ML20034F068

From kanterella
Jump to navigation Jump to search
Insp Repts 50-445/93-08 & 50-446/93-08 on 930111-15. Violations Noted.Major Areas Inspected:Followup of Previously Identified Items
ML20034F068
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 02/23/1993
From: Yandell L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20034F049 List:
References
50-445-93-08, 50-445-93-8, 50-446-93-08, 50-446-93-8, NUDOCS 9303020239
Download: ML20034F068 (44)


See also: IR 05000445/1993008

Text

,

i

APPENDIX B-

!

.

-

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

-

Inspection Report:

50-445/93-08

50-446/93-08

Operating License: NPF-87

Construction Permit: CPPR-127

.

Licensee: TU Electric

Skyway Tower

400 North Olive Street

Lock Box 81

Dallas, Texas 75201

.

Facility Name:

Comanche Peak Steam Electric Station, Units 1 and 2

Inspection At:

Glen Rose, Texas

Inspection Conducted: January 11-15,1993

.;

Inspectors:

P. Madden, Senior Fire Protection Reviewer, Plant Systems Branch,

Office of Nuclear Reactor Regulation

4

M. Murphy, Reactor Inspector, Plant Support Section, Division'of

Reactor Safety, Region IV

T'. Reis, Project Engineer, Project Section B, Division of Reactor

Projects, Region IV

4

A. Singh, Reactor Inspector, Plant Support Section, Division of

Reactor Safety, Region IV

i

Th

Approved:

.L. A. Yandell, Chief, Project Section B,

Date

i

Division of Reactor Projects

!

Inspection Summary

f

Areas Inspected (Unit I):

Inspection of Unit I was limited.to followup of

previously identified unresolved and inspection followup items.

,

Areas Inspected (Unit 2):

Planned, announced inspection of followup on the

!

six unresolved and six inspection followup items from the fire protection team

inspection conducted November-16-20, 1992, and the licensee's procurement,

training, quality assurance, engineering, installation, and testing activities

associated with its use of Thermo-Lag as a fire barrier system.

t

'

.9303020239 930223

PDR

ADOCK 05000445

G

PDR

.

.

.

$

i

-p_

,

.Results (Unit 1):

The licensee connitted to perform hardware modifications necessary to

alleviate the susceptibility of fire induced short circuiting rendering

safe shutdown motor-operated valves (MOVs) inoperable as discussed in

NRC Information Notice 92-18, " Potential for Loss of Remote . Shutdown

Capability During a Control Room Fire," prior to startup from the third

refueling outage (Section 1.3).

.

The licensee committed to take timely actions to address the completion

of the Generic Letter 86-10 associated circuit high impedance fault

study and subsequent necessary modifications and to upgrade the safe.

shutdown emergency lighting batteries (Sections 1.2 and 1.5).

,

o

Based on the commitments and other actions taken, the licensee

adequateli addressed the impact on Unit 1 of the unresolved items

identified in NRC Inspection Report 50-445/92-49; 50-446/92-49.

The

inspection followup items, which potentially impacted Unit 1, from the

referenced report were also resolved (Sections 1.1, 1.2, 1.3, 1.6, 1.9,

1.11, and 1.12).

Implementation of all of the liceasee's commitments is considered an

inspection followup item (Section 1.13).

'

Results (Unit 2):

A sampling of the adequacy of emergency lighting performed to resolve -

Inspection Followup Item 446/9249-06 resulted in a violation.

Unauthorized disconnection by the startup organization of emergency.

lights from their respective battery supplies, apparently to prevent

battery discharge during a bus outage, resulted in the emergency

lighting system being in operations custody with a significant

percentage of inoperative lights (Section 1.6).

The licensee committed to perform hardware modifications necessary to

alleviate the susceptibility of fire induced short circuiting rendering

safe shutdown MOVs inoperable as discussed in NRC Information Notice 92-18, " Potential for Loss of Remote Shutdown Capability During.a

Control Room Fire," prior to startup from the first refueling outage

'

(Section 1.3).

The licensee adequately addressed, contingent upon the-

e

implementation of docketed commitments, the unresolved items

pertaining to the Generic Letter 86-10 high impedance fault study;

the potential for spurious operation and subsequent damage to safe

shutdown required MOVs and the failure of an automatic turbine

,

trip to occur; and the testing, maintenance, and derating of

l

emergency lighting. The licensee adequately addressed, with no'

,

i

i

f

-3-

further action required, the unresolved items pertaining to

testing and maintenance of safe shutdown circuit breakers and

'

relays; the rating and positioning of certain fire suppression

sprinkler heads; and, the design adequacy of a water curtain

intended to satisfy separatson criteria.

(Sections 1.1, 1.2, 1.3,

1.5, 1.9, and 1.11).

Inspection followup items pertaining to positioning of smoke detectors

relative to air flow, and physical obstructions to sprinkler heads were

resolved contingent upon the implementation of docketed commitments.

Inspection followup items pertaining to procedural deficiencies in

Procedure ABN-803B, " Response to a Fire in the Control Room or Cable

,

Spreading Room," completion of fire barriers and seals, and the impact

of missing control room ceiling tiles on smoke detection equipment were

resolved unconditionally (Sections 1.4, 1.7, 1.8, 1.10, and 1.12).

The licensee made further commitments, in docketed correspcndence dated

January 15, 1993, to upgrade the safe shutdown emergency lighting

batteries in accordance with the current replacement schedule beginning

June 1, 1993; designate and control tools and ladders required for the

performance of ABN-803B, " Response to a Fire in the Control or Cable

Spreading Room;" perform 100 percent of the preventive maintenance

procedures for emergency lighting, and complete the engineering

justifications for Thermo-Lag installations which do not conform to

tested configurations. The implementation of these commitments is an

inspecti.on followup item (Sections 1.4, 1.5, 1.6, 1.13, and 2.6).

The licensee's Thermo-Lag installation program contained all essential

elements and complied with the approved installation and specification

procedures.

A comprehensive, multitiered quality assurance / quality

control (QA/QC) program was in place and appeared to be effective.

Some

installed configurations were found that did not conform to the tested

configurations and the licensee was still in the process of preparing

engineering evaluations. These evaluations will be reviewed when

received (Section 2.0).

Implementation of all the licensee's commitments is considered an

e

inspection followup item (Section 1.13).

Summary of Inspection Findings

e

Violation 446/9308-01 was opened (Section 1.6).

,

Inspection Followup Item 445;446/9308-02 was opened (Section 1.13).

e

Unresolved Item 445;446/9249-01 was closed (Section 1.1).

Unresolved item 445;446/9249-02 was closed (Section 1.2).

i

-4-

,

Unresolved Item 445;446/9249-03 was closed (Section 1.3).

Inspection Followup Item 446/9249-04 was closed (Section 1.4).

Unresolved Item 445;446/9249-05 was closed (Section 1.5).

Inspection Followup Item 446/9249-06 was closed (Section 1.6).

Inspection Followup Item 446/9249-07 was closed (Section.1.7).

Inspection followup Item 446/9249-08 was closed (Section 1.8).

Unresolved Item 445;446/9249-09 was closed (Section 1.9).

Inspection Followup Item 446/9249-10 was closed (Section 1.10).

Unresolved Item 445;446/9249-11 was closed (Section 1.11).

Inspection followup Item 445;446/9249-12 was closed (Section 1.12).

Inspection Followup Item 445;446/9225-03 was closed (Section 1.14).

'

Inspection Followup Item 446/9227-01 was closed (Section 1.15).

Attachments: I

,

Attachment 1 - Persons Contacted and Exit Meeting

Attachment 2 - 10 Electric Letter, TXX-92640, dated December 23, 1992

Attachment 3 - TV Electric. Letter, TXX-93034, dated January 15, 1993

Attachment 4 - Areas Requiring Sprinkler Head Relocation or Addition

Attachment 5 - Detailed Review of Omega Point Laboratory Thermo-Lag fire

Test Reports

Attachment 6 - Typical Thermo-Lag Configuration Drawings

Attachment 7 - Thermo-Lag Configurations and Respective Work Documents

Inspected

Attachment 8 - Engineering Justifications for Untested Thermo-Lag

Configurations Reviewed

Attachment 9 - Other Thermo-Lag Configurations Not Bounded by Testing

Program

.

'

,

I

i

-5-

.

DETAILS

1 FOLLOWUP (92701)

1.1

(Closed) Unresolved items 445:446/9249-01: Testing and Maintenance of

j

Breakers and Relays

This item involved the testing and maintenance of circuit breakers, relays,

and power supplies required to achieve postfire safe shutdown.

During the

initial inspection, discussions with licensee personnel left the team with the

understanding that implementation of preventive maintenance and testing

procedures was limited in scope to only power supplies specifically identified

by Technical Specifications. Such implementation would not be sufficient to

encompass all breakers and relays associated with equipment necessary to

support a postfire safe shutdown.

The licensee subsequently demonstrated that

all the subject safe shutdown breakers and relays had been included into the

plant preventive maintenance program in accordance with Procedure _STA-677,

" Preventive Maintenance Program," Revision 2, dated July 14, 1992, for both

Units 1 and 2.

The team reviewed the completed packages anc. verified that' the

breaker surveillances had been performed in accordance with the established

frequency.

1.2 (Closed) Unresolved Items 445:446/9249-02:

Conservatism of Generic

l

Letter 86cl0 High Impedance Fault Stud _y

t

This unresolved item pertained to assumptions the licensee used in performing

the high impedance fault (fault currents of a value that is just below the

trip point of the protective device on each individual circuit) study,

'e

required by Generic Letter 86-10.

The Generic Letter requires that, for

circuits which are associated by a common power supply, simultaneous high

impedance faults for associated circuits in a given fire area should be

considered. The Generic Letter does not provide guidance in the' methodology

to be used in the analysis. The initial inspection found that the licensee

chose an arbitrary five, fire initiated, high impedance faults to be the

maximum that would occur, regardless of the population of circuits which

shared the common power supply.

The team considered that the number of faults assumed should be a function of

the circuit population sharing the common power-supply. The licensee examined

its five assumed faults and determined that, for high and medium voltage power

'

supplies, five represented 31 percent or greater of the population, which the

team considered sufficiently conservative.

However, for low voltage power

supplies (generally 125VDC or 120VAC), the five assumed faults represented

only 14 percent of the population in at least two power supplies, which the

team considered nonconservative.

The licensee agreed that performing the analysis based on an assumed

percentage basis in lieu of the arbitrarily chosen five was an improved

-

methodology.

Both the licensee and the team considered an assumption of

~~

_

_

~

_

_

.

.

i

!

-6-

,

25 percent failures to be sufficiently conservative.

Accordingly, the

licensee revised Calculation 2-EE-0052 to incorporate the failure rate of

.

25 percent in lieu of an assumed five failures.

The reanalysis necessitated

',

the uprating of three breakers in 118VAC Distribution Panel No.'2EC2, 125VDC

,

Distribution Panel No. 2ED2-1, and 125VDC Distribution Panel 2EDI-1,

'

respectively.

The licensee initiated Design Change Authorization (DCA) 87838

dated December 21, 1992, to replace the breakers and, as of January.12,1993,

two of the three had been replaced, with the third awaiting a Train A outage

,

-

to be accomplished.

The team has reviewed the licensee's reanalysis of its high impedance fault

study and considers that the licensee has taken adequate corrective actions to

,

address the teams concerns for Unit 2.

