ML20137E821

From kanterella
Jump to navigation Jump to search
Board Notification 86-002:forwards Insp Repts 50-456/85-37 & 50-457/85-36 on 851105-08 of Emergency Preparedness Exercise on 851106 to Test Licensee,State of Il & Local Organizations Response to Hypothetical Accident Scenario
ML20137E821
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 01/14/1986
From: Stevens J
Office of Nuclear Reactor Regulation
To: Callihan A, Cole R, Grossman A, Grossman H
Atomic Safety and Licensing Board Panel
References
TASK-AS, TASK-BN86-002, TASK-BN86-2 BN-86-002, BN-86-2, NUDOCS 8601170326
Download: ML20137E821 (2)


See also: IR 05000456/1985037

Text

  • A/OOS

oug b

~g UNITED STATES

8' n NUCLEAR REGULATORY COMMISSION  !

$ WASHINGTON, D. C. 20555

'% , , , , , # JAN 141996

l

l

Docket Nos.: 50-456

50-457

MEMORANDUM FOR: Atomic Safety and Licensing Board

for Braidwood Station Units 1 and 2

(H. Grossman, A.D. Callihan, R.F. Cole)

FROM: Janice A. Stevens, Project Manager

PWR Project Directorate #5

Division of PWR Licensing-A

SUBJECT: BOARD NOTIFICATION REGARDING AN INSPECTION OF THE

BRAIDWOOD STATION'S EMERGENCY PREPAREDNESS EXERCISE

(BN-86-02)

. In accordance with the NRC procedures for Board Notifications, the enclosed

inspection report is being provided. This information is applicable to the

Braidwood Station, Units 1 and 2. Parties to the proceeding are being

informed by copy of this memorandum.

A routine announced inspection was conducted by the NRC on November 5-8, 1985,

of the Braidwood Station emergency preparedness exercise. This

full-participation exercise, conducted on November 6, 1985, tested the

integrated response of licensee, State, and local organizations to a

hypothetical accident scenario resulting in a major release of radioactive

material. No violations, deficiencies, or deviations were identified.

However, some exercise weaknesses were identified as summarized in the

Appendix. These weaknesses will be examined during a future inspection.

stIce h

Janice A. Stevens, Project Manager

PWR Project Directorate #5

Division of PWR Licensing-A

Enclosure: As stated

cc: SECY (2) ~'

ED0

OGC

OPE

ACRS (10)

Parties to the Proceeding

See next page

@o11703@

.. .

- .

.

.

,,

,,

aL30LA104Y 14F Jn M A l l ure DISIHidJT10N SYSTEM (RIJSl

ACCLSSIOi NBR:SS12030281 30C.DAIL: 65/11/27 NOTAHlZED: NU DJCKE1 s

FACIL:STN-50-45b 3raiowood Station, unit 1, Commonwealtn Edison Co 05000456

STN-50-457 Braio.ood Station, unit 2, Commonwealth Edison Co 05000457

AUTH.NAME AUTHOR AFFILIATION

SNAFERe a.D. Region 3, Office of Director

RLCIP,NAME RECIPIENT AFFILIATI3N

REED,C. Commonwealth Edison Co.

SUBJECT: Forwards Safety Inso Repts 50-456/85-37 & 50-457/85-36 cc

851105-06.No viointions noteo.neaunesses re merginal

accestability of Joint public info ctr identified. Updated

info & schedule re olenned improvements requested.

'

DISTHIBUTION C00L: IE35J COPIES NECEIVEO:LTH .1 ENCL .b SIZE:

TITLE: Emergency Preparedness-ADDreisel/Ccnfirmatory Action Ltr/ Exercise Reo

NDTES Standardized Plant. 05000456

Standardir.d Plant. 05000457

RECIPIENI CUPIES RECIPIENT COPIES '

ID C3DE/NAME LTTW ENCL LD-C^^C4"44 LTTR ENCL

Pnk-A PD5 PD 1 1 gr~ o l t vr36, J _ _ 1 1

INTERNAL: ADM/LF4d 1 0 IE/DEPER/EPS 3 3

nRH d4R AdiS 1 1 NRM Pod-A ADTS 1 1

NRR Pn4=b AJTS 1 1 NRR/DSRO DIR 1 1

H Giv 3 FILE 01 1 1 RGN2/0RSS/EPRPS 1 1

EXTERNAL: 24x 1 1 LPDH 1 1

IvHC P3R 1 1 NSIC 1 1

.

!

i

l

TOTAL NuudER JF C3PILS REJJIMEu LiiR 16 ENCL 15

'

$

'

.-

NOV 4 7 M

Docket No. 50-456

Docket No. 50-457

Commonwealth Edison Company

ATTN: Mr. Cordell Reed

Vice President

Post Office Box 767

Chicago, IL 60690

Gentlemen:

This refers to the routine safety inspection conducted by Mr. T. Ploski and

others of this office on November 5-8, 1985, of activities at the Braidwood

Nuclear Generating Station, Units 1 and 2, authorized by NRC Construction

Permits No. CPPR-132 and No. CPPR-133, and to the discussion of our findings

with Messrs. D. Galle, E. Fitzpatrick, and others of your staff at the

conclusion of the inspection.

The enclosed copy of our inspection report identifies areas examined during

the inspection: Within these areas, the inspection consisted of a selective

examination of procedures and representative records, observations, and

interviews with personnel.

No violations of NRC requirements were identified during the course of this

inspection. However, weaknesses were identified which will require corrective

action by your staff. These weaknesses are summarized in the Appendix to this

letter. As required by 10 CFR Part 50, Appendix E (IV.F), any weaknesses that

are identified must be corrected. Accordirq1y, please advise us within 30 days

of the date of this letter of the correctiva actions you have taken or plan to

take, showing the estimated dates of completion.

We remain concerned about the marginal acceptability of the facility that serves

as the Joint Public Information Center (JPIC) at Mazon, Illinois. We understand

that you plan to upgrade this facility. We hereby request that, along with your

formal response to the exercise weaknesses, you also provide updated information

regarding the extent of your planned improvements for this JPIC and the current

schedule for completing these improvements.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of

this letter, the enclosures, and your response to this letter will be placed

in the NRC Public Document Room.

