:on 970521,non-environmentally Qualified Matl Existed in Containment Hatch Applications.Caused by Inadequate Design Review.Mods Will Be Performed to Remove Existing Teflon Material| ML20148N666 |
| Person / Time |
|---|
| Site: |
Point Beach  |
|---|
| Issue date: |
06/19/1997 |
|---|
| From: |
Malanowski T WISCONSIN ELECTRIC POWER CO. |
|---|
| To: |
|
|---|
| Shared Package |
|---|
| ML20148N659 |
List: |
|---|
| References |
|---|
| LER-97-027, LER-97-27, NUDOCS 9706270353 |
| Download: ML20148N666 (4) |
|
text
r j
NWC FORM 366 U.S. NUCLEAR REGULATORY CONMISSION APPROVED BY OM8 NO. 3160-0104 (4-95)
EXPIRES 04/30/98 ESTIMATED BURDEN PER RESPONSE TO COMPLY WITH I
THIS INFORMATION COLLECTION REQUEST: 50 0 HRS.
REPORTED LESSONS LEARNED ARE INCORPORATED LICENSEE EVENT REPORT (LER)
INTO THE LICENSING PROCESS AND FED BACK TO INDUSTRY.
FORWARD COMMENTS REGARDING BURDEN ESTMATE TO THE INFORMATION AND (See reverse for required number of RECORDS MANAGEMENT BRANCH (T-6 F 33).
U.S.
digits / characters for each block)
NUCLEAR REGULATORY COMMISSION, WASHINGTON.
1 DC 20555-0001, AND TO THE PAPERWORK REDUCTION PROJECT j
l FACILITY NAME (1)
DOCKET NUMBER (2)
PAGE (3)
Point Beach Nuclear Plant, Unit 1 05000266 1OF4 I
TITLE (4) 1 NON-ENVIRONMENTALLY QUALIFIED MATERIAL IN CONTAINMENT HATCH APPLICATIONS EVENT DATE (5)
LER NUMBER (6)
REPORT DATE (7) 01HER FACILITIES INVOLVED (8) l SEQUENTIAL REVISION FACILITY NAME DOCKET NUMBER l
1 MOPTH DAY YEAR YEAR NUMBER NUMBER MONTH DAY YEAR PBNP Unit 2 05000301 l
l l
FACILITY NAME DOCKET NUMBER l 05 21 97 97 027 --
00 06 19 97 05000 OPERATING THIS REPORT IS SUBMITTED PURSUANT TO THE REQUIREMENTS OF 10 CFR 4: (Check one or more) (11)
MODE (9)
N l 20.220 m 20.2203aH2Hv) 50.73iaH2Hi) 50.73(a)i2Hvm)
POWER 20.2203(aH1) 20.2203(aH3)h) 50.73(aH2)Di) 50.73(aH2Hx) j LEVEL (10)
OQQ 20.2203(aH2)h) 20.2203(aH3Hn) 50.73(aH2Hm) 73.71 j
i l
20.2203(a)(2)hi) 20 2203(aH4) 50.73(aH2Hiv) oTHER I
20.2203(aH2Hm) 50.36(cH 1)
X 60.73(aH2Hv)
Specifv m Absusci below i
20.2203(a H 2Hiv) 50.36tcH2) 50.73(aH2)(vn) or m NRC Form 366A LICENSEE CONTACT FOR THIS LLR (12) lNAME TELEPHONE NUMBER Unclude Area Code)
Thomas G. Malanowski, Senior Project Engineer (414) 221-3950 COMPLETE ONE LINE FOR EACH COMPONENT FAILURE DESCRIBED IN THIS REPORT (13)
CAUSE
SYSTEM COMPONENT MANUFACTURER REPORTABLE
CAUSE
SYSTc COMPONENT MANUFACTURER REPORTABLE TO NPROS M
TO NPRDS I
SUPPLEMENTAL REPORT EXPECTED (14) l PECTED U
YEAR l
YES SUBMISSION (if yes, complete EXPECTED SUBMIESION DATE).