'

However, this issue also impacts Unit 1, and the licensee's reanalysis of the

Unit I high impedance fault study incorporating the 25 percent failure rate

has not been completed.

The licensee has committed to complete the study by

May 1, 1993, submit it to NRC Region IV and complete any hardware

modifications necessitated by the reanalysis during the next available outage

that would support the changeout of any breakers requiring. upgrade.

1.3

(Closed) Unresolved Items 445:446/9249-03:

WCAP'11331 Spurious

l

Operations and Potential for Fire Induced MOV Failure

A portion of this unresolved item pertained to the licensee's transient

I

analyses, as identified in WCAP-11331, " Comanche Peak Steam Electric Station

'

Thermal / Hydraulic Analysis of Fire Safe Shutdown Scenario," of the following

fire induced spurious operations:

!

Stuck Open Pressurizer PORV

Stuck Open Steam Generator PORVs

Spurious Head Vent Operation

'

Auxiliary Feedwater System Misalignment

e

Spurious SI System Operation

Main Feedwater and Turbine Do Not Trip at Reactor Trip

e

Backup Heaters fail On

e

The team determined that the licensee's analysis, as identified in WCAP 11331,

adequately demonstrated that, with the exception of the failure to obtain P4

,

(main feedwater and turbine does not isolate following reactor trip scenario),

all postulated scenarios demonstrated that no challenge to core cooling would

occur.

The WCAP recommended that further evaluation of.the transient

involving failure cf main feedwater and turbine trip following reactor trip be

!

conducted. 'The licensee did not provide the team with objective evidence.that

,

a further evaluation of a failure of main"feedwater and turbine trip at

reactor trip had been conducted.

!

The licensee had considered the probability of this malfunction to occur to be

remote and considered manual actions of shutting-the main steam isolation

,

,

-7-

.

.

valves to isolate.the turbine and thus prevent an uncontrolled cooldown to be

satisfactory.

There was no objective or quantitative evidence to support the

,

capability of isolating the turbine in a timely manner to prevent core damage.

,

In response to this unresolved item, the licensee reevaluated all of the seven

spurious operations and reconfirmed that appropriate procedural guidance was

specified in Procedure ABN-803B, " Response to a Fire in the Control Room or

Cable Spreading Room," to minimize the effects of the six postulated

transients that the team initially found acceptable.

For the postulated scenario of failure of main feedwater and turbine trip to

occur on reactor trip, the licensee has revised Procedure ABN-803B to direct

the reactor operator to manually trip the main turbine in addition to the

reactor prior to control room evacuation. Additionally, Procedure ABN-803B

instructs the reactor operator to close the main steam isolation valves from

the control room prior to evacuation if conditions permit.

The team reviewed revisions to Procedures ABN-803A (Unit 1) and ABN-803B

(Unit 2) and found that they adequately addressed the concerns raised by the

team.

Accordingly, no further action is required on this aspect of Unresolved

Item 445;446/9249-03.

The other portion of this item pertained to the potential for a control room

)

or cable spreading room fire to create a single hot short in the control

circuitry of various MOVs, resulting in their spurious operation.

Additionally, .since the fault would cause the position limit 'and torque

switches to be bypassed, mechanical damage of the valve due to overtorque may

occur, thereby rendering it inoperable.

This concern is the subject of NRC

Information Notice (IN) 92-18, "Poteni bl for Loss of Remote Shutdown

Capability During a Control Room fire, " dated February 28, 1992.

The team had found that the licensee had reviewed the IN for impact on their

facility and found that they did possess circuitry configurations analogous to

those specified in the IN.

The licensee, however, in consultation with the

Nuclear Utility Management and Resources CounciT (NUMARC) determined in August

1992 that the low probability of such an occurrence did not justify any

modifications to the CPSES.

The licensee's contractor, Stone and Webster

Corporation, had identified to the licensee in July 1992 that CPSES Unit 2 did

have 53 MOV circuit configurations similar to these described as vulnerable in

the IN and recommended the control- circuitry be rewired internal to the motor

control center compartments so that the torque and limit switches in the valve

operators are electrically connected downstream of the contacts located in the

motor control center.

At the conclusion of the initial inspection, the team

could not conclude that, without modifications to the vulnerable MOV

circuitry, the existing design conformed to licensee commitments to the

requirements of 10 CFR 50, Appendix R, Section 111.L.7, which states, in part,

that the safe shutdown equipment and systems for each area shall be known to

be isolated from associated non-safety circuits in the fire area so that hot

x

-8-

shorts, open circuits or shorts to ground will not prevent operation of the

safe shutdown equipment.

Accordingly, the issue remained unresolved for

Units 1 and 2.

After further review by the NRC staff, it was determined that the licensee was

not committed to meet the requirements of Section III.L.7.

In further discussions with the NRC staff, the licensee committed in docketed

correspondence dated December 23, 1992, to implement design changes in the

control circuits of the affected MOVs, as required, pursuant to those-

recommended in NRC Information Notice 92-18. The licensee committed to

perform the design changes prior to startup from the first refueling outage

for Unit 2 and prior to startup from the third refueling outage for Unit 1.

f

The licensee has assessed the work to modify those MOV circuits which are

vulnerable to failure as described in the IN for Unit 2 and has determined

that 55 MOVs were potentially affected.

To date, the licensee has determined

that 29 circuit modifications will be required, while 12 circuits are still

"

under review and 14 require no modification.

The Unit I study has not been

compl eted.

Based on the licensee's docketed commitments, this portion of Unresolved

Item 445;446/9249-03 is considered closed.

1.4 (Closed). Inspection Followup Item 446/9249-04:

Procedural and Physical

Deficiencies identified in Procedure ABN-803B.

,

This item involved procedural and physical deficiencies identified during the

walkdown of Procedure' ABN-803B, "Responst to a Fire in the Control Room or

Cable Spreading Room." These deficiencies consisted of typographical errors,

incorrect component identification in the procedure and in the plant,

'

component location errors, and missing tools, which were required -for

equipment operation, such as, T-handle wrenches and ladders.

These

deficiencies were identified in detail in Attachment 3 of the NRC Inspection

3

'

Report 50-445/92-49; 50-446/92-49.

.

In response to these issues, the licensee revised Procedure ABN-803B to

incorporate the identified deficiencies. The team reviewed the revised

version of Procedure ABN-803B and found that it properly addressed the

identified deficiencies.

Additionally, the licensee committed -in Attachment 3

to provide dedicated T-Wrenches and ladders to perform the activities required

by procedures.

. Based on the inspector's reviews and the licensee's commitments, this

inspection followup item is considered closed.

,

-l

i

-

i

t

-9-

l

1.5

(Closed) Unresolved Item 445:446/9249-05: Testing, Maintenance, and

Derating of Emergency Lighting

"

One aspect of this unresolved item pertained to concerns with the licensee's

'

testing and maintenance of emergency lighting in that the licensee opted not

to follow the guidance provided in NRC Information Notice 90-69, " Adequacy of

i

Emergency and Essential Lighting," which suggests that as-found, 8-hour

-

discharge testing is appropriate for safe-shutdown emergency lighting.

Instead, the licensee performs preventive maintenance on the batteries,

-

adjusts the aim of the lanterns, as necessary, and performs a functional check

of the lanterns on a 6-month interval.

The literature provided by the battery

manufacturer, Eagle Picher, indicated that such deep discharge testing is

actually detrimental to the battery and will shorten its expected life.

After

further review, the inspector determined that the licensee's testing and

maintenance program is in accordance with manufacturer guidelines and meets

regulatory requirements.

The other aspect of this unresolved item pertained to the.derating and

shortened lifespan of safe-shutdown batteries which are subjected to elevated

ambient temperatures.

In the initial inspection,'the inspector found in

,

literature provided .by the Halophane Company, the vendor that provided the

'

majority of the safe-shutdown emergency lighting, that significant derating _of

-

the wet lead-acid batteries would be expected in applications with average

ambient temperatures exceeding 90 F and that, at a temperature of 131oF the

!

batteries would only be expected to last 6-9 months.

The licensee's program

called for blanket replacement of all batteries outside containment at 3-year

intervals and for those supporting safe-shutdown lighting inside containment

. at ' a refueling interval .

It could not be determined for locations such as

containment,. safeguards building steam penetration area, emergency diesel

'

generator rooms, and the feedwater penetration area, where elevated ambient

temperatures would be expected, that the emergency lighting' units could

'

maintain an 8-hour discharge with adequate illumination as required by

Appendix R, Section Ill.J.

In response, the licensee performed a review of operator log sheets to

determine temperatures in various areas of Unit 1 over a 1-year period of

Modes 1 and 2 operation and did find areas where average annual ambient

tev eratures approached 90 F and areas in containment where safe-shutdown

lig ting is located where average ambient temperatures of approximately 96of

exi;t,

Th( licensee provided excerpts from a study by the Electric Power Research-

Ins ;tute (EPRI) indicating that "in general, lead-acid battery life is halved

for every 16 to 18 degree Fahrenheit rise above 77 F."

Applying this

methodology, the licensee determined that battery life outside containment in

applications of 90of is just over 36 months and for batteries'inside

containment, life expectancy is approximately 22-25 months.

l'

Therefore, for the nominally rated 5-year Eagle Picher batteries, the

licensee's replacement interval for those areas of elevated temperatures was

,

minically satisfactory.

!

1

______ _ _ - _ _ _ .

-10-

Due to the absence .of margin, however, the licensee has subsequently initiated

a design change, DCN 5491 dated January 8,1993, to replace the Eagle Picher

5-year batteries with Power Battery Company 10-year batteries at the scheduled

i

replacement interval.

The inspector has reviewed the specifications and

determined that the upgraded batteries will provide suff aient margin to

ensure that the 8-hour illumination requirement of Appendix R is met.

The licensee has taken appropriate actions to address this concern and the

current program minimally satisfies regulatory requirements.

Therefore, this

l

i

unresolved item is closed.

1.6

(Closed) Inspection Followup Item 446/9249-06: Blackout Testing of

Emergency Lighting

This inspection followup item was identified by the fire protection team

inspection based on the need to assess the adequacy of illumination of safe

shutdown emergency lighting. The assessment, which requires removing the

power to normal and essential plant lighting, was not performed during the

initial inspection so as to not adversely impact ongoing completion

activities.

As of December 21, 1992, all preoperational testing on emergency lighting had

been completed and the system turned over to operations in accordance with

system turnover Procedure STA-802, " Acceptance of Station Systems and

Equipment."

-

On January 13,' 1993, the inspector arranged with Unit 2 operations to have

normal and essential lighting turned off in eight specific areas which may

require manual remote operations to achieve a postfire safe shutdown.

In the

eight areas selected, six emergency lanterns failed to operate and one room

had no illumination.

The inspector expanded the sample size and arranged to have power turned off

to six more areas.

In this assessment, eight emergency lanterns failed to

operate, two lamps were burned out, and the four main steam penetration rooms

had no illumination.

Based on the observation of this testi..g by the inspector, this inspection

followup item is considered closed.

-

The licensee promptly initiated Operations Notification and Evaluation (ONE)

(,

Form 93-123 to address the failures and formed a task team to investigate the

I

matter.

By the end of the inspection period, the licensee had determined that

the cause of the failures was due to the startup organizations disconnecting

the positive leads from the batteries to the lamps to prevent battery

draindown during a planned essential lighting outage. However, the licensee

determined that the work had been completed in an unauthorized manner outside

the scope of the administrative work control procedures in effect for both the

operations and startup organizations. Without the appropriate administrative

controls, there was no traceability to ensure the reconnection of the leads.