The responses directed by this letter are not subject to the clearance

procedures of the Office of Management and Budget as required by the Paperwork

Reduction Act of 1980, PL 96-511.

/

h

8512030281 851127 6 ,(

PDR ADOCh 0500

G

w, , as ^*-

,

W ns#

.

.

.

.

Commonwealth Edison Company 2

NOV 2 7 G8%

We will gladly discuss any questions you have concerning this inspection.

Sincerely,

%riginalsignedbyW.p.Shafara

W. D. Shafer, Chief

Emergency Preparedness and

Radiological Protection Branch

Enclosures:

1. Appendix, Exercise Weaknesses

2. Inspection Reports

No. 50-456/85037(DRSS);

No. 50-457/85036(DRSS)

cc w/ enclosures:

D. L. Farrar, Director

of Nuclear Licensing

M. Wallace, Project Manager

D. Shamblin, Construction

Superintendent

E. E. Fitzpatrick, Station

Superintendent

C. W. Schroeder, Licensing and

Compliance Superintendent

DCS/RSB (RIDS)

Licensing Fee Management Branch

Resident Inspector, RIII

Braidwood

Resident Inspector, RIII Byron

Phyllis Dunton, Attorney

General's Office, Environmental

Control Division

D. W. Cassel, Jr., Esq.

J. W. McCaffrey, Chief, Public

Utilities Division

H. S. Taylor, Quality Assurance

Division

E. Chan, ELD

J. Stevens, NRR

The Honorable Herbert Grossman, ASLB

The Honorable A. Dixon Callihan, ASLB

The Honorable Richard F. Cole, ASLB

D. Matthews, EPB, OIE

W. Weaver, FEMA, RV

RIII RI RIII RIII e I

l!!D R(

Plos 1/rr P erson

&V UG7

rs Nilliamsen P lips er b

IeIke 5 r

11/27/85 k'

-

.

.

I

Appendix

EXERCISE WEAKNESSES

1. Neither Control Room nor Technical Support Center staff simulated a

call to the NRC Operations Center as a result of the Alert declaration.

(456/85037-01 and 457/85036-01) (Sections 4.a and 4.b)

2. Forecast changes in meteorological conditions were not adequately

incorporated into the offsite protective action decisionmaking process.

(456/85037-02'and 457/85036-02) (Section 4.e)

l

l

l

.

!

!

!

. - - __. ._- . . ._--

.

.

'

.

.

.

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Reports No. 50-456/85037(DRSS): 50-457/85036(DRSS)

Docket Nos. 50-456; 50-457 Licenses No. CPPR-132; CPPR-133

Licensee: Commonwealth Edison Company

Post Office Box 767

Chicago, IL 60690

Facility Name: Braidwood Nuclear Generating Station, Units 1 and 2

Inspection At: Braidwood Station, Braidwood, IL

Inspection Conducted: November 5-8, 1985

Inspectors: T. Ploski

$ ////27/g/f

Team., Leader Date

~ fa &.

.

///1.7/]~9

Patters '

/

Date

f

D. obrer uh

Date

I

L. Kers ///77/ff

Y " l

. a e <? 9ff 5

Date

Approved By: . P. ps, Chief

Emergency Preparedness Section

'/!2N[

Date

Inspection Summary

Inspection on November 5-8, 1985 (Reports No. 50-456/85037(DRSS:

No. 50-457/85036(DRSS))

Areas Inspected: Routine announced inspection of the Braidwood Nuclear

Generating Station's emergency preparedness exercise, involving otservations

by thirteen NRC representatives of key functions and locations during the

exercise. The inspection involved 226 inspector-hours onsite by eight NRC

inspectors and four consultants.

Results: No violations, deficiencies, or deviations were identified.

However, exercise weaknesses were identified as summarized in the Appendix.

8512030287 8511P7

PDR

O ADOCK 05000456

P D.'t

l M,

e - , ,_-

u ey or- r

> w __ $W

'

.

.-

..

DETAILS

1. Persons Contacted

a. NRC Observers and Areas Observed

T. Ploski, Control Room, Technical Support Center (TSC)

J. Patterson, Corporate Command Center (CCC)

M. Phillips, Emergency Operations Facility (EOF)

N. Williamsen, TSC

L. Kers, EOF

D. Rohrer, TSC, EOF

F. McManus, Control Room

F. Carlson, Operational Support Center (OSC), Fire Brigade,

Inplant Teams

G. Stoetzel, OSC, Inplant Teams

E. King, Radiological Environmental Monitoring Teams

R. Lickus, Joint Public Information Center (JPIC) and EOF

J. Strasma, JPIC

b. Commonwealth Edison Personnel

D. Galle, Assistant Vice President and General Manager, Nuclear

Stations

E. Fitzpatrick, Station Manager

D. O'Brien, Assistant Superintendent, Administrative Services

L. Butterfield, Manager, Nuclear Services, Technical

J. Golden, Supervisor of Emergency Planning

T. Blackmon, Lead Controller, EOF

L. Literski, GSEP Coordinator

S. Stapp, Quality Assurance Department *

L. Bush, Controller, Control Room

D. Vestal, Controller, TSC

W. McNeill, Controller, TSC

M. Whitemore, Controller, OSC

J. Barr, Controller, CCC

H. Finch, Controller, Control Room

T. Markwalter, Controller, OSC

T. Greene, Controller, Environs Team

W. Brenner, Lead Emergency Planner

The above licensee personnel attended the November 7, 1985 exit interview.

2. General

An exercise of the licensee's Generating Stations Emergency Plan (GSEP) and

the Braidwood Annex was conducted at the Braidwood Station on November 6,

1985, testing the integrated response of licensee, State, and local

organizations to a hypothetical accident scenario resulting in a major

!

,

!

2

__ . _ .

. ._.

.

.

.

release of radioactive material. The exercise was integrated with a test

of the Illinois State, Will County, Kankakee County, and Grundy County

emergency plans. This was a full participation exercise for the State of

Illinois and all counties. Attachment 1 describes the licensee's scope

of participation for the exercise. Attachment 2 describes the exercise

objectives. Attachment 3 is a narrative summary of the scenario.

