MONTHYEARGO2-24-110, Summary of Changes and Analysis for Revision 45 of Plant Procedures Manual 13.4.1, Emergency Notification2024-11-0404 November 2024 Summary of Changes and Analysis for Revision 45 of Plant Procedures Manual 13.4.1, Emergency Notification GO2-24-109, Summary of Changes and Analysis for Revision 42 of Plant Procedures Manual 13.8.1, Emergency Dose Projection System Operations2024-11-0404 November 2024 Summary of Changes and Analysis for Revision 42 of Plant Procedures Manual 13.8.1, Emergency Dose Projection System Operations ML24290A1142024-10-17017 October 2024 CGS FPTI 2024011 GO2-24-088, Supplement to Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan2024-09-24024 September 2024 Supplement to Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan GO2-24-051, Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements2024-09-23023 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML24247A1572024-09-12012 September 2024 Withholding Determination Letter for Presentation Materials for Energy Northwest Pre-application Meeting 8-9-2024 ML24255A1012024-09-12012 September 2024 Request for Withholding Information from Public Disclosure Energy Northwest Regulatory Engagement Plan, Revision 0 GO2-24-082, Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan2024-09-10010 September 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan IR 05000397/20240052024-08-22022 August 2024 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2024005) IR 07200035/20244012024-08-19019 August 2024 Security Baseline Inspection Report 07200035/2024401 IR 05000397/20244022024-08-13013 August 2024 Security Baseline Inspection Report 05000397/2024402 IR 05000397/20240022024-08-0909 August 2024 Integrated Inspection Report 05000397/2024002 GO2-24-060, Reply to a Notice of Violation, EA-21-170 and EA-23-0542024-07-30030 July 2024 Reply to a Notice of Violation, EA-21-170 and EA-23-054 GO2-24-070, Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program2024-07-29029 July 2024 Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program GO2-24-063, Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan2024-07-15015 July 2024 Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan IR 05000397/20240122024-07-10010 July 2024 – Safety Conscious Work Environment Issue of Concern Follow-up Inspection 05000397/2024012 ML24180A1482024-06-28028 June 2024 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000397/2024011) and Request for Information IR 05000397/20244202024-06-27027 June 2024 – Security Baseline Inspection Report 05000397 2024420 Cover Letter GO2-24-057, Notice of Readiness for Supplemental Inspection2024-06-19019 June 2024 Notice of Readiness for Supplemental Inspection ML24099A2232024-06-12012 June 2024 Issuance of Amendment No. 275 to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling GO2-24-056, Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing2024-06-11011 June 2024 Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing ML24128A2242024-05-31031 May 2024 Issuance of Amendment No. 274 to Revise Technical Specifications to Adopt TSTF-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-13013 May 2024 2023 Annual Radiological Environmental Operating Report GO2-24-050, Annual Environmental Operating Report2024-04-30030 April 2024 Annual Environmental Operating Report IR 05000397/20240012024-04-24024 April 2024 Integrated Inspection Report 05000397/2024001 GO2-24-042, 2023 Annual Radioactive Effluent Release Report2024-04-22022 April 2024 2023 Annual Radioactive Effluent Release Report ML24089A2282024-04-15015 April 2024 – Acceptance of Requested Licensing Action License Amendment Request to Revise Columbia Generating Station Emergency Plan GO2-24-044, Voluntary Response to Regulatory Issue Summary 2024-012024-04-11011 April 2024 Voluntary Response to Regulatory Issue Summary 2024-01 ML24074A4532024-04-11011 April 2024 Request for Withholding Information from Public Disclosure IR 05000397/20244012024-04-0202 April 2024 – Security Baseline Inspection Report 05000397/2024401 (Cover Letter Only) IR 05000397/20244032024-03-28028 March 2024 Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000397/2024403 