X NO DATE (16) t ABSTRACT (Limit to 1400 spaces, i.e., approximately 15 single-spaced typewntten lines) (16)
As a result of a review of operating experience information from another utility for applicability to the Point Beach Nuclear Plant, it was determined that the pressure equalizing valves in the containment personnel hatches utilized a Telfon material in various applications which is not qualified for the worst case post-accident radiation environment.
In addition, packing material associated with a small window in the containment hatch doors is also believed to contain Telfon.
Unit 1 is presently being maintained in cold shutdown.
Unit 2 is presently being refuelad.
Under the present conditions, containment integrity is not required for either unit.
The valves and windows will be replaced or modified to replace the Telfon with a suitable material prior to j
containment integrity being required.
WRC FORM 366 14 951 9706270353 970619 PDR ADOCK 05000266 S
PDR i
.---___~.--.--_-__..~n
_~...,. _.. -
. -.. ~
9U.S. NUCLEAR REGULATORY COMMISSION (4-95)
LICENSEE EVENT REPORT (LER)
TEXT CONTINUATION FACluTY NAME tu DOCILET NUMBER (2)
LER NUMBER 16)
PAGE (3)
YEAR SEQUENTIAL REVISION l
Point Beach Nuclear Plant, Unit 1 05000266 NUMBER NUMBER 2OF4 j
97 027 00 l
TEXT tu more space is reausres use easirionar copes or ivsc Form :166A) (11)
Event Description
Point Beach Nuclear Plant, Unit 1 is presently being maintained in cold shutdown.. Unit 2 is being refueled.
During review of operating experience information from another utility, it was determined that the pressure equalizing ball valves utilized Telfon in various applications.
This material is not qualified for use in the worst case post-accident radicion environment.
l r
INPO Nuclear Network item OE 8390 reported that the shaft seal assemblies on valves used in the containment access hatch systems at the Ginna Station have Telfon packing.
An evaluation at Ginna concluded that the inner door seals could be subjected to radiation levels that could cause the seal to fail, i
A review of containment personnel hatch design at the Point Beach Nuclear Plant was performed.
It has been determined that the prescure equalizing ball valves used on the upper and lower containment personnel access hatches utilize Telfon in various applications.
The inner valves are shielded from containment by 3/4" steel.
In addition, the outer door on upper personnel access is shielded by a lead bulkhead, reducing the exposure to the outer boundary.
In addition, based upon discussions with the manufacturer it has been determined that there is a high likelihood that the material utilized to seal a small window in the hatch doors also contains Telfon.
The radiation threshold for Telfon is 10E4 to 10E5 rads.
The predicted radiation levels in containment following the design basis loss of coolant accident as documented in the Final Safety Analysis Report are approximately 1.5E8 rads.
The Telfon material is likely to degrade to an unacceptable degree in the post-accident radiation environment.
Degradation of the Telfon material in the existing applications in the post-accident containment radiation environment, could result in a direct pathway for leakage of containment atmosphere to the environment.
Safety Assessment
This condition may impact the ability of the hatches, particularly of thel
tU.S. NUCLEAR REGULATORY COMMISSION l
(4-95) j
~
LICENSEE EVENT REPORT (LER)
TEXT CONTINUATION FACILITY NAME (1)
DOCKET NUMBER (2)
LER NUMBER (6)
PAGE (3)
YEAR SEQUENTIAL REVISION Point Beach Nuclear Plant, Unit 1 05000266 NUMBER NUMBER 3OF4 t
97 027 00 TEXT tit more space os requored, use additional copies of IVRC Forrn 366Al (1 D inner door, to perform their safety function.
The upper hatches are equipped with a lead bulkhead and door which would reduce the radiation exposure to the outer door components.
The lower hatches are not shielded.
Under worst case post-accident conditions, the Telfon material could degrade such that a direct leakage pathway from the containment atmosphere to the environment is created.