3. General Observations

'

a. Procedures

This exercise was conducted in accordance with 10 CFR Part 50,

Appendix E requirements using the GSEP, Braidwood Annex, and the

emergency plan implementing procedures used by the Station,

Emergency Operations Facility (EOF), and Corporate Command Center

, (CCC).

b. Coordination

The licensee's response was coordinated, orderly, and timely. If

the events had been real, actions taken by the licensee would have .

ceen sufficient to permit the State and local authorities to take

appropriate actions to protect public health and safety.

c. Observers

Licensee observers observed and critiqued this exercise along with

NRC observers and several Federal Emergency Management Agency (FEMA)

observers. FEMA observations on the responses of the State and local

governments will be provided in a separate report.

d. Critique

The licensee held critiques immediately following the exercise on

November 6, 1985. The NRC critique was held at the Mazon E0F on

November 7, 1985. In addition, a public critique was held on

November 8, 1985 to present both the onsite and offsite preliminary

findings of the NRC and FEMA representatives, respectively.

4. Specific Observations

a. Control Room

The Shift Engineer (SE) activated the Station's Fire Brigade after

receiving a report of heavy smoke in an inplant area. An Unusual

Event was correctly declared when the fire location was not identi-

fied within ten minutes of the smoke report. Initial notifications

to the State of Illinois and the NRC Operations Center were completed

in a correct and timely manner; however, the SE became overly involved

in making the calls himself rather than delegating more calls to a

3

.. . .

--. -

,

.

knowledgeable communicator. Meanwhile, another member of the j

Control Room crew was stopped by an exercise controller while calling 1

the Braidwood Fire Department to request its assistance. Other i

onshift personnel continued to closely monitor radio communications

from the Fire Brigade, which had split into two groups as more than

one fire location was suspected.

.

,

'

As a result of the SEC becoming overly involved in personally making

certain calls and the late controller action in stopping an exercise

participant from contacting the local fire department, there was about

twenty minutes of confusion among all onshift personnel as to whether

the local fire department was responding to the Station. Before the

confusion was resolved, the Corporate Command Center (CCC) and the

Operations Duty Supervisor (005), who later reported to the Technical

Support Center (TSC), had been informed that the fire department was

expected onsite. Several other work groups were also alerted to meet

the fire trucks at the gatehouse. All facilities and work groups

were later informed that offsite firefighting support had only been

simulated.

The SE and 005 were well aware of the potential to upgrade the

emergency classification depending on what plant equipment degrada-

tion had occurred. A proper, conservative decision was made to

activate certain TSC personnel and the Operational Support Center

(OSC) due to the then unknown number of fires and associated damage.

-

Once'the SE learned that there had been only one fire and that it had

not affected safety related equipment, it was decided to continue OSC

and TSC activation for damage assessment and corrective actions

management purposes.

With one exception, personnel demonstrated adequate knowledge and

efficient use of relevant emergency procedures. Personnel neglected

to fill out a Fire / Injury checklist form found in Administrative

Procedure 1110-16. However, onshift personnel did take all proper

actions in response to the fire. Due to the status of Control Room

construction and licensed operator training, operators were, on

several occasions, uncertain whether certain panel switches had yet

been installed. One operator also expressed unfamiliarity with the

meaning of scenario information that the incore thermocouple readout

was "9999 and flashing." Later, there was some uncertainty regarding

whether containment purge line valve IVQ005A was located inside or

outside the containment building. It was determined that this valve

was in containment and, therefore, inaccessible to any team sent to

attempt its closure.

Based on the above findings, the following items should be considered

for improvement:

i

  • Control Room personnel should demonstrate the capability to

,

properly complete all forms and checklists relevant to an

exercise scenario.

f

4

i

e--, __ _ __ . _. _ _ _ _ . , . . . _ - _ , . . _ _ _ _ . _ . . , _ _ _ . . _ . - , , __ _ _ _ - _ _ _ _ , _

- _ _ _ _ . _ . _ _ . _ _ _ _ _ . .

, . . - .

-

.

,

.

  • Knowledgeable communicators should be utilized whenever

appropriate to relieve the SE of becoming overburdened with

telephone communications.

b. Technical Support Center (TSC)

The Technical Support Center (TSC) was activated following the Unusual

Event declaration. The decision to activate this facility, due to one

or more inplant fires of unknown origin and significance, was conser-

vative and appropriate. Activation was rapid and orderly; however,

it included all clerical support staff and the Administrative and

Stores Directors, who would typically not be activated until an Alert

'

had been declared. This over response may have been due to the

knowledge that an exercise was occurring. In the future, the TSC

activation should be limited to the Station Group Directors and other

personnel who would really respond to the TSC for this particular

Unusual Event declaration.

The Station Director (SD) assumed command and control of onsite '

emergency response activities from the SE (acting SD) in a timely

manner, only after having been adequately briefed on the situation

and ensuring that TSC staff were ready. Periodic briefings were

utilized throughout the exercise to keep TSC staff well informed

of scenario events and major decisions, with the only significant

exception being what protective actions were being implemented

offsite. TSC staff demonstrated their capabilities to perform their

assigned responsibilities. Relevant plant drawings were effectively

. utilized in problem analyses. Trending of relevant plant parameters

was well done. There were numerous examples of good teamwork. The

directors maintained adequately detailed records of their actions.

In general, the use of internal message forms was very good; however,

a message containing the analysis results of a post accident sample

was misplaced for a few minutes at a time when this information was

being sought as input to emergency reclassification decisionmaking.

One Director soon realized that this information had been reported,

, and the misplaced message form was found and given to the 50. The

various TSC logs and message forms were transcribed on a personal

computer, enabling administrative staff to generate a duplicate of

an individual log or a comprehensive, chronological record of all key

staffs' log entries. Thus, the applicant would have no trouble

regarding reconstruction of actions and decisions involving TSC

personnel.

The SD's decisions to reclassify conditions as an Alert and later as

a Site Area Emergency were correct and timely. The associated

initial notifications to the State of Illinois, using the Nuclear

Accident Reporting System (NARS), were very prompt. Although the

simulated notification of the NRC Operations Center was performed

i immediately after the State was told of the Site Area Emergency

j declaration, no Control Room or TSC communicator simulated a call

5

w , _ - . _ _ _ _ _ _ _ . - _ _ _

- - _. . - . - , . . _ _ .___-.