GO2-24-034, Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan2024-03-20020 March 2024 Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan ML24058A0692024-03-14014 March 2024 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request for Emergency Plan ML24044A0492024-03-12012 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0064 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) GO2-24-041, Level of Financial Protection - Annual Reporting Requirement2024-03-12012 March 2024 Level of Financial Protection - Annual Reporting Requirement GO2-24-036, Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate2024-03-11011 March 2024 Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate GO2-24-039, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462024-03-11011 March 2024 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 ML24047A0422024-03-0707 March 2024 Issuance of Amendment No. 273 Renewed Facility Operating License and Technical Specification Clean Up IR 05000397/20230062024-02-28028 February 2024 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2023006) IR 05000397/20253012024-02-14014 February 2024 Notification of NRC Initial Operator Licensing Examination 05000397/2025301 GO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan GO2-24-003, Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing2024-01-29029 January 2024 Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing IR 05000397/20230042024-01-29029 January 2024 Integrated Inspection and Independent Spent Fuel Storage Installation Report 05000397/2023004 and 07200035/2023001 05000397/LER-2024-001, Failure to Track Operability of Requirements of Transversing In-Core Probe Valves2024-01-22022 January 2024 Failure to Track Operability of Requirements of Transversing In-Core Probe Valves GO2-24-014, Independent Spent Fuel Storage Installation, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2024-01-15015 January 2024 Independent Spent Fuel Storage Installation, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML24011A1522024-01-10010 January 2024 March 2024 Emergency Preparedness Exercise Inspection-Request for Information GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-136, Guarantee of Payment of Deferred Premium2023-12-20020 December 2023 Guarantee of Payment of Deferred Premium GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-135, Notice of Readiness for Supplemental Inspection2023-12-14014 December 2023 Notice of Readiness for Supplemental Inspection 2024-09-24
[Table view] Category:License-Fitness for Duty (FFD) Performance Report
MONTHYEARML24058A1982024-02-27027 February 2024 Annual Report Form for Drug and Alcohol Tests for 2023 ML24058A2282024-02-27027 February 2024 Single Positive Test Form Collected on 12/18/2023 ML24058A2272024-02-27027 February 2024 Single Positive Test Form Collected on 05/22/2023 ML24058A2062024-02-27027 February 2024 Single Positive Test Form Collected on 04/17/2023 ML24058A2092024-02-27027 February 2024 Single Positive Test Form Collected on 04/19/2023 ML24058A2022024-02-27027 February 2024 Single Positive Test Form Collected on 04/03/2023 ML24058A1992024-02-27027 February 2024 Annual Fatigue Report Form for 2023 ML24058A2032024-02-27027 February 2024 Single Positive Test Form Collected on 04/03/2023 ML24058A2212024-02-27027 February 2024 Single Positive Test Form Collected on 05/02/2023 ML24058A2042024-02-27027 February 2024 Single Positive Test Form Collected on 04/10/2023 ML24058A2142024-02-27027 February 2024 Single Positive Test Form Collected on 04/19/2023 ML24058A2072024-02-27027 February 2024 Single Positive Test Form Collected on 04/17/2023 ML24058A2122024-02-27027 February 2024 Single Positive Test Form Collected on 04/19/2023 ML24058A2082024-02-27027 February 2024 Single Positive Test Form Collected on 04/19/2023 ML24058A2112024-02-27027 February 2024 Single Positive Test Form Collected on 04/19/2023 ML24058A2052024-02-27027 February 2024 Single Positive Test Form Collected on 04/10/2023 ML24058A2002024-02-27027 February 2024 Single Positive Test Form Collected on 02/07/2023 ML24058A2222024-02-27027 February 2024 Single