ML20134M900

From kanterella
Jump to navigation Jump to search
Insp Rept 50-395/85-26 on 850603-07.Violations Noted:Failure to Meet Requirements of App R,Section Iii.G by Maintaining One Train of Hot Standby Sys Free from Fire Damage & Inadequate Fire Barriers
ML20134M900
Person / Time
Site: Summer, 05000385
Issue date: 08/13/1985
From: Conlon T, Hunt M, Madden P, Miller W, Taylor P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20134M887 List:
References
50-395-85-26, NUDOCS 8509040334
Download: ML20134M900 (30)


See also: IR 05000395/1985026

Text

> R Etc UNITED STATES

o NUCLEAR REGULATORY COMMISSION

"

[" p REGION 11

101 MARIETTA STREET, N.W.

,4 j

'

  • - 't ATLANTA, GEORGI A 30323

\...../

Report No.: 50-395/85-26

Licensee: South Carolina Electric and Gas Company

Columbia, SC 29218

Docket No.: 50-395 License No.: NPF-12

Facility Name: Summer

Inspection Conducted: June 3 - 7, 1985

Inspectors: M k. k)

W. H. Miller, Team Leader

b Th3/fb

Jate Signed

M. D.

f/ 8 f// b $- /3 -S S~~

// / Date Signed

5 . ,ry) / 8- t 3 -8$~

[ Date Signed '

P.M.fdde

Yb Ys

P. A. Taylor "

9- / 3 -W

Date Signed

Accompanying Personnel: R. Anan NRC/NRR-ASB

Approved b h 8-/8' M

T. E. Conlon, Chief Date Signed

Plant Systems Section

Division of Reactor Safety

SUMMARY

Scope: This special, announced inspection entailed 144 inspector-hours on site

in the areas of the licensee's actions regarding the implementation of the fire

protection and plant safe shutdown requirements of 10 CFR 50, Appendix R,

Sections III.G, III.J. III.L and III.0.

Results: Four apparent violations and one deviation were identified in the areas

of fire protection and the licensee's compliance with 10 CFR 50 Appendix R

Sections III.G, III.J. III.L and III.0: Failure to Meet the Requirements of

Appendix R,Section III.G, with Regard to Maintaining One Train of Hot Standby

Systems Free From Fire Damage - paragraph 5.a.(1); Failure to Meet the Require-

ments of Appendix R,Section III.G with Regard to Providing Separation for

Nuclear Instrumentation Required to Support Safe Shutdown Fire Areas - paragraph

5.a(1); Inadequate Fire Barrier Between Fire Areas IB-20 and IB-25.6 - paragraph

8.a; Nonfunctional Fire Barrier for Raceway VUL 34B in Fire Zone IB-23.2 - )

paragraph 8.b; and Failure to Conduct Fire Watch Patrol for Fire Area 18-25 -

paragraph 8.c. I

e509040334 850820

PDR ADOCK 05000385

G PDR

.- __

, . -. - _ - . .

.

.

REPORT DETAILS

1. Licensee Employees Contacted

  • 0. W. Dixon, Vice President, Nuclear Operations
  • 0. S. Bradham, Director, Nuclear Plant Operations
  • D. A. Nauman, Director, Nuclear Services
  • J. G. Connelly, Deputy Director, Operations and Maintenance
  • K. Woodward, Manager, Operations
  • M. B. Whitaker, Group Manager Regulatory and Support Services
  • A. R. Koon, Associate Manager Regulatory Compliance
  • J. Barker, Project Manager, Fire Protection
  • H. I. Donnelly, Senior Licensing Engineer
  • L. W. Lunden Nuclear Engineer
  • T. Wessner, Plant Operations
  • H. O'Quinn, Plant Operations
  • C. Fields, Plant Operations Technical Advisor
  • W. L. Safley, Plant Fire Protection Coordinators

Other Organizations

  • D. K. Kelly, Electrical Engineer, Gilbert
  • J. Seibert, Electrical Engineer, Gilbert
  • R. D. Angus, Fire Protection Engineer, Gilbert
  • T. J. Keckeisen, Fire Protection Engineer, Inter Science Incorporated

Rick Christensen, Nuclear Systems Engineer, Inter Science Incorporated

NRC Resident Inspectors

  • C. Hehl

P. Hopkins

  • Attended exit interview

2. Exit Interview

The inspection scope and findings were summarized on June 7,1985, with

those persons indicated in paragraph 1 above. The inspector described the

areas inspected and discussed in detail the inspection findings listed

below. No dissenting coninents were received from the licensee.

a. Unresolved Item (395/85-26-01), Review Resolution of Summer's

Appendix R Reanalysis Issues Regarding Revised Shutdown Schemes.

Associated Circuits and Demonstrating Compliance with Appendix R,

Sections III.G and III.L by NRR - paragraphs 5.a.(1) and 5.a(2)(b).

b. Unresolved Item (395/85-26-02), Review Resolution of Fire Induced

Spurious Signal and Safe Shutdown System Modification by NRR -

paragraph 5.a.(1).

l

,

.

2

c. Violation Item (395/85-26-03), Failure to Meet the_ Requirements of

Appendix R,Section III.G, With Regard to Maintaining One Train of Hot

Standby Systems Free From Fire Damage - paragraph 5.a.(1).

d. Violation Item (395/85-26-04), Failure To Meet the Requirements of

Appendix R,Section III.G. With Regard to Providing Separation for

Nuclear Instrumentation Required to Support Safe Shutdown - paragraph

5.a.(1).

e. Inspector Followup Item (395/85-26-05), Verify Breaker Coordination

Between XBCIA and DPNIHA and XMCIDB2X and APNIFB-EM - paragraph

5.a.(2)(a).

f. Inspector Followup Item (395/85-26-06), Review the Affects of Spurious

Valve Operation for Centrifugal Charging Pump - paragraph 5.a.(2)(b).

g. Unresolved Item (395/85-26-07), Review Resolution of the Licensee's

Associated Circuit Methodology with Regard to the Sample Size and

Circuits Analyzed for Over Current Protection by NRR - paragraph

5.a.(2)(c).

h. Unresolved Item (395/85-26-08), Correct Inadequacies Identified in

Procedure FEP 1.0 Based on Review and Approval of the Licensee's

Appendix R Reanalysis by NRR - paragraph 5.a.(3)(a).

i. Unresolved Item (395/85-26-09), Provide Limiting Times / Assumptions to

Arrive at Operator Action Time Lines to NRR for Review - paragraph

5.a.(3)(b). ,

'

j. Unresolved Item (395/85-26-10), Identify / Issue Procedures to Accomplish

Appendix R Section III.L Requirements and Performance Goals Which are

,

Based on the Appendix R Reanalysis Approved by NRR - paragraph

5.a.(3)(c).

k. Inspector Followup Item (395/85-26-11), Provide Training for All FEP

Procedures to Support Appendix R - paragraph 5.a.(3)(d).

1. Unresolved Item (395/85-26-12), Inadequate Number of 8-Hour Battery

Powered Emergency Lighting Units Provided for Areas Need for Operation

of Safe Shutdown Equipment - paragraph 7.

m. Violation Item (395/85-26-13), Inadequate Fire Barrier Between Fire

Areas 1B-20 and 18-25.6 - paragraph 8.a. ,

n. Violation Item (395/85-26-14), Non-Functional Fire Barrier for Raceway .

VUL 34B in Fire Zone 18-23.2 - paragraph 8.b.

o. Inspector Followup Item (395/85-26-15), Review Licensee's Analysis for

Unprotected Cable Tray Supports - paragraph 8.b.

. ,.

__

,

3

p. Unresolved Item (395/85-26-16), Verification That the "M" Board Fire

Barrier was Reviewed and A Deviation was Granted for This Plant

Condition by NRR - paragraph 8.b.

q. Deviation Item (395/85-26-17), Failure To Conduct Fire Watch Patrol for

Fire Area 18-25 - paragraph 8.c.

The licensee did not identify as proprietary any of the materials provided

to or reviewed by the inspectors during this inspection.

3. Licensee Action on Previous Enforcement Matters

This subject was not addressed in the inspection.