_ _ - - .

.

.

.

.

.

to the NRC concerning the Alert declaration. Had scenario events

been real, it is possible that the Control Room or TSC would have

maintained open line communications with the NRC Operations Center

at any time following the Unusual Event declaration. It is also

possible, however, that a real emergency would not have escalated

beyond that classifiable as an Alert, especially since the reasons

for the Unusual Event and Alert declarations were unrelated (fire and

loss of coolant accident, respectively). The fact that a call to the

'

NRC Operations Center was not simulated for the Alert declaration is

an Exercise Weakness (456/85037-01 and 457/85036-01).

In general, communications between the TSC, CCC, and Emergency

Operations Facility (E0F) were adequate. As the exercise progressed,

TSC dose. assessment staff continued to generate offsite dose pro-

jections and to monitor transmissions from offsite survey teams

under EOF control, thus enabling the SD to have the information he

needed to meaningfully participate with his EOF and CCC counterparts

in offsite protective action decisionmaking. In contrast, there was

some confusion between the TSC and EOF regarding the number and status

(closed or open) of three valves in the release path for this

scenario. For this reason, and due to some dubious scenario infor-

mation regarding an alarming radiation monitor downstream of the "

valves in the release path, personnel in both facilities incorrectly

concluded that the release had initiated shortly after 1030. After

j many communications involving the TSC, EOF, and inplant and offsite

'

survey teams, it was verified that the release had not begun at that

time. However, TSC staff should have been more aggressive in

attempting to have an inplant team attempt closure of one or both

accessible valves in the potential release path, which was a

containment building purge line having three valves - one within and

2 two outside containment. Volunteers should have been sought and

emergency worker exposure limits authorized for this task. Instead,

work on this task was inhibited when an inplant team encountered a

higher radiation field than they were allowed to work within. By.

not providing emergency worker exposure limits such that teams had to

abandon this task, the opportunity to prevent a release from occurring

through this flow path was lost.

Promptly after the Site Area Emergency declaration, the SD ordered

the simulated assembly and accountability of all onsite personnel.

Once informed that this task had been completed, the Station, Rad

Chem, Environs, and Security Directors showed good judgement and

concern for nonessential personnel by simulating their evacuation ~

from the Station along a radiologically safe route. Allowing for

reasonable times for the assembly, accountability, and site

evacuation processes to be accomplished, the latter would have been

completed prior to the radioactive release.

,

e

6

'

. _- ._ . . __ - _ _ - . _ .-. . . _ - _ ..

. - - - _ - - __ -_. - - . - _ . _ .- - --

!

.

.

..

Later in the exercise when the release began through the containment

purge line, TSC staff had no difficulty in confirming the release and 1

the release path. Several inplant survey teams were dispatched to -

confirm that there were no additional unmonitored release paths.

TSC staff then demonstrated good knowledge of plant systems in the

identification of several possible methods to close at least one of

,

the two accessible valves in the release path. Actions were well

underway to close one of these two valves when a scenario message

indicated the closure of a third, inaccessible valve in the release

path. Nevertheless, TSC staff and an inplant team continued their

!

efforts and demonstrated that they could also close one of the two

,

accessible valves, providing further assurance that the release had

been stopped.

.

Following a scenario time jump, TSC staff successfully demonstrated

their ability to identify and prioritize short-term recovery tasks.

<

Based on the above findings, the following item should be considered

for improvement: ,

  • Emergency worker exposure limit should be promptly provided to *

teams that perform tasks which could mitigate or prevent a

release of significant amounts of radioactivity from the plant.

c. Fire Brigade, Operational Support Center (OSC) and Inplant Teams

The strategy of splitting the fire brigade to expedite identifying

the fire location (s) was appropriate. Considering the potential for

having multiple fires, the brigade captain's request for offsite

support was proper. The brigade identified the only fire location

within an acceptable twenty minutes and correctly reported the fire's ,

location to the Control Room. Both portions of the brigade were

adequately equipped, and demonstrated their abilities to keep each

other and the Control Room well informed of their activities.

The OSC was fully operational with adequate staff within an

acceptable thirty minutes of the decision.to activate this facility.

i

The OSC Director effectively managed the facility. Communications

between the OSC, TSC, and Control Room were good. An adequately

,

detailed OSC log was maintained. Personnel were issued high range

dosimetry upon their first arrival at the OSC. Portable radios and

a status board were effectively utilized to track inplant teams.

Dose extensions were requested from the TSC for members of the teams

l who could receive over 100 millires exposure while performing

assigned tasks. Personal exposure records were adequately maintained.

No teams were observed to leave the OSC without Radiation Chemistry

Technician (RCT) support. RCTs routinely checked their survey

instruments for proper operation and current calibration before

leaving the OSC.

4

_. - _ _ . _ _ _ _ _ .- -

_ . _ - _ _ __ _ _

__ _ _ , - - - - _ ,

-- - . _ - - . - . -. - -.

.

l.

.

,

The quality of briefings given to OSC personnel was adequate, with

the exceptions that assembled persons were not told that a General

'

Emergency had been declared for about ninety minutes, and later that

the release had ended around 1345. The quality of briefings given

to specific teams generally improved during the exercise. Although

the briefings addressed rauiological hazards, they did not routinely

incorporate current Area Radiation Monitor (ARM) data available from

the Control Room. Several teams stopped in the Control Room to

obtain such data before proceeding on their missions. In addition,

inplant radia u rn survey information posted on plant layout maps in

the OSC did not always include the valid times of the data,

i

! A contamination control point was established and utilized at the

OSC's entrance while background radiation levels were low. OSC

habitability surveys were periodically done. Several air samples

were also taken in the OSC, beginning before the radioactive release.

, The initial air sample was taken over a twenty-five minute period,

although it was reported as a thirty minute sample. The technician

had difficulty in finding procedural guidance for collecting and

,

counting the sample. The sample cartridge was then improperly left

'

on a table for several hours. A RCT who collected another sample was

observed to be handling the particulate filter without gloves.

