ML20154M370

From kanterella
Jump to navigation Jump to search
Insp Rept 50-289/88-07 on 880306-0409.No Violations Noted. Major Areas Inspected:Loss of B make-up Pump,Loss of D 125-volt Ac Vital Bus,Safety Issues Mgt Sys B-75/85 for Generic Ltr 83-28 & Diesel Generator Exhaust Manifold Fires
ML20154M370
Person / Time
Site: Crane Constellation icon.png
Issue date: 05/25/1988
From: Cowgill C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20154M348 List:
References
TASK-3.D.3.4, TASK-TM 50-289-88-07, 50-289-88-7, DL-83-28, NUDOCS 8806010264
Download: ML20154M370 (32)


See also: IR 05000289/1988007

Text

_

_

___

__

_

.

l

.-

i

l

-

.

!

'

I

-U.S. NUCLEAR REGULATORY COMMISSION.

~'

REGION I

!

Docket / Report No. 50-289/88-07

License: OPR-50

i

Licensee:

GPU Nuclear Corporation

!

P. 0.' Box 480

l

Middletown, Pennsylvania 17057

Facility:

Three Mile Island Nuclear Station, Unit 1

Location:

Middletown, Pennsylvania

Dates:

March 6, 1988 - April 9, 1988

Inspectors:

W. Baunack, Project Engineer, Region I (RI)

R. Conte, Senior Resident Inspector

  • 0. Johnson, Resident Inspector

T. Moslak, Resident Inspector

.

S. Sherbini, Radiation Specialist, RI

-[

A. Sidpara, Resident Inspector

!

C. Woodard, Reactor Engineer, RI

Accompanied

by:

S. Peleschak, Reactor Engineer, RI

  • Reportin Inspector

,

Approved by:

).

._

CT' Cow (1T1, Chief, Reactof Projects Section No. lA

Date

\\

Inspection Summary: The NRC staff conducted routine safety inspections during nor-

!

mal plant power operation.

Plant operational items reviewed were: loss of "B"

make-up pump; loss of "D" 125 volt a.c. vital bus; and, Safety Issues Management

{

System (SIMS) Item No. B-75/85 for Generic Letter 83-28, "Post Trip Review Process."

[

Other items reviewed in other functional areas included: reactor d.c. trip breaker

.

N . 4 failure; diesel generator exhaust manifold fires, SIMS Item Nos. III.D.3.4.3

5

and M64800 on control room habitability; physical security; Independent On-site

Review Group (IOSRG); and, licensee action on previous inspection findings.

,

Inspection Results: Operations activities continued to be accomplished in a safe

manner, operator attention and response to the three operational events was good

in that no major plant transient resulted from these initiating events.

,

The IOSRG activities were improved, although the procedure was not being followed

i

i

exactly. A procedure change is in progress to correct this situation,

e

d

i

licensee action in the areas of radiological controls and engineering support for

j

previous inspection findings was adequate.

o

1

No violations of regulatory requirements were identified. Three unresolved issues

!

i

l

were identified: one involved licensee action to evaluate 125-volt a.c. breaker

!

'

trip sequences; the second concerned licensee action to resolve the problems as-

!

i

sociated with the reactor trip breaker failure; and, the third item involved lic-

l

i

ensee action to modify the 10SRG procedures to properly reflect the actions being

j

accomplished by the 10SRG personnel.

"

88j60 Qj$ $$ob

g9

e

4

.

,

t

.

.

.

.

TABLE OF CONTENTS

Pagg

1.0 Introduction and 0verview............................................

1

1.1 Licensee Activities.................................

...........

1

1.2 NRC Staff Activities..................................

.........

1

1.3 Persons Contacted...............................................

1

2.0 Plant Operations..................

... ..............................

2

2.1 Cri teria/ Scope of Review (NIP 71707) . . . . . . . . . . . . . . . . . . . . . . . . . . . .

2

2.2 Ev e n t s ( N I P 9 2 7 0 3 ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

3

2.2.1

Temporary Loss of "B" Make-Up Pump....................

3

2.2.2

Loss of "0" 125-Volt a.c. Vital

Bus.........

.........

3

2.3 SIMS Item No. B-75/B-85 - Post-Trip Review Process (NIP 25564)..

4

2.4 Operations Summary. . .

5

.............................. ...........

3.0 Radiological Ccntrols (NIP 83722)....................................

5

3.1 Organization and Qualification..................................

5

3.2 Licensee Actions on Previous Unresolved Items...................

6

3.2.1

(Closed) Inspector Follow-Up Item (289/83-26-03):

Temperature Effects on the Output of the Turbine

Building Sump Monitor.

6

...............................

s

3.2.2

(Closed) Inspector Follow-Up Item (289/85-30-03): Rem

j

Audit Tracking System.........

7

1

...... ................

3.2.3

(Closed) Unresolved Item (289/86-12-16): Procedure

Adequacy and Implementation for Shielding

Installation..........................................

7

3.2.4

(Closed) Inspector Follow-Up Item (289/86-13-04):

Radiological Control Department Organization for

TMI-1.................................................

7

3.2.5

(Closed) Violation (289/86-17-10): Failure to Provide

Design Basi s for Radiation Monitor Settings. . . . . . . . . . .

8

3.2.6

(Closed) Violation (289/87-09-12): Failure to Survey for

Letdown Prefilter Cubicle Work........................

8

3.2.7

(Closed) Violation (289/87-09-13): Failure to Follow

Control Procedures for When Standing Radiation Work

Permit Is Not To Be Used..............................

9

3.2.8

(Closed) Unresolved Item (289/87-09-14): Effectiveness

of Licensee Measures to Assure High Radiation Areas

Remain Properly Posted / Barricaded.....................

9

3.3 RIR Review......................................................

9

3.4 Radiological Controls

Summary...................................

11

i

_

.

--.-

e

t

.

.

Table of Contents

/

,

l*

Page

4.0 Equipment Operability Review - Maintenance / Surveillance

(NIP 61726/61703)....................................................

11

4.1 C ri t e ri a/S c ope o f Rev i ew. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

11

4.2 Reactor Tri p Brea ker No. 4 Failure . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

11

4.3 Operational Test of the Emergency Of esel EG-Y-1B. . . . . . . . . . . . . . .

12

4.4 Licensee Actions on Previous Inspection Findings. . . . . . . . . . . . . . . .

14

4.4.1

(0 pen) Inspector Follow-Up Item (289/86-10-02):

Significant Damage to the Diesel-Driven Fire Pump

Building..............................................

14

4.4.2

(0 pen) Ure'esolved Item (289/87-06-05): Review of Delta

Pressure Instrument

Performance.......................

15

4.5 Equipment Operability Summary...................................

15

5.0 Engineering Support (NIP

37700)......................................

15

5.1 SIMS Items......................................................

15

5.1.1

(Closed) SIMS No. I11.0.3.4.2: Control Room

Habitability..........................................

15

5.1.2

(Closed) SIMS No. M64800: Technical Specificstion for

Chlorine Detection and (Closed) Unresolved Item

(289/87-11-03)........................................

16

5.2 Licensee Actions on Previous Inspection Findings. . . . . . . . . . . . . . . .

17

5.2.1

(Closed) Unresolved Item (289/86-12-14): Minimum Motor

Starting Voltages.....................................

17

5.2.2

(Closed) Unresolved Item (289/86-12-12): Design Input

Associated with Emergency Feedwater Pump (EFW) Over-

current Protection....................................

18

5.2.3

(Closed) Unresolved Item (289/86-12-15) and

289/87-10-01: Instrumentation Grounding and Shieldin

S t a n d a rd s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . g

19

..

5.2.4

(Closed) Violation (289/87-01-15): Improper Mounting

of Foxboro D/P Transmitters...........................

19

5.2.5

(Closed) Unresolved Item (289/86-03-22): Procurement

Deficiencies for Back-Up Instrument Ai r. . . . . . . . . . . . . . . 20

5.2.6

(Closed) Unresolved Item (289/86-12-01): Evaluations

of EFW Pump Recirculation Line Design Change..........

20

1

5.3 E n g i n e e r i n g S u p p o r t S uena ry . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

5.0 Physical Security Plan Implementation (NIP 71881)....................

21

l

ii

-

'

), '

r

T

4

p-

f

s

.

i

\\'

'

.

.<

.

J

Table of Contents

)-

,

,

, ,

i

.)

V

}

N

Page

'

I

7.0 Safety Assessment - Independent On-Site Safety Review Group

Performance (N,it' 40700)............ 7.i....................

...........

21

8.0 Eme rg e ncy P rep a redn e s s ( N Ip 717D7 ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

25

\\>

i

9.0 Exit Interview (N!? 30703)....

25

-

,

,

ATTACHMENT

ATTACHMENT 1 - Activities Reviewed

y.

'

}

t

,

'!

f

J

,

'

t

f

r

I

>

{

j

(

s

\\

'

i

<

s

(

t

)

o

9

.f

l

l

l

l'

, l'

'

'

I

r<

,.

