Forwards Safety Evaluation Re Util Response to Generic Ltr 83-28,Items 3.1.1 & 3.1.2 Concerning post-maint Testing to Verify Operability & Guidance for Reactor Trip Sys Components.Util Satisfied Actions Requested by Item 3.1.2
ML20133H840
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 10/11/1985
From: Butcher E
Office of Nuclear Reactor Regulation
To: Withers B
PORTLAND GENERAL ELECTRIC CO.
Shared Package
ML20133H843 List:
References
GL-83-28, TAC-52971, NUDOCS 8510180141
Download: ML20133H840 (2)


Text

.

October 11, 1985 hl Docket No. 50-344 V

O/9 Mr. Bart D. Withers Vice President Nuclear Portland General Electric Company 121 S.W. Salmon Street Portland, Oregon 97204

Dear Mr. Withers:

SUBJECT:

SAFETY EVALUATION FOR GENERIC LETTER 83-28 ITEMS 3.1.1 AND 3.1.2 The staff has completed its review of your response to Generic Letter 83-28, Item 3.1.1, Post-Maintenance Testing to Verify Operability, and Item 3.1.2, Review of Test Recommendations and Guidance for the reactor trip system components. The staff's safety evaluation (SE) is enclosed.

The staff concludes that, based on the confirmation that post-maintenance l

testing is required for safety related equipment and that such testing ensures the equipment is capable of performing its safety function prior to l

return to service, PGE has satisfied the actions requested by Item 3.1.1.

In addition, the staff finds that PGE has reviewed Westinghouse guidance on post-maintenance operability testing and determined that the facility procedures include, or are being revised to include, the guidance required to demonstrate post-maintenance operability of the reactor trip system and therefore satisfies the actions requested by Item 3.1.2.

Sincerely,

/S/

Edward J. Butcher, Acting Chief Operating Reactors Branch No. 3 Division of Licensing

Enclosure:

Safety Evaluation cc w/ enclosure:

See next page Distribution: Docket File PKreutzer ACRS 10 NRC & L PDRs Llazo GZwetzig Branch Files EJordan OELD JPartlow HThompson BGrimes i

ORB #3:DL ORB!3:DL OR P((restzer Llazo;ef E

. er 47 )/85

/0 /10 /85 ja/4/85 f

8510180141 85 0 344 PDR ADOCK 0 PDR Y

?

l

Mr. Bart D. Withers Portland General Eletric Company Trojan Nuclear Plant cc:

Senior Resident Inspector U.S. Nuclear Regulatory Commission Trojan Nuclear Plant Post Office Box 0 Rainier, Oregon 97048 Robert M. Hunt, Chairman Board of County Commissioners Columbia County St. Helens, Oregon 97501 William T. Dixon Oregon Department of Energy Labor and Industries Building Room 111 Salem, Oregon 97310 Regional Administrator, Region V U.S. Nuclear Regulatory Commission Office of Executive Director for Operations 1450 Maria Lane, Suite 210 Walnut Creek, California 94596 T