o .

STONE & WEBSTER MICHIGAN, INC.

P.O. box 2325. BOSTON. M ASSACHUSETTS O2107 United States Nuclear Regulatory Commission December 28, 1983 Midland Site Resident Office Route 7, J.O. No. 14358 Midland, MI. 48640 Ref. MPF 66 Attention : Mr. R. Cook DOCKET No. 50-339/330 MIDLAND PLANT UNITS 1 & 2 INDEPFNCENT ASSESSMENT OF UNDERPINNING REPORT NO. 66 A copy of the Independent Assessment of Underpinning Weekly Report No. 66 for the period of December 18, 1983 through 7ecember 24, 1983 is enclosed with this letter. Included as attachments are the minutes of the daily meetings held during the week between members of the Assessment Team and Site Engineering, Construction and Quality Assurance per:onnel.

If you have any questions with respect to this report please contact me at (617) 589-2067.

u.h1A p as. uk .

A. Stanley Lucks Project Manager Enclosures ASL/pd l

l i

I 8402070155 840203 PDR ADOCK 05000329 G PDR JAN 3W L

J. O. No. 14358 Midicnd Pltnt Units.1 & 2 Independent Assessment of Underpinning Weekly Report No. 66 December 18, 1981 through December 24, 1983 ,

Personnel On Site Stone & Webster Michigan, Inc.

W. Kilker 12/18 - 12/20 J. Springer 12/18 - 12/20 L. Rouen 12/18 - 12/20 P. Majeski 12/19 - 12/23 B. Holsinger 12/20 - 12/23 D. Banvie 12/19 - 12/23 Meetings Attended Date Represented Put, m Stone & Webster Daily Assessment 12/19 - 12/22 Team Meeting Bechtel Consumers Power Stone G Webster Assessment Team 12/19 Meeting with MPQAD MPQAD Bechtel Weekly Interorganizational 12/19 Meeting Consumers Power MPQAD Mergentimo Stone & Webster Consumers Power FCR/FCN Review 12/21 Coordination Meeting MPQAD Bechtel Stone & Webster Consumers Power Agenda Review Meeting 12/22 for NRC Site Visit Bechtel Stone & Webster Underpinning and Remedial Soils Activities - Construction The Stop Work Order issued October 21, 1983 continued in effect throughout the week. Rejacking activities were performed, as required, by the project procedures.

y,-. - -- , . .

2 J. O. No. 14358 Midland Plant

-Units 1 G,2 Independent Assessment of Underpinning .

Assessment Team Observations The Assessment Team, in conjunction with the Stone & Webster Construction Implementation Overview Team, has begun its review of the Phase III activities performed for lifting of the Stop Work Order. The Initial Action in this It is anticipated that the review is an audit of Central Document Control.

Stop Work Orders will be lifted by work activity, with Soils work having the highest priority.

Work Activity Packages The following is a listing cf the Work Activity Packages overviewed by the Assessment Team that are in the open response stage or have been completed during the past week.

Title Status WAP No.

SWPS-Thru Anchor Open 71 Bolt Holes Nonconformance Identification Reports Description Date NIR No. (Opened) (Closed)

Concrete Admixture 12/1/83 20 Dispenser Calibration Open Items Items discussed during meetings are categorized as follows:

'OPEN ITEM - An item for which an action is required. The item will remain Tracking is required.

open until the required action has been taken.

CLOSED ITEM - An item, usually brought forward by the Assessment Team, that is discussed and adequately responded to. No tracking is required.

INFORMATION ITEM - An item, brought forward to provide general background information regarding work, such as work status or an upcoming design change.

No tracking-is required.

OPINION. ITEM - An opinion or suggestion, given by the Assessment Team, The expressing an alternate construction or quality assurance technique.

opinion or suggestion is given as a possible alternate that may facilitate an operation. No-response or implementation is required as a result of an .

Opinion Item.

~ --- - - - - _ . _ . . _ . _ _ _ _ _ _ _ _ _ _ _ , _ _

3 J. O. No. 14358 Midland Plcnt Units 1 & 2 Independent Assessment of Underpinning CLOSES ITEM -XX-XX- This notation identifies an action that closes a previously identified open item. Tracking of the open item stops.

The following is a listing of all Open Items from the Daily Meeting Notes with Bechtel, the Weekly Meeting with MPQAD or the text of Weekly Reports.

Carry-over items from past woeks which have been Closed this week are also listed.

Description Closure Item No.

Weld Tech Sheets Open WR 54, Pg. 3 Wall Ties open 57-17 Lack of Drawing Open WR 58, Pg. 2 Reference Tubular Steel Open 58-3 Lagging Inspection of Non- 66-14 WR 60,.Pg. 2 Structural Welds QAP Review Program Open 64-7 FCR/FCN Processing 66-6 64-9 Trend Analysis Open 64-10 U.S. Testing Open WR 64, Pg. 1 Corrective Action Settlement at SWPS 66-12 65-7 Crack Mapped Areas 66-7 65-11 Crack Definition 66-8 65-12 Review of Phase III Open 65-19 SWO Resolution Review of Phase III Open 66-3Q SWO Resolution Request for IR Open 66-5Q Distribution 66-7 Check of Crack Open Mapped Areas

$g Qb YS 4 Yp A S Project Manager Project Engineer

- + .