\\

t

,

n

'

/

/

,

1

e

t

/

!

,

,

<

t

.

(

'l

^

.

i

/

'

-

e

/

j

/

/

1

'

iii

/

i

,

1

-

_

-.

e

_

.-

. _ .

.

.

.

.

.

. .

-

a

G

$

.

.

R

.l

DETAILS

'1.0

Introduct_ '

10verview

1.1 Licensee , tj- ;tes

During th'

ort period.- the plant operated at full power. As of 8':00

a.m. on April 9,1988, TMI-1 was operating at full power with the' reactor

coolant system (RCS) at normal operating temperature.(579 F average) and

pressure (2155 psig).

1.2 NRC Staff Activities

The purpose of this inspection was to assess licensee activities during

the power operations mode as they related to reactor safety, safeguards,

and radiation protection. Within each area, the inspectors documented

the specific purpose of the area under review, acceptance criteria and

scer of inspection, along with appropriate. findings / conclusions. - The

inspectors made this assessment by observation of licensee activities,

interviews with licensee personnel, measurement of radiation levels, or

independent calculation and selective review of listed applicable docu-

ments. NRC staff inspections are generally conducted in accordance with

NRC Inspection Procedures (NIP's).

These NIP's are noted under the

appropriate section in the Table of Contents to this report.

s

Also, the inspector verified proper implementation, on a sampling basis,

-

of licensee actions related to.the below-listeo NRC Safety Issue Manage-

ment system (SIMS) item.

The inspectior, approach for the SIMS item was:

--

research various licensee and NRC correspondence, including Safety

Evaluation Reports (SER's) to identify key assumptions, commitments,

or other licensee actions to. be taken to resolve the safety issues;

--

identify any additional items which need to be verified as deline-

ated in the related NRC Temporary Instruction or other inspection

procedures;

verify proper implementation of the items planned above; and,

--

assess licensee performance related to that implementation and re-

--

lated to dissemination of the issue and its resolution to licensee

personnel who need to know, such as by procedural upgrading and

training.

1.3 Persons Contacted

During this inspection, the following key licensee parsonnel- provided

substantial information in the development of the inspectors' findings.

- -

- - -

-

- -

.

- - -

-

~

.

.

_ -

..

--.

.

. .

, , .

.

4

2

.

D. Atherholt, Plant Operations. Engineer

--

S. Babzcak, Administrator, Sr., Human Resources

--

--

H. Behling, Manager, Radiological Health, TMI-1

R. Barth, Fire Protection Engineer

--

-J. Bowmen, Electr.ical Maintenance

--

13. Brandt, Plant' Security

--

--

G. Broughton, Operations / Maintenance Director

J. Colitr, Manager, Plant Engineering

--

--

  • J. Curry, 10SRG Chairman

--'

J. Dullinger , Plant Engineering

L. Edwards, Operations _ Quality Assurance Monitor

--

K. Garthwaite, Plant Engineering

--

--

R. Germann, Nuclear Safety Assessment Director

--

D. Hassler,. Licensing Engineer

--

H. Hukill, Vice President and Director, TMI-1

C. Incorvati, Audit Manager

--

  • R. Knight, Licensing Engineer

--

P. Levine, Electrical Engineer

--

T. O'Connor, Lead Fire Protection Engineer

--

--

A. Palmer, Manager, Radiological Controls Field Operations

J. Pearce, Plant Materiel

--

--

  • M. Ross, Director, Plant Operations-

--

J. Schmidt, Radiological Engineer

R. Shaw, Manager, Radiologica1LEngineer, TMI-1.

--

--

H. Shipman, Piant'0perations E..gineer

--

D. Shovlin, Plant Materiel Director

--

r Smyth, Manager, Licensing

--

  • r. Snyder, Materiel Assessment Manager

J. Stevens, Corporate Engineer

--

--

R. Warren, 10SRG

--

S. Williams, Radiological Engineer

  • Denotes attendance at final exit rneeting (see also Section 9).

2.0 Plant Operations

2.1 Criteria / Scope of Review

The resident inspectors periodically inspected the facility to determine

the licensee's compliance with the general operating. requirements of

Section 6 of the Technical Specifications (TS) in the following areas:

review of selected plant parameters foe abnormal trends;

--

plant status from a matntenance/ modification viewooint, including

--

plant housekeeping and fire protection measures;

control of ongoing and special evoluticNs, including control room

--

personnel awareness of these evolutions;

.

-

- - - - -

-

-

-

-

-

- - -

-

-

-

- - -

- - - -

-

-

--

_ _

. _ . _

.

_ _

_.

._

_

_

_

_ - _

._

,

.

.

3

.

control of documents, including,logkeeping practices;

--

--

implementation of radiological controls; and,.

,

implementation of the. security plan, including access control,

--

boundary integrity, and badging p'actices.

r

The inspectors focused on the areas listed in Attachment 1.

. Findings.

and conclusions in this functional-area are . addressed below and, in other

functional areas, in other sections of this report.

2.2 Events

2.2.1

Temporary Loss of "B" Make-Up pump

On March.29, 1988, electricians were performing preventive

maintenance on.the "S" 480-volt a.c. bus tie breaker to the

"P" bus (Breaker 1S-12).

Main annunciator alarras C-2-7 "4KV

Engineered Safeguards (ES) motor trip" and C-3-7 "480.V ES

motor trip" were received.

Operators identified MU-P-1B as

being tripped and auxiliary / fuel handling buildings and control

tower ventilation as being shut down.

The control room operators promptly restored make-up and seal

injection using the "A" make-up pump. At essentially the same

time, the electrician' working in the "S" bus room-reported

i

accidentally bumping and tripping.the supply breaker.to IC ES

valves Motor Control Center (MCC), which resulted in loss of

-

the make-up pump lube oil pumps.

Letdown was re-estabitsbed

at 2.5 gpm and the "B" make-up pump was returned-to service

following hand rotating the pump.

The licensee prepared Plant Incident Report (PIR) No.1-88-01

~

to document this occurrence and prescribe ~ corrective actions.

The inspector reviewed the report and concluded that the cause

was attributable to worker activities while performing main-

tenance-activities.

Corrective actions consisted of worker

and crew briefings which re-emphasized'the need to use care

when working with energized equipment that affects plant

operations. The inspector concurred that this event was an

isolated occurrence and not indicative of an overall problem

with worker actions having a negative affect on plant opera-

tions.

Licensee corrective actions were acceptable.

~

j

2.2.2

Loss of "D" 125-Volt a.c. Vital Bus

-

On March 31, 1988, the pisnt experienced the loss of the "D"

- 125-volt a.c. vital bus.

This resulted in the control room

receiving multiple plant' alarms on the main annunciator board.

Electricians were in the process of performing maintenance on

,

.yp

,- ,.

,

,sw- , , , . .

---,,m-

,,,,..,,,,pm-%

,- . , , - . . - - .

,,.,,,,,,,,,,--sm.,

, 9

,n-....

- --

-m,

.

,,,--.,-r9

,-.

.- . . .

- -.. -.

-

.

-.

.

. ._

-

.. .

- . -

..

..

.

.

.

4

.

the "D" battery charger; and, durin'g the' accomplishment'of the

maintenance, the d.c..and a.c. input breakers for thes"0"'in-

verter opened which resulted in the de-energizationLof the;"D"

125-volt a.c. bus.

The breakers tripped asca result of high.

voltage testing of. the "D" battery charger. Altho' ugh the

-

charger was to be isolated during the test, it was not.

'

Thelicensee-issueda-Plant'ilncidentReport(PIR)No.1-88-02

to document the problem and specify corrective actions.

The

.cause was a misinterpretation of procedure PM-E-18, which

called for the "0" battery charger to be re-energized per.

Operations Procedure (0P) 1107-2.

This resulted in'the "D"

battery charger being connected to the "0" inverter, which was-

not the intent of the PM procedure.

The result was that the

high test voltage applied to.the-battery charger tripped the

inverter input breakers.

Communication between maintenance andioperations' personnel.has

been re-emphasized. Additionally, an engineering evaluation

was requested to determine-if the breaker trip / coordination

sequence was proper. At the end of the inspection period, .the

'

engineering evaluation was not completed. The licensee will

clari fy procedure PM-E-18 to more correctly specify the re-

'

quired electrical alignment. 'This will remain an unresolved

.

item (289/88-07-01) pending completion of. the~ engineering re-

view.

The inspector concluded'that licensee corrective actions

for this event-was acceptable.

2.3 S:MS Item No. B-75/B-85 - Post-Trip Review and Data

The inspector conducted a review to verify that a post-trip review pro-

cess was implemented and that post-trip data collection capability was

available as spe;1fied in the licensee response to-Items 1.1 and 1.2 of

Generic Letter 83-28 (Salem ATWS).

The licensee response to this item was contained in letters dated Novem-

ber 8,1983 and February 1, -1984.

