Comment Opposing Petition for Rulemaking PRM-30-59 Re Rev of Decommissioning Regulations to Provide for Means of self-guarantee of Decommissioning Funding Costs by Licensees Meeting Stringent Financial Assurance Requirements
ML20086F893
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 11/11/1991
From: Gates W
OMAHA PUBLIC POWER DISTRICT
To: Chilk S
NRC OFFICE OF THE SECRETARY (SECY)
References
FRN-56FR48445, FRN-58FR3515, FRN-58FR3516, RULE-PRM-30-59 56FR48445-00004, 56FR48445-4, AE16-1-009, AE16-1-8, AE16-1-9, LIC-91-307R, NUDOCS 9112040039
Download: ML20086F893 (1)


Text

- - - - - . - -.. -. - _ _ - - - .

CETITION RULE PRM 30'h (RFRH'Nh November 11, 1991 Omaha Public Power District LIC-91-307R 444 South 16th Street Mall 71 NOV 21 P3 :53 Omaha, Nebraska 68102-2247 402/636~2000 Mr. Samuel J. Chilk Sr retary of the Comission QiM%)$ sRANc4 i U. S. Nuclear Regulatory Comission ,

Washington, DC 20555  !

l Attention: Docketing and Service Branch

Reference:

Docket No. 50-285

Dear Mr. Chilk:

SUBJECT:

Coments on General Electric Company (GE) and Westinghouse Electric Corporation (Westinghouse) Petition for Rulemaking (Docket No. PRM-30-59)

Omaha Public Power strict (OPPD) has the following coments on the petition for rulemaking published in the Federal Register on September 25, 1991 (56 FR 48445). In this petition, GE and Westinghouse requested that the NRC amend the decomissioning regulations contained in 10 CFR Parts 30, 40, 50, 70, and '/2 to provide a means for self-guarantee of decomissioning funding costs by certain NRC licensees who meet stringent financial assurance and oversight requirements.

Electric utility reactor licensees under 10 CFR Part 50 are not included in this petition. It is OPPD's position that any decomissioning regulations should apply to all licensees equally and that compliance alternatives contingent on licensee financial status and size should also be available to utilities.

4 If you should have any questions, please contact me.

Sincerely, AL N/h W. G. Gates Division Manager Nuclear _ Operations WGG/sel c: LeBoeuf, Lamb, Leiby & MacRae R. D. Martin, NRC Regional Administrator, Region IV D. L. Wigginton, NRC Senior Project Manager R. P. Mullikin, NRC Senior Resident inspector Document Control Desk 9112040039 911111 PDR PRM 30-59 PDR assiza EmrwnergEgem

-.