4. Unresolved Items

Unresolved items are matters about which more information is required to

determine whether they are acceptable or may involve violations or devia-

tions. Eight new unresolved items identified during this inspection are

discussed in paragraphs 5.a.(1), 5.a.(2)(a), 5.a.(3)(a), 5.a.(3)(b),

5.a.(3)(c), 7 and 8.b.

5. Compliance With 10 CFR 50, Appendix R, Section III.G And III.L

i Operating License Section 2.c.(18)a issued on November 12, 1982, states that

SCE&G shall maintain in effect, and fully implement, all provisions of the

approved fire protection plan, as amended through Amendment No. 33 to the

Final Safety Analysis Report (FSAR). In addition, this license section also

requires SCE&G to maintain the fire protection program set forth in

Appendix R to 10 CFR 50.

By letter dated April 20, 1981, SCE&G committed to the NRC to comply with

the requirements of 10 CFR 50 Appendix R Sections III.G, III.J. and 111.0.

Subsequently, on June 1,1981, SCE&G requested deviations with regard to the

literal technical requirements of 10 CFR 50 Appendix R for the following:

- Component Cooling Water Pumps B&C do not meet Appendix R separation

requirements

-

HVAC equipment water chiller pumps do not meet Appendix R separation

requirements

- Partial automatic suppression provided in the auxiliary building and

intermediate building

. - Fire detection capabilities are not provided throughout the auxiliary

,

building and intermediate building

.- . - -- - - - .

. ..--_ -. - . _. . . -- - .. - .

.

'

4

' On the basis of the licensee's fire hazard analysis, their commitment to

meet 10 CFR 50 Appendix R Section III.G, III.J and III.0 and the above

,

deviations, the NRC issued Safety Evaluation Report (SER) Supplement Nos. 3

and 4 on January and August 1982, respectively.

SER Supplement No. 3 indicated that the licensee's safe shutdown analysis

i identified the systems necessary to achieve and maintain. hot and cold

shutdown conditions. In addition, the SER stipulated that one of the

redundant trains required for safe shutdown would be maintained free from

fire damage by providing separation, fire barriers, repair procedures (for

i equipment required for cold shutdown only) and/or alternative shutdown

capabilities. Also, SER Supplement No. 3 indicated that the licensee's safe

,' shutdown analysis identified those components, cabling and support equipment

required for safe shutdown and performed a cable separation analysis for all '

j rooms of the plant housing safe shutdown equipment. The licensee by letter

! dated June 1, 1981, committed to provide a li hour fire rated barrier for

l

one safe shutdown train where redundant shutdown circuits or equipment are

j not separated by 20 feet with a very low intervening fire load or no

intervening combustibles. SER Supplement . No. 3 concluded that the

licensee's separation analysis was an acceptable means of demonstrating that

separation exists between redundant safe shutdown system trains.

SER Supplement No. 4 granted the licensee's request to deviate from the

technical requirement of 10 CFR 50 Appendix R with regard to the component

cooling water pumps, HVAC water chiller pumps and partial automatic

suppression and fire detection capabilities in the auxiliary and inter-

i~

mediate buildings. Therefore, SER Supplement No. 3 and 4 concluded that the

fire protection program, with the accepted deviations, meets the technical

requirements of Appendix R to 10 CFR 50.

,

'

On the basis of the additional guidance and information obtained at the

May 4, 1984, NRC Region II Appendix R Fire Protection Workshop SCE&G

initiated an Appendix R Reanalysis. The licensee contends that the

associated circuit review guidance pertaining to spurious signals provided

in Generic Letter 81-12 and its clarification letter was not considered in

their original Appendix R safe shutdown evaluation. The licensee stated

that.this guidance was not provided to them during plant licensing and in

order to ensure compliance a complete reevaluation of-their shutdown scheme

.was required. Generic Letters 81-12, 83-33 and Draft 85-01 and other -

, applicable interpretive documents were used as guidance for their reanalysis

j effort.

'

Therefore, an inspection of the licensee's reanalysis and revised shutdown

scheme was conducted to detennine if fire protection features provided for

structures, systems, and components important to safe shutdown at the Summer t

. facility were in compliance with 10 CFR 50, Appendix R. Sections III.G and

i III.L. The scope of this inspection determined if the fire protection

,

features ' provided for reactor coolant system inventory control, steam

i

t

l

_ -. ._ _ _ _ . __ __ _. __ .. . . . _ _ _ _ . _ _ - _ _ _

_ _ - _ _ _ _ _ _ __ __

.

5

generator inventory control, and reactor coolant system pressure control

were capable of limiting fire damage so that one train of these systems

essential to achieving and maintaining hot standby from either the control

room or emergency control stations are free from fire damage.

a. Safe Shutdown Capabilities

l In order to ensure safe shutdown capabilities, where redundant trains

of systems necessary to achieve and maintain hot standby conditions are

located outside the primary containment,10 CFR 50 Appendix R requires

l that one train of hot standby systems be maintained free of fire damage

l by providing fire protection features which meet the requirements of

l either Sections III.G.2.a. III.G.2.b, or III.G.2.c.

-On the basis of the above Appendix R criteria,' the inspectors made an

inspection of cabling and. components associated with the chemical

volume control system, emergency feedwater system, service water

system, chilled water system, instrumentation associated with reactor

inventory and steam generator inventory control and onsite powr-

distribution to determine the adequacy of the fire protection features

and the separation afforded for these essential systems.

(1) Separation / Fire Protection of Redundant Cabling to Safe Shutdown

Equipment

Based on the licensee's Appendix R Reevaluation, SCE8G has changed

their shutdown scheme with respect to fire conditions occurring in

plant areas outside of the control room, relay room and cable

spreading room. The licensee's preliminary results indicate that

a fire in certain plant areas outside the control room complex

could potentially cause damage to both trains of safe shutdown

systems. Thus, it appears control of the safe shutdown function

from the control room could be rendered inoperable. The licensee

indicated that local operator actions outside the control room

,

would be required in order to regain control of one train of the

fire damaged safe shutdown (hot. standby) function.

The following table, identifies the fire areas outside the control

room complex which, when affected by a fire may require local-

' operator actions in order to regain a safe shutdown function or

system and notes the safe shutdown train which will be controlled:

Level of

Designated Actions Required

Building Fire Area Shutdown Train To Regain Control

Auxiliary AB-1 A or B* Minor Local Control

i

Control CB-5 B Minor Local Control

l

- - - - _

.

6

Control CB-10 B Minor Local Control

Control CB-12 A Minor Local Control

Control CB-18 B Minor Local Control

Control CB-20 A Minor Local Control

Intermediate 18-25 A or B* Moderate Local

Control

Control CB-1 A Minor Local Control

Control CB-2 A Minor Local Control

Turbine TB-1 A or B Very Minor Local

Control

  • Shutdown train utilized depends on the location of the fire

in the fire area, B train preferred.

By letter dated May 29, 1985, the licensee identified the

following B-Train equipment which is necessary for safe shutdown

and is subject to maloperation due to fire induced hot shorts.

Equipment Tag # Description

XPP-43B-CSS Charging Pump "B"

XPP-458-SW S. W. Booster Pump "B"

.

XPP-1B-CC Component Cooling Pump "B"

XPP-488-VU Chilled Water Pump "B"

MFN-978-AH and Reactor Building Train B-

MFN-97D-AH Cooling Fans

XSW-1DB-ES, U4 Switchgear, XSW-1EB Feeder

XSW-1DB-ES, U7 Switchgear, XSW-1DB1 and XSW-IDB2 Feeder

XSW-IEB-ES, U3 Switchgear, XSW-1EB1 Feeder

XSW-1DB1-ES 480V Main Breaker

XSW-1DB2-ES 480V Main Breaker

XSW-1EB1-ES 480V Main Breaker

XFN-45A-AH Diesel Generator "B" Cooling Fans

XFN-458-AH Diesel Generator '?B" Cooling Fans

XPP-39B-SW S.W. Pump "B"

XEG-1B-DG Diesel Generator "B"

XHX-1B-VU Chiller Unit "B"

At the time of this inspection, the licensee had not identified

the control cable routing for these B-Train components. There -

fore, they could not ' verify if these B-Train safe shutdown

functions were separated from the A-Train. The licensee contends

that their revised fire / shutdown scheme takes credit for local

manual control of this equipment. However, in order to implement

-_ _ __ _ _ _ _ . _ ,__ _ _ . . . __. _

i

i

~

.