Not03 cf D:lly Me: ting Independ:ht Asse cment of Und;rpinning Midland Plant Units 1 & 2 Consumers Power Company Held at Midland Site Midland, Michigan December 19, 1983 .

Present for:

Consumers Power Bachtel MPQAD Stone & Webster G. Murray J. Fisher R. Sevo W. Kilker J. Gaydos J. McMaster J. Springer E. Cvikl PURPOSE This meeting is held each day to discuss items regarding the Independent Soils Assessment at the Midland Plant Units 1 & 2.

DISCUSSION Status Items Item 66 Rejacking of Piers & Grillages.

J. Fisher reported that pier Ell rejacking was completed on 12-16. Piers E/W12 required rejacking on 12-16 and continued on active jacks today. There is no indication that E/W 8 rejacking will be required in the near future.

(INFORMATION ITEM)

Item 66 FSO Document Control Station.

J. Fisher reported that the FSO document control station is prepared for (INFORMATION ITEM; an MPQAD and/or Assessment Team audit.

Item 66 Christmas Holiday Field Work.

J. Fisher stated the crafts will not work night shift on Christmas Eve or the day shift Christmas day. (INFORMATION ITEM)

Item 66 Bechtel Direct Hire Effort in 1984.

J. Fisher reported the Bechtel direct-hire effort in 1984 will be limited to supporting the underpinning contracts. (INFORMATION ITEM)

Item 66 SWPS Instrumentation Update.

E. Cvikl reported there has been no further movement on the west side of the SWPS that showed 20 mils movement on 12/11/83. The necessity of lifting-off the tendon load is now being evaluated. (1 tem 65-7 REMAINS OPEN) (INFORFATICN ITEM)

New Items No new items were discussed.

2 Notes of Daily Meeting i

Independent Assessment of Underpinning l Midland Plant Units 1 t. 2 Consumers Power Company Held at Midland Site Midland, Michigan December 19, 1983 Response Items Item 66 FCR/FCN Interim Approval Process.

W. Kilker stated that the Assessment Team has reviewed the recently revised project procedures on FCRs/FCNs. The Team believes the procedures, as revised, addressed the concerns raised in the W. Craig report of October, 1983.

(CLOSES ITEM 04-9)

ITEM 66 Check of Crack Mapped Areas.

E. Cvikl reported that as a result of discussions described in Item 65-11, modifications are being made to the . project specifications and procedures.

New definitions of magnitude of cracks requiring mapping have been established.

The baseline crack data will remain as documented. This revision was discussed with CTL, the program consultant. The WJE data reviewer vill now be required to look at each wall prior to signing-off on the data sheet. E. Cviki said the revision will be finalized by 12/21/83. (CLOSES ITEM 65-11) (OPEN ITEM)

Item 66 Definition of Cracks.

In response to the Assessment Team question raised in Item 65-12, E. Cvikl said there has been no attempt made to dif ferentiate between structural and non-structural cracks. CTL says virtually all of the cracks monitored are volumetric change related. No areas of tite building are assigned a higher priority. All designated areas are mapped completely as committed to in the procedural requirements. However, the RSE can use judgement in requiring a given area be evaluated.(CLOSES ITEM 65-12)

- - - - - _ _ - ~ _ _ _ . - _ . _ _ _ _

t .

Notes of Daily Meeting Independent Assessment of Underpinning Midland Plant Units 1 & 2 Consumers Power Company Held at Midland Site Midland, Michigan December 20, 1983 Present For:

Consumers Power Bechtel MPQAD Stone & Webster G. Murray J. Fisher R. Sevo P. Majeski J. Gaydos J. McMaster D. Benvie' J. Springer L. Rouen PURPOSE This meeting is held each day to discuss items regarding the Independent Soils Assessment at the Midland Plant Units 1 & 2.

DISCUSSION Status Items Item 66 Pier i:sjacking.

J. Fisher indicated that pier E12 was locked off 12/19/83 Pier W12 remains on active jacks. (INFORMATION ITEM)

New Items Item 66 Phase III Document Review.

The Assessment Team is awaiting completion of the MPQAD audit of Phase III of the FCR/FCN Review before performing their overview. The Team is also awaiting MPQAD's decision to audit the Soils work separate from the Main Plant in order to allow an earlier start date for the Soils work. (INFORMA-TION ITEM)

Response Item There were no response items discussed.