.__

_ _ _ _ _ _ _ _ _ _ - _ _ - - -

_ _ _

i

,

-11-

.

t

.

'

At the conclusion of the inspection, it had been determined that the startup

organization had performed the unauthorized disconnections, but it had not

'

been determined whether this had occurred before or after' December 21, 1992,

when the system was accepted by the operations department.

,

The licensee committed the task team to perform a root cause analysis, and

provide reasonable assurance that the unauthorized, and therefore untraceable,

I

work activities were limited to emergency lighting as a condition to fuel'

-load, and to perform the preventive maintenance procedures on 100 percent of

the Unit 2 emergency lighting prior to Mode 4 operations. This commitment is.

.

provided in Attachment 3.

The unauthorized work activity is a violation of 10 CFR 50, Appendix B,

Criterion V (446/9308-01).

,

1.7 (Closed) Inspection Followup Item 446/9249-07:

Positioning of Smoke

Detectors Relative to Air Flow

This item involved the positioning of the smoke detectors relative.to air flow

-

in the safeguard building (Elevation 773 feet), in the containment spray pump

rooms, residual heat removal pump rooms, and the safety injection pump rooms.

The automatic smoke detectors were installed in all of the above pump rooms

.

and these rooms contained self-contained chiller units which start coincident

with the actuation of the respective pumps. The smoke detectors were

installed on the ceiling above the chiller units. Once the chiller starts,

t

the resulting, airflow is predominately through the chiller, with the supply

air discharging from the bottom of the unit onto the pump motor.

When the

chiller is operating, the ceiling airflow pattern appears to be stagnant.

This condition could cause a delay in early detection of a fire condition if

this event were to occur during those times when the pumps were operating.

s

In response to this issue, the licensee performed an evaluation which

identified the Unit 2 plant areas where heating, ventilation, and air-

conditioning airflows could affect the detection system.

The purpose of the

review was to identify areas where detectors could be adversely impacted due

,

to proximity to air diffusers and excessive air flow due to spot coolers.

This. evaluation identified several vulnerable areas in the Unit 2 safeguards

~

building. As a result of this evaluation, the licensee has committed to

.

i

relocate five existing detectors and add four additional detectors.

This

commitment is provided in Attachment 3.

Based on the licensee's evaluation and the referenced commitments, this

inspection followup item is considered closed.

1.8 (Closed) Inspection Followup Item 446/9249-08:

Completion of Fire

i

Barriers and Seals in Fire Area 2SA and 2SB

l

This item involved the completion of the fire area barrier separating Fire

r

l

Area 25A from 2SB.

Specif'cally, the penetration seals associated with.this

fire barrier had not been completed at the time of the initial inspection.

'

,

l

1

..

.

-12-

t

During followup inspections, the team walked down the subject fire barrier and

confirmed that the penetration seals had been completed. The team also

reviewed the completed work package for the fire barrier. The inspector

determined that the penetration seals were installed in accordance with the

established procedures and that the licensee's corrective actions

'

appropriately addressed the identified issue.

Based on the inspector's

review, this inspection followup item is considered closed.

1.9 (Closed) Unresolved Item 445:446/9249-09:

Fire Sprinkler Head Selection

The licensee has installed automatic fixed water fire suppression systems in

safety-related areas of the plant where a high fire hazard exists, where

redundant safe shutdown equipment or cabling outside the containment building

is located in the same fire area and is not separated by a 3-hour fire

barrier, and where there is a congestion of cabling (e.g., tray stacks of four

trays or more).

During the plant walkdowns conducted as part of NRC Inspection

Report 50-445/92-49; 50-446/92-49, the inspectors noted that the sprinklers

installed at ceiling level throughout the plant had a thermal actuation

setpoint of 212 F.

The inspectors noted that all the plant areas, provided

with sprinkler protection, were air conditioned. The inspectors viewed these

plant areas as having an average maximum ceiling temperature of 75-90oF with

an environmental profile similar to that of a typical air conditioned

commercial building. Under these conditions, the guidance of National Fire

Protection Association (NFPA) 13, recommends that, for ceiling temperature

'

less than 100oF, the sprinkler temperature actuation setpoint should be in the

range 135 F to 170 F.

The inspectors reviewed the Unit 2 Environmental Data Sheets

'

(Drawings M2-3000, Sheets 3, 4, 5, and 6, " Environmental Data Outside the

Containment"), which indicated that the maximum peak ceiling temperature for

the general areas outside the containment in the safeguards building was

104*F.

Using this temperature data, the licensee indicated that the guidance

-

of NFPA 13 for the selection of the temperature ratings for the sprinkler

heads recommends the use of sprinklers with an actuation actuation setpoint in

the range 175of to 225cf.

t

'

The licensee's use of 212 F rated sprinklers yields an actuation threshold of

108 F as compared to a 61 F actuation threshold for the 165of rated sprinkler

which would be used in a commercial building under similar conditions.

Fire development conditions, based on the type of combustibles present in a

nuclear power plant, is considered to be slow.

Under such conditions, due to

the increased thermal energy required to activate the 212 F sprinklers, the

inspectors were concerned that an increase in fire damage and fire

'

temperatures could be expected.

In addition, the inspectors were concerned

that the 212 F thermal actuation setpoints for the sprinklers installed at

i

significant distances below the ceiling (e.g., intermediate level sprinklers)

would cause delays in sprinkler response.

,

.

.

-

_- .

-13-

,

i

In response to these concerns, the licensee performed an independent

engineering evaluation (ER-ME-080, Revision 0). The scope of this evaluation

I

assessed the thermal response of the type of sprinkler heads (Grinnell Model F

.

950) installed within the facility. This thermal response analysis' considered

.

the Response Time Index for the Model F 950 sprinkler head.

The analysis

determined, for a recm with a 20-foot ceiling height, the minimum fire heat

L

release rate which would be required to actuate a ceiling level sprinkler.

The minimum heat release rate required to achieve the sprinkler actuation

temperature was based on a 5-minute fire duration.

The analysis indicated

that a fire with a minimum of 1300kW heat release rate would be'requireo to-

actuate a 212 F Model F 950 sprinkler head.

To place this in perspective, a

i

lube oil pan fire of approximately 5 square feet would develop 1300kW.

The licensee, to augment the ceiling level sprinklers, has provided automatic

fixed cable tray suppression systems in areas where cable congestion is

present.

This cable tray suppression coverage is an extension of the

,

sprinklers provided for area coverage.

The current layout of these systems,

for horizontal tray stacks, has the nozzles arranged in a " vertical stand-off"

t

fashion, spaced 6-12 int' s away from the tray side rails.

The nozzles are on

only one side of the tra: stack and are offset 6-12 inches above the

horizontal plane of th , rays.

In addition, the top of the tray is protected

!

by nozzles positioned 9v2r the mid-line of the top tray. These nozzles are

provided with baffles.

These baffles have a dual function in that they

prevent " cold solder" effects and act as a heat collector to improve the

nozzle actuation time.

The licensee's design basis for these systems is to

confine a fire to the congested tray array. The licensee applied certain

aspects of NFPA 15, " Water Spray Fixed Systems For Fire Protection," to the

'

'

design of the cable tray suppression systems. The licensee indicated that

they designed these systems to apply a water spray application density of 0.15

gpm per ft".

The table water spray nozzles have an actuation setpoint of

175of.

If a fire were to occur within a bank of cable trays protected by the

witer spray system, the expected response would be as follows:

as the fire

transitions from a smoldering to a flaming phase the heat generated by the

fire plume would be collected by the water spray _ nozzle baffle; this baffic,

i

acting as a heat collector, would collect the heat in the fire plume and

'

direct the heat towards the water spray nozzle fusible actuation element; and

finally, based on the design and layout of these cable tray water spray

systems, the upper level nozzles would react firs * to the fire condition to

,

provide a water spray on the cable trays.

The inspector, after reviewing

4

these systems during plant walkdowns, found them adequate to control a cable

-

~

tray fire.

l

.

Reviewing the Comanche Peak Unit 2 fire protection program from a " Defense-in-

Depth" fire safety perspective, the inspector found the plant areas that were

inspected to ha,' the appropriate levels of early warning fire detection

coverage, adequats distribution of manual fire fighting equipment, fire

i

barriers applied to one train of safe shutdown systems, and the appropriate

"

level of automatic fire suppression coverage to assure prompt mitigation of an

-

3

in plant fire condition.

In addition, the plant has administrative control

~

measures established that control transient combustible and ignition sources

i

i

.

_

_

_

._.

I

-14-

'

and has a fully trained onsite fire brigade.

Looking at.the overall level of

fire protection, even if a slow developing fire were to occur in a plant area

and was not sufficient to generate enough thermal energy to activate the

sprinkler system, the smoke generated by the fire would be detected by the

early warning fire detection devices in the area and the. appropriate fire

.

control and suppression actions will be initiated by the fire brigade.

Therefore, this issue is closed for Units 1 and 2.

'

l.10 (Closed) Inspection Followup Item 446/9249-10:

Physical Obstructions to

Sprinklers

This item involved physical obstructions to the ceiling level sprinklers in

Fire Area 2SB4 due to the presence of cable trays; piping; and heating,

ventilation, and air conditioning ducting. As a result of this issue, the

licensee initiated an engineering walkdown of the affected plant sprinkler

,

systems.

This walkdown focused on the evaluation of obstructions to

.

- sprinklers and their impact on the sprinkler system's ability to apply water

directly to a fire.

The licensee's engineering evaluation identified six areas in Unit ? which

,

required 316dditional sprinkler heads and the relocation of 10 sprinklers due

to equipment obstructions.

These areas are listed in Attachment 4.

.

The licensee also initiated modificailcn packages to correct the physical

obstructions of the sprinklers. As documented in Attachment 3, the licensee

'

committed to complete these modifications by the end of the first refueling

outage. Based on the licensee's stated commitment to modify the sprinkler

system, it was determined that appropriate corrective actions had been

.;

developed to address the identified concern and this inspection followup item

is considered closed.

]

1.11

(Closed) Unresolved Item 445:446/9249-11. Essential Chiller Room Water

Curtain Desian

r

'!

The Unit l 2 essential chiller area deviates from the requirements of Appendix.R

and the deviation had been approved by the NRC staff.

The chillers and pumps

,

are separated by partial height 1-hour equipment fire barrier walls.. During.

the plant walkdown, the wall was verified to extend above and along the entire

length of the chiller units.

The licensee, as part of their fire' protection

'

enhancements, has installed curbs from where the. chiller pump partial wall

terminates to the wall of the room. These curbs are installed to preclude a

combustible liquid spill fire from impacting both chiller pumps.

In addition,

l

- the licensee has installed additional smoke detectors in this area to enhance

their ability to rapidly detect a fire conditionan this area. .In the

-

overhead of this room, cable. trays _ transverse the area.

These trays are an

intervening combustible hazard to redundant' chillers and their: associated

pumps. -In order to preclude fire propagation, caused by an electrically

originated fire along these trays, the ' licensee has installed fire stops in.

the trays at the vertical extension plane of the walls.

The intent of these

3

stops is to preclude fire propagation along the tray so that a tray fire.

,

,

r

v

.

.

.

.

.

m

.

,

.

-15-

presents an exposure to only one chiller or pump. The chiller area is

protected by area wide sprinklers installed at the ceiling level.