Based on the above findings, the following items should be considered

for improvement:

  • All persons in the OSC should be kept well informed of all

major events during an emergency, including any emergency

reclassifications.

  • Briefings given to inplant teams should incorporate relevant

ARM data in addition to available survey information. Valid

times of these types of data should be available in the OSC.

~

* RCTs assigned to collect air samples should receive additional -

training on sample collection, counting, and handling techniques.

d. Corporate Command Center (CCC)

i

The CCC was activated in a timely manner. Actual transfer of command

and control of emergency response activities from the TSC to the CCC

was appropriately delayed for a short time, as persons in the TSC

l were very involved in finalizing an emergency reclassification

decision and in completing the associated initial offsite notifica-

tions. Subsequent transfers of command and control from the TSC to

the CCC, and later from the CCC to the EOF were smooth and done only

after the managers of both involved facilities had been adequately

'

briefed. Optional transfer of control of the Station's offsite

l monitoring teams from the TSC to the CCC was not accomplished, per

l the agreement of the staffs of both facilities. The CCC Director

kept in close communication with his TSC and EOF counterparts, and

'

l

8

i

_. . . . . _ - _ . - . ._

_. - ._ . _

- - - .-_; - -- . - - _ _ - - . _ . .. . - - - -- - -

.

'

ensured that his staff did likewise. Key staff maintained adequately

,

detailed records of their activities. In general, status boards were

kept up to date; however, offsite monitoring team data could have

been posted in a more timely manner.  ;

e. Emergency Operations Facility (EOF)

The EOF became fully operational within one hour of the decision to

activate this facility. Access control was adequate, although over-

zealous regarding NRC personnel who displayed proper identification

'

and had already been granted unescorted access to all areas of the

EOF building. Staff briefings were adequately detailed, but could

have been more frequent later in the exercise. Recordkeeping was

sufficient to provide adequate reconstruction of EOF activities and

j major decisions. Status boards were adequately maintained with a

, few, relatively minor informational discrepancies. Trending of

critical plant parameters was adequate.

!

All offsite notifications for the General Emergency and subsequent

major events, such as the beginning and end of the simulated release

and what protective actions were being recommended, were completed -

in a timely and accurate manner. Based on the radioactive release

rate and containment radiation level data available from the scenario,

EOF staff developed the appropriate offsite protective action

recommendations.

Although EOF staff issued appropriate protective action recommenda-

tions, the Recovery Manag a (RM) did not maintain a sufficient

awareness of what recommendations had been implemented offsite or

what was the progress of their implementation. Such information was

not, therefore, relayed to the TSC, CCC, or to the offsite monitoring

teams. Although TSC and EOF staff followed procedures and acquired

a meteorological forecast, a forecast shift in wind direction was not

'

incorporated into the protective action decisionmaking process. The

forecast wind direction shift did not occur prior to release termina-

tion. Nevertheless, the failure to adequately consider forecast

,

changes in meteorological conditions during the protective action

-

decisionmaking process is an Exercise Weakness (456/85037-02 and

, 457/85036-02).

,

Environs staff compiled and analyzed data received from the Station's

offsite survey teams; however, it was not evident that attempts were

made to acquire and utilize survey results from the State's teams

which were kept further from the Station.

l

'

In addition to the exercise weakness, the following items should be

considered for improvement:

  • Movements of NRC personnel displaying proper identification

should not be inhibited within the EOF once facility access

l has been granted.

,

9 ,

l

,

I

I

i

l -= r-

. _ _ _ _ _ __ __ _ .__

.

.-

  • The Recovery Manager and appropriate aides should maintain

adequate knowledge of the protective actions being implemented

offsite, including their completion status. Such information

should be relayed to the CCC, TSC, and to offsite survey teams.

  • Offsite survey results from State field teams should be

routinely acquired and utilized by EOF environs staff.

f. Radiological Environmental Monitorina Teams

Two teams were activated for this exercise. Both were adequately

briefed prior to being dispatched. They checked their field survey

kits for completeness, equipment operability, and equipment calibra-

tion before leaving the Station. Radios were also performance

checked; however, one team's only radio failed during the exercise,

resulting in a temporary loss of communications with this team.

The teams were well utilized by the TSC Environs staff to help

verify that no release had begun shortly after 1030. Both teams

remained relatively close to the Station throughout the exercise,

while the State's teams remained further away. The teams were

provided with adequately detailed, legible maps and exhibited

no difficulties in finding the locations to which they were directed

by TSC or EOF staffs. The team which was accompanied during the

exercise demonstrated proper techniques in collecting, handling, and

'

storing air, soil, and vegetation samples and in taking direct

radiation readings. Samples were adequately labeled for later iden-

tification. Proper care was taken to avoid spreading contamination

in the vehicle and among the sampling equipment. The team spent

much of its time in sampling at only one or two locat:ons and then

waiting outside the plume for further instructions. At no time was

either team utilized to determine the approximate borders of the

plume in order to ascertain whether its location in the environment

corresponded closely to predictions made by the Environs staff. On

one occasion, a team was told to replace environmental dosimeters.

However, no replacement dosimeters were available in their van,

, although it was understood that the van contained such equipment.

l

Radio communications between the teams and their TSC or EOF

,

controllers were not always easily understood, especially when a

team member attempted to communicate while wearing a face mask and

a throat microphone. However, those involved in the communications

persisted until the messages were understood. The teams were kept

sufficiently appraised of major scenario events, with two notable

exceptions. They were not promptly told when a Site Area Emergency

had been declared, and they were never infornied of what protective

actions were being implemented offsite.

10

_ _ _ _ _

_ _ _ _ - - .-. _ .__

.

'

..

..

Based on the above findings, the following items should be considered

for improvement:

  • All environmental monitoring teams should be equipped with

multiple radios.

  • Teams should be occasionally directed to ascertain the

approximate boundaries of the plume.

  • The teams should be provided with environmental dosimeters, if

they are expected to replace those currently deployed in the

field.