Positive Test Form Collected on 05/04/2023 ML24058A2102024-02-27027 February 2024 Single Positive Test Form Collected on 04/19/2023 ML24058A2232024-02-27027 February 2024 Single Positive Test Form Collected on 05/03/2023 ML24058A2132024-02-27027 February 2024 Single Positive Test Form Collected on 04/19/2023 ML24058A2202024-02-27027 February 2024 Single Positive Test Form Collected on 04/26/2023 ML24058A2162024-02-27027 February 2024 Single Positive Test Form Collected on 04/19/2023 ML24058A2182024-02-27027 February 2024 Single Positive Test Form Collected on 04/24/2023 ML24058A2242024-02-27027 February 2024 Single Positive Test Form Collected on 05/15/2023 ML24058A2252024-02-27027 February 2024 Single Positive Test Form Collected on 05/15/2023 ML24058A2152024-02-27027 February 2024 Single Positive Test Form Collected on 04/19/2023 ML24058A2262024-02-27027 February 2024 Single Positive Test Form Collected on 05/22/2023 ML24058A2172024-02-27027 February 2024 Single Positive Test Form Collected on 04/24/2023 ML24058A2192024-02-27027 February 2024 Single Positive Test Form Collected on 04/24/2023 ML24058A2292024-02-27027 February 2024 Single Positive Test Form Collected on 12/27/2023 ML23054A3662023-02-23023 February 2023 Single Positive Test Form Collected on 03/08/2022 ML23054A3762023-02-23023 February 2023 Annual Fatigue Report Form for 2022 ML23054A3682023-02-23023 February 2023 Single Positive Test Form Collected on 05/02/2022 ML23054A3752023-02-23023 February 2023 Annual Report Form for Drug and Alcohol Tests for 2022 ML23054A3722023-02-23023 February 2023 Single Positive Test Form Collected on 10/31/2022 ML23054A3652023-02-23023 February 2023 Single Positive Test Form Collected on 02/07/2022 ML23054A3672023-02-23023 February 2023 Single Positive Test Form Collected on 05/02/2022 ML23054A3692023-02-23023 February 2023 Single Positive Test Form Collected on 06/06/2022 ML23054A3742023-02-23023 February 2023 Single Positive Test Form Collected on 11/01/2022 ML23054A3702023-02-23023 February 2023 Single Positive Test Form Collected on 06/28/2022 ML23054A3712023-02-23023 February 2023 Single Positive Test Form Collected on 10/24/2022 ML22055B1952022-02-24024 February 2022 Single Positive Test Form Collected on 05/17/2021 ML22055B1832022-02-24024 February 2022 Single Positive Test Form Collected on 03/30/2021 ML22055B1972022-02-24024 February 2022 Annual Fatigue Report Form for 2021 ML22055B1932022-02-24024 February 2022 Single Positive Test Form Collected on 05/05/2021 ML22055B1922022-02-24024 February 2022 Single Positive Test Form Collected on 04/26/2021 ML22055B1962022-02-24024 February 2022 Annual Report Form for Drug and Alcohol Tests for 2021 ML22055B1902022-02-24024 February 2022 Single Positive Test Form Collected on 04/22/2021 ML22055B1912022-02-24024 February 2022 Single Positive Test Form Collected on 04/22/2021 2024-02-27
[Table view] |
Text
April 7, 2020 Mr. Brad Sawatzke Chief Executive Officer Energy Northwest MD 1023 P.O. Box 968 Richland, WA 99352-0968
SUBJECT:
COLUMBIA GENERATING STATION LICENSED OPERATOR POSITIVE FITNESS-FOR-DUTY TEST
Dear Mr. Sawatzke:
On April 1, 2020, in accordance with Title 10 of the Code of Federal Regulations (CFR) 26.719, your facility reported that an NRC-licensed operator tested positive following a random fitness-for-duty test administered on April 1, 2020 (Event Report 54630). Although we have obtained preliminary information, this letter is a formal request for information pertaining to this occurrence. Within 30 days of the date of this letter, please provide a response to the questions listed in the enclosure, In addition, please provide other records and information on this operator's fitness-for-duty that are relevant to this occurrence. If you are unable to meet this deadline, please notify us no later than 15 days from the date of this letter with the reasons for the delay and a proposed date of submittal.
We request that any personal, proprietary, or Safeguards Information in your response be contained in a separate enclosure and appropriately marked. The affidavit required by 10 CFR 2.390(b) must accompany your response, where applicable.
