020010 IR 05000395/20204022020-12-0303 December 2020 NRC Inspection Report 05000395/2020402 IR 05000395/20200032020-11-0505 November 2020 Integrated Inspection Report 05000395/2020003 IR 05000395/20200022020-08-0404 August 2020 Integrated Inspection Report 05000395/2020002 and Independent Spent Fuel Storage Installation Inspection (ISFSI) Report 07201038/2020001 ML20196L7782020-07-13013 July 2020 Notification of Virgil C. Summer Nuclear Station Design Bases Assurance Inspection U.S. Nuclear Regulatory Commission Inspection Report 05000395/2020010 2024-01-31
[Table view] Category:Letter
MONTHYEARML24038A0322024-02-0707 February 2024 (Vcsns), Unit 1, 10 CFR 21 Report - Emergency Diesel Generator Flash Contactor Relay IR 05000395/20230042024-01-31031 January 2024 Integrated Inspection Report 05000395/2023004 ML24022A1582024-01-22022 January 2024 (Vcsns), Unit 1 - Reply to a Notice of Violation: EA-23-093 ML24022A1202024-01-22022 January 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000395/2024403) ML24018A0112024-01-18018 January 2024 CFR 21 Report Emergency Diesel Generator Fuel Oil Piping IR 05000395/20240112024-01-17017 January 2024 Notification of VC Summer Station Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000395/2024011 ML23361A1042023-12-21021 December 2023 Inservice Testing Program for Pumps and Valves Fifth Interval Update and Associated Relief and Alternative Requests IR 05000395/20230912023-12-21021 December 2023 Final Significance Determination of a White Finding and Notice of Violation and Assessment Followup Letternrc Inspection Report 05000395/2023091 ML23354A1802023-12-20020 December 2023 301 Examination Report with Cover Letter ML23347A0492023-12-12012 December 2023 Technical Specification Bases Changes Updated Through November 2023 ML23334A2462023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23334A2372023-11-30030 November 2023 (Vvsns), Unit 1 - Annual Commitment Change Summary Report ML23332A1942023-11-28028 November 2023 (Vcsns), Unit 1, Correction of Typographical Error in License Amendment Request - Inverter Allowed Outage Time (AOT) Extension ML23317A2242023-11-0909 November 2023 (Vcsns), Unit 1 - License Amendment Request - Inverter Allowed Outage Time (AOT) Extension ML23289A1172023-11-0303 November 2023 Tribal Request for Scoping Comments Concerning the Environmental Review of the V.C. Summer SLRA ML23289A1152023-11-0303 November 2023 Ltr to R. Nelson - Request for Scoping Comments Concerning the Environmental Review of the V.C. Summer SLRA ML23289A1162023-11-0303 November 2023 Ltr to W. Emerson - Request for Scoping Comments Concerning the Environmental Review of the V.C. Summer SLRA IR 05000395/20234032023-11-0101 November 2023 Material Control and Accounting Program Inspection Report 05000395/2023403 Cover IR 05000395/20230032023-11-0101 November 2023 Integrated Inspection Report 05000395/2023003 ML23284A1792023-10-16016 October 2023 Subsequent License Renewal Application Online Reference Portal ML23275A0142023-10-11011 October 2023 SLRA - Acceptance and Opportunity for Hearing - Letter ML23284A1662023-10-10010 October 2023 (Vcsns), Unit 1 - Request for Regulatory Conference; (EA-23-093) IR 05000395/20230902023-10-0404 October 2023 NRC Inspection Report 05000395/2023090 and Preliminary Yellow Finding and Apparent Violation IR 05000395/20230112023-09-27027 September 2023 Focused Engineering Inspection Report 05000395/2023011 ML23250A3112023-09-20020 September 2023 Request to Revise Reactor Vessel Material Surveillance Capsule Withdrawal Schedules ML23244A2352023-09-18018 September 2023 Request to Use a Subsequent Edition of the ASME Code, Section XI