MONTHYEARML20009E8641981-05-31031 May 1981 Revised Main Control Room Habitability Study Project stage: Other ML20009E8541981-07-20020 July 1981 Forwards Revised Main Control Room Habitability Study, Per NUREG-0737,Item III.D.3.4.Revision Corrects Errors in Radiological Analysis Assumptions.Mods Recommended in Toxic Chemical Study Will Be Scheduled for Completion by 830101 Project stage: Other ML20024B0851983-07-0101 July 1983 Application to Amend Licenses DPR-42 & DPR-60,revising Tech Specs Re Containment Sys Recombiners,Control Room Air Treatment Sys & Ref to FSAR Table 7.7-2 Project stage: Request ML20024B0831983-07-0101 July 1983 Forwards Application to Amend Licenses DPR-42 & DPR-60, Revising Tech Specs Re Containment Sys Recombiners,Control Room Air Treatment Sys & Ref to FSAR Table 7.7-2.Changes Do Not Constitute Significant Hazards Consideration Project stage: Request ML20024B0871983-07-0101 July 1983 Proposed Tech Specs Re Containment Sys Recombiners,Control Room Air Treatment Sys & Ref to FSAR Table 7.7-2 Project stage: Other ML20077N9441983-08-26026 August 1983 Application for Amend to Licenses DPR-42 & DPR-60, Changing Tech Specs Re Addition of Instruments to Event Monitoring Instrumentation & Chlorine Detection Sys Project stage: Request ML20077N9221983-08-26026 August 1983 Forwards Application for Amend to Licenses DPR-42 & DPR-60, Changing Tech Specs Re Addition of Instruments to Event Monitoring Instrumentation & Chlorine Detection Sys Project stage: Request ML20077N9561983-08-26026 August 1983 Proposed Tech Specs Re Event Monitoring Instrumentation & Chlorine Detection Sys Project stage: Other ML20079G0381984-01-13013 January 1984 Forwards Application for Amend to Licenses DPR-42 & DPR-60, to Provide Assurance of Reactor Coolant Vent Sys Operability & Reliability,Implementing Requirements of NUREG-0737,Item II.B.1 Project stage: Request ML20079G0461984-01-13013 January 1984 Application for Amend to License DPR-42 & DPR-60,providing Assurance of Reactor Coolant Vent Sys Operability & Reliability,Implementing Requirements of NUREG-0737,Item II.B.1 Project stage: Request ML20079G0541984-01-13013 January 1984 Proposed Tech Spec Changes Providing Assurance of Reactor Coolant Vent Sys Operability & Reliability Project stage: Other ML20088A2551984-03-27027 March 1984 Safety Evaluation Supporting Amends 69 & 63 to Licenses DPR-42 & DPR-60,respectively Project stage: Approval ML20088A8861984-04-10010 April 1984 Forwards Application to Amend Licenses DPR-42 & DPR-60, Revising Tech Specs in Response to Generic Ltr 83-37,to Implement Requirements of NUREG-0737,Items II.B.3,II.F.1.2 & III.D.3.4 Project stage: Request ML20088A8931984-04-10010 April 1984 Application to Amend Licenses DPR-42 & DPR-60,revising Tech Specs in Response to Generic Ltr 83-37 to Implement Requirements of NUREG-0737,Items II.B.3,II.F.1.2 & III.D.3.4 Project stage: Request ML20088A8961984-04-10010 April 1984 Proposed Tech Specs in Response to Generic Ltr 83-37, Implementing Requirements of NUREG-0737,Items II.B.3, II.F.1.2 & III.D.3.4 Project stage: Other ML20090D3981984-06-20020 June 1984 Toxic Chemical Study Project stage: Other ML20090D3761984-07-0909 July 1984 Suppl 1 to 840410 Application for Amend to Licenses DPR-42 & DPR-60,changing Tech Specs to Delete Requirement for Ammonia,Hydrocloric Acid & Formaldehyde Gas Detection Sys in Main Control Room,Per NUREG-0737,Item III.D.3.4 Project stage: Request ML20090D3651984-07-0909 July 1984 