Csuse The cause of this event has been determined to be an inadequate original design review in that the environmental conditions were apparently not 1
considered when selecting the Telfon material for use in these applications.
i Component and System Description:
The Point Beach Nuclear Plant primary reactor containment structures are designed and constructed with two containment personnel access hatches.
Each personnel access hatch is a double door (airlock), welded steel assembly.
The airlocks are designed to withstand all containment design conditions with either or both doors locked closed.
Both doors open toward the interior of the containment and are therefore sealed under containment pressure.
The volume between the doors is pressurized to test for leak tightness.
Quick-acting type equalizing valves are provided to connect the personnel lock with the interior and exterior of the containment vessel for the purposes of equalizing pressure when entering or leaving containment.
The doors and valves are interlocked to prevent both doors and/or both valves from being opened simultaneously during periods when containment integrity is required.
The pressure equalizing ball valves are two-inch, full port WKM Dyna Seal valves.
The valves contain Telfon seats, stem gaskets, seat cup, tail piece gasket and pacring.
The containment hatch windows are original construction and were manufactured by Pressure Products Company.
Corrective Actions
l l
l A review was performed of the component instruction manuals, drawings and CHAMPS to identify possible uses of Telfon in PBNP hatches.
The review NriO FORM 366A (4-95)
~~
- - -. ~,. - _... -. -.. ~. _... - - - ~ - -.
NRC FORM 36TA U.S. NUCLEAR REGULATORY COMMIS$10N (4 95)
LICENSEE EVENT REPORT (LER)
TEXT CONTINUATION i
FACILITY NAME (1)
DOCKET NUMBER (2)
LER NUMBER (6)
PAGE (31 YEAR SEQUENTIAL REVISION Point Beach Nuclear Plant, Unit 1 05000266 NUMBER NUMBER 4OF4 j
97 027 00 i
TEXT tot more space is requeed, use additional copies of NRC form 366A) (1 11 l
found the above use of Telfon.
I Modifications will be performed to remove the existing Telfon material and l
replace it with material qualified for the post-accident radiation i
environmen t.
l Appropriate 1eak rate testing wi11 be performed fal1owing modifications to l
ensure the integrity of the e ntainment boundary.
I i
These actions will be completed prior to establishing conditions that require containment integrity.
A root cause evaluation is being completed.
Additional corrective actions
will be taken as determined appropria to from recommendations contained in l
the root cause evalua tion.
i
Reportability
l This condition is being reported in accordance with 10 CFR
- 50. 73 (a) (2) (v) (D), "Any event or condition that alone could have prevented the fulfillment of the safety function of structures or systems that are needed to mitigate the consequences of an accident."
l Similar occurrences l
l None.
l EIIS System and Component Identifiers I
Valve, Isolation ISV j
l F
|
|---|
|
|
| | | Reporting criterion |
|---|
| 05000266/LER-1997-001, :on 970108,safety Injection Delay Times Exceeded Design Basis Values.Caused by Degraded Voltage Conditions.Licensee Engineers Will Prepare FSAR Change Requests to Reflect LBLOCA Evaluation |
- on 970108,safety Injection Delay Times Exceeded Design Basis Values.Caused by Degraded Voltage Conditions.Licensee Engineers Will Prepare FSAR Change Requests to Reflect LBLOCA Evaluation
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000301/LER-1997-001, Forwards LER 97-001-00,re Containment Structure Where Internal Containment Structural Members Could Have Damaged Containment Liner During Safe Shutdown Earthquake | Forwards LER 97-001-00,re Containment Structure Where Internal Containment Structural Members Could Have Damaged Containment Liner During Safe Shutdown Earthquake | | | 05000301/LER-1997-001-01, :on 970107,containment Liner Clearance Was Not IAW Plant Design Basis.Caused by Void Between Containment Liner & Concrete Containment Structure.Inspected Containment |