ML23230A0012023-09-15015 September 2023 Request to Use a Provision of a Previous Edition of the ASME Boiler and Pressure Vessel Code, Section XI, for Non-Destructive Examinations ML23235A0432023-09-0505 September 2023 Receipt and Availability of the Subsequent License Renewal Application IR 05000395/20234012023-08-30030 August 2023 Security Baseline Inspection Report 05000395/2023401 ML23242A1192023-08-29029 August 2023 (Vcsns), Unit 1 - Inservice Inspection (ISI) Owner'S Activity Report (OAR) for Refueling Outage 27 ML23243B0362023-08-25025 August 2023 Request for FEMA Consultation on the Dominion Energy Proposal to Consolidate the Emergency Operations Facility for the Virgil C. Summer Nuclear Station Unit 1 IR 05000395/20230052023-08-23023 August 2023 Updated Inspection Plan for Virgil C. Summer Nuclear Station (Report 05000395 2023005) ML23233A1752023-08-17017 August 2023 Application for Subsequent Renewed Operating License IR 05000395/20230022023-08-14014 August 2023 Integrated Inspection Report - Integrated Inspection Report 05000395/2023002 and Apparent Violation IR 05000395/20230102023-08-12012 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000395/2023010 ML23207A1102023-07-26026 July 2023 NRC Regulatory Issues Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations IR 05000395/20234412023-07-17017 July 2023 95001 Supplemental Inspection Report 05000395/2023441 and Follow Up Assessment Letter ML23190A0012023-07-0909 July 2023 Special Report 2023-003 Inoperable Radiation Monitoring Instrumentation Channel ML23187A5092023-07-0606 July 2023 Request for Federal Emergency Management Agency Consultation on the Dominion Energy Proposal to Consolidate the Emergency Operations Facility for the Virgil C. Summer Nuclear Station Unit 1 ML23178A1682023-06-26026 June 2023 2022 Annual Report of Emergency Core Cooling System (ECCS) Model Changes Pursuant to the Requirements of 10 CFR 50.46 ML23173A1052023-06-22022 June 2023 Special Report 2023-002 Inoperable Loose-Part Monitoring System Channel ML23163A2352023-06-12012 June 2023 Request to Use a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI, for the SPS Sixth Inservice Inspection (Isi) Intervals and VCSNS Fifth ISI Interval ML23159A2332023-06-0808 June 2023 License Amendment Request - Emergency Response Organization Augmentation Time Change, Emergency Operations Facility Relocation and Other Emergency Plan Changes ML23156A3092023-06-0505 June 2023 Requalification Program Inspection Virgil C. Summer Nuclear Station Unit 1 - 05000395/2023003 2024-02-07
[Table view] |
Text
June 11, 2020
SUBJECT:
VIRGIL C. SUMMER NUCLEAR STATION - MATERIAL CONTROL AND ACCOUNTING PROGRAM INSPECTION REPORT 05000395/2020401
Dear Mr. Stoddard:
On May 26, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Virgil C. Summer Nuclear Station and discussed the results of this inspection with Mr. George Lippard, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
The enclosed report contains Security-Related Information, so the enclosed report will not be made publicly available in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii).
Sincerely,
/RA/
Randall A. Musser, Chief Reactor Projects Branch 3 Division of Reactor Projects Docket No. 05000395 License No. NPF-12 Enclosure:
As stated cc w/o encl: Distribution via LISTSERV cc:
Mr. Michael S. Moore, Manager Nuclear Licensing Virgil C. Summer Nuclear Station Bradham Blvd & Hwy 215 Post Office Box 88, Mail Code 830 Jenkinsville, SC 29065 ML20164A223 Cover Letter Only: X Non-Sensitive X Publicly Available X SUNSI Review Sensitive Non-Publicly Available OFFICE DRP DRP DRP NAME JDolecki LPressley RMusser DATE 6/10/2020 6/11/2020 6/11/2020