These responses were reviewed by NRR

and censidered acceptable as documented in Safety Evaluation Reports

(SER's) dated May 31, 1985 and June 12, 1986.

During previous inspections, the licensee exercised the post-trip review

process for aight reactor trips since restart in October 1985. -The lic-

ensee utilized Administrative Procedure (AP) 1063 as. the primar/ post-

trip review process guideline.

The inspectors monito' red these post-trip /

reviews and verified that the licensee properly implemented the process

in accordance with the procedures.

These reviews were documented in-past

inspection reports.

The inspector discussed various portions of the

procedure and the personnel responsibilities involved with various lic-

ensee operations personnel. De procedure was well understood and was

carried out .in the past with few oroblems.

.,

=

..

. . .

.,

- , _ _ _ _ , .

.

.

_. _ ._,, 2 ,, -

. . -

-.

- .

.. ,

..

.

.

.

.

'

.

.

.

5

.

The data -collection capabilities via- the transient monitor were reviewed.

All parameters required by the generic letter or as exempted in the NRR

SER have the capability of.being recorded.

This capability was enhanced

by the sequence of events. printout and the alarm printout data, which

was also available.

Strip chart records were available if the computer

was not available at the time of the trip.

The inspector concluded that the requirements of Generic letter 83-28-

for post-trip review were properly implemented at TMI-1.

An unresolved item presently exists (289/86-06-09) concerning the tem-

perature lag for instrumenthtion for the T-SAT monitor. 'This is a sepa-

rate issue that dces not affect 'the required capability of the post-trip

review process.

2.4 Operations Summary

Plant operations continued to be conducted in a safe manner. Operator

response during the "B" MU pump and "D" 125-volt a.c. vital bus incidents

wcs good and licensee corrective actions were adequate.

The problem with

poor- communications between operations and maintenance personnel was

viewed as having the potential to cause other problems with future

evolutions if not properly resolved.

Licensee review of procedures and

proper briefing of personnel prior to the conduct of these evolutions

was viewed by the inspector to bc vital to safe plant operations.

Lic-

ensee corrective action in this area will be monitored periodically in

future inspections.

3.0 Radiological Controls

3.1 Organization and Qualifications

The inspector reviewed the organization of the Unit-1 rsdiological con-

trols staff.

The qualifications of all members of the staff were also

reviewed to ensure that they met the minimum requirements of the Tech-

nical Specifications and applicable standards.

Nearly all positions

identified in the organization were staffed.

The staff members were

~

fcund in all cases ta have qualifications at -least up to the required

levels and, in many cases, had much more formal and/or experience than

the minimum required for their positions within the. organization.

Additional review in the radiological controls area focused on licensee

action cn past findings.

l

. - - -

. - - . - - -

.

. -

. .

- --

-

- -

.

--

.

. '

.

~

.

i

.

.

6

3.2 Licensee Actions on Previous Findings

)

3.2.1

(Closed) Inspector Follow-Up Item (289/83-26-03): Temperature

Effects on the Output of the Turbine Building Sump Monitor

This item was opened'in connection with the observed. changes

in the output of the' sump monitor.with changes in.the water

temperature in the sump.

Investigations by the licensee showed

that these temperature-dependent changes were caused by changes

in the gain of the photomultiplier tube (PH) in the detector

assembly.

The detector is a scintillation detector with a.

s.dium iodide (Nal) crystal detector.

The gain changes were

caused by changes in the resistances of the resistors in the

PM tube voltage divider.

The detector was sent to the manu-

facturer.(Harshaw) to fix the problem.

The resistors were

changed to thermistors with negative temperature coefficients.

The licensee performed experiments with the modified detector

in place in the sump in June 1987. These experiments showed

that the temperature effects had been effectively corrected.

However, the data also showed that the output of the detector

changed with changes in sump water level.

These changes were

caused by changes in the amount of shielding provided by the

water in the sump. As the water level dropped, the shielding

effect decreased and the radiation fields in the turbine build-

ing above the sump caused an increase in detector reading.

Discussions with the licensee also showed that the method used

to calibrate.the detector was not representative. The detector

was calibrated by immersion in a 55 gallon drum containing

radioactive water.

The sensitivity of the detector determined

in that manner will be less than that with the detector im-

mersed in the sump water because the source size in.the sump

is larger than that in the drum.

In other words, the detector

in the sump should give a higher count rate for a given acti-

vity concentration than it would for the same concentration

in the barrel.

A review of the above considerations show that, although the

effects of calibration and water level dependence will cause

the detector's output to be different from predicted, both

effects are on the conservative side; that is, both effects

will cause the detector to register a higher than p edicted

reading for a given concentration of activity in the sump.

The trigger setpoint placed on the output of the detector is

used to trip the sump pump and, thus, prevent it from pumping

water from the sump to tSe Industrial Waste Treatment System,

which, in turn, discharges into the Susquehanna River.

The

calculated setpoint was 7600 counts per second (cps),' but the

setpoint used is 195 cps.

The licensee' stated that the main

reason for choosing this low setpoint was that it falls in the

- - -

-

-

-

-

. - -

.-.

-

.-.

-

l

.

.

.

R

7

.

output ranga of the detector for which calibration data is

available. Use of a higher setpoint would place.the setpoint

in a different output . range, which, in turn, would require

additional calibration data. Based on the above considerations,

the current uncertainties and setpoint are regarded as being

conservative and acceptable.

This item-is'therefore considered

closed.

3.2.2

(Closed) Inspector Follow-Up Item (289/85-30-03): REM Audit

Tracking System

The licensee needed to revise procedure 9100-ADM-1201. The

audits were performed periodically by Radiological Engineering

and the subject of the audits was the radiological controls

program. At the time the item was identified, there was no

mechanism to ensure that all elements of the program were

audited within an audit cycle.

The licensee has modified the audit procedure and incorporated

an audit matrix in procedure 9100-ADM-1201.09, "Internal As-

sessments Procedare." The program _to be audited is divided

into ten elements and the procedure requires that an element

be audited at least every six months by a minimum of two radio-

logical engineers. The complete audit cycle would take five

years.

The inspector stated that an audit of a program element

once per five years appears to be too infrcquent. The licensee

stated that the six-month period between element audits speci-

fied in the procedure allows for a relaxation of' audit efforts

during exceptionally busy periods, such as outages.

The lic-

ensee stated that an' element is normally' audited every calendar

quarter, giving an audit cycle of less than three years.

This

item is closed.

3.2.3

(Closed) Unresolved Item (289/86-12-16): Procedure Adequacy

and Implementation for Shielding Installation

This item was opened in connection with the procedure for in-

sta11ation and removal of temporary shielding'. A procedure

was developed for installation of temporary shielding (9100-

,

ADM-3282.01, "Installation of Temporary Shielding"). A review

l

of this procedure indicated that the weaknesses identified in

connection with this item had been corrected.

3.2.4

(Closed) Inspector Follow-Up Item (289/86-13-04): Radiological

Control Department Organization for TMI_-1

At the time this item was opened, the position of Deputy Field

Operations Manager was included in the actual organization,

but it did not appear in the organization plan. Also, at that

time, certain functions, such as dosimetry, respiratory pro-

l

1

,

_-----__-,-----__--------__---------,-a-_.-

- - - - - - - - - - - - - , -

- - . . - - - .

- - - -

- , - - -

- - - - . -

---am.

--.- ----r-.

--

- , , - - - - .

_ .

_

- __ _

i

.

.

,

'

'

,

-

8-

1

.

tection, and in plant radiological. training, were not part of

the Unit-1 organization. .These functions had been transferred

i

to Unit 1.

- ,

The position of Deputy Manager Field Operations is currently

listed in procedure 9100-A0M-1010.01, "Department Organization

Plan," but it is not currently staffed and does not appear on

the department's organization chart.

The licensee indicated

that_this position will be"filled when the Unit-1 and Unit-2

radiological organizations are merged in the near future. 'The

omission of the position from the organization chart will be

corrected.

3.2.5

(Closed) Violation (289/86-17-10): Failure to Provide Design

Basis for Radiation Monitor Settings

'

This item is related to the selection of setpoints for monitors

RM-G16 through RM-G21 and RM-L1,

RM-G16 through RM-G21 are

ionization chamber area monitors.

Each detector is placed in

a location to monitor the radiation field from a pipe that

penetrates contaihment.

RM-G21 monitors the activity in the

reactor building sump.

The function of the detectors is to

isolate the lines (or sump pump) if the activity within them

exceeds predetermined levels.

This is~ intended to prevent

transfer of radioactivity outside of containment. -The isola-

tion setpoints were chosen on the basis of activities inside

the lines, expressed in uCi/cc.

However, the actual detector

settings were in mR/hr. At the time the violation was issued,

there was no data to show the relationship between the pipe

activities in uCi/cc and the detector setpoints in mR/hr.

The

licensee has since performed a series of calculationslof'ex'

posure rates at each detector location for specified activities

in the respective pipes.

