Corrected Page to Monthly Operating Rept for June 1985
ML20141N709
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 06/30/1985
From: Woodard J
ALABAMA POWER CO.
To:
Shared Package
ML20141N703 List:
References
NUDOCS 8603170548
Download: ML20141N709 (1)


Text

,

i-OPERATING DATA REPORT DOCKET NO. 50-364 DATg March 4.1986 COMPLETED BY J. u. woodard

~

TELEPHONE 203-s99-5156 OPERATdNG STATUS l

Joseph M. Farley - Unit 2 Notes

,, pg,

2. Reperdas Per6od-I'm. tons
1) Cum'ulative data since
3. Liesseed Thennel Power (MWt):

2652 7-30-81, date of commercial

4. Nameplete Raties (Genes MWe):

860 operation.

829

5. Design Electrial Ranns (Net MWe):

530,2

6. Maximum Dependable Capacity (Gross MWe):
7. Maaimum Dependebie Capacity (Not MWe):

809.2

8. If Changes Occur in Capacity Ratings (Itenne Number 3 Tluough 7) Since Last Report. Give Reasons:

N/A A

9. Power Level To Which Restricted.lf Amy (Net MWe):
10. Reasons For Restrictions,if Any:

N/A This Moeth Yr..to-Dete Cumulative

~

720 4.343 34,368

11. Hours la Reporting Pened
12. Nanber Of Hours Reactor Was Critical 7on n 2.563.8 29.482.3 l

0.0

13. Reactor Reserve Shutdown Hours nn 11e n
14. Hours Generator On-Line 720.0

? ;1o n 29.097.1

15. Unit Reserve Shetdown Hours 0.0 o,o o,o'
16. Gross Thennel Energy Generated (MWH)
1. AM 72; 6,260,885 73.I13.633 4
17. Genes Electrieel Inorgy Generated (MWH) 618.8s8 2.078.366 "R.024.646 i
18. Net Electrieel Energy Generated (MWH) 589.612 1.952.084

% //1.UVO

19. Unit Service Facto, 100.0 58.0 84,7 l
20. Unit Availability Factor 100.0 58.0 84.7 5_._6 81.6
21. Unit Capacity Factor (Using MDC Nt) 10'.2 5

90.8 54.2 79.9

22. Unit cepeesty Factor (Using DER Nt)
23. Unit Forced Outage Rate nn 1.1 5.1
24. Shutdowns Scheduled Over Wat 6 Mooths (Type. Dete and Duration of Each t:

N/A 1

25. If Shut Down At End Of Report Period. Estimated Date of Startup:

l

26. Units in Test Status tPrior to Commercial Operation):

Forecast Achwved j

05-06-81 05-08-81 INITIAL CRITICALITY 05-24-81 05-25-81 INITIAL ELECTRICITY 08-01-81 07-30-61 COMMERCIAL OPERATION 8603170549 960310 ADOCK O' % g 4 pA DR

.