In

addition, the licensee has installed a water curtain.at the vertical extension

plane of these partial height walls. This water curtain consists of closely

spaced fast response sprinklers (212 F) designed to apply a discharge rate of

3 gpm/ linear foot of curtain length.

The inspector reviewed portions of

Design Change Notice 4338, Revision 3, and could.not confirm the use of draft

stops. The inspector was concerned that, without the installation of-draft

stops to collect heat in the area of the water curtain ceiling level

sprinklers, the actuation.of the curtain would be delayed in the event of a

fire in the area of the fire barrier walls.

During the inspection effort performed as part of NRC Inspection

Report 50-445/92-49; 50-446/92-49, the inspector could.not perform a full

assessment of the water curtain and assess its ability to perform its fire

protection function because of the construction activities (e.g., scaffolding)

in the essential chiller room.

h addition, the inspector reviewed the

licensee's Engineering Report ER-ME-080, Revision 0, " Assessment of Fire

Protection Features for Separation of Unit 2 Redundant Safety Related Chiller

Components." As part of this assessment, the inspector performed a walkdown

of the chiller area to review the placement of the water curtain and.the

ceiling level sprinklers in the area of the partial height fire barrier.

The

inspector confirmed that the water curtain heads were at ceiling level with a

level of fast response heads installed under cable tray obstructions.

The

ceiling level water curtain fast response sprinklers are spaced every 6 feet

across the ful.1 width of the room directly over the partial height fire

barrier walls.

In addition, the inspector noted the layout of the beam

pockets at the ceiling elevation.

The ceiling of the chiller room has.

30 x 60 beams running across the width of +he room. The location of these

beams has created a beam pocket over the chiller pumps and two beam pockets

nyer the chiller equipment. The significance of these beam pockets 'is that

they will aid in the collection of heat in the ceiling area directly over the

fire and will improve the response of the ceiling level' area and the water

curtain fast response sprinklers.

For example, if a fire were to involve a chiller pump, the fire plume would

develop and heat wnuld spread across the ceiling and be collected within the

beam pocket directly over the pumps.

The fire barrier wall between the' pumps

would preclude direct fire exposure to the redundant chiller pump until the

water curtain fast response and ceiling level area sprinklers reacted to the=

fire condition.

Based on the type of sprinklers used for the water curtain -

it is anticipated that they will respond to the fire condition prior to the

actuation of the ceiling level sprinklers.

The inspector's assessment of the

fire protection features provided 'for the Unit 2 essential chiller. area finds

these features to provide an adequate level of protection which will assure

that a fire would te mitigated and the potential fire damage would be limited

i

to one train of essential chillers.

The inspector was also concerned that sprinklers over the redundant chiller

i

pump, which is not on fire, could actuate and impact the operability of this

____

'

-16-

!

pump. The licensee's analysis of inadvertent or advertent effects of

sprinkler actuation indicated that all essential equipment associated with the

operation of the chillers are enclosed in NEMA Type 12 cabinets and the

chiller pump motors are fully enclosed.

In addition, the licensee's analysis

1

indicated that water shields have been 'provided on the tops of essential

electrical control panels and cabinets, and the conduit entrances to these:

panels and cabinets are sealed.

Considering the potential accumulation of

water on the floor of the chiller room as a result of fire suppression

i

discharge, the essential equipment has either been installed on concrete pads

,

sized to accommodate the postulated flood levels or the equipment is mounted

in such a manner that it is above the flood level.

In addition to the normal

.

floor drains, the essential chiller room is provided with eight 6-inch

diameter flood mitigation drain lines installed at the floor leve1~.

Based on

,

the review of the licensee's analysis, the inspector found the measures the

.

'

licensee has taken to mitigate the affects of fire suppression water discharge

on the essential chiller water system components to be adequate.

'

The water curtain feature was found not to be utilizea in the Unit 1 essential

chiller area. Accordingly, the unresolved item is closed for Units 1 and 2.

1.12

(Closed) Inspection Followup Item 445:446/9249-12: Missing Ceilina

Tiles

This item involved missing ceiling tiles around the smoke detectors in the

control room behind the horseshoe area.

The licensee indicated that the

ceiling tiles Jiad been removed in order to assure the seismic qualification of

'

the control room suspended ceiling.

Initially, the team could not conclude

that the smoke detectors in their current configuration would provide rapid

,

detection of a fire in the back panel arer in that smoke from a postulated

fire could flow through these openings in the ceiling and bypass the

,

detectors.

As a result of this concern, the licensee performed-a walkdown of the system

,

and developed a technical evaluation which addressed this issue.

This

-;

evaluation established that the at ea above the suspended ceiling in the

control room has full-area detection coverage.

Furthermore, this evaluation

.

concluded that., although ceiling tiles were missing in~ the suspended ceiling.

- 5

of the control room, the fire detection adequacy in the control room was

maintained due to full-area coverage at the structural ceiling level.

The

team walked down these areas to confirm the installation of the smoke

detectors at the structural ceiling level in the control room.

Based nn these

field inspections, it was determ,ned that the fire detection coverage was in

'

accordance with the requirements of National Fire Protection

Association (NFPA) 72-E. criteria.

Accordingly, this issue is closed for

.l

Units 1 and 2.

+

1.13 Tracking of Commitments

Inspection Followup Item 445;446/9308-02 is opened to track the licensee's

- commitments made with respect to completion of the high impedance fault study

!

t

>

-17-

,

,

>

and hardware modifications for Unit 1; implementation of hardware

l

modifications to prevent fire induced failure of safe shutdown MOVs; upgrading

of safe shutdown emergency lighting batteries; additions and relocations of

sprinkler heads; the dedication of ladders and tools. required to support

l

Procedure ABN-803B; completion of preventive maintenance procedures on

'

100 percent of emergency lighting prior to Mode 4 operations; and completion

of the engineering analyses for untested Thermo-Lag configurations.

These

commitments are docketed in licensee correspondence ~ dated December 23, 1992,

and January 15, 1993. This correspondence is provided as Attachments 2 and 3,

respectively.

i

1.14 (Closed) Inspection Followup Item 445:446/9225-03:

Failures of

'

Thermo-Lao Configurations

,

This inspection followup item was identified to track test failures of

,

particular Thermo-Lag fire. barrier configurations.

Based on the discussion in

S:ction 2.0 below and that found in Supplement 26 to NUREG 0737, " Safety

Evaluation related to the operation of Comanche Peak Steam Electric Station,.

Units 1 and 2,"

SSER 26, Section 9.5.1.5, this item is closed for Units 1 and

2.

f

l 15 (Closed) Inspection Followup Item 446/9227-01:

Installed Thermo-Laq

which Deviates from Tested Configurations

Field verification of Thermo-Lag installations by inspectors revealed

installed Thermo-Lag applications which did not conform to tested

configurations.

Based on the discussions in Section 2 below, SSER 26,

Section 9.5.1.5, and the licensees commitment provided in Attachment 3, this

r

item is considered closed.

,

2 THERMO-LAG l-HOUR FIRE BARRIERS

l

During this inspection, an assessment of the licensee's procurement, testing,

.;

engineering, installation, training, and quality assurance activities

'

associated with the use of Thermo-Lag as a fire barrier system was performed.

i

The details are provided below.

2.1

Procurement of Thermo-Lao Fire Barrier Materials

The inspectors reviewed the licensee's Thermo-Lag' fire barrier material

,

procurement process. The licensee's program is controlled by Appendix A,

" Receipt, Dispensing, Quality and Inspection Requirements for Thermo-Lag Fire

,

Barrier Meterials," to Procurement-Specification 2323-MS-38H.

This document-

J

contains the_ receipt inspection / verification criteria imposed on_this

material. This document require's that- QC receiving verify the weight / density -

l

(lbs/ft') checks of Thermo-Lag panels and conduit preshapes.

In addition,

>

this document specifies the minimum weight / density values acceptable for

panels and the various conduit preshapes sizes.

Procurement

Specification 2323-MS-38H requires QC receiving to verify the following:

material thickness; no holes or cracks exist in the material wider than

.

.

. _ - _

_

.

.

_

_

. _ _

l

i

-18-

1

0.05 inches; no holes or cracks exist in the material that extend through the

material to the stress skin; and no signs of visible damage (i.e., gouges,

breaks, tears, etc.).

From the Thermo-Lag material. physical verification

information contained in Specification 2323-MS-38H, Appendix A, Procurement

,

Engineering developed Pre-Engineering Item Data Sheet (PEIDS) for Thermo-Lag

!

fire barrier material (PEIDS NES00ll). This document contains the physical,

weight / density, and condition criteria to be followed by the procurement QC

- '

personnel performing these inspections.

The inspector verified that the QC

inspection criteria established by PEIDS NES0011 was consistent with the

material physical attributes specified by Design Specification, " Procurement

,

and Installation of Fire Barrier and Fireproofing Materials," CPES-N-2032.

,

The licensee, when purchasing the Thermo-Lag fire barrier material, issues a

,

purchase order (PO) to Thermal Science, Inc. (TSI), the manufacturer of

Thermo-Lag fire barrier material .

The P0 specifies the fire barrier materials

,

.

needed.

Once the material has been manufactured and is ready to ship, TSI

notifies the lictasae that the commodities requested by the P0 are ready to be

,

'

released. Upon receiving this notification, the licensee sends a QC

representative to TSI's manufacturing facility in St. Louis, Missouri, to

l

,

perform QC Verification Plan (VP) VP-NES0011-03, " Source Inspection

Verification Plan - Thermo-Lag Fire Barrier Materials," prior to shipment.

This VP verifies the thickness, weight / linear density, condition of the

material, and the material moisture content of the shipment.

Once the VP has

-

been satisfied, the TU Electric QC representative signs off on the

!

authorization-releasing the material for shipment.

.

'

Upon receipt of the TSI shipment at the licensee's facility, the licensee

performs Verification Plan VP-NES0011-02, " Receipt Inspection Verification

,

Plan - Thermo-Lag Fire Barrier Materials." This VP verifies the part

number / identification of the material, performs a general receipt inspection

of the material, performs a review of the material to determine if the items

,

being received are substandard or fraudulent, and verifies that the quality

l

!

authorization to ship is traceable to the PO for the material in the shipment.

"

'

Once the fire barrier materials have satisfied the requirements' of the receipt

inspection VP, the material is released to the warehouse.

,

I

The inspectors reviewed the traceability of the following Thermo-Lag related

.'

l~

P0s and confirmed that the required source and receipt inspections were

'

properly documented by the licensee:

'

l

Purchase Orders

1

B0028658-014

!

i

80029659-008

l

B0028659-010

B0029659-014

"

L

B0029659-015

.

B0029659-016

!

B0029659-017

l

S0056079-705

j

i

.

U

I

l'

~v

h

. ~ . . . . ,

. -

- - - - . .

- - - - - -

. .

- -

. - .

- -

L------ -

. -

. .-O

-

-19-

The shipments which were made to Omega Point were made under a Return Material

Shipping Order (RMS0). An RM50 is required by the licensee's procedures to be

-comp e el t d whenever a commodity is removed.from stock as result of being

rejected by the receipt inspection or as result of being shipped off site for

use at another facility. The inspector confirmed that the' licensee issued.an .

RMSO for those commodities which were shipped to Omega Point.