You should determine whether the operator meets the requirements of 10 CFR 55.33(a)(1).
You should ensure that (1) the operator meets the general health requirements of American National Standards Institute (ANSI) / American Nuclear Society (ANS)-Standard 3.4-1983; (2) the operator does not have a disqualifying condition under Section 5.3 of that standard; and (3) documentation describing the designated physician's conclusion that the operator meets the requirements of ANSI/ANS-3.4--1983 is available for review by the NRC. If a conditional license is requested per 10 CFR 55.25, that condition should be documented on NRC Form 396, "Certification of Medical Examination by Facility Licensee," and sent to the U.S. Nuclear Regulatory Commission, ATTN: Regional Administrator, Region IV, 1600 East Lamar Blvd.,
Arlington, TX 76011-4511.
If you determine that the operator no longer meets the medical qualifications described in 10 CFR 55.33(a)(1), then, in accordance with 10 CFR 55 25, you must notify the NRC, in writing, of the operator's permanent incapacitation. For example, you must notify the NRC if you determine, based on your employee assistance program in consultation with your designated physician, that the operator can no longer meet the medical criteria of ANSI/ANS-3.4-1983.
B. Sawatzke 2 The NRC will evaluate the information in your response to this letter to determine if further action is warranted pursuant to 10 CFR Part 50 or Part 55. The information supplied will be maintained in NRC Privacy Systems of Records-16 and will be subject to the Privacy Act.
Please provide a copy of this letter, as well as your response to this letter, to the operator. If you are unwilling to provide this information to the operator for any reason, the NRC will provide the information to the operator when it is available as part of the operators docket file.
If you have any questions concerning this matter, please contact Mr. Gregory Werner, Chief, Operations Branch, 817-200-1159. The requested information should be sent to Mr. Werners attention at NRC Region IV, 1600 East Lamar Blvd., Arlington, TX 76011-4511. Your cooperation is appreciated.
Sincerely,
/RA/
Gregory E. Werner, Chief Division of Reactor Safety Docket No. 05000397 Licensee No. NPF-21
Enclosure:
Fitness-for-Duty Request for Additional Information cc w/encl: Distribution via LISTSERV
ML20098F265 X SUNSI Review ADAMS: Non-Publicly Available X Non-Sensitive Keyword:
By: GWerner X Yes No X Publicly Available Sensitive NRC-002 OFFICE OB:OE OB:BC NAME NHernandez GWerner SIGNATURE NAH GEW DATE 04/02/2020 04/07/2020 Licensed Operator Fitness-for-Duty Request for Additional Information The Columbia Generating Station is requested to provide the following information concerning the fitness-for-duty occurrence (10 CFR Part 26.719) reported on April 1, 2020, regarding the involved licensed operator:
- 1. Name, Docket Number, and responsibilities of the operator.
- 2. A summary of the operator's entire fitness-for-duty testing history. Please include the dates and times the operator was tested, the reasons for the tests (i.e., random, for-cause, or follow-up), the results of the tests, including quantification (both initial and confirmatory), and the dates that any tests were confirmed positive.
- 3. Since this individual was working at home, please provide details associated with the individuals responsibilities (e.g., on standby to report as an on-shift licensed operator, work control personnel, or shift technical advisor)
- 5. Whether the operator fulfilled a position that was required to meet minimum licensed operating staffing requirements (fire brigade, emergency plan operations, etc.) while under the influence.
- 6. Whether the operator was involved in procedural errors related to this occurrence. If so, please provide the details of the procedural errors and the consequences of the errors.
- 7. The extent to which you reviewed the operator's past work history, both on the day of the occurrence and prior to April 1, 2020.
- 8. Your intentions with regard to the operator's resumption of duties under the 10 CFR Part 50 and Part 55 licenses, including your plans for follow-up testing.
Include an estimated timeline, if applicable, for any planned treatment, training, and requalification.