- on 970107,containment Liner Clearance Was Not IAW Plant Design Basis.Caused by Void Between Containment Liner & Concrete Containment Structure.Inspected Containment
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) | | 05000266/LER-1997-002, :on 970109,potential to Overpressurize Piping Between Containment Isolation Valves Occurred.Caused by Original Design Not Providing Overpressure Protection for Piping.Review Completed |
- on 970109,potential to Overpressurize Piping Between Containment Isolation Valves Occurred.Caused by Original Design Not Providing Overpressure Protection for Piping.Review Completed
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000301/LER-1997-002-01, :on 970415,potential Reactor Coolant Sys Branch Connection Stresses Beyond Design Basis,Indicated.Caused by Mod Initiated to Remove RTD Bypass Line Isolation Valves. Stress Analysis Conducted on RTD Bypass Piping |
- on 970415,potential Reactor Coolant Sys Branch Connection Stresses Beyond Design Basis,Indicated.Caused by Mod Initiated to Remove RTD Bypass Line Isolation Valves. Stress Analysis Conducted on RTD Bypass Piping
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000266/LER-1997-003, :on 970109,did Not Perform Leak Test on Spare Containment Penetrations Per Ts.Caused by Lack of Routine Testing.Tested Penetrations W/Satisfactory Results |
- on 970109,did Not Perform Leak Test on Spare Containment Penetrations Per Ts.Caused by Lack of Routine Testing.Tested Penetrations W/Satisfactory Results
| 10 CFR 50.73(a)(2)(1) | | 05000301/LER-1997-004-01, :on 970729,declared RHR Loop Inoperable Due to CCW Leak.Caused by Failure of RHR Heat Exchanger CCW Piping. Repaired Piping & Declared RHR Loop Operable |
- on 970729,declared RHR Loop Inoperable Due to CCW Leak.Caused by Failure of RHR Heat Exchanger CCW Piping. Repaired Piping & Declared RHR Loop Operable
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000266/LER-1997-004, :on 970113,potential for Particular Common Mode Failure That Could Affect Opposite Trains of Unit 2 Safeguards Equipment Was Noted.Caused by Lack of Physical Separation.Replaced Subject Circuit Breakers |
- on 970113,potential for Particular Common Mode Failure That Could Affect Opposite Trains of Unit 2 Safeguards Equipment Was Noted.Caused by Lack of Physical Separation.Replaced Subject Circuit Breakers
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000301/LER-1997-005-01, :on 970806,RHR Pump Was Declared Inoperable Due to Abnormal Seal Leakage from Loop a RHR 2P-10A.Repaired RHR Pump |
- on 970806,RHR Pump Was Declared Inoperable Due to Abnormal Seal Leakage from Loop a RHR 2P-10A.Repaired RHR Pump
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000266/LER-1997-005, :on 970116,1SI-852A Was Not Tested IAW Inservice Test Program Required by Tss.Caused Because Condition Revealed That Valve 1SI-852A Had Not Been Completely Tested.Tests Will Be Reviewed |
- on 970116,1SI-852A Was Not Tested IAW Inservice Test Program Required by Tss.Caused Because Condition Revealed That Valve 1SI-852A Had Not Been Completely Tested.Tests Will Be Reviewed
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) | | 05000266/LER-1997-006, :on 970120,refueling Cavity Drain Failed During Loca.Caused by Inadequate Evaluation of Original Design.Design of Refueling Cavity Drains Was Revised with Respect Capability to Withstand an Earthquake |
- on 970120,refueling Cavity Drain Failed During Loca.Caused by Inadequate Evaluation of Original Design.Design of Refueling Cavity Drains Was Revised with Respect Capability to Withstand an Earthquake
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000266/LER-1997-007, :on 970124,determined That Potential Existed for EDG Overload Condition.Caused by Failure to Recognize This Condition When Plants Initially Licensed W/Two Edgs. Implemented Procedure Changes |