4

7

7

.

local manual operator actions, the licensee proposes to either

modify this equipment by-adding control transfer switches and

j local . controls or develope jumper procedures. The licensee

proposes to complete the plant modifications and develope the

,

appropriate jumper procedures by the end of the 3rd refueling i

outage. The inspectors informed the licensee that repairs (i.e.,

termination of leads, fuse pulling utilization of jumpers) to

.

achieve and maintain hot standby conditions have been found to be

unacceptable. The inspectors indicated that, in order to comply

l with 10 CFR 50 Appendix R Section III.G, one train of systems

j necessary to achieve and maintain hot standby conditions from

,

either the control room or emergency control stations must be

i maintained free from fire damage. The licensee contends that

repair procedures are functionally equivalent to the requirements

of 10 CFR 50 Appendix R, Section III.G.

With regard to the licensee's Appendix R reanalysis program the

,

inspectors identified the following concerns: i

- The Appendix R reanalysis does not specifically demonstrate

that the alternative shutdown capability provided for the

,

control room, cable spreading room and relay room can achieve

and maintain cold shutdown conditions within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.

-

The Appendix R reanalysis does not identify all the equip-

ment, components and cabling required to achieve and maintain

hot standby and cold shutdown conditions. ,

4 ,

- The Appendix R Associated Circuit Reanalysis does not appear

- to follow the guidance provided in generic letter 81-12 and

I

its- April 7.1982,. clarification letter with respect to

'

fuse / breaker coordination, common enclosures, and spurious

signals.

,

-

The Appendix R reanalysis does not identify the analysis

-

assumptions associated with the local control of safe

j shutdown systems for fires which affect plant areas outside

4

the control room complex nor did the reanalysis justify the

timeliness associated with these local controls

-

_The Appendix R reanalysis relies on fuse removal to isolate

' spurious signal to equipment and/or components which can

i cause the maloperation of systems necessary to achieve and

-maintain hot standby.

i Upon completion of the Appendix R reanalysis, the licensee

committed to revise Summer's fire protection evaluation report and

- submit a draft revision during the second quarter of 1986 to the ,

! NRC staff for review. The licensee indicated that their submittal

! will address the above inspection concerns, . describe the safe

,

shutdown system modifications required as a ' result of the

,. , .- ,.s ~ ~ , - .,, -

-e.,4m,.- , .- -,w---.n, m. c- ,,- . ep------,-m-nw---n-,4--

,

'

.

8

reanalysis, and explain the various shutdown schemes for fires

outside the control room which utilize local manual operator

actions to regain control of shutdown functions independent of the

control room. This is identified as Unresolved Item (395/85-

26-01), Review resolution of Summer's Appendix R reanalysis issues

regarding revised shutdown schemes, associated circuits and

demonstrating compliance with Appendix R Sections III.G and III.L

by NRR.

An inspection was made to determine if the cables or equipment

including associated nonsafety circuits that could prevent

operation or cause maloperation due to hot shorts, open circuits,

or shorts to ground, of redundant trains of systems necessary to

achieve and maintain hot shutdown conditions were provided with

adequate separation and/or fire protection features in accordance

with Appendix R Section III.G.2.

(a) Auxiliary Spray Valve Cabling

Control cabling associated with auxiliary spray valve

(XVT-8145-CS) are routed through the following fire areas:

-

Auxiliary Building Fire Area AB-1

-

Control Building Fire Areas CB-6, CB-10, CB-15, and

CB-17

-

Intermediate Building Fire Area IB-25

-

Reactor Building Fire Area RB-1

Therefore, a fire occurring in any of the above listed fire

areas could cause spurious operation of the auxiliary spray

valve due to a hot short to the solenoid control cable.

Inadvertent opening of this valve with a charging pump in

operation could result in primary plant de-pressurization.

By letter dated May 29, 1985, the licensee identified this

condition to the NRC.

In order to preclude the potential spurious operation of the

auxiliary spray valve from an external hot short, the

licensee proposes to replace the control cables from the

control room to the valve with cabling which includes a

grounded shield. In addition, the licensee proposes to

provide a second control power disconnect independent from

the control room disconnect in order to prevent spurious

auxiliary spray valve operation in the event of a control

room fire. This modification has been scheduled to be

completed by the end of the third refueling outage (second

quarterof1987).

.

'

.

9

(b) Steam Generator Power Operated Relief Valve Cabling

Control cabling associated with the steam generator power

operated relief valves (IPV-2000-MS, IPV-2010-MS, and

IPV-2020-MS) are routed through the following fire areas:

- Auxiliary Building Fire Area AB-1

- Control Building Fire Areas CB-1, CB-2, CB-4, CB-5,

CB-6, CB-10, CB-12, CB-17, CB-18

- Intermediate Building Fire Areas 18-20, IB-22 and 18-25

Therefore, a fire occurring in any of the fire areas listed

above, could cause spurious operation of steam generator

power operated relief valves due to a hot short to the

control cables associated with either of the two control

solenoids for each valve. Inadvertent opening of these

valves could cause excessive cooldown and reactor coolant

system shrinkage. By letter dated May 29, 1985, the licensee

identified this condition to the NRC.

In order to preclude the potential spurious operation of the

steam generator power operated relief valves from an external

hot short, the licensee proposes to replace the control

'.

cables with cabling from the control room to the valves which

includes a grounded shield. In addition, the licensee

proposes to provide a second control power disconnect inde-

'

pendent from the control room disconnect in order to prevent

spurious steam generator power operated relief valve opera-

tion in the event of a control room fire. This modification

is scheduled to be completed by the end of the third refuel-

ing outage (second quarter of 1987).

(c) Excess Letdown Isolation Valve Cabling

Control cabling associated with the excess letdown isolation

,

valves (XVT-8153-CS and XVT-8154-CS) are routed through the

following fire areas:

-

Control Building Fire Areas CB-1, CB-6, CB-12, CB-15 and

CB-17

-

Intermediate Building Fire Area 18-25

-

Reactor Building Fire Area RB-1

Therefore, a fire occurring in any of the above listed fire

areas could cause spurious operation of both excess letdown

isolation valves. Inadvertent opening of these valves could

cause a loss of reactor coolant system inventory. By letter

dated May 29, 1985, this condition was identified by the

licensee to the NRC.

- . - . .

'

.

10

In order to preclude the potential spurious operation of both

excess letdown isolation valves, the licensee proposes to

identify the control power disconnects in the control room

and install a second set of control power disconnects in the

cable spreading room. The licensee contends that this will

ensure closure of these valves and two independent hot shorts

would have to occur in order to open these valves. This

modification is scheduled to be completed by the end of the

third refueling outage (second quarter of 1987).

4

(d) Main Steam Isolation and Bypass Valve Cabling

Control cabling associated with the main steam isolation and

bypass valves (XVM-2801A, B, C and XVT-2869A, B, C-MS) are

routed through the following fire areas:

- Control Building Fire Areas

'

CB-1, CB-2, CB-4, CB-6, CB-10, CB 12, CB-15,

CB-17 and CB-18

- Intermediate Building Fire Areas

18-20, 18-22, and IB-25

Therefore, a fire occurring in any of the above listed fire

areas could cause spurious operation of the main steam

isolation and bypass valves. Inadvertent opening of these

valves due to external hot shorts could cause a loss of

secondary side inventory. By letter dated May 29, 1985, this

condition was identified by the licensee to the NRC.

,

In order to preclude the potential spurious operation of the

main steam isolation and bypass valves the licensee proposes

to identify the control power disconnects in the control room

, and install a second set of disconnects in a separate fire

area. The licensee contends that this will ensure closure of

these valves and two independent hot shorts would have to

occur in order to open these valves. This modification is

scheduled to be completed by the end of the third refueling

outage (second quarter of 1987).

(e) Pressurizer Power Operated Relief Valve Cabling

Control cabling associated with the pressurizer power operat-

ed relief valves (IPV-4448, IPV-445A, and IPV-445B) are

routed through the following fire areas:

-

Auxiliary Building Fire Area AB-1

-

Control Building Fire Areas

CB-10, CB-15 and CB-18

-

-Intermediate Building Fire Areas

18-14, 18-20, 18-21, 18-22 and IB-25

-

Reactor Building Fire Area RB-1

-- - - . --.