  • Teams should be promptly kept informed of all emergency

reclassifications and all protective actions being implemented

offsite.

g. Joint Public Information Center (JPIC)

The Joint Public Information Center (JPIC) was located in a storage /

workshop area at the eastern end of the EOF building. This location

has been utilized as the licensee's JPIC for all exercises of the

Dresden and LaSalle County Stations' emergency plans subsequent to

June 1983. The staff's concerns regarding the JPIC's marginal accept-

ability, in terms of its size; inadequate soundproofing evident when

the building's heating, ventilation, air conditioning, or water

pumping equipment are operating; and its inadequate number of

electrical outlets for the expected amount of media equipment have

already been documented in Inspection Reports No. 373/84018(DRSS)

and No. 374/84024(DRSS). The staff understands that the licensee has

budgeted funds for improving this and its other JPIC facilities,

although no schedule has been established for planned improvements.

The licensee issued six press releases during the exercise. All but

the first release, which was issued by the CCC, were approved by the

RM. None of the press releases contained false information; however,

the use of the word " stable" in Press Release No. 4 when describing

j the core's condition was confusing. While this press release

correctly stated that no release had yet occurred, there was already

sufficient evidence of significant core degradation. Emergency class

definitions were included where appropriate in the press releases.

However, the General Emergency definition was incompletely stated

in Press Release No. 3. None of the press releases adequately

addressed the licensee's prognoses on scenario events, the serious-

ness of the events, or what activities were being taken to mitigate

the consequences of the accident.

Several problems were evident regarding the performance of the

licensee's technical spokesperson. First, several of the licensee's

press briefings were not well coordinated with those of the govern-

mental spokesperson. At the first briefing, the licensee

spokesperson read an outdated press release issued by the CCC which

11

__. _ _ _ _ - _ . .

_ . _ _ _ .- _ _ _ . .

. _ _ . _ _ _ . _ . , . . _ _ _ _ . _ _ _ _ ._ _ _ _ _ _ _

-

.

i.

.

! .

.

P

'

dealt with the Alert phase of the emergency. While the spokesperson

'

said that an updated release was being prepared, his presentation

'

was then followed by that of a State spokesperson who was prepared

to discuss the current Site Area Emergency situation. The licensee

1ater held a-briefing regarding the General Emergency very soon

after it had been declared; however, the State spokesperson was not

yet ready to follow with his presentation in response to this.

significant change of scenario events. The second major problem

1

with the performance of the technical spokesperson was that he failed

to anticipate some basic questions relative to the emergency

conditions and thuc was not readily able to answer the audience's

questions. Such basic questions addressed when had the Loss of

!

Coolant Accident begun, and was the reactor core currently covered.

The spokesperson did, however, provide adequate answers to such

obvious questions at a later time.

I

i Such problems involving the performance of the licensee's technical

! spokespersons had been identified during several exercises at

the licensee's other nuclear generating facilities. By letter dated

September 5, 1985, the licensee has committed to complete several

specific corrective acticas to upgrade the capabilities of its

-

technical spokespersons. This will consist of revising the selection

i criteria for technical spokespersons and providing expanded training.

The current scheduled completion date for these corrective actions is

,

'

December 1986. As the inadequate performance of the licensee's

technical spokespersons has previously been identified as an exercise

,

,

weakness and a schtdule for corrective actions has already been

i estaolished, the performance of the technical spokesperson at the 1985

i

Braidwood Exercise is not a new exercise weakness. However, the

licensee's progress toward completing its commitments to improve the

!

capabilities of its technical spokespersons will be closely tracked

-

as will adherence to scheduled corrective action completion dates.

!

Other problems evident in this exercise were that the spokesperson

'

too often left the JPIC between press briefings, leaving no licensee

person obviously available to address media concerns in between press

briefings. Also, the building's ventilation and water pump equipment

was occasionally shut off to reduce background noise levels during

i

press briefings. The water pump equipment was restarted between

briefings when the building's water pressure was lost.

l Based on the above findings, the following items should be considered

l for improvement:

!

i

e Additional attention should be paid to the contents of press

j releases so that all information is clearly stated and complete.

  • Press releases should include, where appropriate, additional

. details to give some indications of the prognoses of the current

l situation, and activities to mitigate the consequences of the

event.

!

12

.

.

.

,

.

.

.

  • A knowledgeable licensee representatives should be clearly

designated and readily available within the JPIC at all times

when the technical spokesperson is absent from the JPIC.

5. Exit Interview

The inspectors held an exit interview on November 7, 1985 with those

licensee personnel identified in Paragraph 1. The inspectors discussed

the scope and preliminary findings of the inspection. The licensee

agreed to consider the items discussed. The inspectors determined from

the licensee that none of the information discussed was proprietary in

nature.

Attachments:

1. Exercise Scope

of Participation

2. ExerciseObjectives

3. Exercise Narrative

Summary

P

l

13

I

'

-

.

.

'

.-

t

E94IDWOOD 1985 GSEP EXERCISE

' SCOPE OF PARTICIPATION

,

Commonwealth Edison will participate in the Braidwood Station

exercise by activating the on-site emergency response organization

and the off-site emergency response organization as appropriate,

subject to limitations that may become necessary to provide for safe

efficient operation of Braidwood Station and other CECO nuclear

generating stations.

Activation of tne TSC and other on-site participants will oe

conducted on a real time basis during the day time hours. The

exerciseshiftwillreceivetheinitialscenarioinformation{and

respond accordingly.

The Nuclear Duty Person and the balance of the Recovery Group

will be prepositioneo close to Byron to permit use of Recovery Group

personnel from oistant locations.

The Corporate Command Center will be activated.

Commonwealth Edison will' demonstrate the capability to make

contact with contractors whose essistance would be required by the

simulated accident situation, but will not actually incur the expense

of using contractor ser:!ces to simulate emergency response except

as prearranged specificali, for the exercise.

Commonwealth Edison vil! arrange to provide actual

transportation and comagiire: ion support in accordance with existing

agreements to the eF$($P $pi.:ifically prearranged for the exercise.

j Commonwealth Edison ffli E ,<1de unforeseen actual assistance only to

the extent the resources are available and do not hinder normal

operation of the company.

l

l On-site assemoly and accountability along with High Range

Sampling System (HRSS) procedures will be simulated during the

!

exercise. Assembly and accountability will be demonstrated at a

'

date ano time selected to minimize disruption of construction work

in progress. HRSS will be demonstrated upon the completion of the

system at the Braidwood Station.

i

f

.