The setpoints were selected for ac-

tivities expected to exist in the pipes for 1 percent failed

fuel conditions.

The calculated exposure rates were then used

to determine the appropriate setpoints. These setpoints have

been incorporated into OP 1101-2.1, "Radiation Monitoring Sys-

tem Setpoints." This item is therefore considered closed.

,

~

[ Closed) Violation (289/87-09-12): Failure to Survey for Let-

3.2.6

down Prefilter Cubicle Work

This violation was issued in conr.eetion with an incident that

occurred in the letdown prefilter room on March 7, 1987. As

a result of the events connected with that incident, two

workers were found to have internal contamination. A prelim-

inary critique of the incident was held by the licensee on

March 7, 1987, and a formal critique was held on' March 10, 1987.

Radiological Incident Report (RIR) was issued by the licensee

,

-,

r-r

-

-

-r

-

<-

g

~w-

w

,,w

g

,y

,

,o

.-

g+y,

-

wv

s -

,e,-w-

v--

sr--

,- -

.

-

.

-

_

- .

.

. . . .

.

.

..

.

9

on March 25, 1987 (RIR 87-0192). ~ The critiques and the RIR

were reviewed by the inspector. The corrective actions were

acceptable and the item is closed.

3.2.7

(Closed) Violation (289/87-09-13): Failure to Follow Control

Procedures for When Standing Radiation Work Permit is Not to-

be Used

The violation was issued in connection with an incident that

occurred on March 12,.1987. As a result of the incident, two

workers showed-external and internal contamination. Contamina-

tion occurred when the workers removed a yellow plastic bag

from a splash ring used on a high integrity container used for

spent filters. .The plastic bag did not have a radioactive

material label. A critique was held by the licensee on March

12, 1987, and an RIR was issued on March 12, 1987. The cri-

tique and RIR were reviewed by the inspector.

The corrective

actions were found to be adequate, and this. item is therefore

considered to be closed.

3.2.8

(Closed) Unresolved Item (289/87-09-14): Effectiveness of

Licensee Measures to Assure High Radiation Areas Remain

Properly Posted / Barricaded

High radiation areas are required by' Technical Specifications

to be barric:ded and posted. On.an inspection tour on April

20, 1987, the NRC inspector found the door to the waste

evaporator cubicle to be open with no barricade. The cubicle

was posted as a high radiation area (HRA), but surveys of the-

area at that time showed the radiation fields to be.less (40

mR/hr) than those that would require establishment of a high.

radiation area (100 mR/hr).

The licensee stated that this-

situation has been corrected by moving the posting for the

cubicle outside the door area.

This allows the door to be left

open to facilitate work in the area and still maintain proper

posting and barricading.

The inspector reviewed procedure

9100-ADM-4110.01, "Establishing and Posting Areas." The pro-

cedure only defines a HRA but does not explain what a barricade

is and how to establish such barricades.

The licensee stated ~

that the procedure will be changed to address-this weakness,

i

This item is therefore considered closed.

3.3 RIR Review

The RIRs generated in connection with closecut items 87-09-12 and 87-09-

)

13 discussed abovo were reviewed during this inspection.

In the case

of item 87-09-12, although RIR identified most of the problems that oc-

curred during the incident, it did not clearly identify and isolate the

root causes of the incident. A review of the events by the inspector

shows that two factors were responsible for the incident: the radiologi-

1

_ _ .

_ _ _ .

-

. ,

_ _ . . .

_ . _ . _ . _ , _

_ , , - -

,, _ , _ , , _ _.

,

. . ,

_

_

_

_

,-

.,

.

.

-10

.

cal controls technician who covered the job did not attend the pre-job

briefing, and the technician.and his supervisor failed to observe the

requirements of the RWP for the job.

The RWP clearly indicated that

respiratory protection was required for any activity other than visual

inspection.

The activities involved in the incident included movement-

of equipment inside the filter: room, but respiratory protection was not

used. The corrective. actions specified in~the RIR were limited to memos

to various supervisors to observe certain requirements and precautions.

The RIR did not clearly identify the -reasons for not attending. pre-job

briefings and for violating RWP requirements.

It did not, therefore,

propose changes in procedure that would address these deficiencies, nor

did it clearly identify the. persons and organization responsible for the

incident.

The inspector expressed these concerns to the licensee. The

licensee stated that the RIR was weak and.that efforts will be made in

the future to correct this weakness.

As in the case of the above incident, the RIR produced in connection with

item 87-09-13 also did not clearly isolate the root causes of the inci-

dent.

Corrective actions were again limited to memos to various super-

visors alerting them to precautions to take in similar situations.

How-

ever, the persons directly. responsible for the incident, and the proce-

dural violations involved, were not clearly identified. A review of the

incident by the inspector indicated that the root cause of the incident

was the fact that the plastic bag was not labeled.

The licensee stated

that the bag was yellow in color, indicating radioactivity, and that the

workers involved should have known that fact.

However, there was no

discussion in the RIR of why the workers did not respond appropriately

to the color of the bag, if indeed that statement is valid. There was

no clear indication in the RIR of why the bag was not labeled, and who

was responsible for this omission. The licensee stated that contaminated

items in radiologically controlled areas do not-need to be labeled (Pro-

cedure 3000-IMP-4400 01), "Radioactive Material Identification and Hand-

ling." However, the same procedure specifies that the labeling exemption

is for "... radioactive material being worked or otherwise handled by a

radiation worker." Otherwise, the material must be ' labeled to ". . . pro-

vide sufficient information to permit individuals handling or using the

material / containers or working in the vicinity thereof, to take precau-

tions to avoid or minimize exposure." The'RIR did not discuss these

considerations to determine how this procedural requirement applied in

the case in question, and if it applied, why there was no label; or, if

it did not apply, how might the procedure be modified to prevent recur-

rence of similar incidents involving unlabeled contaminated items. The

ir.spector expressed concern about regarding RIR serving the function for

which it wac intended, namely, identifying and correcting root causes.

The licensee acknowledged the inspector's concern and stated that they

planned improvements in preparing RIRs.

This area will be reviewed dur-

ing future inspections.

1

.

-

-

-

-

-

-

-

- -

-

-

-

-

-

~

- .

-

-

-

.

-_

..

..

-

.

.

,

.

11

.

3.4' Radiological Controls Summ'ary

l

Licensee actions on various RIR's were generally, weak. The RIR's were

not effective in identifying roct causes of the problems. .The licensee

committed to review the process to ensure that adequate reviews of

radiological' problems are conducted in the future.

Licensee action on

'

the remaining open issues was satisfactory.

4.0 Equipment Operability Review - Maintenance / Surveillance

4.1 Criteria / Scope of Review

The inspectors reviewed selected activities to verify proper implementa-

tion of the applicable portions of the maintenance and surveillance pro-

grams. The inspector used the general criteria listed under the plant

,

operations section of the report.

Specific areas of review are listed

in Attachment 1.

A mare detailed review of equipment operability is

addressed below.

4.2 Reactor Trip Breaker No. 4 Failure

On March 16, 1988, th(' licensee reported that a reactor trip breaker had

failed a portion of the menthly surveillance test.

The licensee was

,

performing Surveillance Procedure (SP) 1303-4 1 on Channel "0" of the

Reactor Protection System (R N ).

~

This serveillance is accomplished.on each of four RPS channels on a

rotating monthly basis. One channel is checked each week; hence, the

entire RPS surveillance is completed monthly. A part _of the surveillance

for Channel

"D" is to check the Nos. 3 and 4 d.c. reactor trip breakers

to verify that the shunt trip and undervoltage (UV) trip coil each func-

tion. The surveillance is accomplished with a test switch which can be

positioned to trip each coil independently.

On a normal reactor trip

signal, both coils actuate.

During the portion of the surveillance that checked the UV coil, it was

observed that when the test switch was positioned to de-energize the coil

.

for the No. 4 reactor trip breaker, the breaker did not trip.

The shunt

trip function was checked; and, it was verified that the shunt trip coil

was operable and, if an actual RPS trip signal was generated, the breaker

would have tripped.

j

The licensee removed the breaker and installed a previously tested spare.

The surveillance test for Channel "0" was completed satisfactorily.

The

technical specifications (TS) allow a_48-hour period to repair a faulty

reactor trip breaker, if only one of the diverse trip features was in-

operable (TS 3.5.1.7).

As the failure did not result in loss of redun-

dancy, no other action by the licensee was required. An evaluation for

1

-

-

. - .

-

-

-

.

_

.s

.

.

12

.

reportability was made and the licensee determined that the event was

not reportable.

The inspector concurred in this evaluation based on a

review of.10 CFR 50.72/73.

The licensee disassembled the failed breaker to' determine the cause of

the failure.

Initial nbservations showed that the trip paddle for the

UV device had become mispositioned with respect to the armature of the

UV trip coil. This prevented the UV armature from moving to actuate the

trip paddle to trip the breaker.

The operation of the trip-shaft was

not affected as the shunt trip paddle was able to complete a breaker trip.