'

.

11

Therefore, a fire occurring in any of the fire areas iisted

above could cause spurious operation of a pressurizer power

operated relief valve. Inadvertent opening of a pressurizer

power operated relief valve due to an external hot shorts

could cause a loss of reactor coolant inventory. By letter

dated May 29, 1985, the licensee identified this condition to

the NRC.

Thus, in order to preclude the potential spurious operation

of a pressurizer power operated relief valve the licensee

proposes to replace the control cabling from the control room

to the valves with cable which includes a grounded shield.

In addition, the licensee proposes to install a second set of

control power disconnects independent from the control room

disconnects in order to prevent spurious pressurizer power

operated relief valve operation in the event of a control

room fire. This modification is scheduled to be completed by

the end of the third refueling outage (second quarter of

1987).

(f) Diesel Generator Control Transfer Switch

Cables (DGM 29B, DGM 21B, and DGM 228) associated with the

train "B" diesel generator control transfer switch are routed

through the cable spreading room, CB-15. Therefore, a fire

in the cable spreading room could result in external hat

shorts which could render the Train 8 diesel generator

inoperable in addition to damaging cabling associated with

the Train "A" diesel generator. Thus, the ability to achieve

and maintain hot standby conditions from the control room

evacuation panel (CREP) utilizing onsite power capabilities

may be jeopardized.

The licensee proposes to relocate cables DGM 218 and 22B

outside the fire area of concern and cable DGM 29B will be

isolated by modifying the circuit and utilizing additional

contacts associated with the existing control transfer

switch. This modification is scheduled to be completed by

the end of the second refueling outage (fourth quarter of

1985).

(g) Current Transformer Circuits

A fire in either the contrcl room or cable spreading room

could damage both trains of switchgear required for safe

, shutdown by damaging the current transformer circuits. The

fire could possibly cause the current transformer circuit to

open, resulting in a secondary fire at the current trans-

former in the respective switchgear. By letter dated May 29,

1985, the licensee identified this condition to the NRC.

- ..

.

12

Thus, in order to preclude the potential secondary fire in

the switchgear the licensee proposes to install surge sup-

pressors in the circuit parallel with the current trans-

former. This will prevent the over voltage surge which could

occur in the event of an open current transformer circuit.

This modification is scheduled to be completed by the end of

the second refueling outage (fourth quarter of 1985).

(h) Reactor Coolant Temperature Instrumentation Cabling

The licensee indicated that for fires which could potentially

.,

disable Train "B" power it is intended to shutdown from the

'

control room using RCS Loop "B" and steam generator "B". A

fire in the following fire areas could cause a loss of

Train "B" power:

-

Control Building Fire Areas

CB-1, CB-2, CB-12, and CB-20

-

Diesel Generator Building Fire Area DG-2

-

Intermediate Building Fire Areas IB-4, IB-6, IB-9 and

15-20

The loss of Train "B" power presently results in a loss of

RCS instrumentation (ITE-420-RC and ITE-420A-RC) for loop "B"

Tcold. By letter dated May 29, 1985, the licensee identified

this condition to the NRC.

Thus, in order to preclude the loss of Tcold instrumentation

on RCS Loop "B" the licensee proposes to provide Train "A"

power in lieu of Train "B" power to this instrumentation.

This modification is scheduled to be completed by the end of

the third refueling outage (second quarter in 1987).

(i) Emergency Feedwater System Cabling

In the Intermediate Building, on elevation 412'-0", Fire Area

1B-25.1, over the motor driven emergency feedwater pumps on

the mezzanine level, power cables for the "A" and "B" train

motor driven emergency feedwater pumps interact with control

cabling associated with turbine driven emergency feedwater

pump discharge valves (IFV-3556-EF and IFV-3546-EF) to steam

generators B and C.

Since, these cables are not provided with 20 feet of spacial

separation without intervening combustibles, a postulated

fire in this area could potentially cause fire damage to both

redundant trains of emergency feedwater. Thus, if an expo-

sure fire were to occur in this area, there is a potential

that both trains of motor driven emergency feedwater pumps

and discharge from the turbine driven emergency feedwater

pump could be rendered inoperable. The_ licensee's proposed

'

.

13

..

shutdown scheme for a fire in this area is to fail the valves

open by pulling the control fuses in the main control board,

regaining local manual control of the turbine speed control

valve and controlling the flow to the steam generators from

inside the turbine driven pump room.

The licensee proposes to enclose Train "A" Cable Tray 3088 in

a 1-hour Fire Barrier throughout fire area IB-725. This

modification is scheduled to be completed by the end of the

first quarter of 1986.

(j) Source Range Nuclear Instrumentation Cabling

A fire in the north cable chase of the control building on

elevation 436'-0" could cause all three of the available

source range nuclear instruments to be damaged. On May 29,

1985, by letter, the licensee identified this condition to

the NRC.

In order to preclude the loss of all three source range

instruments due to a fire in fire area CB-1 the licensee

proposes to either enclose one train of source range cabling

i in an 1-hour fire barrier or install a power source selector

switch for one train of source range instrumentation. This

modification is scheduled to be completed by the end of the

first quarter in 1986.

(k) Power Cable Tray Separation

A fire in the southwest corner of elevation 412'-0" of the

intermediate building, fire area 18-25, near column line

7.5/G.4, redundant cabling required for systems necessary to

achieve and maintain hot standby conditions could be damaged.

2 Tray 3088 contains Train "A" DC control power to all ess 2n-

l tial safe shutdown systems interacts with Tray 4149 which

contains Train "B" control power for the chilled water system

and the component cooling water system. In addition, conduit

VUC-2B which contains Train "B" control power cabling for the

chilled water system and trays 1025, 2058 and 3128 which

contain Train "B" power to the chilled water system and

component cooling water system also interact with cable tray

3088. Since, the chilled water system provides bearing

cooling capabilities to the charging pumps, a fire in this

area affecting the chilled water system could possibly render

both charging pumps inoperable. By letter dated May 29,

1985, the licensee identified this condition to the NRC.

The inspector indicated that operator access into the turbine

driven pump room in order to implement local manual operator

actions may be difficult since, the access door to this area

is adjacent to the plant area experiencing the fire.

--_ .

- . _. .-. .- . . . - -._- . . . . . . - . . - . . _

'

- .

_

14

Based on our review of the associated circuit issue, it was

established that the licensee did not receive Generic

l Letter 81-12, associated circuit guidance during the licensing

! phase. Thus, it appears that the original associated circuit

analysis was inadequate with regard to meeting the requirements.of

! 10 CFR 50 Appendix R, Sections III.G and III.L. Therefore, the

j safe shutdown capability concerns identified in 5.a.(1)(a) through

,

5.a(1)(i) could have prevented the operation or caused the mal-

operation of -safe shutdown functions due to fire induced hot

,'

shorts, open circuits, or shorts to ground. This item is identi-

'

fied as Unresolved Item (395/85-26-02), Review Resolution of Fire

. Induced Spurious Signal and Safe Shutdown System Modifications By

NRR.

. In addition, at the time of the inspection it appears that if a -

? fire were to occur of the' plant area identified in 5.a(1)(k),

l redundant hot standby systems could be rendered inoperable; thus,

the plant's ability to achieve and maintain hot standby could not

be assured. This is identified as Violation Item (395/85-26-03),

l

Failure To Meet the' Requirements of Appendix R,Section III.G.

' With Regard to Maintaining One' Train of Hot Standby Systems Free

From Fire Damage.

k In order to achieve and maint'ain safe shutdown. conditions, process

i monitoring functions necessary to provido direct-readings of the

process variables are required. It appears that if a fire were to

occur in the area identified-in 5.a(1)(j) redundant direct reading

nuclear instrumentation functions could be rendered inoperable;

thus, certain process variable could not be monitored. This is

l- identified as Violation Item (395/85-26-04), Failure to Meet the

i Requirements of Appendix R,Section III.G with Regard to Providing

'

Separation for Nuclear Instrumentation Required to Support Safe

Shutdown.

