e OPERATING DATA REPORT DOCKET No. 50-364 DATE 4/9/90 COMPLETED BY D. N. Morey TELEPHONE (205)899-5156-OPERATING STATUS-Notes
- 1. Unit Names Joseph M. Parley - Unit 2
- 1) Cumulatie data since
- 2. Reporting Period:
March 1990 7-30-81, date of
- 3. Licensed Thermal Power (MVt):
2,652 commercial operation.
- 4. Nameplate Rating (Gross MWe):
860
- 5. Design Electrical Rating (Net MWe):
829
- 6. Maximum Dependable Capacity (Gross MVe):
868.6
- 7. Maximum Dependable Capacity (Net MWe):
828.2
- 8. If Changes Occur in Capacity Ratings (Items Number.3 Through 7) Since Last Report, Give Reasons: N/A
- 9. Power Level To Which Restricted, If Any (Net MWe):
N/A
- 10. Reasons For Restrictions, If Any:
N/A This Month Yr-to-Date Cumulative
- 11. Hours In Reporting Period 744 2,160 76,009
- 12. Number Of Hours Reactor Vas Critical 744 2,160 66,0437T~ l
- 13. Reactor Reserve Shutdown Hours 0.0 0.0 TR 14.; Hours Generator On-Line 744 2,160 62,328.0
- 15. Unit Reserve Shutdown Hours 0.0 0.'D 0.0
- 16. Gross. Thermal Energy Generated (MVH) 1,971,205
_ 5,572,824 165,829,091
- 17. Gross Electrical Energy Generated (MVH) 652,214 1,844,604 54.511 146
- 18. Net Electrical Energy Generated (MVH) 622,170 1,756,594
~3I~,
,4
- 19. Unit Service Factor 100 100 85.8
- 20. Unit Availability Factor 100 100 85.8
- 21. Unit Capacity Factor (Using MDC Net) 101 98.2 83.1 l
- 22. Unit Capacity Factor (Using DER Net) 100.9 98.1 82.0
- 23. Unitt Forced Outage Rate 0.0 0.0 4.4-
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):
. Refueling / Maintenance Outage, September 14, 1990, approximately 7 weeks.
- 25. If Shut Down At End Of Report Period, Estimated Date of Startup: N/A
- 26. Units In Test Status (Prior to Commercial Operation):
Forecast Achieved INITIAL CRITICALITY 05/06/81 05/08/81 INITIAL ELECTRICITY 05/24/81 05/25/81 COMMERCIAL OPERATION 08/01/81 07/30/81 Form 2/30 t