This was verified on three separate occasions.

Subsequent licensee investigation revealed that the clearances between

the end of the UV coil armature and trip paddle prevented the armature

from moving when the UV device was de-energized.

This was possibly due

to manufacturing anomalies with the UV device armature and'the trip

paddle.

The licensee was investigating changes in the preventive main-

tenance (PM) process to ensure that the clearance between the trip paddle

and.UV armature was proper.

Other reactor trip breakers at the facility

had not experienced this problem and the licensee had initially concluded

that this problem was not applicable to other breakers.

The inspector concluded that there was ressenable assurance that the

reactor trip system can function as designed.

This problem appeared to

be unique to the one particular breaker and the surveillance test

1

sequence and PM program used by the licensee should identify any other

breakers with this problem,

The inspectors will continue to follow lic-

ensee' actions to determine what additional PM effort or testing is re-

quired to enhance the reactor trip breaker operability.

-

The licensee has been in contact with the Babcock & Wilcox Owners Group

(BWOG) and General Electric (GE) to determine if any other corrective

action is needed. The licensee expects to receive guidance from B&W

concerning any additional preventiva maintenance that can be accomplished

to more adequately verify that the same condition that existed with' the

No. 4 d.c. reactor trip breaker does not exist with other breakers. This

guidance will be factored into site preventive maintenance procedures

after evaluation.

This item remains unresolved (289/88-07-02) pending

licensee changes to the preventive maintenance program. Additionally,

s

the licencee committed to provide a special report to the NRC staff-on

'

this problem, as a Licensee Event Report (LER) was not mandatory.

4.3 Operational Test of the Emergency Diesel EG-Y-1B

On March 6, 1988 at 4:13 a.m., during the shutdown following a surveil-

lance test, the diese? exhaust manifold caught fire.

The emergency

diesel room was manned during the test and the fire was put out immedi-

ately.

The local and remote speed indication was lost due to the tem-

perature which caused a disconnect of the internal tachometer wires.

The diesel was declared inoperable and diesel 6-Y-1A was tested as re-

-

.

-

- ._

_

_.

.

-

- -

-- .

-

.

. .--

..

,,

,

.

13

.

.-

quired by Technical Specifications Section 3.7.2. -The diesel was re-

paired and back in service at 8:15 p.m. the same. day. Continued reactor

operation would have been allowed for 7 days.

The cause of the fire was determined to be a small leak of engine coolant

on the hot exhaust manifold.

There have been small fires in the past

caused by engine oil leakage through an exhaust manifold joint.

The licensee developed a detailed corrective action plan that included:

(1) removal of the exhaust manifold, inspection, cleaning, and reinstal-

lation with new gaskets; (2) replacement of all twelve thermocouples;

(3) repair of the small coolant line; and, (4) repair of the tachometer.

The inspection cf the exhaust system and the mating surfaces did.not

indicate any significant defects.

Following the above-mentinned repairs, the diesel was tested satisfac-

torily.

The inspector witnessed these activities, including job planning,

and reviewed the associated work packages for adequacy and completeness.

The inspector made the following observations.

The licensee initially planned on replacing two thermocouples (Nos.

--

4 and 12).

Further examination identified additional thermocouple

_

problems and the licensee decided to replace all thermocouples.

--

The inspector also noted two different styles of the replacement

thermocouples.

Some were of original construction and some had

smaller diameter metal sheaths.

Both styles have the same part

number and were accepted by licensee Quality Control (QC) inspec-

tors; however, the old style did not have a shelf life limit, while

'

the new style had a six years shelf life.

The licensee prepared

an engineering evaluation supporting the installation and also in-

formed the vendor.

It was the vendor's position that the shelf life

l

on the new style was not applicable and both styles were acceptable

for the application.

However, the vendor did not advise the licen-

see about the apparent difference in construction, as well as the

shelf life issue. Also, it appears that the licensee's receipt

inspection system did not detect the apparent discrepancy.

In re-

sponse to previous firdings (NRC Inspection Report No. 50-289/88-01),.

l

the licensee already has initiated efforts to correct such problems.

The residents office will review the effectiveness of the corrective

actions onc? implemented.

The inspectors discussed the diesel fire issue with licensee's man-

--

agement on March 21, 1988, to assess long-term actions. The licen-

see has developed a long term plan using Kepner Tregce techniques.

The technique is a management tool utilized to scientifically

analyze the generic issues with safety significance and then im-

plement an action plan.

The licensee plans to assess the adequacy

of the corrective actions already taken using this system.

-

..

.. .

'

,

.

14

The repair was well pisnned and the licensee did an accepu ole Job in

implementing the shcrt-term actior.s. -The inspector reviewed a total of

seven job tichets.

The job tickets were well prepare.d and all the

planned work was accomplished and the diesel was declared operable on

the same day.

The inspector reviewed SP 1303-4.16 for botn emergency diesels.

The

surveillance data was recorded as required.

On both diesels, the-in-

spector noted that the temperature readings for several cylinders were

outside the recommended range.

However, they were still within the

allowable limits of maximum cylinder teraperature, as well as the maximum

differential temperature between any two cylinders. The rperability of

the diesels was not compromised by tnis temperature anomaly:'however,

the-licensee was in contact with the vendor to establish appropriate

normal operating limits.

The inspector also reviewed the annual surveillance performed per SP

1301-8.2 on both emergency diesels.

The inspector noted that on an older

surveillance (June 1987), some of the data corrections were not initialed.

This situation was corrected for the current annual surveillance.

The inspectors noted substantial efforts of senior licensee managen,en*.

in look?ng ct new ways to more efficiently condt.ct troubleshooting and

in developing a long-tern solution for correcting generic issues.

The

inspector had no furthe questions' regarding this issue.

4.4 Licensee Actions on Previous Inspection Findings

4.4.1

(0 pen) Inspector Follow Item (289/86-10-02): Significant

Damage to the Diesel-Driven Fire Pump Building

This item remained open pending Borated Wate: Storage Tank

(BWST) pipe tunnel plugging and evalut. tion of a fire pump dis-

charge check valve preventive maintenance program.

To prevent flooding.of the auxiliary building through the BW3T

pipe tunnel, the conduit duct banks in the 86T tunnel were

resealed. The inspector reviewed Job Ticket (JT) No.130 on

which this work was completed.

The inspector had no further

questions.

The licensee has completed inspections of eaisting Walworth

check valves in the plant.

The results of these inspections

indicate that there are no problems with other check valves

of this design.

The licensae is currently utilizing a non-destructive exacnina-

tion system (checkmate) that allows check valve performance /

operability determination without disassembly.

The results

of the checkmate examinations are to be verified by comparison

j

l

.

.

- .

.

- -

-..

- . -

.

. . - .

-

.,

.

.

"

"

. .

,

.

.

15

P

'

with the results of'other check valve examination techniques.

After verification, the-licensee will' determine the appropriate

preventive mainterance- frequency for the Walworth check valves.-

.

This item remains open pending determination of the preventive

maintenance frequency of Walworth check valves. The licenses

plans- to determine -the frequency of PM's -by the end of this

year.

4.4.2

-(Open) Unresolved Item (289/87-06-05): Review of Differential /.

Pressure (D/P) Instrument Performance

.

This item remained open pending completion of licensee evalu-

ative actions.

The licensee'had increased the frequency of calibration of the

. main feed pump differential / pressure (0/P) switches from a

refueling basis to quarterly.

The data continued'to be un-

acceptable;

i.e.,

the setpoint continued to drift.

Licensee

personnel are evaluating possible corrective actions; one of

which is replacement of the D/P switches, which appears to.be

the best option.

No plans have been made, as yet, to accomp-

lish this task. This item remains open pending completion of.

licensee action to correct:this situation.

4.5 Equipment Operability Summary

Maintenance and testing activities continue to be accomplished in a safe

.

manner. No forced outages resulted from poor or incorrect maintenance

activities.

Licensee corrective action forfthe problems associated with

the reactor trip breaker are inconclusive, as yet, and any changes in

the maintenance practices for the breakers will .tre examined in future

inspections. The longstanding issues associated with diesel generator

fires, fire service check valve, and feedwater D/P instrument appears

open for an excessive amout.t of time.

This may be due in part to an

inappropriate prioritization of engineering actions.

5.0 Engineering Support

5.1 SIMS Items

5.1.1

(Closed) SIMS No. III.D.3.4.2: Control Room-Habitability

The 10 CFR Appendix A, General Design Criteria 19, "Control

Room," as well as NUREG 0737, Item III.D.3.4, defines the

specific criteria necessary to assure that the control room

is maintained in a safe habitable condition to assure that the

control room operators are adequately protected against the-

i

- - -

-

-

- -

.

-

-

- - - -

.

. --

- ~.

-

.

.-

-.

-.

. - - .

.

.

-

"

..

,

,

.

16

.

accidental release of toxic 'and radioactive gases and to assure

the plant can be safely operated or shut down under design

basis-accident conditions.