(2) Protection of Associated Circuits

'

The inspection was conducted to verify compliance with associated

circuit provisions of .10 CFR 50 Appendix R, Sections.III.G and

- III.L. The emphasis was on the following area of concern
-

.

'

Common Bus Concern

,

Spurious Signal Concern

Common Enclosure Concern

,

(a) -Coninon Bus Concern

i

The common bus concern is found in circuits, either safety or

,

nonsafety-related, where there is a conunon power source with

_ ,

shutdown equipment and the power source is not electrically

protected from the circuit of concern.- The licensee selected

the worst case load breaker for each unit substation. motor

i

'

a

I'

, _ , . , . _ , . - f_-.._ ..,._,...,m.- -, ,. - _ . _ - . _ . - _ . . . _ , _ , . . , _ . . .

.

15

control center (MCC) and distribution panel. Time-current

characteristic curves were then plotted to demonstrate the

coordination for each grouping of electrical equipment

associated with a common bus based on the worst case

condition.

The following time-current characteristic curves were

reviewed:

1) 7200V Board (Bvd) XSW1DA to 480V Bvd XSW10A1 to service

water pump XPP-45-A-SW motor

2) 7200V Bvd XSW1DA to 480V Bvd XSW10A2 to 480V Motor

control Center (MCC) XMCIDA2Y to Battery charger

l XBCIA-1B

] 3) MCC XMCIDA2Y to Battery Charger XBCIA-1B and 75 HP Motor

4) MCC XMCIDA2Z and Panel XPN47

5) 7200 V Bvd XSW1EA to 480V Bvd XSW1EA1, 480VMCC XMCIEAIX,

480V MCC XMC1EC1X to XPP44C (penetration pressurizing

.

equipment)

6) 125VDC Battery Bvds XBCIA, XBAIA to Distribution Panel

, DPN1HA to DPN1HA1 to Service Water System Control

Circuits XSW1DA and XSW1EA

, 7) 480V MCC XMC 1082X-ES to 125V Feeder Panel APN1FB or

'

APN1FA to the rod position indication panel which has

150A fuse protection

During discussions with the licensee representatives it was

noted that the coordination study for item (6) above was

border line in that the upper limits of the feeder breaker to

distribution panel DPN1HA1 from distribution panel DPN1HA and

the lower limit of the feeder breaker to DPN1HA from the

125VDC Battery Board XBCIA appear to overlap and approach a

comon current interrupt value. This item was identified to

the licensee who agreed to further investigate these breaker

limits.

Another possible coordination problem was identified later by

the inspector in the fuse / breaker coordination between the

feeder breaker to the rod position indication panel located

on Distribution Panel APN1FB-EM and the feeder breaker from

MCC XMCIDB2X-ES to APNIFB-EM should a fault occur between the

rod position indication panel feeder breaker and its protec-

tive fuse.

.- _ _ __ ._ _ . _ _ _ _ - - _ _ __. . _ _ ___ ._ _ __

'

.

i 16

i

i

These two items are identified as Inspector Followup Item

'

1 (395/85-26-05), Verify Breaker Coordination Between XBCIA and

DPN1HA and XMCIDB2X and APN1FB-EM. ,

,

(b) Spurious Signal Concern

! A review of the licensee's spurious signal analysis was

j conducted to determine if the following conditions had been

considered:

) -

Unwanted motor operations, control signals undesired or

.l

not responsive and false instrument readings such as

what occurred at the 1975 Browns Ferry Fire, that could

'

'

affect safe shutdown of the plant. These could be

caused _ by fire-initiated grounds, shorts or open

'

circuits,

i

! -

Spurious operation of safety-related or_ non-safety-

l related components that would adversely affect shutdown

capability (e.g., RHR/RCS Isolation Valves).

The licensee developed a composite equipment list for the

safe shutdown of the plant. The list was then evaluated for

equipment that if it were to operate spuriously the resultant

operation could jeopardize the capability to safely shutdown

+

the plant. From the evaluation, the licensee advises that-

j fuses will be pulled.on the control circuits for the equip-

ment identified as being detrimental to safe shutdown if

spuriously operated. - Additionally, the licensee has proposed

. to install disconnect switches in circuits to replace the

fuse removal operation and perform the control functions

manually. This action is taken in lieu of protection of a

train of shutdown equipment. The present plant condition

appears to conflict with the license requirements for compli-

~

ance with Appendix R IIIG. This is another example of

Unresolved Item (395/85-26-01).

!

The inspector also reviewed the possible consequences of a

.. fire in the area termination cabinets with a loss of offsite

i

power and the consequences of spurious operation of the

charging pump suction and discharge valves when the centrifu-

gal charging pumps are sequenced into operation from the

2

onsite power source. During discussions it was determined

that the suction and discharge valves for the auxiliary

feedwater and service water pumps are manually locked in the

proper position at all times and would not be affected. The

licensee advised that they have selected Train B as the

4 preferred shutdown train. They further advised that they

will clear the 7200 volt Boards XSWIDA and XSWIDB in that

order upon evacuation of the control room. These actions are

! an effort to protect /save equipment during a fire. Through

l

4

.- ._. -- -. - - __ - - - . . - . _ - - . - - - . - -

- _ - _ _ _ _ _

.

17

manual operation of breakers the needed equipment will be

started. However, the concern is the possible damage to

equipment during the time required for an operator to move to

the 7200V board rooms and deenergize the boards. The licen-

see advised that the additional charging pump "C" would be

available if it not in operation in place of the "A" pump or

the "B" pump. This substitute condition is classified as an

out of normal operating mode and is not addressed as an

Appendix R requirement. This item will be examined further

and is identified as an Inspector Followup Item

(395/85-26-06), Review the Affects of Spurious Valve Opera-

tion for Centrifugal Charging Pumps.

(c) The Comon Enclosure Concern

The common enclosure concern is found when redundant trains

are routed together with a non-safety circuit which crosses

from one raceway or enclosure to another, and the non-safety

circuit is not electrically protected or fire can destroy

both redundant trains due to inadequate fire protection

means.

The licensee performed a statistical analysis to produce a

report which indicated that there was 95% confidence that 95%

of the power circuits with cables greater than 10AWG have

overcurrent protection. A total of 1834 power circuits were

identified which had power feeds using wire size greater than

  1. 10. A random sample of 59 circuits was selected from all

the power circuits in the overall plant. The NRC inspector

,

'

noted that the sample included two spare circuits, sixteen

welding system feeds, eight air handling system power cir-

cuits and four control rods and position indication system

circuits. The remaining 31 circuits were spread over various

systems with no more than two circuits selected for any

system. Of these remaining circuits, several were not

associated with systems required for safe shutdown. The

actual circuits were identified by circuit number only; thus,

the actual function of the circuits could not be determined.

s But just by counting those analyzed circuits in systems that

l

would not nonnally be used for safe shutdown, there were

approximately 32 circuits or 54% of the total sample circuits

that are not related to safe shutdown systems. This was

discussed with the licensee in view of the fact that most

,

licensees have performed a 100% analysis of the safety-

l related and nonsafety circuits that are required for shutdown

in order to determine those circuits requiring protection.

The analysis results reviewed for the circuits chosen indi-

! cated that each circuit is fuse / breaker protected such that

! the power will be tripped off before auto ignition of the

cable would occur. During the inspection, the licensee

i

.- . .. .-_ - _ _ _ _ _ _ _

~

.

18

presented the analysis for two circuits to replace the two

spare circuits. Neither of these two circuits could be

identified as circuits required for safe shutdown. The

licensee was advised of the inspector's concern regarding the

number of circuits used for safe shutdown that were analyzed

versus the number of total circuits analyzed. The licensee

was advised that this concern will be identified as an

Unresolved Item (395/85-26-07), Review Resolution of the

Licensee's Associated Circuit Methodology with Regard to the

Sample Size and Circuits Analyzed for Over Current Protection

by NRR.

