Corrected Monthly Operating Rept for Jan 1990 for Jm Farley Nuclear Plant Unit 2
ML20055F755
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 01/31/1990
From: Dennis Morey
ALABAMA POWER CO.
To:
Shared Package
ML20055F742 List:
References
NUDOCS 9007190156
Download: ML20055F755 (1)


Text

. _ -..

l

' OPERATING DATA REPORT DOCKET NO.

50-364 DATE 2/2/90 COMPLETED BY D. N. Morey _

TELEPHONE (205)B99-5156 OPERATING STATUS Notes

1. Unit Name:

Joseph M. Farley - Unit 2

1) Cumulative data since
2. Reporting Period:

January 1990 7-30-81, date of

3. Licensed Thermal Power (MVt):

2,652 commercial operation.

4. Nameplate Rating (Gross MVe):

860

5. Design Electrical Ratn.g (Net MWe): 829 6.-Maximum Dependable Capacity (Gross MVe):

868.6

7. Maximum Dependable Capacity (Net MVe):

828.2

8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since LCEReport, Give Reasons: N/A
9. Power-Level To Which Restricted, If Any (Net MVe):

N/A

10. Reasons For Restrictions, If Any:

N/A This Month Yr-to-Date cumulative

11. Hours In Reporting Period 744 744 74,593 12.-Number of Hours Reactor Was Critical 744.0 744.0 64,627.1 l

'13. Reactor Reserve Shutdown Hours 0.0 0.0 138.0 14.-Hours Generator On-Line 744.0 744,0 63,816.0 l.

1 15.-Unit Reserve Shutdown Hours 0.0 0.0 0.0 i

16. Gross Thermal Energy Generated (MVH) 1,970,306 1,970,306 162 225,573 l
17. Gross Electrical Energy Generated (MWH) 654,930 654,930 1,472
18. Net Electrical Energy Generated (MWH) 624,764 624,764 50,568,154
19. Unit Service Factor 100.0 100.0 85.6
20. Unit Availability Factor 100.0 100.0 85.6
21. Unit Capacity Factor-(Using MDC Net) 101.4 101.4 82.9
22. Unit-Capacity Factor (Using DER Net) 101.3 101.3 81.8
23. Unit Forced Outage Rate 0.0 0.0 4.5 l
24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

[

N/A 1

25. If-Shut Down At End Of Report Period, Estimated Date of Startup: N/A I"
26. Units In Test Status (Prior to Commercial Operation):

Forecast Achieved l

INITIAL CRITICALITY 05/06/81 05/08/81' INITIAL ELECTRICITY 05/24/81 05/25/81 l

COMMERCIAL OPERATION 08/01/81 07/30/81 l

Form 2/30

+