The licensee's design was reviewed by the inspector and was

found to be acceptable.

The inspector had previously .identi-

fied-a few exceptions from NUREG 0737 requirements as docu-

mented in NRC Inspection: Report No. 50-289/87-02. During this

inspection period, the inspector reviewed these exceptions.

The details are os follows.

1

System Design Description (500): TI-670F on the chlorine

--

detection system stated the location of the two chlorine

probes, CE-776-2 and CE-777-2, being below the grade level

in the air intake structure.

The actual location,-however,

is above grade at the 320-foot evaluation.

The necessary.

change notice is in place and the SDD will be revised

accordingly.

--

SDD TI 670F, Section 1.6.6.2.2 stated the location of a

reset button was on Scrtion A of the heating and ventila-

tion (H&V) panel.

The actual location, however, was on

the Section 8 of the H&V panel.

This was the only excep-

tion and it re ri.1ed uncorrected. . The licensee intends

to revise the SDD to incorporate this. exception.

--

Operating Procedure (0P) 1104-19, as well as the Emergency

Procedure (EP) 1203-34 have now been revised to reflect

the current design of the Chlorine Detection System (CDS).

b

The chlorine detection system (CDS) is now fully operational.

The required testing and surveillance are being performed per

established procedures.

The inspector. reviewed the relevant

data and found it to be satisfactory.

The CDS requires con-

tinuous maintenance involving frequent replacement of the

<

chlorine detectors.

The licensee, however, maintains its

operability status by depending upon the routine surveillance

)

and testing, as well as the built-in, self-diagnostic features.

'

The inspector had no other comments on the installation and

)

operation of the CDS.

.

5.1.2

(Closed) SIMS M64800: Technical Specification for Chlorine

Detection and (Closed) Unresolved Item (289/87-11-03)

The safety grade Chlorine Detection System (CDS) was installed

for Cycle 6 startup.

The CDS involved installation of four

chlorine detectors.

Two detectors, CE 766-1 ano CE 777-1, were-

installed at the river water screenhouse and the second set

'

of detectors, CE 776-2 and CE 777-2, were installed at the vir

intake tunnel.

The system is designed so that any chlorine

-

--

.

-

-

.

-

-

'

' '

i

.

,

'

17

release in excess of 5 parts per million (ppm), the system' will

automatically be actuated and the Control Room Ventilation

System (CRVS) placed into a recirculation mode to prevent out-

side chlorine from entering the control room environment and,~

thus' maintain the required control room. habitability.

,

NRC Inspection Report No. 50-289/87-11 addressed the unplanned

periodic actuation of the CRVS_ caused by spurious high chlorine

detector resporse. All the items of concern have.been resolved

as follows.

The inspection report incorr2ctly. noted that the sensi-

--

tivity of the chlorine detectors was having a negative

impact on the system. According to plant engineering,

the electrolyte being used is chlorine-specific and does

not have any effect on the detectura sensitivity.

The

spurious actuation was caused by the direct exposure of

the detecters to the harsh environmental ccnditions.

Through the Change Modification Request (CMR) No. 0820M,

the licensee has corrected this problem by installing a

prot 9ctive umbrella over the detectors.

Since then, the

CDS is operating satisfactorily without any spurious

actuations.

--

In NRC Inspection Report No. 50-289/87-11, the inspector

also had questioned the effectiveness of the weekly pre-

ventive maintenance procedure 1C-145.

The review of this

procedure during the current insnection period does not

indicate any weaknesses.

The root cause of the problem

was corrected by the above-mentioned CMR.

All the open items on control room habitability, as previously

"dentified, have been resolved and verified by the_ inspector

and this item is closed.

5.2 Licensee Actions on Previous Inspection Findings

5.2.1

(Closed) Unresolved Item (289/86-12-14): Minimum Motor Starting

Voltages

NRC Inspection 50-289/86-03 identified concerns regarding the

adequacy of analysis performed to assure that sufficient volt-

age was available to start and operate certain safety-related

motor-operated valves (MOVi ).

An earlier analysis, which was

s

performed in 1979, resulted in the modificatfons of some of

the MOV units to ensure proper operatien.

However, this an-

alysis did not cover MOV's in the EFW and main steas (MS) sys-

tems, since at that time they were not considered safety re-

lated.

Further, the analysis assumed that the unit MCC bus

voltage and the voltage at the motor terminals were the same,

e

f

. I

T

_ ,

--,

y

,re

- - , -,- - --,

y..y--

--

,.wq

,

,.y.-

.ry..y,-

,v.

-

,--_ve,-q

,-w-.-

.~. - -

-

- .-.

. .- .

.

-.

_

.

J'a

..

&

,

. 18'

4

The following documents which reflect licensee analysis / studies

and actions taken to ensure adequate 1 voltage were reviewed.

GPUN-TDR No. 114, Revision 1, "Adequacy of Station Elec-

--

tric Distribution System Voltages"

GPUN TDR No. 836, Revision 0, "Evaluation of Loading for

--

the Emergency Diesel Generators and Engineering Safeguards

Buses"

GPUN Memorandum, R. J. Hrabak/M. A. Materjorich to G.

S.'

--

Saduska, "1986 TMI 230 KV Grid Voltage Study"

The licensee analyses were performed,.using their "DAPPER"

computer program with appropriate verification measurements

of voltage at selected locations, to provide confidence ir the

accura:y of the program. Based upon the analyses'which show

,

reinforcements in the grid transmission system, since the

original analysis, the licensee has increased the minimum

switchyard voltage consid9 red for degraded grid operation from

225 KV to 227 KV.

The min! mum voltages at the MOV terminals

were measured for both motor starting and full load currents.

The resultant voltages were found to be acceptable in accord-

ance with the criteria previously established in TDR No '114.

This item is closed.

5.2.2

(Closed) Unresolved Item (289/86-12-12): JDesign Input Associ-

^

ated with Emergency Feedwater Pump (EFW) Overcurrent Protection

During NRC Inspection 50-289/86-03, concerns were identified

,

regarding the overcurrent relay protection provided for large

safety-related motors. Of particular concern were the EFW

pumps and motors which originally were considered non-safety-

related nuclear components.

Design analysis support for the

EFW pump motor overcurrent protection were considered weak due

to incorrect relay settings and the apparent lack of considera-

tion for'long-term thermal degradation of the motors.

In response, the relay protection was evaluated for the EFW

pump motors and other large safety-related motors including:

Reactor Building (RB) Spray Pump Motors (BS-P-1A,-BS-P-1B)

--

Decay Heat Removal Pump Motors (DH-P-1A, DH-P-18)~

--

EFW Pump Motors (EF-P-2A, EF-P-2B)

--

Make-Up Pump Motors (MU-P-1A, MU-P-1B, MU-P-1C)

--

--

RB Emergency Cooling Pump Motors (RR-P-1A, RR-P-18)

i

I

. - ,

r.

, ~

.c.

.-- ,,

- . ,,. _

_...,m,

,,

-...r.--....

, - . . ._.

. -

e,e,

-.w.

,. ,, ,, , _ ,

,w

.

.

. _ - .

b., C .

,

.

19

.

These evaluations identified protective relay setting changes

for the spray pumps, decay heat removal' pumps,.and the EFW

pumps.

The inspector confirmed licensee implementation of' the

required changes.

5.2.3

(Closed) Unresolved' Items (289/86-12-15 and 289/87-10-01):

Instrumentation Grounding and Shield Standards

During NRC Inspection.50-289/86-03, concerns were identified

regarding the lack of established formal standard procedures

to cover proper grounding and shielding practices for instru-

mentation and control signal circuits. .NRC Inspection 50-289/

87-10 identified.a specific area of questionable shield

grounding in the Heat Sink Protection System (HSPS) instrumen-

tation.

This inspection confirmed that the licensee has established

and implemented Engineering Standard (ES)-028, Revision 0,

September 25, 1987.

This standard endorses Division of Reactor

Implement and Technology, USAEC, RDT Standard Cl-1T, "Instru-

mentation and Control Equipment Grounding and Shield'r.g Prac-

tices."

Field inspection and review confirmed that the licensee has

also investigated and corrected / resolved questionable ground-

ing/ shielding in the HSPS instrumentation under Field Change

Notice (FCR) No. C038886 and 056084.

These items are closed.

i

5.2.4

(Closed) Violation (289/87-01-15): Improper Mounting of Foxboro

0/P Transmitters

NRC Inspection Report No. 50-289/87-01, examined selected

safety-related components _ including Limitorque MOV's, Foxboro

transmitters, Rosemount transmitters, Target Rock solenoid

valves, level switches, radiation detectors,-temperature de-

tectors, and electrical splices.

This inspection revealed two

Foxboro transmitters mounting using U-bolts on vertical pipe

sections.

Tha 4-bolts were loose on both units. This mounting

is contrary t. _.e qualified seismic mounting specified in the

vendors manual.