(3) Alternative Shutdown Capability

In a letter dated May 2,1985, to Dr. J. Nelson Grace, Regional

Administrator, Region II, the licensee submitted several sections

of a manual entitled, Preaudit Submittal Package for NRC

Appendix R Compliance Audit. This document Volume 3, Section 8.0

identifies new procedures to be used when fire has made the

control room uninhabitable and shutdown from outside the control

room must be implemented. The development of new operating

procedures is due to the licensee's Appendix R Reanalysis the

results of which were submitted to the NRC in a letter to

H. R. Denton, Director, NRR dated May 29, 1985.

(a) Procedure Development Review

Fire Emergency Procedure (FEP) 1.0, Revision 1, Control Room

Evacuation Due to Fire, is the new procedure to use for fire

in the control room complex or control building that has made

controls and indications unreliable. This procedure was

approved and issued for use May 30, 1985.

The basic concept and approach that this procedure takes is  ;

one in which manual operator actions are taken to isolate the

primary and secondary system volumes to prevent significant

losses in plant water inventory and pressure. In addition

'

electrical breakers are opened such that the incoming and

, s emergency power to the 7.2 kw switchgear loads are removed,

all electrical breakers on train A and B motor control

centers (MCC) are open to prevent spurious operation of

equipment and motor operated valves. Fluid systems such as

chemical and volume control system (CVCS), emergency feed-

water system (EFW), and service water system (SWS) have

manual valve alignments conducted in order to supply make up

water to RCS and steam generator and cooling water for the B

diesel generator. Borated makeup water from the RWST to the

RCS is via a CVCS charging pump to the reactor coolant pump i

seals. The B diesel generator is manually started and 1

operator action is taken to restore power to electrical buses

and essential equipment is energized. The licensee concept

I

-- a

.

19

indicates that pressure control for the RCS is the use of

pressurizer heaters and code safety valves. The steam

generator safety valves are used for steam generator pressure

control and decay heat removal. It should also be noted that

the licensee has selected train B equipment to provide the

Alternative Shutdown Capability.

The inspectors reviewed and walked through FEPl.0, Control

Room Evacuation Due to Fire, to verify that the procedure

incorporates the requirements delineated by Appendix R

Section III.L and the procedure can be implemented. The

following inadequacies and concerns were presented to the

licensee for resolution:

1) Procedure contains no check-off or sign-off blocks for

procedure action steps. This practice is presently

required for the plant's emergency operating procedures.

2) Procedure steps have not been provided to determine if

Natural Circulation has been established nor operator

actions to be taken if it is not established.

3) Appendix R Section III.L.2.d requires that the process

monitoring function shall be capable of providing direct

readings of the process variables that are being used.

Make up water to the reactor coolant system will be from

the refueling water storage tank (RWST). No direct

reading of tank water level is provided outside the

control room at the control room evacuation panels

(CREP) or locally at the tank to monitor changes in RWST

level.

4) Procedure step 9 Caution h allows taking the pressurizer

to solid water conditions then use the pressurizer code

safeties for pressure control. The procedure presently

requires the charging pump to be run centinuously

through the RCP seal. The licensee indicated that the

pulsation from starting and stopping the charging pump

may damage the RCP seals. The inspectors concerns with

this operation is that no analysis was provided to

ensure that taking the pressurizer solid through the

code safeties will not cause damage to the valves if

water comes in contact with the safety valve seating

surfaces. Warped valve seating surfaces could cause

pressure control and inventory control problems within

the reactor coolant system. In addition, the licensee

provided no plant procedure outlining the operational

controls necessary to manage solid plant operation if

this method was to be used.

_ . . _ _ __

_ _ _ _ _ _ _ _ _

.

20 ,

5) Procedure step 9 note h states " Consider Emergency

Boration for Shutdown Margin See Attachment VII." The

inspector is concerned that this note does not provide

the operator with the parameters or reasons he would

need to evaluate, in order to make the detennination to

emergency borate.

6) Procedure, Attachment II Step 1.0. This step as

presently written does not provide the operator with

those indications (e.g., decrease reactor power level,

rod bottom lights, etc.) to verify that'the reactor has

tripped. This infonnation is necessary in order to

determine if the " Alternative Action" steps that are

provided need to be implemented. These steps would

direct the operator to trip the reactor at the rod drive

MG sets.

7) Procedure, Attachment III Step 1.0 provides operator

actions to stop multiple spurious operation of primary

and secondary system valves (e.g., steam generator power

operated relief . valves (PORV), pressurizer PORVs,

pressurizer spray valve, main steam isolation valves,

etc.) by pulling fuses inside the main control board

thus securing the loss of water inventory from the RCS

j and steam generators. The Alternative Action states "If

fuses are not accessible, maintenance personnel will be

required to implement Attachment X when they report to

control room evacuation panels". The operator time line

shows the maintenance personnel not arriving at the CREP

for 20 minutes once FEP 1.0 is initiated. They are also

assigned to start Attachment V when they arrive at CREP.

Attachment V duties consist of opening all breakers on

the 480VAC motor control center then restoring selected

equipment needed to achieve and maintain hot standby

conditions. Attachment X consists of lifting leads to

stop multiple spurious valve operation. The time of

maintenance personnel arrival at the CREP coupled with

performing Attachment X would lead to the performance

goals and conditions of Appendix R Section III.L being

jeopardized. In addition, no operator time lines have

been established for Attachment X.

8) Attachments I through V and also procedure steps 1

through 9 are % nsary to be accomplished in order to

'

achieve and ti<im in hot standby conditions. These

portions Of tw e ocedure describe equipment such as

flash lig & , uj#, fuse pullers, wire cutters, screw

drivers, etc. as being necessary in order to do the

steps in the procedure. This equipment needs to be

placed in emergency kits at appropriate locations for

r operator use. In addition, inventory check lists need

- .- . . -- ..- -

-

. .

'

21

.

to be established under the routine surveillance program

i to ensure availability of this equipment.

9) Correct the following typographical errors:

- Procedure step 10.b change Attachment VII to VI

- Attachment V step 8b change 06EH to 06El

10) Procedure, Attachment II, steps 6 and 7 rearrange XSW1DB

bus stripping sequence to deenergize Train B switchgear

first as this train has been identified by the licensee

'

as the alternative shutdown capability.

11) Add headsets to the emergency kits as noise level could

prevent connunication using hand held radios in areas of

diesel generator operation.

12) Procedure, Attachment VI, page 3 add a note to provide

the operator with a breaker charging spring tool so

7.2kw breakers can be manually operated. This tool

should be part of the emergency kit being established

,

for this procedure.

13) Procedure Step 9.c.2 list valve XVT-8102B RCP B seal

supply isolation valve as being in 412W penetration room

(the valve is located in 412E penetration room).

<

'

14) Procedure Step 9d requires opening valve XVT-8102C, RCP

C seal supply isolation valve and the valve is located

in 412E penetration room. Entry to this room is through

door PA103 which was locked. The operator had keys to

unlock other doors, but not this one. The valves listed

in item (13) and (14) is the flowpath to supply sealing

water for RCP B and C and make up water to the RCS.

The above procedure inadequacies and concerns will remain unre-

'

solved until the licensee has completed his reanalysis and submit-

ted his new Appendix R program to the NRC for review.and final

approval. This area is identified as Unresolved Item

(395/85-26-08), Correct Inadequacies Identified in Procedure FEP

1.0 Based on Review and approval of the licensee's Appendix R

Reanalysis by NRR.

(b) Operator Action Time Line to Achieve and Maintain Hot Standby

As previously discussed, the licensee's new program will be one of

a series of manual operations to regain control of the plant

systems on the on set of a control ~ room complex fire and subse-

l quently achieve and maintain the plant in hot standby condition.

The inspector requested the licensee's analyses and assumptions on

which the operator time lines are based. The licensee indicated

__ _ __ _ _-

.

22

!

that this analysis was not complete and no infomation was given

to the inspectors. The inspectors presented the following areas

of concern, but is not to be misinterpreted as a complete listing j

of areas that the licensee should be considering when conducting i

his analysis. 1

- Provide limiting times required to isolate and secure the l

primary volume to ensure that loss of reactor coolant system

'

water inventory and pressure doesn't exceed the performance

goals and conditions of Appendix R Section III.L.

- Provide limiting time required to isolate and secure the

secondary volume to ensure that a loss of steam generator

water inventory doesn't impair the decay heat removal capa-

bility and emergency feedwater system (EFS) is put into

service to prevent this from occurring and the perfomance

goals and conditions of Appendix R,Section III.L are met.

