Forwards LER 95-033-14.Design Change Package Will Be Completed Which Will Revise RBM Bypass Setpoint Calculation
ML20133A706
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 12/23/1996
From: Bezilla M
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20133A711 List:
References
LR-N96428, NUDOCS 9701020069
Download: ML20133A706 (2)


LER-1995-033, Forwards LER 95-033-14.Design Change Package Will Be Completed Which Will Revise RBM Bypass Setpoint Calculation
Event date:
Report date:
Reporting criterion: 10 CFR 50.73(a)(2)(1)
3541995033R14 - NRC Website

text

-. -.

a o

O PSEG Public Service Electric and Gas Company P.O. Box 236 Hancocks Bridge, New Jersey 08038-0236 Nuclear Business Unit DEC 231996 LR-N96428 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 HOPE CREEK GENERATING STATION DOCKET NO. 50-354 UNIT NO. 1 LICENSEE EVENT REPORT NO. 95-033-14

Dear Sir:

This Licensee Event Report supplement entitled " Technical Specification Surveillance Requirement Implementation Deficiencies" is being submitted pursuant to the requirements of 10CFR50.73 (a) (2) (1) (B).

This supplement documents the discovery of a Technical Specification surveillance implementation deficiency identified by the Technical Specification Surveillance Improvement Program (TSSIP).

As stated in LER 354/95-033-01, additional Technical Specification surveillance implementation deficiencies discovered by TSSIP with minimal safety significance will be documented in supplements to this LER until completion of the TSSIP project.

S

erely,

, s/

j

% tNb Ma Bezi la General Manager, Hope Creek Operations 300060 JWK/mrh SORC MtJ.96-117 [b

l C

Distribution LER File 9701020069 961223 gDR ADOCK0500gg4 The powerisin yourlurids.

95 2168 REV 694

l Document Control Desk LR-N96428 Attachment A The following item represents the commitment that the Public Service Electric and Gas Company is making to the Nuclear Regulatory Commission relative to LER 354/95-033-14:

A design change package will be completed which will revise the RBM bypass setpoint calculation (SC-SE-0017) to ensure that with the hysterisis and calibration tolerances considered, the maximum reset values will be less than or equal to 30% of Rated Thermal Power.

This design change will drive the required revisions to Channel Calibration procedures, HC.IC-CC.SE-0019(Q) and HC.IC-CC.SE-0020(Q) as well as other procedures that may be impacted.

The design change request has been issued and this design change will be completed prior to the next scheduled RBM Channel Calibration (March 1997) and prior to exceeding 30%

power during the next plant startup.

4