- on 970124,determined That Potential Existed for EDG Overload Condition.Caused by Failure to Recognize This Condition When Plants Initially Licensed W/Two Edgs. Implemented Procedure Changes
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000266/LER-1997-008, :on 970131,non-seismic Ductwork Located Above safety-related Equipment in Containment Occurred.Caused by Incomplete Seismic Evaluation.Mods Will Be Completed During Current Unit 2 Refueling Outage |
- on 970131,non-seismic Ductwork Located Above safety-related Equipment in Containment Occurred.Caused by Incomplete Seismic Evaluation.Mods Will Be Completed During Current Unit 2 Refueling Outage
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(x) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition | | 05000266/LER-1997-009, :on 970214,potential for Safety Injection Failure During Filling of Safety Injection Accumulator Discovered.Caused by Situation Not Adequately Covered by Procedures.Procedure OI-100 Revised |
- on 970214,potential for Safety Injection Failure During Filling of Safety Injection Accumulator Discovered.Caused by Situation Not Adequately Covered by Procedures.Procedure OI-100 Revised
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000266/LER-1997-010, :on 970219,svc Water & Component Cooling Water TS Action Requirements Were Not Met.Caused Because Licensee Did Not Comply W/Cold Shutdown Requirements of TS 15.3.3.C.2 & 15.3.3.D.2.Evaluations Were Performed |
- on 970219,svc Water & Component Cooling Water TS Action Requirements Were Not Met.Caused Because Licensee Did Not Comply W/Cold Shutdown Requirements of TS 15.3.3.C.2 & 15.3.3.D.2.Evaluations Were Performed
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000266/LER-1997-011, :on 970305,containment Fan Cooler Accident Fans Were Not Tested in Accordance with Tss.Caused by non-conservative Interpretation of Literal Requirements of Tss.Unit 1 & 2 Accident Fans Were Tested |
- on 970305,containment Fan Cooler Accident Fans Were Not Tested in Accordance with Tss.Caused by non-conservative Interpretation of Literal Requirements of Tss.Unit 1 & 2 Accident Fans Were Tested
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(1) | | 05000266/LER-1997-012, :on 970304,diesel-drive Fire Pump Day Tank Not Sampled IAW TSs.Non-conservative Interpretation of TS Led to Failure.Day Tank T-30 Sample Was Drawn & Analyzed W/Satisfactory Results |
- on 970304,diesel-drive Fire Pump Day Tank Not Sampled IAW TSs.Non-conservative Interpretation of TS Led to Failure.Day Tank T-30 Sample Was Drawn & Analyzed W/Satisfactory Results
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(1) | | 05000266/LER-1997-013, :on 970304,CCWS Found Not in Accordance W/ Plant Design Basis.Caused by Inoperable Valve Due to Overtorquing in Closed position.Cross-tie Will Be Resolved |
- on 970304,CCWS Found Not in Accordance W/ Plant Design Basis.Caused by Inoperable Valve Due to Overtorquing in Closed position.Cross-tie Will Be Resolved
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000266/LER-1997-013-01, Forwards Suppl LER 97-013-01,re Component Cooling Water Sys Not IAW Plant Design Basis.Rept Replaces LER 97-013-00 in Its Entirety & Includes Addl Similar Occurrence Not Previously Reported to NRC | Forwards Suppl LER 97-013-01,re Component Cooling Water Sys Not IAW Plant Design Basis.Rept Replaces LER 97-013-00 in Its Entirety & Includes Addl Similar Occurrence Not Previously Reported to NRC | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000266/LER-1997-014, :on 970321,auxiliary Feedwater Sys Inoperability Due to Loss of Instrument Air.Design Mods Initiated,Providing Pneumatic Supply to Control Valves |
- on 970321,auxiliary Feedwater Sys Inoperability Due to Loss of Instrument Air.Design Mods Initiated,Providing Pneumatic Supply to Control Valves