- Detemine the time that reactor coolant pumps (RCP) seals can

be without chemical volume control system (CVCS) sealing

water to ensure that damage to the RCP seals doesn't occur

which would result in loss of makeup water to the RCS. The

licensee source of makeup water to RCS is via the reactor

coolant pump seals which is a nominal 15gpm. Presently no

operator time line is provided as to when the CVCS charging

pump must be put into service.

The above matter will remain unresolved until the licensee has

completed his reanalysis and submitted his new Appendix R program

to the NRC for review and final approval.

This item is identified as Unresolved Item (395/85-26-09), Provide

Limiting Times / Assumptions to Arrive at Operater Action Time Lines

to NRR for Review.

(c) Additional Ple a Operating Procedure

The inspectors were provided a draft copy of FEP 1.1 Plant Shut- l

down From Hot Standby to Cold Shutdown Due to Fire In Control s

Building. This procedure is still under development and is not

complete.

The licensee has identified several fire areas outside the control

room complex where a fire could potentially effect both trains of

l systems necessary to achieve and maintain hot standby conditions.

The licensee provided a tentative completion schedule of the third

quarter 1986 for issuing these procedures which describe operator

action.

_ _. _

. _

- .

-

.

23

The above matter will remain unresolved until the licensee has

completed his reanalysis and submitted his new Appendix R program

to the NRC for review and final approval.

This item is identified as Unresolved Item (395/85-26-10) Iden-

tify/ Issue Procedures to Accomplish Appendix R Section III.L

Requirements and Performance Goals Which are Based on the

Appendix R Reanalysis Approved t,y NRR. J

l

(d) Training

l

The licensee has initiated training on procedure FEP 1.0 which

consists of a lecture series for senior reactor operators (SRO),

reactor operators (RO), and Shift Technical Advisors (STA). This

training is essentially completed for all shift operating person-

nel. The licensee is presently reviewing method of training that

will be used and how this training will be factored into the

required licensed operator requalification program. The inspector

discussed the additional FEPs that will be issued and the licensee

plans to include all FEPs in the requalification program. The

training of operators as well as maintenance personnel that are

required to support the FEPs will be reviewed at a subsequent

inspe: tion. This is identified as Inspector Followup Item

(395/85-26-11), Provide Training for All FEP Procedures to Support

Appendix R.

(e) Damage Control Measures

Appendix R Sections III.G.1.b and III.L.5 require fire protection

features to be provided for structures, systems and components

important to safe shutdown and to be capable uf limiting fire

damage so that systems necessary to achieve and maintain cold i

shutdown are free of fire damage or can be repaired such that the l

equipment can be made operable and cold shutdown achieved within

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. Materials for such repairs are required to be readily

available on site and procedures are to be in effect to implement

such repairs.

The licensee has identified the power supply cables for the RHR pumps -

as items which could be damaged by a fire and which must be repaired to

permit cold plant shutdown. Procedure EMP-100.002, Emergency Installa-

tion of Cable For "B" RHR Motor, has been prepared to provide a guide

for installation of spare feeder cable following a fire which has

caused a loss of both RHR pumps. This procedure also identifies the

material which is to be maintained on site to accomplish these repairs.

The inspector (s) conducted an inspection to verify that the required

materials were available. Procedure EMP-100.002 Section 7.1.1 requires

a 500' reel of 3C-350 MCM cable,12 mechanical wire lugs, 3 boxes of

"biseals," 2 boxes of scotch 33+ tape, and a roll of rope. This

material is stored in warehouse "B". The cable is stored on a reel and

._

_.

.

24

4

the other items are stored in a wooden box and marked with a hold tag. l

This material appeared to be properly stored and maintained. I

A plant tour was made by the inspector (s) which verified that the cable

routes specified by Procedure EMP-100.002, Section 7.2 were feasible.

! 6. Compliance to 10 CFR 50 Appendix R Section III.0 Oil Collection System for

Reactor Coolant Pumps

The reactor coolant pumps are required to be equipped. with an oil collection

system if the containment is not inerted during nonnal plant operations.

The oil collection system is to be so designed, engineered and installed

such that failure will not lead to fire during normal or design basis

accident conditions and there is reasonable assurance that the system will

withstand the " Safe Shutdown Earthquake." The systen is to be adequately

i

sized and capable of collecting lube oil from all potential leakage sites in

the reactor coolant pump lube oil system. Leakage is to be collected and

'

drained to a closed container sized to hold the entire lube oil system

inventory. A flame arrester is required in the container vent if the flash

point characteristics of the oil presents the hazard of fire flash back.

The inspectors reviewed the design of the oil collection system for the

reactor coolant pumps. An inspection of the system was not made since the

plant was in operation and access to the containment was not possible.

However, Gilbert's Drawing B-305-601, Sheets 1-3 and Westinghouse Drawings

a 9550034, 1540E28 - E30, 1540E81 - E83, 1540E88 and 1188F97 were reviewed.

These drawings indicate that the oil collection system provided for each

pump motor contains sufficient splash guards, catch basins and enclosures at

potential oil leakage locations on the reactor coolant pump motors to

collect and drain off potential oil leaks to a collection tank. Each motor

is provided with an independent collection system arranged with a drain

piping system which terminates in a 275 gallon tank. Each tank is sized to

receive the total lube o*,1 capacity of 240 gallons for the pump to which it

is connected to. The tank vents are provided with flame arresters. The oil

spillage enclosures on each pump motor, drain piping and collection tank

have been evaluated and certified by the design organization, Gilbert /

Comonwealth, in letters dated April 12, 1982 and May 20, 1985, to remain

functional following a safe shutdown earthquake. The licensee's QC office

has conducted a detailed inspection of the collection system for reactor

coolant pump "A" and verified that the installed system is in conformance

with the construction drawings, except for several minor discrepancies which

have been reviewed by the licensee and the designer and found to be accept-

able. The oil collection systems for pumps "B" and "C" are to be inspected

by the licensee to verify that these are also in conformance with the design

requirements. These inspections are to be completed prior to startup from

the next refueling outage.

Within the areas examined, no violations or deviations were identified.

_ _. _ _ -

_ - _ _ _ _ .

._ .

'

. l

l

25

,

l

7. Compliance to 10 CFR 50 Appendix R Section III.J. Emergency Lighting l

l

Emergency lighting units equipped with at least an 8-hour battery power l

> supply are required to be provided in all areas required for operation of l

safe shutdown equipment and in access and egress routes thereto.

The inspectors reviewed the licensee's evaluation of the plant's emergency

lighting in Appendix R Audit Support Package Volume 22 Section 8-3. Approx-

imately thirty 8-hour emergency lighting units are presently provided.

However, the licensee's evaluation identified.the need for approximately 40

additional lighting units and the relocation of three existing lighting

units. Approximately 20 units are required to provide illumination for

3

equipment needed for manual shutdown operations as a result of the

'

Appendix R reevaluation, and approximately 20 units are required for egress

and access to this equipment. Several other plant areas presently are not

provided with emergency lighting and will either require lighting or devia-

tion requests to permit the use of portable lights for reading gauges,

-

verification of valve alignment, or to supplement the existing access

lighting.

During the plant tour the inspectors verified that emergency lighting was

not provided for the following plant areas as required by Appendix R: 388'

of auxiliary building at charging pumps, 412' of intermediate building, east

and west penetration rooms on 412' and 436' elevations, 424' of auxiliary

building, 436' auxiliary building filter galley, 485' of auxiliary building,

427' of diesel generator building, turbine building areas, portions of

service water pump building, and outside yard areas. This discrepancy is

identified as Unresolved Item (395/85-26-12), Inadequate Number of 8-Hour

Battery Powered Emergency Lighting Units Provided for Areas Needed for

Operation of Safe Shutdown Equipment, pending resolution of the licensee's

Appendix R reanalysis by NRR.

8. Fire Protection and Prevention Program

,

a. Structural Fire Barriers

A general walkthrough inspection was conducted of the walls, floors,

, ceiling and associated penetrations of the following plant areas to

verify that 3-hour fire resistance construction is provided between

adjacent fire areas as required:

Fire Area Description

IB-2 Train A Battery Room

,

IB-3 Train A Battery Charger

IB-4 Train B Battery Charges

IB-6 Train B Battery Room

IB-7 Water Chiller Pump Room

!

