MONTHYEARML18031B0841986-12-10010 December 1986 Summary of 861119 Meeting W/Util & GE Re Review Schedules for Startup Issues.Revised Schedule,List of Attendees & List of Upcoming Meetings Encl Project stage: Meeting ML18031B1321987-01-15015 January 1987 Summary of 861210 Meeting W/Util in Bethesda,Md Re Fire Protection Program Mgt & Plant Electrical Design Review Calculations.List of Attendees Encl Project stage: Meeting ML20150C3481988-03-11011 March 1988 Summary of 880229 Meeting W/Tva Re Util Resolution of Concerns on Electrical Cable Ampacity.Meeting Agenda & Viewgraphs Encl Project stage: Meeting ML20151Y1711988-04-28028 April 1988 Submits Addl Info Re Thermal Overload,Splice Review,Fuse Program & Flexible Conduit Review.Encl 1 Describes Issues & Suppls Section III.13.0 of Nuclear Performance Plan Vol 3, Rev 1.Status of Remaining Issues from Section III Listed Project stage: Other ML20151E7231988-06-30030 June 1988 Evaluation of Browns Ferry Nuclear Plant Cable Installation Concerns Project stage: Other ML20151E7101988-07-18018 July 1988 Provides Results of Licensee Program to Resolve Cable Installation Issues Identified in Section III.13.1 of Plant Nuclear Performance Plan & Identify Corrective Actions Required for Each Plant Unit Project stage: Other ML18033A3031988-08-10010 August 1988 Forwards Request for Addl Info Re Listed Restart Issues. Response Requested by 880915 Project stage: RAI ML18033A3071988-08-10010 August 1988 Forwards Request for Addl Info Re Util 880707 Cable Ampacity Program Plan.Response Required by 880915 Project stage: RAI ML20154Q7791988-09-21021 September 1988 Forwards Response to NRC 880810 Request for Addl Info Re Electric Circuit Protection by Current Limiting Fuses, Including Design Stds & Calculation & Tabulation Sheets.W/ Two Oversize Drawings Project stage: Request ML20155B6151988-09-23023 September 1988 Responds to NRC 880810 Request for Addl Info Re Overload Protection of Motor Control Ctr circuits.W/8 Oversize Encls Project stage: Request ML18033A4451988-11-21021 November 1988 Forwards Request for Addl Info Re Electrical issues-cable Ampacity Program,Cable Installation Program,Fuse Program & Thermal Overload Program.Responses Requested by 881209 Project stage: RAI ML20235L8491989-02-15015 February 1989 Summary of 890201-03 & 06 Meetings at Site Re Electrical Cable Installation & Ampacity Issues & Action Plan for Closure.Attendance Rosters & List of Major Items Which TVA Is to Accomplish as Part of Resolution of Cable Issue Encl Project stage: Meeting ML18033A6441989-02-21021 February 1989 Confirms Agreements Reached W/Nrc During 890202 & 09 Meetings Re Electrical Cable Ampacity.Util Plans to Incorporate Div of Operating Reactors Guidelines Into Environ Qualification Program at Facility Project stage: Meeting ML18033A6511989-02-28028 February 1989 Provides Corrections to Thermal Overload Heaters Sizing Criteria Submitted by TVA .Based on in-depth Evaluations & Discussions w/motor-operated Valve Mfgs,Tva Issued Quality Info Rept to Specify Listed Criteria Project stage: Other ML18033A6831989-03-17017 March 1989 Responds to NRC Questions from 890202 Meeting Re Electrical Cable Ampacity Program Project stage: Meeting ML18033A6851989-03-21021 March 1989 Forwards Request for Addl Info on Cable Ampacity Program Plan Submitted by Util 880707 & 0930 Ltrs for Response by 890428 Project stage: RAI ML18033A7261989-04-27027 April 1989 Forwards Response to 890321 Request for Addl Info Re Electrical Cable Ampacity,Consisting of Results of Two NRC Cable Tray Simulation Cases Project stage: Request ML18033A7491989-05-11011 May 1989 Responds to Re Electrical Cable Ampacity.Item a Interpreted as Stating That Cable Does Not Have to Operate During Accident That Creates Transients in Excess of 205 F Project stage: Other ML18033A7521989-05-15015 May 1989 Provides Clarification to Sizing Criteria for Thermal Overload Heaters.Trip Setting for 200% Nominal Torque Current Is 1 Duty Cycle & 8 Minutes (Ac) Project stage: Supplement ML18033A8161989-06-28028 June 1989 Forwards List of Submittals Required of Util to Support NRC Decisions Re Restart.Util Will Be Apprised of Need for Addl Info to Resolve Technical Issues If Submittals Incomplete Project stage: Other ML18033A8211989-07-0707 July 1989 Responds to NRC Which Provided Clarification on Util Use of Div of Operating Reactors Guidelines Re Electrical Cable Ampacity.Util Does Not Intend Qualifying Cables to Guidelines Required to Operate Under Criteria B Project stage: Other ML18033A8971989-08-18018 August 1989 Describes Program Plan for Resolution of Flexible Conduit Installation Issues.Evaluation of Flexible Conduit Providing Background Info,Plan for Resolution,Outline of Acceptance Criteria & Schedule for Completion Encl Project stage: Other ML18033A9831989-10-0606 October 1989 Forwards Details & Summary of Recently Completed Testing of Cable Tray Configurations,Summary of Scope & Results of Ampacity Evaluations & Radon Cable Fill within Tray,Per NRC 890710 Request Project stage: Other ML18033B0891989-12-19019 December 1989 Requests Addl Info on Section III.13.3 of Plant Nuclear Performance Plan Re Flexible Conduit within 60 Days of Ltr Receipt Project stage: Other ML20011D6591989-12-19019 December 1989 Forwards Safety Evaluation Supporting Util Corrective Actions to Resolve Inadequacies in Electrical Design Stds for Cable Ampacity Program,Per Section III.13.2 of Nuclear Performance Plan Project stage: Approval ML18033B1911990-03-0202 March 1990 Responds to NRC for Addl Info Re Flexible Conduit.Calculation Will Be Revised to Reflect Accelerometer Displacement & Summation of Displacement W/Test Table Displacement Will Be Used to Establish Max Top of Cabinet Project stage: Other ML18033B4251990-07-10010 July 1990 Forwards Cable Installation Supplemental Rept,In Response to NRC Request During 900506 Telcon.Rept Contains Results of Walkdowns & Testing Except Work on Ongoing Cable Pullby Issue Project stage: Supplement ML20059L5741990-09-19019 September 1990 Forwards Rev 2 to Browns Ferry Nuclear Plant Cable Issues Supplemental Rept Corrective Actions,Sept 1990. Rept Revised to Clarify Cable Bend Radius & Support of Vertical Cable & Document Resolution of Jamming Issues Project stage: Supplement 1989-02-15
[Table View] |
Text
TENNESSEE VALLEY AUTHORITY 3
CH AiTANOOGA, TENNESSEE 374o1 SN 137B Lookout Place SEP 191990 U.S. Nuclear Regulatory Commission ATTN Document Control Desk Washington, D.C.
20555 centlemen:
In the Matter of
)
Docket Nos. 50-259 Tennessee Valley Authority
)
50-260 50-296 BROWNS FERRY NUCLEAR PLANT (BFN) - UNIT 2 - RESOLUTION OF CABLE INSTALLATION i
ISSUES SUPPLEMENTAL REPORT CORRECTIVE ACTIONS - CABLE PULLBY Reference 1.
TVA's lette-to NRC dated June 19, 1989, Electrical Cable l
Insta11at.vu - Revised Valkdown and Summary Reports l
(TAC No. 62260) 2.
TVA's letter to NRC dated July 10, 1990 - Cable Installation Issues Supplemental Report Corrective Actions This' letter transmits BFN's report titled " Cable Installation issues Supplemental Report Corrective Actions." This report supercedes the re'jort i
transmitted by Reference 2.
Reference 1 transmitted a summary report (dated March 1989) on the evaluation of BFN cable installation concerns. Reference 2 transmitted a summary report which addressed the recommended actions contained in the March 1989 report l
required to resolve BFN's cable issues. Additionally, Reference 2 contained a i
summary of the remaining actions required for closure of BfN cable installation concerna except for cable pullby. The cable pullby program is now complete and the report transmitted by Reference 2 has been revised to provide the results of this prog am.
Additionally, this report has been revised to clarify cable bend radius and support of vertical cable, and to document resolution of BFN's januning issues with NRC.
It should be noted that during the hi-pot testing being performed to resolve the cable pullby issue, cable damage was identified.
However, the. damage was
-attributed to a disconnected cable bushing at a mio point pull box (JB) and not cable pullby. Subsequent to the discovery of this anomaly BFN established a program to identify conduits at JBs with missing bushings.
contains the results of the walkdown and subsequent hi-pot testing that was performed to resolve this issue. Conduits'at JBs with missing bushings were identified during BFN's walkdowns, but the hi-pot testing and investigations of the ef fected cable indicated that cable damage that was originally identified during the cable pullby testing program was an isolated case.
9009'296133 9999g9 s
{DR ADOCK 05000259 0
0 An Equal Opportunity Employer k
7
' m U.S. Nuclear Regulatory Commission ElEiP 191990 i
It is TVA's position that the agressive program of walkdowns, inspections, and testing confirms that cable installation damage is not present at BFN and the enclosed report provides the documentation required for closure of this issue by NRC. identifies the commitments contained in this submittal.
If you have any questions, please telephone Patrick P. Carier, BFN, Site Licensing, (205) 729-3566.
Very truly yours, TENNESSEE VALLEY AUTHORITY
/
4-c-< -
E. G. Wallace, Manager Nuclear Licensing and Regulatory Affairs Enclosures cc (Enclosures):
Ms. S. C. Black, Deputy Director Project Directorate II-4 U.S. Nuclear Regulatory Commission One White Flint, North 11555 Rockville Pike, Rockville, Maryland 20852 NRC Resident Inspector Browns Ferry Nuclear Plant Route 12, Box 637 Athens, Alabama 35609-2000 Mr. Thierry M. Ross, Project Manager U. S. Nuclear Regulatory Commission One White Flint, North 11?-sh Rockville Pike Rot'/.1113 Maryland 20852 Mr. B. A. Wilson, Project Chief U.S. Nuc. ear Regulatory Commission Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323 4
l-t
-n
J,,.
c i
1 i
l l
I ENCLOSURE 1 i
CABLE INSTALLATION SUPPLEMENTAL REPORT 1
1 J
t t
1 1
t 4
i b
t Y
t b
i 2.
-