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii) | | 05000266/LER-1997-015, :on 970324,control Room Ventilation Sys Declared Inoperable Due to Failures of Backdraft Damper & Vent Duct Access Door.Backdraft Damper,Replaced |
- on 970324,control Room Ventilation Sys Declared Inoperable Due to Failures of Backdraft Damper & Vent Duct Access Door.Backdraft Damper,Replaced
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000266/LER-1997-016, :on 970325,SG Level Logic Was Not Tested IAW Ts.Caused by Nonconservative Interpretation of Tss.Ts Amends Proposed to Provide Consistency Between Test Requirements & LCO Associated W/Sg Tests |
- on 970325,SG Level Logic Was Not Tested IAW Ts.Caused by Nonconservative Interpretation of Tss.Ts Amends Proposed to Provide Consistency Between Test Requirements & LCO Associated W/Sg Tests
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000266/LER-1997-017, :on 920508,containment Third Door Was Blocked Open During Refueling Operations.Caused by Interpretation That Movement of Core Components Per TS Definitions Rather than Literal Wording.Routine Maintenance Procedure Revised |
- on 920508,containment Third Door Was Blocked Open During Refueling Operations.Caused by Interpretation That Movement of Core Components Per TS Definitions Rather than Literal Wording.Routine Maintenance Procedure Revised
| 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition | | 05000266/LER-1997-018, :on 970403,potential for RHR Overpressure During Accidents Was Discovered.Original Design Did Not Provide Overpressure Protection for Isolated Piping Section. Evaluation Was Performed to Determine Stress on Piping |
- on 970403,potential for RHR Overpressure During Accidents Was Discovered.Original Design Did Not Provide Overpressure Protection for Isolated Piping Section. Evaluation Was Performed to Determine Stress on Piping
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000266/LER-1997-019, :on 970404,RHR Not Aligned IAW TS Requirements. Caused by non-conservative Decision Making & Not Recognizing When TS Were Not Controlling Plant Operations.Pbnp Mgt Philosophy Re TS Interpretations Changed to Minimize Use |
- on 970404,RHR Not Aligned IAW TS Requirements. Caused by non-conservative Decision Making & Not Recognizing When TS Were Not Controlling Plant Operations.Pbnp Mgt Philosophy Re TS Interpretations Changed to Minimize Use
| 10 CFR 50.73(a)(2)(1) | | 05000266/LER-1997-020-01, Forwards LER 97-020-01,describing Plant Conditions in Which Ability to Achieve & Maintain Safe Shutdown in Event of Postulated Fire May Have Been Adversely Affected | Forwards LER 97-020-01,describing Plant Conditions in Which Ability to Achieve & Maintain Safe Shutdown in Event of Postulated Fire May Have Been Adversely Affected | 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor | | 05000266/LER-1997-021, :on 970430,determined That Spent Fuel Pool Cooling Sys Was Not in Accordance W/Plant Design Basis.Cause Indeterminate.Closed & re-tagged Valves SF-27 & SF-28 & Investigated Basis for Fsar,App a |
- on 970430,determined That Spent Fuel Pool Cooling Sys Was Not in Accordance W/Plant Design Basis.Cause Indeterminate.Closed & re-tagged Valves SF-27 & SF-28 & Investigated Basis for Fsar,App a
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000266/LER-1997-022, :on 970507,discovered That Postulated Control Room Fire May Cause Electrical Hot Short That Disables Limit or Torque Switches for Certain Movs.Mods Initiated to Remedy Condition |
- on 970507,discovered That Postulated Control Room Fire May Cause Electrical Hot Short That Disables Limit or Torque Switches for Certain Movs.Mods Initiated to Remedy Condition
| 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor | | 05000266/LER-1997-023, :on 970508,discovered Noncompliant Emergency Lighting for Postulated App R Fires.Caused by Alternative Provisions Made in Original Safe Shutdown Analysis.Emergency Lights Will Be Installed |