'

. . _ . _ _ _ _ _ _ _ . . _ _ _ _ _ . . _ _ _ _ . . _

-

.

26

IB-8 HVAC Equipment C Water Chiller

TB-1 Turbine Driven Feed Water Pump Room

IB-12 Train B Speed Switchgear Rocm

IB-13 Train C Speed Switchgear Room

1B-14 CREP Room

IB-16 ESF Switchgear Room

Room Cooling Units - Train A

IB-17 ESF Switchgear Room Cooling Units - Train B

IB-20 Train A Switchgear Room

IB-22.2 Train B S:witchgear Room

18-23.3 Train A Speed Switchgear Room

DG-1 Diesel Generator A

DG-2 Diesel Generator B

The walls, floors, ceiling and penetrations of the above fire areas

appear to meet the required fire resistance rating, except for fire

area IB-20. This room cannunicated with fire area IB-25.6 on the below

elevation below through an open floor penetration, approximately

6-inches by 30 feet in size, along the north wall of the switchgear

room. The lack of protection for this floor penetration is a failure

to meet Technical Specification Section 3.7.10 and is identified as

Violation Item (395/85-26-13), Inadequate Fire Barrier Between Fire

Areas IB-20 and 1B-25.6.

b. Raceway Fire Barriers

An inspection was made of the following raceways to verify that each

raceway was provided with the 3-inch "Kaowool" wrap to provide a

nominal 1-hour fire resistant rating:

Fire Zones Raceway No. Function

AB-19 1012 "B" Power Cable for B and C

CVCS

AB-1.4 & 1.9 4065 "B" Control Cable for B and C

CVCS

CB-12 4284 All A Train Power

IB-23.2 XX-3115B Component Cooling Pump B Power

IB-11 XX-3116A Component Cooling Pump A Power

AB-1.9 CSM1A Charging / Safety Injection

Pump A Power

AB-1.4 CSM11B Chargir.g/ Safety Injection

Pump B Power

CB-10 ESM 171B Train B 480V Power

i

-

-

.

27

IB-25.6 ESM 171B Train B 480V Power

18-25.1 SWL 11A Service Water Booster Pump

Power

AB-1.9 VLC4B Charging / Safety Injection

Pump B Cooling Power

IB-23.2 VUL 34B Chilled Water Pump B Power

IB-16 and IB-17 VLC'44B Cooling Fan Power for B

Train Switchgear Room

The barriers were found to be in place and appeared to be properly

, installed, except the barrier for raceway no. VUL34B in Fire Zone

18-23.2 was not complete, in that portions of the conduit raceway was

exposed and thus not functional. This is identified as Violation Item

(395/85-26-14), Nonfunctional Fire Barrier for Raceway VUL34B in Fire

Zone 18-23.2. Also, the structural supports for the raceways enclosed

within the fire barriers have not been provided with protec', ion to

provide a fire resistance rating equivalent to the fire resistance

rating of the barriers. The licensee is preparing an analysis which is

to provide justification for the lack of this protection. A prelimi-

nary review of the licensee's incomplete analysis indicates that

sufficient data is to be provided to justify the lack of protection for

these structural supports. This item is identified as Inspector

Followup Item (395/85-26-15), Review Licensee's Analysis for Unpro-

tected Cable Tray Supports, and will be reviewed during a subsequent

NRC inspection following completion of the licensee's analysis.

The inspectors performed an evaluation to determine the adequacy of the

horizontal "M" board fire barrier provided over the "A" train service

water booster pump on elevation 412'-0" of the intermediate building to

provide protection equivalent to that of the one-hour barrier require-

ment of Appendix R Section III.G. By letter dated June 1,1981, the

licensee requested an exemption for the following:

(1) Component cooling water pump area, separation between pumps B and

C does not meet Appendix R. s

(2) HVAC equipment water chiller pump area, separation between pumps

does not meet Appendix R.

(3) Partial automatic fire suppression provided in the auxiliary and

intermediate buildings.

-(4) Partial fire detection provided in the auxiliary and intermediate

buildings.

'

.

28

The licensee's June 1,1981 letter identified the rationale for their

exemption request and identified the "M" board barrier as a fire

protection feature which supports the above exemption requests.

Howevar, the licensee's June 1, 1981 letter did not specifically ask

for exemption to the technical requirements of Appendix R with regard

to the service water booster pump area. Therefore, safety evaluation

report supplement no. 4 dated August 1982, granted the licensee's

request to deviate from the Appendix R Section III.G requirement for

only those areas identified above.

'

The horizontal "M" board fire barrier provided over the "A" Train

service water booster pump is supported by unprotected rod hangers and

a steel uni-strut frame assembly. This non-rated fire barrier design

was provided to separate the "A" Train pump from redundant "B" train

circuits routed in overhead raceway near the ceiling of fire zone

18-25.1.

The in-situ fire load for fire zone 1B-25.1 is 43,000 BTV/FT2 with a

total BTU content of 471,145,000 BTVs. Area sprinkler protection and

fire detection capabilities are provided above and below the barrier

assembly. In addition, fusible type water spray nozzles are provided

for the cable tray stacks in the overhead. However, the area sprinkler

protection installed in the ceiling overhead is obstructed by piping,

electrical. raceway and HVAC ducting. The sprinkler design does not

meet with the design guidance of NFPA-13, in that the system does not

compensate for significant obstructions and overlapping obstructions

exceeding 48 inches. In the event of an exposure fire in this area,

the sprinkler response to the fire condition could be delayed due to

the sprinkler obstructions. This, in conjunction with the nonfire

rated structural steel supporting the "M" board barrier, could jeopar-

dize the fire barrier design by causing structural deformation to the

barrier support system. The failure of the barrier support system

could cause both redundant trains of shutdown systems to be damaged by

fire. The licensee contends that this barrier design was found accept-

able as documented by their Jure 1,1981 letter. Therefore, this item I

is identified as Unresolved Item (395/85-26-16), Verification That the I

"M" Board Fire Barrier was Reviewed and a Dcviation was Granted for

this Plant Condition by NRR.

,

c. Fire Watch

I

During the licensee's Appendix R reanalysis two areas were identified

in which the need for a roving fire watch were required. SCE&G's

letter of May 29,1985, from 0. W. Dixon, Jr., SCE&G to H. R. Denton,

NRC/NRR stated that a roving fire watch was to be provided for Fire

Areas IB-25/ Room 1202, (intermediate building 412' elevation) and CB-12

(control building cable chase, room 3603).

The inspector (s) reviewed the licensee's fire watch program. Nuclear

Education and Training Group Manual, Attachment X indicates the train-

ing required for fire watch personnel. Training records for four of

_ .- - _ .

_ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _

~

.

29

the fire watch personnel were reviewed. These personnel had received

the required training within the past twelve months.

The fire watch log data for May 29-31 and June 1-2, 1985 was reviewed.

It was noted that the log did not specify that room IB 1202 was covered

by the roving fire watch as stipulated by the above May 29, 1985

letter. This item is identified as Deviation Item (395/85-26-17),

Failure to Conduct Fire Watch Patrol for Fire Area 18-25. Fire watch

patrol was provided for the other areas indicated by the above May 29,

1985 letter.

d. Fire Brigade Drill

During this inspection, the inspectors witnessed an unannounced fire

brigade drill. The fire scenario was a fire in the cable spreading

room, fire area CB-15 on control building elevation 448'-0", the

initial fire scenario condition inside the room upon the arrival of the

fire brigade leader was heavy fire involvement in the cable trays below

the termination cabinets with heavy smoke conditions inside the room.

In addition, the sprinkler protection inside the room had operated;

however, the system was not effectively controlling and or suppressing

the fire. Five fire brigade members, in full protective clothing and

self-contained breathing apparatus, responded to the fire and placed

two.11-inch hose lines in service on the fire in approximately 25

minutes. Based on the drill / fire scenario, it was the inspectors'

observation that additional fire brigade training emphasis was needed

in ventilation, hose deployment, breathing apparatus donning, and

salvage techniques.

..

l

l