The inspector confirmed that the licensee has evaluated the

questionable mounting in accordance with NRC Generic Letter

(GEL) 87-02, "Verification o' Seismic Adequacy of Mechanical

and Electrical Equipment (USI) A-46."

In addition, the licen-

-

-

-

-

-

.

- . -

-

- -

.

..

-.

__

_

_~

.

.

.

.

20

.

see is addressing the seismic adequacy of all: safety-related

equipment in order to provide the response required by GEL-

87-02.

This item is closed.

5.2.5

(Closed) Unresolved Item (289/86-03-22): Procurement Deficien-

cies for Back-Up Instrument Air

The inspector reviewed a Quality Deficiency Report (QDR), which

was issued because Purchase Order No. TP-035330 was issued with.

a safety classification of non-important to safety (NITS) and

incorrect dewpoint and filtration requirements.

The inspector verified that a Certificate of Confoer.ance was.

issued by the vendor ( \\ir ~ Products, Inc.).

The inspector also

determined that the quality of air received from the vendor

exceeded the~ required design dewpoint and filtration require-

ments. The purchase order has been revised to ensure adequate

controls on future procurement by classifying the-purchase

order as important to safety (ITS).

The inspector also reviewed the installation documentation for

the modification which installed an air compressor to provide

a permanent source of charging air for the.two-hour back-up

instrument air storage bottles.

The inspector verified that

dewpoints and filtration requirements are being met by this

modi ficatiori .

This item is closed.

5.2.6

(Closed) Unresolved Item (289/86-12-10): Evaluations of EFW

Pump Recirculation Line Design Change

Corrective Maintenance Modification No. CM0515M removed the

. instrument air tubing from the instrument air line downstream

of IA-V-1125 to EF-V-8A.

The justification for removal of the

instrument air line was that it was a potential safety' hazard.

Also, the instrument air supply to EF-V-8A is not credited as

a back-up supply since the instrument air compressors which

feed it are not important to safety ~(NITS).

The work was per-

formed under JT CH-269 per CM0515M.

This item was opened as a PAT inspection finding in NRC In-

spection Report No. 289/86-12 because the prcper safety evalu-

ation could not be located. An adequate safety evaluation was

performed and work was completed as ITS.

The inspector deter-

mined that removal of this line was previously evaluated by

NRC and approved.

This item is closed.

.

- -

.

. .

-

.-.

.- -

.

- .

. - -

_- -

.

.: # .

,.

.

21

5.3 Engineering Support Summary -

Licensee action on previously identified areas-in the engineering ' support

area was completed in an acceptable manner.

6.0 Physical Security Plan Implementation

On March 11, 1988, the inspector reviewed licensee's Physical Security Plan

and inspected several areas as mentioned below to assess plan implementation.

The installed search equipment, used by the licensee was found to be operable.

Some redundant equipment was not operable, was covered by the required com-

pensatory measures. The inspection also reviewed equipment test procedures,

test data, and their completeness.

No unacceptable conditions were identified.

The inspector toured the protected area with a security department represen-

tative. The protective fence, gates, locks, etc. were well maintained and

the isolation zones on both sides of the protected area was clean and clear

of any obstacles.

No weakness was observed.

The inspector witnessed the shift change at the Processing Center.

The

security guard officers were found to be very attentive.

The inspector also witnessed an inspection of a vehicle, which was performed

by the security guard.

It was done thoroughly.

The inspector inspected -the CAS and Secondary Alarm Station (SAS), reviewed

'

the relevant documentation, and monitored the operation of various equipment.

The entire operation was accomplished satisfactorily and_both facilities are

well maintained.

The assessment system had adequate clarity. _ The manning

of the security guards was in compliance with the security plan requirements.

The inspector joined the routine patrol with the "Scout" security guard.

This

patrol involves monitoring several equipment areas, fencing, gates, building

roofs, isolation zones, emergency power supply rooms, lighting, etc.

The

patrol activities were documented by the security guard, as required.

'

The entire security crew was found to be professional, well trained, and ex-

perienced.

The overall security functions reviewed were found to be adequate.

7.0 Safety Assessment - (Closed) Violation (289/85-27-09): Independent On-Site

Safety Review Group Performance

An inspection was conducted to evaluate the performance of the Independent

On-Site Safety Review Group (IOSRG) and to verify the corrective and preven-

tive actions taken by the licensee as described in a letter, H. Hukill to

T. Murley, dated February 10, 1986,-in response to a violation related to

10SRG activities identified during NRC Inspection 50-289/85-27.

I

.

.

.

.

. .

. . .

.

.

. m.

_

.

_.

.

_.

_

.-

__

. _ . _ _. _ .

. . _ .

,__

..

.

..s

..

,

.

22

-During Inspection 50-289/85-27,'certain requirements associated with the per-

formance of the 10SRG were' identified as not having been performed. ' Also,

it was determined the overall effectiveness of the. group was difficult.to

-assess. 'During this inspection, the 1.icensee's corrective' action which had

been taken, the effectiveness of the corrective action, and overall perform-

ance of the group was evaluated.

An important factor in arriving at any conclusion associated 'with the , perform-

'ance of-the' group is that, since Inspection 50-289/85-07, all 10SRG members,

the Man'ager.of Nuclear Safety and the NSAD Director.to whom the:10SRG reports

have all been replaced with new personnel.

These personnel changes appear

to' have had a significant impact on the implementation of the corrective

action committed.to for the prevention of recurrence of previous ' procedure

adherence problems. As discussed later, however, a few of the previous prob-

l

lems still exist.

In addition to discussions with personnel, the following documentation was

reviewed to determine adherence to Technical Specifications (TS).and admini-

strative requirements.

,

Independent On-Site Safety Review Group Procedure - TMI-1, 6310-ADM-

--

1010.01, Revision 5

--

Qualification forms for each member of the group

Personnel training records for each member with the exception of the

--

consultant currently part of the group

--

Various 10SRG monthly reports

Various 10SRG bi-monthly reports

--

TMI 10SRG work projections fcr 1987

--

--

Various 10SRG record of review / investigation forms

'

--

Records of TS Change Request reviews

Also, the following documentation associated with evaluations and assessments

,

'

were reviewed,

i

Human Performance Evaluation System Report - Replacement of Expansion

--

Joint for RR-P-1B with Wrong Model

--

Human Performance Evaluation System Report - Both Emergency Diesels Re-

moved from ES Standby LCO Violation

Containment Integrity, dated October 16, 1987

--

__

. _ . _

_

_

__

_

"

.

.

,

3

23

.

'

Effectiveness Evaluation of GPUN Operating Experience. Review, dated June

--

'1987

Evaluation of Shift Scheduling at TMI-1

--

Differences Between TMI-1 Administrative Procedure (AP) 1043 and Cor-

--

porate Procedure 1504-ADM-3040.01

--

Potential for Hydrngen Combustion in the RCS

Failure Rate of RPS System

--

Heated Posts

--

TMI Saturation Monitor - Time Response

--

As a result of the above reviews, many positive findings were identified.

.

However, some negative findings were also made.

In general, the IOSRG re-

'

quirements of the TS appeared to be met.

Some implementing procedure non-

adherences were again noted and the corrective action committed as a result

of a previous violation was marginally implemented.

As required by TS, the group is comprised of a Manager - Nuclear Safety and

a staff of three qualified members.

In addition, another engineer skilled

in human performance evaluation has recently been assigned to the group.

'

The documentation considered to be formal evaluations performed by the group

are comprehensive, detailed, and well documented. These evaluations appear

to satisfy the overview review functions required by the TS.

The evaluations

appeared to be effective in that it was noted certain-reviews were brought

to the attention of the president of GPUN. A TS change was being made and

procedure revisions undertaken as a result of 10SRG evaluations.

Site per-

sonnel appear interested in the human performance evaluations being performed,

recommendations was being considered by operations, training had interfaced

with 10SRG, and top level corporate management had requested group evaluations.

A recommendation follow-up system should make the assessment of the group's

effectiveness even easier.

Monthly and bi-monthly reports are also prepared. These reports generally

summarize the significant activities of the 10SRG.

The monthly reports gene-

i

rally provide slightly more information than the bi-monthly reports.

These

reports although identified as providing a summary of 10SRG activities do

quite frequently also contain some assessments.

The 10SRG procedure requires only bi-monthly summary reports and formal re-

ports of evaluations and assessments.

Inspection findings show the monthly

and bi-monthly reports do frequently include assessments and that reports

considered to be formal reports are not generally so identified.

For the most

.

.

.

_

_

.

!

.-

.

,

.

24

-

,

part,' documentation which serves as a formal report is usually distributed

as a memorandum. Also, the report distribution is not always as required by

TS or the procedure.

Other areas where the practice'is not in accordance with 10SRG procedure is

in the e

of "review records"- and the annual trending'of these records.

The

.

use of "review records" was judged to be inappropriate and has been completely

discontinued. ;Also, the 10SRG, procedure describe; a method by which group

findings are resolved with responsible management and that only items which

are not resolved become recommendations.