- on 970508,discovered Noncompliant Emergency Lighting for Postulated App R Fires.Caused by Alternative Provisions Made in Original Safe Shutdown Analysis.Emergency Lights Will Be Installed
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000266/LER-1997-024, :on 970501,determined Post Accident Sampling Sys Degradation.Caused by Inadequate Design Review.Will Upgrade Containment Atmosphere Sample Sys & Will Perform Mod to Reduce Dose within GDC 19 Dose Limits |
- on 970501,determined Post Accident Sampling Sys Degradation.Caused by Inadequate Design Review.Will Upgrade Containment Atmosphere Sample Sys & Will Perform Mod to Reduce Dose within GDC 19 Dose Limits
| | | 05000266/LER-1997-025, :on 970520,pressurizer Level Was Controlled Higher than Assumed in Accident Analysis.Caused by Inappropriately Changing Procedures W/O Adequate Consideration.Listed Affected Procedures Will Be Revised |
- on 970520,pressurizer Level Was Controlled Higher than Assumed in Accident Analysis.Caused by Inappropriately Changing Procedures W/O Adequate Consideration.Listed Affected Procedures Will Be Revised
| 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition | | 05000266/LER-1997-026, :on 970521,discovered TS Violation of Operability Requirement of MSL Isolation.Caused by Inadequate Consideration for Operability of All Required Functions.Verified Low RCS Sys Average Temp |
- on 970521,discovered TS Violation of Operability Requirement of MSL Isolation.Caused by Inadequate Consideration for Operability of All Required Functions.Verified Low RCS Sys Average Temp
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000266/LER-1997-027, :on 970521,non-environmentally Qualified Matl Existed in Containment Hatch Applications.Caused by Inadequate Design Review.Mods Will Be Performed to Remove Existing Teflon Material |
- on 970521,non-environmentally Qualified Matl Existed in Containment Hatch Applications.Caused by Inadequate Design Review.Mods Will Be Performed to Remove Existing Teflon Material
| | | 05000266/LER-1997-031, :on 970619,discovered That Auxiliary Feedwater (AFW) Pump Low Suction Pressure Trip Setpoints May Not Ensure Adequate Suction Pressure Protection for AFW Pumps Following Tornado Event.Caused by Inadequate Design |
- on 970619,discovered That Auxiliary Feedwater (AFW) Pump Low Suction Pressure Trip Setpoints May Not Ensure Adequate Suction Pressure Protection for AFW Pumps Following Tornado Event.Caused by Inadequate Design
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000266/LER-1997-032, :on 970630,discovered Inadequately Rated Electrical Buses Could Disable Switchgear & Cause Secondary Fires.Caused by Characteristic of Original Design. Established twice-per-shift Fire Watches |
- on 970630,discovered Inadequately Rated Electrical Buses Could Disable Switchgear & Cause Secondary Fires.Caused by Characteristic of Original Design. Established twice-per-shift Fire Watches
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000266/LER-1997-034, :on 970707,discovered Unplanned Loss of Voltage on Train B Safeguards Buses.Caused by Inadequate Design & Design Review for Installation of New Train B Edgs.Incorrect Wiring Reworked |
- on 970707,discovered Unplanned Loss of Voltage on Train B Safeguards Buses.Caused by Inadequate Design & Design Review for Installation of New Train B Edgs.Incorrect Wiring Reworked
| 10 CFR 50.73(a)(2)(iv), System Actuation | | 05000266/LER-1997-035, :on 970516,discovered Inadequate Seismic Support for Reactor Coolant Pump Rotor Stand.Caused by Rotor Stand Being Stored Since Initial Plant Construction.Moved Rotor Stand & Verified as Seismically Adequate |
- on 970516,discovered Inadequate Seismic Support for Reactor Coolant Pump Rotor Stand.Caused by Rotor Stand Being Stored Since Initial Plant Construction.Moved Rotor Stand & Verified as Seismically Adequate