In addition,

the inspector confirmed by reviewing the above sampled P0s and VPs that the

Thermo-Lag Shipments made from Comanche Peak to Omega Point.were source land

receipt inspected using the same inspection criteria as those procured under-

P0s for Thermo-Lag used to construct the Unit 2 fire barrier assemblies. The

inspector, based on the documentation reviewed, did not identify any concerns

or discrepancies with regard to the traceability and source and receipt

inspection of fire barrier material used by the licensee in the construction

of the fire test specimens and the Unit 2 fire barrier assemblies.

'

2.2 Trainina for Thermo-Lao Installers / Craftsmen / Field / Construction Enoineers

The licensee has established a specific training program for individuals

involved with the installation of Thermo-Lag material for Unit 2, which is

defined in CPSES Unit Procedure for Project Trainity Program 2PP-1.16,

Revision 2, dated February 27, 1992.

This program requires craftsmen, field

.*

engineers, construc. tion engineers, foremen, and superintendents involved in

the Thermo-Lag installation process to be trained.

1

Specifically,,this procedure established -the responsibilities for trainine the-

construction personnel involved in the installation of Thermo-Lag at Unit 2.

The construction training department for Unit 2 is responsible for developing

and scheduling the training. The installation of Thermo-Lag material is being

performed by the craftsmen employed by Peak Seals, Inc. (contractor for

TV Electric).

.

The inspectors reviewed the lesson plans for both classroom training and :

practical training.

The team also reviewed the training records of

30 randomly selected individuals.

This review indicated that the individuals

were trained and qualified in accordance with the established procedures.

'

However, one item of concern was identified by the team during the review of

,

completed work packages. The team noted that- Figure 7.10,. Electrical QC

Inspection Checklist, Item 1.a (Block 7, CQP 213), .was _ signed by a Peak Seals-

!

i field engineer when no physical work was required.

Additionally, as a result

i

of the review of completed work documents, it was determined,that open/ blank-

blocks existed. - As stated by the licensee bec'ause of' the interpretation of

!

the Revision 2, Procedure CQP-213, " Construction Quality Procedure,"

requirements, a collective decision was made to sign the' subject attribute in

j

lieu of leaving it $ lank. . Additionally, as stated by the licensee, the

.,

appropr; ate person to sign _for this activity was the individual; requesting the

inspection.

As determined.by the inspectors, in the majority of instances

j

.

this individual was a Peak Seals field engineer.

Additionally, this signature-

'

was backdated into all. in-process packages without including an explanation

regarding the backdating of signatures, when no actual work was performed.

,

.'

However, CQP-CV-107, " Construction / Quality Documentation Preparation Use,.

,

'

d

tw

.

~

..

.

,

P

l

l

,

-20-

3

i

Control and Review," Attachment 8.C, " Checklist -Instructions" for installation

,

craft, Block 7, states, in part, do not sign attributes which have not had

'

work performed.

The inspectors noted that, generally, this block has been

signed by Thermo-Lag contractor personnel even when no physical work.was

!

required or performed.

In response to this issue, the licensee promptly

issued Operations Notification Evaluation Form 93-127 to resolve the

deficiency.

The licensee also issued a procedure change notice to CQP-213 to

clarify actions required when no field work was required or performed.

The

licensee also initiated supplemental training for appropriate personnel to

1

'

clarify the process change regarding checklist blanks /open blocks.

Specifically, Block 7 shall remain open and no signatures are required when no

work is performed. Alternatively, an

"X" through the block- may be placed by

the Peak Seals field engineering or closure group personnel when processing

'

the work packages. A copy of this procedural change is to be inserted into

all Thermo-Lag Construction Work Documents (CWDs) during the closure process

and will be backfit into all previously vaulted packages. Although'not a

regulatory issue, the inspectors concluded that the procedure changes and

other actions taken by the licensee adequately addressed this concern.

,

2.3 Quality Assurance and Control

!

The inspectors reviewed with the licensee the quality assurance and quality

control aspects of the installation of Thermo-Lag.

Attributes and acceptance

standards are incorporated in each work package as check lists from the

installation procedure. The contractor responsible for Thermo-Lag

,

installation provides the first two levels of quality control with the craft

i

supervision and the contractor's quality control inspectors.

In. process

j

inspections are documented on the check lists in the official copy of- the CWD. .

The licensee provides an equivalent level of quality control on a continuous

monitoring basis.

The effectiveness of the licensee's multi-level QC program was demonstrated

i

when, in October 1992, unacceptable voids and delamination 'in Thermo-Lag 330-1

conduit sections for both 2- and 3-inch conduit were identified during .the

installation process.

The void formation was apparently caused by failure-of.

1

the manufacturer, TSI, to fill the. longitudinal stress cracks caused during

,

normal fabrication with Thermo-Lag. 330-1 trowel grade material in accordance

i

with TSI procedures. The delamination was apparently caused by TSI personnel

attempting to correct a material thickness problem.

Both conditions appear to

have originated from the conduit .section forming process.

This process,.which.

i

shapes Thermo-Lag 330-1 flat panel stock into half-round sections,. inherently

'

results in the development of cracks along the entire 3-foot _ length of each-

conduit section.

The subject samples displayed inspection marks from the TSI

in-process quality control monitoring, indicating that localized thinning-

i

along the sections had been detected and required trowel grade buildup in

'

accordance with TSI procedures.

This thinning was apparently aggravated by

.the original flat panel fabrication process.

The buildup' material apparently-

,

>

did not adhere to the base material during the curing process and attempts to-

"

correct the delamination resulted in the use of staples'along the mating. edges-

,

- _ _ _ _ _ _ __ _ _ _ _

_ . _ _ _

-21-

of the " cap" layer. Neither of these in-process corrective actions were in

accordance with the manufacturers procedures.

The licensee stopped all conduit section installation and proceeded to conduct

a thorough and comprehensive inspection and evaluation of all suspect

material. This effort covered all material not installed on site, material

that was in-process with TSI, and material at Omega Point Laboratories, the

test facility at wi.ich the licensee's fire tests were conducted. The licensee.

also conducted a visit to TSI to discuss corrective actions necessary to

prevent recurrence. TSI agreed to continue the improved flat panel forming

process and insure that procedures reflected the approved processes only.

TSI

personnel were reinstructed in the approved procedures. The licensee

established source inspection activities at the TSI site whereby TU Electric

source QC personnel are authorized to overview TSI's process for repair of

longitudinal cracks during forming of conduit sections.

The licensee, in conjunction with TSI, determined that the material affected

by the void, cracking, delamination, and stapling concern was limited to two

lots of prefabricated conduit sections.

The majority of the affected lots was

accounted for and was not installed. Any affected conduit sections that may

have been installed in Unit 2 were considered to be acceptable by the

licensee.

The basis for this determination was that representative samples of

the affected 2- and 3-inch conduit sections were satisfactorily tested at

Omega Point Laboratories.

Further discussion of fire barrier testing is found-

in paragraph 2.4.1 and Attachment 5.

The licensee's QA group provides broad programmatic oversight and periodic

installation inspections that are documented in QA audits.

The inspectors

reviewed a sample of the QA/QC documentation a )d confirmed that the licensee

has an effective in-process Thermo-Lag installation QA/QC program,

f

1

2.4 Thermo-Lag Fire Barrier Design and Installation Process

The inspectors observed the installation of Thermo-Lag 330 fire barrier

material on conduits and cable trays.

These observations were made on

October 13 and 21, 1992, and January 7, 1993.

Observations were also-made by

the resident inspectors and documented in NRC Inspection Reports 50-445/92-34;

50-446/92-34 and 50-445/92-42; 50-446/92-42.

The purpose of.these

observations was to determine if the installations conformed to the

fabrication practices developed during test specimen construction for the

I

licensee's sponsored fire tests.

Installation was found to be in accordance

I

with Procedure CQP-CV-107, " Application of Fire Barrier and Fireproofing

Materials," Revision 0, dated January 6, 1992, and Orocedure Change Notice 1

through 5, as well as Specification CPES-N-2032, "P ocurement and Installation

u

of Fire Barrier and Fireproofing Materials," Revision 0, dated February 28,

'

1991, and DCA 95794.7.

These procedures were found to be maintained up to

date with fabrication improvements identified during test specimen

I

development. To confirm the correlation between the test. specimen fabrication

l

techniques and the installation procedure and specification, the NRC

l

lp

i

______ _ _2_-______-___-___-_

_ . _ _ _ _ _ _ _ - _ _ _

_

__

-

,

-22-

,

,

!

inspectors also observed test specimen construction and fire endurance testing

activities at Omega Point Laboratories in San Antonio, Texas.

.

-

In addition to witnessing the licensee's test specimen construction and fire

testing activities at Omega Point Laboratories, the inspectors reviewed the

programmatic aspects of the CPSES, Unit 2, Thermo-Lag fire barrier design and

installation process. The inspectors, as part of this inspection process,

reviewed selected TU/0mega Point Thermo-Lag' fire barrier fire-endurance test

reports, the licensee design and installation specification, the licensee's

-

construction and installation procedure, and selec,ted Thermo-Lag fire barrier

j

installations and their associated installation work packages. The_ inspection

of the' field installations consisted of assuring that the work packages

3

reflected the programmatic process and that the construction attributes were

^

consistent with the design and construction criteria established by the

licensee's fire testing program. The following summarizes the areas

inspected:

' '

2.4.1 Fire Tested Configurations

!

The inspectors reviewed the construction attributes of the Thermo-Lag-fire

barrier test specimens described below to determine if they were properly

incorporated init the design and installation of the fire barrier. systems

- '

installed in Unit 2.

The following summarizes fire test reports reviewed:

Omega Point Project No. 12340-94367a, Scheme 9 - Assembly 1, Fire

Endurance Test of Thermo-Lag 330-1 Fire Protective Envelope (3/4-inch,

3-inch, and 5-inch Conduits with Radial Bends) November 23, 1992.

Omega Point Project No. 12340-94367c, Scheme 10 - Assembly 1, Fire

'

Endurance Test of Thermo-Lag 330-1 Fire Protective Envelope (Two 3-inch

Conduits with Junction Boxes) December 2, 1992.

Attachment 5 provides details of the inspector's review of the test ~ reports.

>

Using the test specimen design and installation descriptions'.documentsd in the-

'

subject test reports and verified by the supporting-QA/QC documentation, the

inspectors reviewed the licensee's design and installation specification to-

confirm that the design and construction attributes. verified by-the licensee's

'

fire endurance testing program were being properly implemented -into the design

and installation of the Unit 2 Thermo-Lag fire barrier' assemblies.

The

inspectors found that the attributes had been properly translated into the

licensee's design and installation _ procedures.

The adequacy of the licensee's

'

-fire test reports to qualify the Thermo-Lag fire barrier systems being

installed in Unit 2 is being evaluated by the Office of Nuclear Reactor

P,egulation and will be addressed in SSER 26.

.

.

2.4.2 Fire Barrier Design Specification

The inspectors reviewed Unit 2 Specification CPES-M-2032, " Procurement and

. Installation of' Fire Barrier and Fire Proofing Materials," to determine thatL

,

a

w

w

.

_.

-

_ . -

-

-

-

.

.

-23-

the design and installation attributes, confirmed by the fire testing of

Scheme 9 - Assembly 1 and Scheme 10 - Assembly 1,-were properly incorporated

into the scope of this document.

Section III of the specification contains

the material and installation reouirements for the Unit 2 Thermo-Lag fire

barrier assemblies.