0453K

.

-

,

l

l

.

1

' .-

BRAIDWOOD 1985 GSEP EXERCISE  !

OBJECTIVES l

Primary Objective:

Demonstrate the capability to implement the Commonwealth

Edison Generating Stations Emergency Plan in cooperation with the

Illinois Plan for Radiological Accidents to protect the public in

the event of a major accident at the Braidwood Station. This

capability will De demonstrated during the hours to qualify as a

day-time exercise in accordance with NRC guidance.

Supporting Objectives:

.

1) Incident Assessment and Classification

a. Demonstrate the capaoility to assess the accident

conditions, to determine which Emergency Action ,

Level (EAL) has been reached, and to classify the

accident level correctly in accordance with GSEP.

- (EOF, CCC, TSC, CR)

2) Notification and Communication

a. Demonstrate tne capability to notify the .

principal offsite organizations within 15 minutes

of declaring an accioent classification.

- (EOF, CCC, TSC, CR)

b. Demonstrate the capability to notify the NRC

within one hour of the initial incident.

-

(CR)

c. Demonstrate the capability to contact

organizations that would normally assist in an

emergency, but are not participating in this

exercise (e.g. INPO, Murray & Trettel,

Westinghouse, etc.)

- (CR, CCC, EOF, TSC)

d. Demonstrate the ability to provide accurate and

timely information so that reports may De made to

the emergency news center for press releases.

- (EOF, CCC, TSC)

e. Demonstrate the ability to provice follow-up

information to the State in a timely manner.

-

(EOF)

3) Radiological Assessment

a. Demonstrate the capability to calculate off-site

l cose projections.

- (EOF, CCC, TSC)

-

.

.

.

..

-

.

l

..

-2-

b. Demonstrate the capability of environmental

field teams to conduct field raoiation surveys

and collect air, liquid, vegetation and soil

samples when needed.

- (EOF, CCC, TSC, ENV)

c. Demonstrate the capability to conduct in-plant

raciation protection activities.

- (OSC, HP)

d. Demonstrate the ability to perform calculations

with radiological survey information, trend this

information, and make appropriate

recommendations concerning protective actions.

- (EOF, CCC, OSC, HP)

4) Emergency Facilities

a. Demonstrate the capability to activate the

emergency organization and staff the nu~ clear

4

station emergency response facilities in

accordance with procedures during a day time

period.

- (EOF, TSC, HP, CCC, OSC)

b. Demonstrate througn aiscussion and staff

planning, the ability to perform a shift change

in the TSC, EOF and control room.

- (EOF, TSC, CCC)

5) Emergency Direction and Control

a. Demonstrate the ability of the directors to

manage the emergency organizations in the

implementation of the GSEP.

- (EOF, CCC, OSC, TSC, CR)

b. Demonstrate the capability of cooroinating the

'

direction of emergency response among CECO and

Illinois offsite command centers by using

Liasion personnel and communicators.

- (EOF)

6) Recovery and Re-entry

a. Demonstrate the capability of the emergency

response personnel to identify requirements,

, programs, and policies governing damage

i

assessments and implementing procedures for

i

'

recovery and re-entry.

- (EOF, CCC, TSC)

l - (Groups that are primarily concerneo)

, GA53W

i

- - , - , . _ _ _ _ _ _ . _ . . _ - . . , _ . . _

. _ _ _ _ _ _ . . _ . . _ _ - . _- - ._, ~,..---_-, - - .-

-

"

.

.

.

( NOVEMBER 1985 EXERCISE

Narrative Stannary

IMITIAL SITUATION 0'700 - 0'115 (15 minute duration)

  • Plant Status

Unit One: In operation at 100% power with a normal full power

electrical lineup with the exception of the IB Diesel Generator.

Surveillance testing of the Reactor Protection System was completed on the

previous shift. No power changes are anticipated. RCS activity is steady at

18 uci/gn. A tube leak of 0.15 gallon per minute atti;ibuted to tubes in the

la Steam Generator and well below Tech Spec limits is being tracked.

Unit Two: Shutdown in Mode 5 with major steam generator maintenance in

progress. Shutdown occurred within previous % hours following greater than

180 full power days of operation. Secondary plant maintenance is in progress

on the feedwater system and the turbine auxiliary systems.

  • Service Report

Unit One: Diesel Generator la has been out of service for 65 hours7.523148e-4 days <br />0.0181 hours <br />1.074735e-4 weeks <br />2.47325e-5 months <br /> for

turbocharoe- bearing changeout. It is_ estimated that three hours remain to

8

restore ic to service. 1B centrifugal charging pump was placed out of service

at 0500 today for work on the coupling. A Mini Purge is in progress to

balance containment pressure.

Unit Two: Steam Generator's 2A and 2B have tube plugging in progress

based upon previously scheduled repairs. Steam Generator 2C's secondary side

,

is drained and repairs are in progress to a secondary side inspection aanway.

l

  • Precursor Events

Two coal powered stations on the grid have gone off the line for

emergency maintenance within the past 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> and the Load Dispatcher has

advised that maximum power should be maintained on Unit one.

In the following zones of the fire protection system, a number of

ionization detectors but less than one-half the total for each zone, have been

reported as inoperable due to failure of their ionization detectors in the

surveillance test administered 11/4/85.

Zone 8 - 401' elevation

zone 9 - 401' elevation

Zone 10 - 383' elevation

zone 11 - 330' elevation

Zone 13 - 383' elevation

Zone 29 - 383' elevation

( Zone '76 - 426' elevation

._ _

.

'

.

.

J

%

.

.

Page 2

Generator fuel storage tank.At this time, investigatory work is being conducted in I

the last shift and is in the process of being replaced.The condens

instruments, on the average, were indicating 0.4% high.A calor

taken. No action has been

.

UNUSUAL EVDIT (0715 - 0800) (45 minute duration)

t = + 15

'

EAL 5A Fire.