| 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat | | 05000266/LER-1997-036, :on 970826,potential Common Mode Failure in DC Power Supply Which Could Disable AFW Sys Was Noted.Caused by Inadequate Design & Design Review.Plant Mods Were Performed to Eliminate Potential Common Mode Failure |
- on 970826,potential Common Mode Failure in DC Power Supply Which Could Disable AFW Sys Was Noted.Caused by Inadequate Design & Design Review.Plant Mods Were Performed to Eliminate Potential Common Mode Failure
| | | 05000266/LER-1997-037, :on 970903,potential Failure of EDG Load Sequence Occurred.Caused by Inadequate Design of EDG Load Sequencing Logic.Mod Restored Operability of EDG During Load Sequencing |
- on 970903,potential Failure of EDG Load Sequence Occurred.Caused by Inadequate Design of EDG Load Sequencing Logic.Mod Restored Operability of EDG During Load Sequencing
| | | 05000266/LER-1997-038, :on 970926,determined That Inoperability of Standby Emergency Power Placed Unit 2 in 7-day Lco.Caused by Failure That Occurred When EDG G-03 Was Shutdown.Repaired Governor & Returned EDG G-03 to Service |
- on 970926,determined That Inoperability of Standby Emergency Power Placed Unit 2 in 7-day Lco.Caused by Failure That Occurred When EDG G-03 Was Shutdown.Repaired Governor & Returned EDG G-03 to Service
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000266/LER-1997-039-01, :on 970615,RHR Loop Inoperable.Caused by Removal of CCW Pump from Svc.Ccw Pump Restored |
- on 970615,RHR Loop Inoperable.Caused by Removal of CCW Pump from Svc.Ccw Pump Restored
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000266/LER-1997-039, Forwards LER 97-039-00 Re RHR Loop Inoperable,Due to Inoperable CCW Pump.New Commitments within Rept Indicated in Italics | Forwards LER 97-039-00 Re RHR Loop Inoperable,Due to Inoperable CCW Pump.New Commitments within Rept Indicated in Italics | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000266/LER-1997-040-01, Forwards LER 97-040-01 Which Documents Event That Occurred at Point Beach Nuclear Plant,Unit 1.Commitments Made within Ltr,Encl | Forwards LER 97-040-01 Which Documents Event That Occurred at Point Beach Nuclear Plant,Unit 1.Commitments Made within Ltr,Encl | 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition | | 05000266/LER-1997-041, :on 971023,potential Common Mode Failure in Afws Control Circuits Was Noted.Caused by AFW Control Circuits Installed by Plant Mods.Temporary Mods Will Restore Physical Separation for Cables |
- on 971023,potential Common Mode Failure in Afws Control Circuits Was Noted.Caused by AFW Control Circuits Installed by Plant Mods.Temporary Mods Will Restore Physical Separation for Cables
| | | 05000266/LER-1997-042, :on 971030,discovered That Upper Containment Personnel Air Interlock Had Been Inoperable.Caused by Removal of Remote Operating Gear.Reinstalled Remote Operating Connector Gear |
- on 971030,discovered That Upper Containment Personnel Air Interlock Had Been Inoperable.Caused by Removal of Remote Operating Gear.Reinstalled Remote Operating Connector Gear
| 10 CFR 50.73(a)(2)(1) | | 05000266/LER-1997-043-01, Forwards LER 97-043-01,re Discovery That TS Surveillance of Reactor Trip Sys Interlocks Were Not Adequate. Supplemental Info Is Provided at End of Rept.Previous Commitments Made within Rept Also Encl | Forwards LER 97-043-01,re Discovery That TS Surveillance of Reactor Trip Sys Interlocks Were Not Adequate. Supplemental Info Is Provided at End of Rept.Previous Commitments Made within Rept Also Encl | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | | 05000266/LER-1997-044, :on 971216,use of Dedicated Operators During IST of Containment Spray Sys Constituted Operation Prohibited by Ts.Caused by Improper Consideration for Use of Dedicated Operators.Revised Procedures |
- on 971216,use of Dedicated Operators During IST of Containment Spray Sys Constituted Operation Prohibited by Ts.Caused by Improper Consideration for Use of Dedicated Operators.Revised Procedures
| |
|