The IOSRG in its documentation of

assessments and evaluations does not adhere zo this procedural requirement.

This is' discussed later in this section. Although not part of the 10SRG pro-

cedure, weaknesses were noted in that 10SRG recommendations are not:always

clearly identified.

That is, they are sometimes part of a conclusion while

at other times they are clearly noted as recommendations. Also, the results

of recommendations are not maintained, nor is any open item list maintained-

of internal commitments made in monthly ~ and bi-monthly reports.

These issues were discussed in detail with the licensee, particularly since

some of the findings were similar to those identified in NRC Inspection Report

No. 50-289/85-27.

The licensee was aware of the fact that-the 10SRG procedure was not being

fully adhered to.

A complete rewrite of the procedure in draft form had been

prepared and was still in the review process prior to being issued. The draft

procedure, among other things, addresses 10SRG project selection, schedules,

assessment reporting, records, and responsibilities. Along with the require-

ment for procedural compliance, the weaknesses primarily in the areas of

identification of what is an 10SRG assessment, assessment distribution in

order to meet requirements and to be most effective, and the identification

and follow-up to recommendations was discussed in detail with the licensee.

The licensee indicated these matters would be clearly addressed in the review

of the 10SRG procedure.

The licensee further committed to have the revised

procedure issued by August 5, 1988.

This item remains unresolved pending the

issuance of the revised procedure-(289/88-07-03).

,

During the follow-up to the corrective action specified by the licensee, it

was noted that certain of the 10SRG procedure changes which were committed

to in order to avoid further violations were marginally implemented or in-

effective.

For example: (1) The corrective action stated procedural clarifi-

cation would be made so that the use of the word "schedule" would be unam-

biguous. This was accomplished by completely eliminating the word "schedule"

in the revised procedure.

(2) Procedure clarification was specified which

would identify which reports of evaluations and assessments satisfy the TS

requirements. The revised procedure specifies bi-monthly reports are to pro-

vide a summary of reports of evaluations and assessments and formal reports

,

'

of evaluations and assessments.

Currently, monthly reports and bi-monthly

reports are prepared which summarize major 10SRG activities and frequently

contain some assessments.

Few formal reports are issued; however, formal

evaluations are frequently issued, not as formal reports but as memoranda.

,

,

+

~

-

--

- , -

--

-

,-m

, -

.

_ .

.

.

.

.

,

.

25

.

(3)' procedural clarification was committed to, . ensure uniformity and consis-

tency in the documentation and handling of 10SRG recommendations.

The revised

procedure describes a discussion of. assessment findings with responsible

management and the preparation of a memorandum to document agreement reached

in.the development'of corrective or problem solving action. The procedure

specifies only those items which are not resolved may become recommendations.

This method of resolution of 10SRG assessments is not generally used.

Many

recommendations are specified in assessments, both clearly identified as

recommendations or frequently not clearly identified in a conclusion section

of an assessment.

This poor follow-up to committed corrective action and the need for accurate

communication with the NRC was discussed in detail with the licensee.

The

licensee indicated that there was no intent to be anything but fully respon-

sive to their implementation of these corrective actions.

However, with the

significar t changes in personnel that have taken place during the implementa-

tion and follow-up of the corrective action, the desired improvements had not

been fully achieved.

In order to address this situation, the licensee pre--

pared a draft procedure, which will correct this poor implementation of cor-

rective action. The quality of the. revised procedure and its implementation

following its issuance will be closely reviewed by the NRC to fully resolve

this matter.

This section closes outstanding item 289/85-27-09.

8.0 Emergency preparedness - Information Flow During Emergency Exercise

During the past emergency exercises, some communication problems surfaced be-

tween the licensee and the NRC Operations Center.

The licensee's Emergency

Notification System (ENS) and Health Physics Network (HPN) communicators could

not readily provide the requested information by the NRC, as required per 10 CFR 50.72(c)(3).

The problem was the large amount of information, as well

as the type of information.

In order to correct this problem the licensee

was provided additional guidance by NRC Region I.

Subsequently, the licensee

has revised two of their emergency-procedures.

The inspector reviewed these

procedures which reflect the changes consistent with the NRC guidelines.

The

guidelines were provided in a letter dated August 31, 1987, from Thomas T.

Martin, Director, Division of Radiation Safety and Safeguards to Mr. H. D.

Hukill, Director and Vice President of TMI-1.

The communication difficulties were related to the emergency exercises only.

The normal operations are not affected.

The communication during normal

operations is conducted per approved procedures and no inadequacies have been

observed. No further follow-up is necessary,

,

9.0 Exit Interview

The inspectors discussed the inspection scope and finding with licensee man-

agement at a final exit meeting on April 8,1988.

Interim exit meetings were

conducted on March 25, 1988, concerning radiological controls; March 31, 1988,

-- _ _ .

.

.

.

- .

_

___.__.,____ _ _ _ _ _ _

_

"

'

.

e

26

4

concerning several unresolved items; and, on April 5, 1988, concerning IOSRG.

In addition to those marked by cn asterisk in paragraph 1.3, senior licensee

personnel at the final exit meeting included:

--

J. Colitz, Manager, Plant Engineering

--

M. Hukill, Director, TMI-1

The inspection results as discussed at the meeting are summarized in the cover

page of the inspection report.

Licensee representatives did not indicate that

any of the subjects discussed contained proprietary or safeguards information.

Unresolved Items are matters about which more information is required in order

to ascertain whether they are acceptable, violations, or deviations.

Unre-

solved items discussed during the exit meeting are addressed in paragraphs

3.2, 4.3, and 5.2.

Inspector Follow Items

Inspector follow items are matters that necessitate further review and evalu-

ation by the inspectors.

TFese items are used to document, track, and ensure

adequate follow-up on matters of concern to the inspector.

Inspector follow

items are addressed in paragraphs 3.2 and 4.4.

,

-.~.

.

.-

--

.

. - .

.

-.

.

.

.

v. o ,

,

.

1

,

ATTACHMENT 1

NRC INSPECTION rep 0RT N0. 50-289/88-07

ACTIVITIES REVIEWED-

Plant Operations

--

Control room operations during regular and back shift hours, including fre-

quent observation'of activities in progress and periodic reviews of selected

sections of the shift foreman's log and control room operator's log and

selected sections of other control room daily logs

Areas outside the control room

--

,

--

Selected licensee planning meetings

During this inspection period, the inspectors conducted direct inspections during

the following back shift hours.

Day /Date

Time

3/11/88

3:30 - 7:00 a.m.

Maintenance / Surveillance

Job Ticket (JT) CR-771/772 - Diesel generator thermocouple repair

--

JT CR-744 - Diesel generator oil leak repair -

--

JT CP-504 - Diesel generator cooling system leak .epair

--

--

JT CP-505 - Diesel generator exhaust manifold flatness check

Surveillance Procedure (SP) 1301-4.1, Revision 42, effective April 13, 1988,-

--

"Weekly Surveillance Checks"

SP 1302-3.10, Revision 1, effective March 15, 198L, Chlorine Detection System

--

Instrumentation Channel Calibration"

--

SP 1303-5.16, Revision 3, effective November 17, 1987, "Chlorine Detection

System Instrumentation Channel Test"

Reactor Coolant System (RCS) Leak Rate

-The inspector selectively reviewed RCS leak rate data for the past inspection

period. The inspector independently calculated certain RCS leak rate data reviewed

l

using licensee input data and a generic NRC "BASIC" computer program "RCSLK9" as

specified in NUREG 1107.

Licensee (L) and NRC (N) data are tabulated'below.

.

- - _ ,

,-- ..

. _ _ _ - , , , . . . _ _ _ _ _ . - , . - - _ . . , _ _ . . . . . . . _ . . , _ _ - - . . _ _ . . - , _ . _ . _ _ _ . _ _ _ . .

, 5 " ,1

y '3 -

.

'

,

/.

-

,

o

,

,,s

,

,

4

Attachment 1

2

,

TABLE

RCS LEAK RATE DATA

All Values GPM

DATE/ TIME

(NUREG 1107)

CORRECTED

OURATION

L

N

N

N

L

G

G

U

U

U

3/14/88

0.4260

0.43

-0.03

0.07

0.0720

1:03 a.m

2 Hours

3/15/88

0.6760

0.68

-0.02

0.08

0.0843

7:58 a.m.

2 Hours

3/28/88

0.2902

0.29

-0.05

0.05

0.0568

2:23 p.m.

2 Hours

3/30/88

0.3161

0.32

0.05

0.15

0.1562

4:11 p.m.

2 Hours

G = Identified gross leakage

U = Unidentified leakage

L - Licensee calculated

N = NRC calculated

  • Declared invalid by licensee due to water addition to make-up tank.

Columns 2 and 3, 5 and 6 correlate + 0.2 gpm in accordance with NUREG 1107.

N is corrected by adding 0.1044 gpm to the NUREG 1107 N due to total purge flow

u

u

through the No. 3 seal from RCP's.