The inspectors confirmed that the appropriate design and

i

installation criteria, consistent with the criteria established by the testing

program (Scheme 9 - Assembly 1 and Scheme 10 - Assembly 1), were incorporated

.i

into this document.

For example, Section 3.2.5.2 to CPES-M-2032, requires the

3/4-inch preshape overlay to be applied over the 1/2-inch conduit fire barrier

,

4

preshape on 3/4-inch, 1-inch, 1 1/2-inch, and 2-inch conduits.

In_ addition,

i

this section specified the appropriate precaulking considerations and-.

)

consistent methods of fastening the conduit fire barrier assemblies in place.

The inspectors also confirmed that the appropriate design and installation -

'

attributes tested by Scheme 9 - Assembly 1 and Scheme 10 - Assembly 1, for the

radial bends, lateral bends (LBDs), and junction boxes (JBs) were incorporated

'

into this specification.

Section 3.2.5.4 to CPSES-M-2032 addresses the design

'

,

and installation of Thermo-Lag fire barrier material on radial bends while

,

Section 3.2.5.7 addresses the design and installation of Thermo-Lag fire

,

!

barrier assemblies for LBDs and JBs. The inspectors found these design and

installation attributes specified by the subject specification sections to be

consistent with those used for design and installation of the fire barrier

assemblies on fire test specimen Scheme 9 - Assembly 1 and Scheme 10 -

,

Assembly 1.

.,

In addition, to the design specification, the inspectors reviewed the

engineering drawings associated with the design and installation of the

'

Thermo-Lag fire barrier materials.

The drawings reviewed were the M2-1701

series (Sheets 1-15).

These drawings identified the typical details

associated with the installation of the harriers.

Attachment 6 provides a

summary of the typical details contained on these drawings.

!

,

The licensee has issued approximately 270 DCAs against these details.

DCAs

are issued by design engineering to provide a design detail which addresses a

i

field installation condition which cannot be implemented through the

application of one of the typical installation details.

The inspectors

reviewed a sample of these DCAs to determine if they applied the required

i

design and installation attributes required by the licensee design and

installation specification. The discussion of this review is contained in

Section 2.6.

2.4.3

Fire Barrier Installatis , Procedure

,

In order to implement the design and installation criteria specified by Design

' '

Specification CPES-M-2032, the licensee established Construction / Quality

Procedure CQP-CV-107, " Application of Fire Barrier and Fire Proofing

';

Materials." This procedure establishes the instaliation instructions used by-

installers and QC. inspectors to construct and verify that the Thermo-Lag

raceway fire barrier assemblies were installed properly and that the

construction attributes associated with these barrier systems were done

-

consistently and in a similar manner to those methods use to construct the

i

,

i

..

.

-

. . -

- - - - -

.

.

.

L

.

.,

-24-

,

fire test assemblies.

The inspectors reviewed Section 6.4 to CQP-CV-107,-

4

"Thermo-Lag 330-1 Applications for Cable and Raceway," to verify that the

design and construction criteria established by Design Specification

-

CPES-M-2023,. as supported by fire tested configurations Scheme 9 - Assembly 1

,

and Scheme 10 - Assembly 1, were incorporated into this procedure. The-

,

inspectors verified that Section 6.4.4. A has the special requirements for

installing Thermo-Lag on conduits, fittings, and JBs and found the

'

installation criteria established by Section 6.4.4.A to be consistent with the.

criteria established by Sections 3.2.5.2, 3.2.5.4, and 3.2.5.7 to Design

Specification CPES-M-2032.

'

'

In order to assure that the Unit 2 Thermo-Lag raceway fire barrier systems are

being installed in accordance with the installation criteria specified by

>

Installation Procedure CQP-CV-107, this procedure establishes the use _of _

-

checklists which are followed by the craftsmen performing the installation-and .

used by QC to verify that the installation is being installed in accordance

i

with the applicable sections of the installation prc edure. The. inspectors

confirmed that the major construction considerations and attributes of.these-

fire barrier assemblies were properly identified by the checklists.

Specifically,_the inspectors reviewed Procedure CQP-CV-107, figure 17.13,

"Backfit Verifications for Conduit - Checklist," and Figure.17.16, Thermo-Lag

330-1 Application on Conduit - Checklist."' The inspectors found these

checklists to provide the necessary inspection attributes which would

establish the basis for determining that the installed fire barrier design

conformed to the installation . criteria established by Procedure CQP-CV-107.

)

a

2.5 Fire Barrier Installation Work Packages

!

,

The inspectors toured Unit 2 to review the ongoing installation of Thermo-Lag

fire raceway fire barriers.

During this walkdown, the inspectors selected a

.

sample of protected raceways which had the Thermo-Lag fire barrier material

- !

installed to review the fire barrier installation documentation.

The inspectors found that the appropriate installation checklists were

t i

^

contained in the CWD packages and that the packages containeo. sufficient

detail to facilitate the implementation of the work by the craft.

In

,

addition, for those installation configurations which deviated from the

standard construction and installation guidance provided by-

'

Procedure CQP-CV-107, the inspectors verified that these packages-contained

the appropriate DCAs.

As part of the construction process: associated with _

.

'

- each installation, QC performed a surveillance of the installation while work:

was in progress.

These surveillance activities were performed daily and were

- found appropriately documented.

In addition, any rework resulting from these

QC surveillance activities was. identified and documented. A summary of fire'

barrier installations inspected, applicable components, and CWDs reviewed;is

provided as Attachment 74

From these visual inspection, the inspectors could verify that certain

'

upgrades as required by Installation Procedure CQP-CV-107 and design and

,

-Installation Specification-CPES-M2032 had been implemented. On the multitray!

[

't

i

t

_,

.9

,

, _ _ . .

.

.

h

-25-

and the two-tray configuration, the inspector was able to verify that the

seams and joints were upgraded with stress skin and properly skim coated with

trowel grade material.

On the JBs inspected the inspectors could verify that

the corners and joints of these boxes were upgraded with stress skin.

The

inspection of the conduits (1 1/2-inch) in the Unit 2 essential chiller room

and on Elevation 832' of the safeguards building visually verified that these

conduits were upgraded with the required overlay.

This was done by evaluating

the diameter of the fire barrier material applied to conduits.

From this

limited visual inspection of the fire barrier assemblies identified in

Attachment 7, the inspectors found that the upgrades required by the

licensee's installation procedure and design specification were being-

implemented.

2.6 Fire Barrier Deviations and Special Configurations

The inspectors sampled conditions where the fire barrier installations

dc'/iated from the conditions of the licensee's fire test program, the design

,

and' installation procedure, and the installation procedure.

The. licensee

documents these deviations by issuing a DCA against the field condition which

deviates.

The DCA identifies the fire barrier installation problem and

.

,

provides the design detail and the applicable installation guidance to resolve

the problem.

In addition, the DCA provides the engineering basis for the

change and assesses the impact of the change on the fire rating of the

commodity being protected by the Thermo-Lag fire barrier material.

The

inspectors reviewed the DCAs listed in Attachment 8 to determine if the

licensee considered the fire barrier upgrade attributes and if the fire

barrier design considerations specified by the design and installation

specification were applied in the resolution of these fire barrier deviation

conditions.

From the DCAs reviewed the inspectors found that, as fire barrier design

- '

configurations are being. qualified by the licensee's Thermo-Lag fire Sarrier

fire testing program, these upgrade changes are being incorporated in o the

typical design details.

The inspectors also found that for the'DCAs issued to

address cases which deviate from tested configurations, the same design and.

,

installation attributes were applied.

The inspectors also reviewed eight Thermo-Lag fire barrier installations which

the inspectors viewed as not being bounded by the 1icensee's fire barrier

testing program.

This review included conducting a visual inspection of these

barriers.

At the time of this inspection, the licensee had not completed

,

their engineering evaluation justifying the fire resistance of these designs.

The adequacy of the licensee's engineering evaluations' for those conditions-

which deviate from the tested configurations is being evaluated by the Office

t

'

of Nuclear Reactor Regulation and will be addressed by the staff in SSER 26,

Attachment 9 summarizes the design of the fire barrier assemblies reviewed as

part of this inspection.

The construction and upgrade attributes used on the above configurations

i

appeared to be consistent with the design and installation requirements

..

--

.

-

--

.

-

.

-26-

I

?

established by the licensee's design and installation specification and the

installation procedure. The inspectors found the continuity of material

application, the thickness of the material applied, and the. upgrade techniques

used to follow the same logic to those attributes applied to the fire test

specimens tested as part of Scheme 9 - Assembly 1 and Scheme 10 - Assembly 1.

2.7 Fire Brigade Use of Hose Streams

t

During the conduct of fire tests at Omega Point Laboratories in San Antonio,

i

Texas, an NRC inspector noted that the hose nozzle used for the hose stream

test produced a straight stream.

Previous tests using a straight: stream had

produced damage to the Thermo-Lag construction.

The licensee had stipulated-

that only a fog nozzle pattern would be used for the tests and suppression

practice in the plant would only allow use of a fog patte n since only E-rated :

nozzles were installed in the hose stations and these nozzles, by

construction, limit the hose stream to a minimum 30 degree fog pattern.

An NRC inspector reviewed the licensee's actions to prevent the inadvertent

use of a straight stream in areas of the plant where Thermo-Lag is installed.

The initial issues of the fire preplans for Unit 2 contain a precaution

requiring the use of a fog cattern in areas containing_Thermo-Lag

installations. The licensee has issued PCNs for the Unit 1 fire preplans that_

incorporate the same precaution.

The licensee has also incorporated this

information in the fire brigade training program, both as a current events

review and in-the initial fire brigade training. The NRC inspector conducted

a walkdown of a sampling of fire hose stations in Units 1 and 2 power blocks.

All observed hose stations were equipped with an E-rated hose nozzle that-

limits the hose stream to a minimum 30 degree fog pattern.

2.8 Conclusions

q

The inspectors found activities pertaining to the procurement, testing,

,

engineering, training, installation, and quality' assurance of Thermo-Lag as a

'

fire barrier .. ,: am to be strong. The -licensee has provided reasonable

assurance that implementation of Thermo-Lag will satisfy the intended function =

to protect fire safe shutdowa power and control circuitry.

The licensee has .

J

taken appropriate actions to preclude Thermo-tag from being damaged _by the use

_

of a straight stream suppression nozzle.

3

,

I

l

l

o

_

_

_

.

,

-

,

i

4

=

.,

ATTACHMENT 1

i

1 PERSONS CONTACTED

i

-1.]

TV ELECTRIC

T. Hope, Site Licensing Manager

H. Carmichael, Unit 2 Project Management

D. Moore, Maintenance Manager

C. Hooton, Unit 2 Engineering

J. Ayres, Operations QA Manager

D. McAfee, Manager, QA

W. Grace, Safety Services Manager, Production Division

,

R. Wakeman, Fire Protection Supervisor, Production Division

B. Taylor, Staff Assistant for Vice President, Nuclear Production

C. Beckett, Principal Engineer, Design Engineering

H. Dempsey, Electrical Engineer, Stone & Webster Engineering Corporation

M. Blevins, Director of Nuclear Overview

S. Harrison, Unit 2 Engineering Manager

R. Dible, Mechanical Engineer, Impell Corporation

C. Terry, Vice President, Nuclear Engineering and Support

H. Bruner, Senior Vice President

J. Snyder, Otartup Manager

C. Rau, Unit 2 Project Manoger

K. Williamson, Unit 2 Project Manager

J. Conly, Unit 2 Licensing Engineer

1.3 NRC Persannel

'

A. Singh, Reactor Inspector, Division of Reactor Safety (DRS)

P. Madden, Senior Fire Protection Reviewer, Office of Nuclear Reactor

Regulation

T.Reis,ProjectEngineer,DivisionofReactorProjects(DfP)

<

M. Murphy, Reactor Inspector, DRS

D. Graves, Senior Resident inspector, DRP

G. Constable, Chief,. Plant Support, DRS

.