Forwards Suppl 1 to 840410 Application for Amend to Licenses DPR-42 & DPR-60,changing Tech Specs to Delete Requirement for Ammonia,Hydrocloric Acid & Formaldehyde Gas Detection Sys in Main Control Room,Per NUREG-0737,Item III.D.3.4 Project stage: Request ML20108B1621984-10-25025 October 1984 Corrected Amends 70 & 64 to Licenses DPR-42 & DPR-60, Respectively,Adding Tech Spec 3.14-4 Re Operator Action for Inoperable Containment Ventilation Isolation Sys, Inadvertently Omitted from 840912 Amends Project stage: Other ML20106J8841984-10-26026 October 1984 Advises That Manual Isolation Valves in Unit 1 Vent Line Blocked & Tagged in Accordance W/Requirements of Tech Spec 4.18.Tech Spec for Reactor Coolant Vent Sys Implemented Project stage: Other 1984-10-25
[Table View] |
Text
.
TS.3.13-1A REV E.
Two chlorine detection systems, each consisting of two channels of instrumentation shall be operable at all times except as specified below. The alarm / trip setpoint shall be adjusted to actuate at a
chlorine concentration of less than or equal to 5 ppm.
- 1. If one chlorine detection channel for one train of ventilation is inoperable, then within seven days:
a.
Restore the inoperable channel to operable status, or b.
Operate the redundant ventilation 'systen in the normal (non-recirculation) mode, and close the outside air suction dampers for the affected train of ventilation
- 2. If both chlorine detection channels for one train of ventilation are inoperable then within six hours:
a.
Restore at least one channel to operable status, or b.
Operate the redundant ventilation system in the normal (non-recirculation) mode and close the outside air suction dampers for the affected train of ventilation
- 3. If all chlorine monitors for both trains of ventilation are inoperable then within six hours close all Control Room ventilation outside air suction dampers.
8309130258 830826 PDR ADOCK 05000282 P
PDR
-. = - _. -
TABLE TS.3,15-1 1
EVENT MONITORING INSTRUMENTATION - PROCESS & CONTAINMENT Required Total No.
Minimum Channels Instrument of Channels Operable 1
- 1. Pressurizer Water Level 2
1
- 2. Auxiliary Feedwater Flow to Steam Generators 2/ steam gen 1/ steam gen (One Channel Finw and One' Channel Wide Range.
Level for Each Steam Generator)
- 3. Reactor Coolant System Subcooling Margin ***
2 1
i
- 4. Pressurizer Power Operated Relief Valve Position 2/ valve 1/ valve (One Common Channel Temperature, One Channel Limit Switch per Valve, and One Channel Acoustic Sensor per Valve *)
I 2
- 5. Pressurizer Power Operated Relief Block Valve 2/ valve 1/ valve Position (One Common Channel Temperature, One Channel Limit Switch per Valve, and One Channel Acoustic Sensor per Valve *)
- 6. Pressurizer Safety Valve Position 2/ valve 1/ valve (One Channel Temperature per Valve j
and Common Acoustic Sensor **)
i
- 7. Containment Water Level (wide range) 2 1
N y!
l
- 8. Containment Hydrogen Monitor (2 sensors per Channel) 2 1
4
- 9. Containment Pressure 2
1 F
Un
,L
- A common acoustic sensor provides backup position indication for each pressurizer power operated relief valve and its associated block valve.
1
- The acoustic sensor channel is common to both valves. When operabl'e, the acoustic sensor may be considered as an operable channel for each valve.
- - Fully qualified input instrumentation is being installed in accordance with the HRC's TMI Action Plan.
Until installation is completed, this function will be satisfied using the plant process computer.
4 9