Notes of Daily Meeting Independer,t Assessment of Underpinning Midland Plant Units 1 & 2 Consumers Power Company Held at Midland Site Midland, Michigan December 21, 1983 Present For:

Consumers Power Bechtel MPQAD, Stone & Webster G. Murray J. Fisher R. Sevo P. Majeski J. Gaydos J. McMaster D. Benvie E. Cviki PURPOSE This meeting is held each day to discuss items regarding the Independent Soils Assessment at the Midland Plant Units 1 & 2.

DISCUSSION Status Item .

Item 66-11 - Pier Rejacking.

J. Fisher reported that W12 was locked off on 12/20. Rejacking commenced on KC-2 on 12/20 and on KC 13 on 12/21. (INFORMATION ITEM)

New Items There were no new items discussed.

Response Item Item 66 SWPS Instrumentation.

E. Cviki provided a plot of the most recent delta settlement information for the west side of the SWPS. The delta settlement now is approximately 25 mils (the alert level is 50 mils). A visual check of the tendons, an optical survey and a review of dewatering data revealed no indication of t problem. In addition, the delta settlement is currently decreasing with time. Based upon this information, a lift off test on the tendons is not considered necessary. The erratic movement noted on 12/11 was probably an instrument malfunction. Engineering will continue to closely monitor the movement. This response satisfactorily addresses the Team's request for additonal information concerning this matter. (CLOSES ITEM 65-7)

l l

Not03 of Daily Menting Independent Assessment of Underpinning Midland Plant Units 1 & 2 Consumers Power Company Held at Midland Site Midland, Michigan December 22, 1983 Present for Bechtel MPQAD Stone & Webster Consumers Power R. Sevo P. Majeski G. Murray J. Fisher J. Gaydos J. McMaster D. Benvie B. Holsinger E. Cviki PURPOSE This meeting is held each day to discuss items regarding the Independent Soils Assessment at the Midland Plant Units 1 & 2.

DISCUSSION Status Item Item 66 Pier Rejacking.

J. Fisher reported that Kc-2 and Kc-Il are on active jacks.

New Items Item 66 Phase III Review.

P. Majeski indicated that the Assessment Team's audit of Phase III ofItthe is FCR/FCN Review will begin today with a review of Document Control.

expected that the Team's audit of the Soils Document Stations will begin next week after completion of the MPQAD audit. (INFORMATION ITEM)

Response IEems Item 66 Inspection of Non-Structural Welds.

P. Majeski indicated that the changes made to the welding PQCI, requiring inspection of the base metal at non-structural welds, address the Team's concern. (CLOSES ITEM WR60, PG. 2)

Not00 of D;ily Mesting Independent Assessment of Underpinning Midland Plant Units 1 & 2 Consumers Power Company Held at Midland Site Midland, Michigan December 23, 1983 No meeting was held this day.

Not03 cf MPQAD Me: ting Independ:nt As00ccment of Undsrpinning Midland Plant Units 1 & 2 Held at Midland Site Midland, Michigan '

December 19, 1983 Present fort Stone & Webster MPQAD D. Benvie J. Meisenheimer P. Majeski R. Oliver L. Rouen M. DeWitt J. Springer D. Horn J. McMaster PURPOSE This meeting is held to obtain and discuss information relative to QA activities for soils underpinning work at the Midland Units 1 & 2.

DISCUSSION Status Items Item 66 NIR's 16, 18, 19.

L. Rouen stated that NIR's 16, 18 & 19 have been closed. (INFORMATION ITEM)

New Items Item 66 Assessment Team Overview.

L. Rouen stated the Assessment Team is reserving the option to overview or assess the MPQAD review of irs issued on the Soils Remedial Work prior to September 1982. Refer to Item 64-2Q. (CLOSED ITEM)

Item 66 Review of Phase III SWO Resolution.

J. Meisenheimer said MPQAD may perform Phase III of SWO resolution separately for the Soils Remedial area. L. Rouen replied the Assessment Team will perform it's evaluation of Phase III resolution if Stone & Webster CIO concurs with the approach. (OPEN ITEM)

Item 66 MPQAD Response to NIRs.

~L. Rouen requested that MPQAD respond to Assessment Team NIRs on a separate attachment in the future. This will leave the bottom portion of the NIR torm for the Asr.essment Team's closure statements. (CLOSED ITEM)

Item 66-SQ - Request for IR Distribution.

L. Rouen requested that the Assessment Team receive copies of the closed irs on crack monitoring. J. Meisenheimer said the Team is on distribution and will receive copics. (OPEN ITEM)

2 Notes of MPQAD Meeting Independent Assessment of Underpinning ~

Midland Plant Unit 1 & 2 Held at Midland Site Midland, Michigan December 19, 1983 Response Item Item 66-6Q - MPQAD Supervisory Personnel.

L. Rouen indicated that the Assessment Team has accepted the MPQAD response describing the availability and use of Level III certified QA staff to provide guidance and resolving conflicts between Level II inspectors and non-certified QC supervisors. (CLOSES ITEM 57-6Q) i