The personnel listed above attended the exit meeting.

In addition to the

l

personnel listed above, the inspectors contacted other personnel during this

inspection period.

q

2 EXIT MEETING

An exit meeting was conducted on January 15, 1993. During f.his meeting, thel

.

inspectors reviewed the scope and findings of the report.

The licensee did

not identify as proprietary any information provided to or reviewed by the

inspectors.

.

s-,

-

-

ATTACHitENT'2

1

M

Log # TXX-92640

,

=== 9

File # 10120

j

  1. 907.4

)

--'

--

  1. 909.5

--

--

!

1UELECTRIC

December 23, 1992

wnh.= J.c wa Jr.

o, , veam.* e

'

U. S. Nuclear Regulatory Commission

Attn: Document Control Desk

Washington, DC 20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES) - UNITS 1 & 2

DOCKET HOS. 50-445 AND 50-446

IN 92-18. PDTENTIAL FOR LOSS OF REMOTE SHUTDOWN

CAPABILITY DURING A CONTROL ROOM FIRE.

-

i

Gentlemen:

The subject of matcr-operated valve (MOV) bot shorts was discussed during

the Unit 2 Fire Protection Inspection status meeting with the NRC on

December 17, 1992.

Although TV Electric considers this scenario to.have an

extremely low probability, TU Electric committed to implement design changes

in the control circuits of the affected MOVs (as required) similar to

Figures 5-and 6 of th6 subject NRC Notice.

Per our discussions-with the

Staff. TU. Electric is comMtting to implement these hardware modifications

prior to startup from the first refueling outage for Unit 2 and prior to-

>

startup from the third refueling outage for Unit 1.

Sincerely,

'

)

.;

'

.

W1111am J. Cahi.11 Jr.

By:

M

Roger D. Walker

.

Manager of Regulatory Affairs

for NEO

>

JTC/ds

c - Mr. J. - L-. Milhoan, Region IV

Resident Inspectors CPSES (2)

Mr. B. E. Holian, NRR

Hr. T. A. Bergman, NRR

,

-

..m = ~ ~..

i = ..

n.n.. r,,- 2sw

e

.,

-

ATTACHMENT 3

.

M==

h

5

Log

  1. TXX-93034
-

File # 10010

,

1UELECTRIC

$gl4g

g,7,

y

January. 15, 1993

wmm J. CaMil.Jr.

am,, vw r o%w

U. 5 Nuclear Regulatory Commission

Attn: Document Control Desk

Washington, DC 20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 AND 50-446

FIRE PROTECTION INSPECTION

Gentlemen:

TU Electric hereby commits to the following corrective actions in response

to the NRC Fire Protection Inspection of Unit 2 conducted during

January 11-15, 1993.

Additions and relocations of detectors and sprinkler heads identified as

necessary by TU Electric's walkdown of Unit 2 will be completed by the end

of the fjrst refueling outage.

The high'. impedance fault study for Unit I will be reviewed to increase the

margin in the number of simultaneous cable faults assumed for low voltage

power supplies in safe shutdown circuitry by March 1, 1993. Any necessary

hardware modifications will be implemented at the next available opportunity

following issuance of the revised design, but not later than the next

refueling outage.

The existing emergency lighting batteries will be replaced in both Units

with 10-year-life batteries in accordance with the current replacement

schedule beginning June 1, 1993.

Specific Unit 2 thermolag configurations which deviate from tested

configurations have been technically justified through our design control

process.

An evaluation to compare these configurations to those tested or

provide in-depth anal) .is of these configurations is in process. The

scheduled completion date is currently under review.

Ladders and tools required for the successful performance of ABN-803B in

Unit 2 will be clearly identified and controlled to ensure their

availability as done in Unit 1.

This will be accomplished prior to entry

into Mode 4.

400 N. Olive Strm LB. 81 Dallas. Texas 75201

TXX-93034

Pap,e 2 of 2

The preventive maintenance procedures will be performed on 100% of the Unit

2 safe shutdown emergency lighting prior to entering Mode 4.

A fornal root

cause evaluation of the emergency light failures will be performed in

accordance with existing site procedures.

,

i

Sincerely,

y

William J. Cahill, Jr.

JTC/tg

c- Mr. J. L. Milhoan. Region IV

Mr. B. E. Holian, NRR

Resident Inspectors, CPSES (2)

.

6

8

.

E

i

.

. ATTACHMENT 4

,

AREAS REQUIRING SPRINKLER HEAD RELOCATION OR ADDITION

Addition and relocation of fire detectors in the various areas of the Unit 2

safeguard building are listed below:

Elevation

Room

Description

'

773

2-051

Containment Spray Pump Room 2-02/2-04

773

2-054

Containment Spray Pump Room 2-01-2-03

.

773

2-060

Safety injection Pump Room 2-02

773

2-062

Safety Injection Pump Room 2-01

852

2-100B

Feedwater ISO Valve Room

852

2-100C

Feedwater ISO Valve Room

NOTE:

The identified dimensions are from face of wall at the column line

indicated, not from the column centerline.

ROOM 2-051

CONTAINMENT SPPAY PUMP ROOM 2-02/2-04

Relocate existing detector to 9'-0"

E of A-S, 6'-4" S of 10-S.

Add new detec?or at 6'-9" W of D-S, 8'-1" N of 9-S.

.

ROOM 2-054

CONTAINMENT SPRAY PUMP ROOM 2-01/2-03

,

Relocate existing detector to 10'-3" E of C-S,

9'-6" S of 10-S.

Add new

'

detector,at 9'-0" W of D-S, 8'-0" N of 9-S.

,

ROOM 2-060

SAFETY INJECTION PUMP ROOM 2-02

,

Add new detector at 7'-0" E of A-5, 8'-0" N of 9-S.

ROOM 2-062

SAFETY INJECTION PUMP ROOM 2-01

Relocate existing detector to 5'-0" E of A-S, 5'7" N of 12.2-S.

Add new

detector at 6'-10" E of A-5, 7'-8" S of 13-S.

,

ROOM 2-100B.

FEEDWATER 150 VALVE ROOM

Relocate existing detector to 9'-4" E of D-S, 6'-10" N of 10-S.

ROOM 2-100C

FEEDWATER 150 VALVE ROOM

Relocate existing detector to 10'-0" E of D-5,

6'-0" N of Il-S.

-;

f

l

,

...- .

.

.

.

.

.

!

,

-2-

The following lists the areas where the licensee has identified th3 addition

and relocation of sprinklers at Unit 2.

1.

790 Corridor area

Sprinkler head modifications

Room-2-070

Add

2

.

Room 2-071

Add

8

Rel

2

i

Del

1

'

2.

810 Corridor area

!

-Sprinkler head modifications

Room 2-082

Add

2

'

3.

810 Electrical equipment room .

s

Sprinkler head modifications

I

Room 2-083

Add

9

4.

831 Corridor area

Sprinkler head modifications

Room 2-094

Add

2

5. -852 Electrical equipment room

Sprinkler head modifications

Raom 2-103

Add

7

.

Rel

7

.

Del-

1

6.

Pipe penetration area

'

Sprinkler head modifications

Room 2-100

Re1

1

.

Room 2-107'

Add

1

i

i

si

,

2

. 9

a

9

!

1

h

n

a

s

-

,,

e

-,

l

I

. ATTACHMENT 5

DETAILED REVIEW OF OMEGA POINT LABORATORY

THERMO-LAG FIRE TEST REPORTS

.

Omega Point Project No. 12340-94367a, Scheme 9 - Assembly 1

The assembly fire endurance test, by Scheme 9 - Assembly 1, consisted of ~three

conduit loop configuration (5-inch, 3-inch, and 3/4-inch).

Each of these

loops extended through the furnace fire test deck, down into the furnace into

a 90* elbow (long side vertical) with a 8'-6" total horizontal run of conduit

which transitions to a 90* radial bend and back up through the furnace fire

test deck.

The Thermo-Lag 330-1 was applied to the test assembly (Scheme 9 - Assembly 1)

in the following manner:

Each rigid conduit was covered first with Thermo-Lag 330-1 preshaped

material sections prior to installing Thermo-Lag fire barrier material

to the trapeze conduit supporting member.

All conduit joints and seams

were precaulked (prebuttered) with Thermo-Lag 330-1 trowel grade

material and secured in place with stainless steel tie wire and banding

inateri al .

(Note - The fastener (banding / tie wire) spacing for the

prefabricated Thermo-Lag conduit sections on the vertical and horizontal

conduit runs was verified by the licensee QC inspection process not to

exceed 12 inches maximum on center.)

~

The Uni-Strut trapeze support member was covered with Thermo-Lag flat

panels. ~ The licensee's 9 inch coverage rule was applied, which treated

this support as a protruding item and required this support to be

-

protected by Thermo-Lag for a minimum distance of 9 inches from the

closest Thermo-Lag conduit preshape application.

The remaining Uni-

Strut support supporting the test specimen from the furnace fire test

deck was left unprotected from the-furnace fire source.

The joints and-

seams associated with the application of the fire barrier panels to the

trapeze support were precaulked with trowel grade material and secured

in place with stainless steel tie wire.

Each conduit 90 LBD fitting was covered with a flat panel fire barrier

material.

The fire barrier panels to cover the vertical sections of the

5-inch LBD fitting was scored in 12 places at 3-inch spacing to conform

to the LBD curvatur,e. All the joints and seams of the LDB Thermo-Lag

fire barrier box configurations were precaulked and secured in place

with stainless steel banding material.

After the initial installation of the Thermo-Lag fire barrier material

onto the surface of the test specimen, the licensee installed the

following upgrades:

The 3/4-inch conduit, after having the 1/2-inch nominal thickness

Thermo-Lag 330-1 conduit pre-shape applied, was upgraded by installing

an additional 1/4-inch nominal thickness overlay Thermo-Lag preshape

,

.

.

.

..

.

-. . .

-

i

-2-

'

conduit section.

The joints and seams of the 1/4-inch preshape overlay

were precaulked with trowel grade material and secured to the assembly

I

with stainless steel banding (banding used on the vertical and

horizontal conduit runs) or tie wire (tie wire used on the radial

,

bends).

For the radial bends, trowel grade material was applied to the outer

surface of the Thermo-Lag fire barrier radial bend preshape to depth of

i

'

approximately 3/16 inch and allowed to set until tacky. Strips of

Thermo-Lag 330-69 stress skin 2 inches wide were trimmed into an

I

hourglass shape with the thinness dimension being 3/4 inch at the center

l

of the shape and circumferentially wrapped around the radial bend and

i

worked into the tacky trowel grade material.

The stress skin was then

secured in plac; to the Thermo-Lag radial bend preshape with 1/2-inch

-

staples and stainless steel -tie wire.

Once the stress skin was properly

secured, a skim coat of trowel grade material was applied over the

stress sHn.