10 minutes. Fire requires WRC notification if not identified within

located in the Unit 1 ESV Pump room (330'Heavy elevation).An

EP1B which iselectrical

smoke is carried

i IPM09J, zone 25; Aux Building HVAC system energized.through

Ten minutes later

annunciation on 2PM09J, zone 1*l. helping to localize the problem. Upon local

determination, the fire is classified as not requiring offsite assistance .

The non-safety related equipment within the tray is rendered inoperable.

!

(

A1.ERT 0800 - 0900 (60 minute duration)

t = +60

EAL 16 loss of Primary Coolant.

A > 50 gym leakage _ increase in a 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />

period

flow, or VCT level changes. leak rate calculation, charging pump

as indicated by either

leak of approximately 55 gym to develop suddenly.A stressed weld in

high VCT make-up.and a Pressurizer level decrease are the initial indications f

the humidity (slowly). Area radiation monitors in containment trend up, as does

initiated. A power rampdown of approximately 12 Mw/ min is

NOTE:

When this occurs, valve Ivg005A will fail to shut.An automatic securing of Mi

k

- ..

. ._

- - - . . ._

. - _ . .

.-

,

.

.

.

'.

Page 3

(

SITE EMERGENCY 0900 - 1030 (90 minute duration)

t = +120

EA1. 16 14ss of Primary Coolant. Primary system leakage is beyond makeup

capabilities of charging pumps.

The two inch cold leg bypass pipe shears with an instant leak rate of

approximately 1400 gym. Safety Injection is initiated either manually or

shortly thereafter automatically. High head SI flow is prevented from

entering the RCS by manual valves ISI 8810 A, B, C, and D, which have been

lined up in.the shut position instead of the open position. Initiation of

high head SI breaks loose a cap on the test connection in the line to these

valves, which allows flow through the line and out the test tee. Five minutes

after the initiation of the break, thermocouple and structural material broken

loose by the high velocity break flow lodges in the broken pipe and reduces

the break flow to 300 - 350 gpm. Shortly thereafter the primary pressure

begins to cycle between 1300 and 1550 PSIG as limited SI pump input and high

decay heat provide insufficient cooling for the core.

NOTE: Any attempt to depressurize the primary via the Pressurizer

PORV's during this time period will be met with failure. PORV 1 RY 455A is

inoperable due to a leaking diagram. PORV 1 RY 456 is inoperable due to a

(

bleed down of the nitrogen flask through a leaking check valve connection.

t = +130 (At 0920 hours0.0106 days <br />0.256 hours <br />0.00152 weeks <br />3.5006e-4 months <br /> an electrical fire reoccurs this time in the safety

system, tripping Bus 141 on overcurrent. Temperature spikes greater than

15000F noted by mainboard annunciation occur on thermocouple readout in

certain areas. Core damage occurs in the form of rod bursts,

t = +165

"With the restoration of Bus 141 and the second Safety Injection pump,

some cooling begins to take place in the core, which up until now had been

voiding and flooding, voiding and flooding due to insufficient cooling and

deeper and deeper core uncovery (greater mass loss than mass input and little

cooling effect from voided steam generator tubes). Increased cooling to the

hotter core areas, causes stress damage to the marginal clad / fuel positions,

resulting in more fission product release to the coolant and containment."

t = +180

Containment Radiation monitors indicates levels inside in excess of

4,000 R/hr.

t = +195

Coolant grab sample results delivered. [ Greater than 300 uci/gm].

\

.- . . - _ - . -_ . _ _ -__ - - - - - .

._ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _

l

..

.' -

'

.

- '

-

1

'

..

Page 4  ;

( l

GENERAL EMERGENCY 1030 - 1330 (210 minute duration)

t = +210

EAL 24 Loss of Fission Product Barriers.

A. > 2.0E 3 R/hr Primary containment Radiation, bhp.

B. Loss of two of the following three fission product barriers

with an imminent loss of the third barrier:

1. cladding; grab sample results > 300 uci/gm equivalent of

. 1-131,

2. Reactor coolant System;

a) containment pressure > 5 psig 3,gg,

b) containment temperature > 1500 F gnd,

c) containment humidity > 50%.

3. Primary Containment;

a) containment pressure > 50 psig g ,

b) Containment temperature > 2800 F E,

c) Loss of Containment integrity when containment integrity

, is required.

One containment Purge path valve (1VQ 005A) is already open. Indication

of mid position is seen for valve IV9005B.

t = +250

With the decrease in RCS pressures, the debris partially blocking the *

break flow shifts positions, and the leak increases to 1100-1200 gym. Break '

flow and charging flow counterbalance each other as cooling continues.

t = +315

Release path open via remaining purge valve (1VQ 005C) failing -

neophrene/ rubber seal fails under heat and pressure. Containment begins

venting to atmosphere through the path outlined above, an open exhaust damper,

and out the plant vent stack.

At 1345 valve IV9005A, purge valve, returns to it's shut position, thus

terminating the release.

RECOVERY / REENTRY (1430)

At 1430 hours0.0166 days <br />0.397 hours <br />0.00236 weeks <br />5.44115e-4 months <br />, a. 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> time jtamp occurs. The plant condition is

deemed stable, with sufficient subcooling, containment conditions under

( control (temperature, pressure, hydrogen levels, and sump recirculation in

progress.) No further indications of fire in the electrical system are found,

and radiation levels in containment have stabilized.

DSV/1mk/6342E/52 .

t

- -, , . . . . - _ _ . . - . - . _ - _ _ _ - _ , . _ .

'

jf . . ~ , . -. . ~.

.

DISTRIBUTION LIST FOR BOARD NOTIFICATION

Braidwood

Docket No. 50-456-457

Comonwealth Edison Company

Region III, U.S. Nuclear

Regulatory Comission

Dr. A. Dixon Callihan

Douglass W. Cassel, Esq.

Dr. Richard F. Cole

Lorraine Creek

H. Joseph Flynn, Esq.

Joseph Gallo, Esq.

Herbert Grossman

Erie Jones

Rebecca J. Lauer, Esq.

Ms. Bridget Little Rorem

Elena Z. Kezelis, Esq.

Jane M. Wicher

Mr. William Kortier

C. Allen Bock

'lhmas J, Gordon

Mr. Edward R. Crass

U. S. Koclear Regulatory Cannision'.

Resident Inspectors Office

ACRS (10)

.