All the flat Thermo-Lag panels applied to-the LDBs had their joints

coated with trowel grade material (allowed to set ~ and become tacky) and

j

stress skin with a 2-inch overlap onto adjoining panels was applied to .

all LBD joints / seams. Where the conduit enters and exits the LBD,

stress skin was cut and applied in such a manner.that, when folded,

,

2-inch overlay of stress skin lapped over onto adjoining fire barrier

I

panels and preshape conduit. sections.

The stress skin was secured to

the Thermo-Lag LBD fire barrier boxes with 1/2-inch long staples. Where

the stra.s skin was attached to the conduit pre-shapes, a 2 in. stress

skin coliar was circumferentially wrapped around the conduit and stapled

in place.

Upon completion of the application of the stress skin to the

,

l

LBD seams and joints, a skim coat of Thermo-Lag trowel grade material

'

was applied over the stress skin.

Omega Point Project No. 12340-94367c, Scheme 10 - Assembly 1

The assembly fire endurance tested, by Scheme 10 - Assembly 1, consisted of

two parallel 3-inch conduit loops.

Each of these loops extended through the

l

furnace fire test deck, down into the furnace and into the 18-inch side of an

'

18 x 12 x 6-inch JB (vertically installed 21 inches above the horizontal run

of the conduits).

The two conduits exit the JB and are routed into 90' LBD

fittings (long side horizontal). The two conduits run horizontally from the -

elbows and enter a .second 18 x 12 x 6-inch JB (installed _ horizontally at the

mid span of the horizontal conduit run).

The conduits exit the JB and.are

routed horizontally.into a second. set of 90 LDB fittings- (long side vertical)

and back up through the furnace fire test deck.

The Thermo-Lag 330-1 was applied to the test assembly (Scheme 10 - Assembly 1)

in the following manner:

Each 3-inch rigid conduit was covered first with Thermo-Lag 330-1

preshaped material sections. All conduit joints and seams were

L

.

-

.

. _ _ .

-3-

'

precaulked (prebuttered) with Thermo-Lag 330-1 trowel grade material and

secured in place with stainless steel banding. material.

(Note - The .

fastener (banding wire) spacing for the prefabricated Thermo-Lag conduit

!

sections on the vertical and horizontal conduit runs was verified by the

licensee QC inspection process nct to exceed 12 inches maximum on

center.)

Each conduit 90 LBD fitting was covered with a' flat panel fire barrier

material. All the joints and seams of the LDB fitting Thermo-Lag fire

barrier box configurations were precaulked and secured in place with

stainless steel banding material.

The midplane tube steel support member supporting the JB in the

horizontal conduit run, was covered with Thermo-Lag flat single panel

sections.

The licensee's 9 inch coverage rule was applied, which

treated this support as a protruding item and required this support to

be protected by Thermo-Lag for a minimum distance of 9 inches from the.

,

JB Thermo-Lag preshape application.

The remaining tube steel support

-

to the furnace fire test deck was left unprotected from .the furnace fire

source.

The joints and seams associated with the application of the:

'

fire barrier panels to the support were precaulked with trowel grade

i

material and secured in place with stainless steal tie wire.

1

The JBs were covered with 1/2-inch thick flat panel material'and all

joints and seams of the fire barrier material were precaulked with

",

trowel grade material and .the assembly secured in place with stainless

steel banding,

,

After_the initial installation of the Thermo-Lag fire barrier material-

onto the surface of the test specimen, the licensee installed the

following upgrades:

Following the application of the first layer of Thermo-Lag flat panel

fire barrier material to the JBs, a second layer of Thermo-Lag' V-ribbed

panel material was applied over the first layer.

The ~ joints and seams

were precaulked and secured in place with stainless steel banding,

i

After the second layer of Thermo-Lag was installed, a layer _of trowel ~

grade material was applied over all joints and seams (approximately

3/16-inch thick) and overlapping 2_ inches onto the Thermo-Lag. panels.

The trowel grade was allowed to set'until tacky to touch, then 4-inch

wide strips of. stress skin were applied to the joints (2-inch overlay in

either direction from the JBs corners) and the stress skin was worked

into the tacky trowel grade material in order to achieve proper bonding

of the stress skin to the preshape JB fire barrier panels. The stress ~

,

skin overlays were secured in place using 1/2-inch long staples and a

,

skim coat of trowel grade material was applied over the' stress-skin.

The1 application of-the fire barrier upgrades applied to the LBDs for

,

this fire. test configuration were the same as those applied to Scheme 9

l

' Assembly 1.

D

<

-

4

.

.

ATTACHMENT 6

TYPICAL THERM 0 - LAG CONFIGURATION DRAWINGS

I

H2-1701, Sheet 1

Details concerning the application of Thermo-Lag to support steel.

.

M2-1701, Sheet 2

Banding and fire barrier material application details for JBs; details

for the construction of JBs with removable covers; and the installation

of fire stops in the conduits entering JBs.

M2-1701, Sheet 3

Detail for an air drop into the center of a cable tray.

L

M2-1701, Sheet 3A

Detail for an air drop cable routed between two raceway protected by

Thermo-Lag fire barrier material.

,

M2-1701, Sheet 3B

Detail for an air drop cable which penetrates through Thermo-Lag fire

barrier prefabricated panels.

M2-1701[ Sheet 4

Details for the installation of conduit preshapes and Thermo-Lag 660

'

fire barrier material.

M2-1701, Sheet 4A

Details for Thermo-Lcg fire barrier (conduits) penetrating wall or

fl oo r.

M2-1701, Sheet 5

,

Details for the installation of Thermo-Lag fire barrier prefabricated

panels on cable trays (e.g., straight runs) and_ the details associated

with the installation of a fire stop.in a cable tray.

M2-1701, Sheet 5A

Detail for the interface between Thermo-Lag fire barrier assembly and a

penetration seal.

M2-1701, Sheet 6

Details'for conduit LBDs, snug fit and box design.

t

-2-

,

'

M2-1701, Sheet 7

Containment penetration /Thermo-Lag fire barrier interface detail.

'

M2-1701, Sheet 8

l

. Identifies additional details for Thermo-Lag protected 'JBs with

removable covers and provides a detail for a cable bundle protected with

Thermo-Lag 660 material that splits into two bundles.

M2-1701, Sheet 9

'

Detail for applying Thermo-Lag fire barrier materials to a vertical

cable tray which is mounted flush to the wall.

M2-1701, Sheet 10

Thermo-Lag fire barrier shimming details.

M2-1701, Sheet 11

'

Details for attaching the bottom and side Thermo-Lag panels to cable

trays.

,

M2-1701,, Sheet 12

,

Detail requiring the use of Sil-Temp to cover cables in tray that have a

fill within 1/2 inch of the top of the Thermo-Lag fire barrier tray

cover.

M2-1701,. Sheet 13

Details associated with fire barrier interferences (i.e., cable trays,

pipes conduits).

3

M2-1701, Sheet 14

Additional details associated with conduit / cable tray interferences.

M2-1701,. Sheet 15

Details associated with .the use of Thermo-Lag 660 material to wrap

cables routed in cable trays.

E

'

t

,

a

ATTACHMENT 7

THERM 0 - LAG CONFICURATIONS AND RESPECTIVE WORK DOCUMENTS INSPECTED

TABLE

FIRE BARRIER ASSEMBLIES / CONSTRUCTION WORK DOCUMENTS

PLANT LOCATION

RACEWAY

CONSTRUCTION WORK

DOCUMENT REVIEWED

.

,

Unit 2 Essential

Conduits C23G06046 and

TL-ECll5B778-COND-12

Chiller Room

CHCICE-06 and Junction

Box JB2A-0126.

Conduits C24W41899 and

TL-SB0094832-COND14

[

Safeguards Building

Junction Box JB255376W.

TL-SB0094832-SUPL-C14

'

'

Elev. 832', Room 2-094

TLSB0083810-COND3

Safeguards Building

Conduits C22G03990 and

-COND4

Elev. 816', Electrical

C22G0627 and Junction

-COND5

Equipment Area 2-083

Box JB2S605G

-COND6

-SUPLC5

-SUPLC6

Safeguards Building

Elev. 810', Room 2-082

Tray T23GECE63 and

TLSB0082810-TRAY 3

Multi-Airdrop

-SUPLT3

Auxiliary Building

Configuration

Elev. 810', Corridor 2-

'

Multi-Tray and Air Drop

TL-AB0207810-TRAY 14

207.

-

Enclosure (trays

-TRAY 15

T230ACG55, T230ACG52-

-TRAY 38

55, T230ACG75-76 and 40

conduit sleeves with

air drops into the

l

trays)2

,

!

,

I

,

j

i

'

Configuration not bounded by the licensee's fire testing program.

Engineering evaluation justifying the configuration is required.

!

-2-

.

FIRE BARRIER ASSEMBLIES / CONSTRUCTION WORK DOCUMENTS

PLANT LOCATION

RACEWAY

CONSTRUCTION WORK

DOCUMENT REVIEWED

~

,

Auxiliary Building

Two Tray Configuration

TL-AB0174790-TRAY 1

Elev. 790', Room 2-174

in Common Enclosure

-TRAY 2

(trays T220ABC14 and

T220ABC15)'

'

Safeguards Building

Junction Box with

Elev. 832', Electrical

Removable cover (JB27-

TL-SB0096832-COND5

Equipment Area Room 2-

942)*

096.

,

d

4

S

9

_ - ____ - __

-_-_-

-

'

.

. ATTACHMENT 8

ENGINEERING JUSTIFICATIONS FOR UNTESTED THERM 0 - LAG CONFIGURATIONS REVIEWED

,

DCA 100820 -

This DCA provided additional details for conditions

l

where Thermo-Lag interfaces with penetration seals;

'

revised the banding and tie wire details for cable

,

tray Tee sections; and provided additional details for

'

"V" groove / scoring Thermo-Lag for Raceway bends.

'

l

DCA 101358 -

Provided details for installing Thermo-Lag fire

barrier material on structural steel used to support

the gypsum stairwell wall enclosures.

(Note - This

DCA is not applicable to raceway fire barrier

enclosures) .

.

DCA 101524 -

Incorporated installation notes for structural steel

fire proofing details contained on M2-1701, Sheet 16.

DCA 101625 -

Pro" ides a detail to address the hanger plate

interference with conduit r25WO7502.

DCA 101918 -

Cable tray detail for making the transition from a

flat 330 panel to a V-ribbed 330 panel.

DCA 102729 -

Provide a detail for flex conduit protected by

Flexiblanket 660 interfacing with a penetration seal

blockout.

-

,

DCA 102933 -

Identified a detail of the backfit of air drops of

2 inches and less with the addition of a third layer

of Flexiblanket 660 fire barrier material.

J

1

DCA 102957 -

Detail for covering longitudinal cable tray

I

joints / seams where interferences is to close to

j

install stress skin and a 330 build-up.

!

DCA 103061 -

Detail for enclosing two 2-inch conduits, C24Y41955

and C24W41900 into one Flexiblanket 660 enclosure.

DCA 103063 -

Provided a detail for protecting a protruding

structural steel support which interfaces with a

concrete wall (interpretation of the 9-inch rule).

DCA 103020 -

This DCA revised several of the M2-1701 typical

details to incorporate the fire barrier upgrades

qualified by the licensee fire barrier fire endurance

testing program.

The following is a summary of the

detail revisions:

-

Revised JB detail, Sheet 2, Detail 2-3.3.

l

i

_ - - _ _ -

,

..

.

-

,

,

.

,

2 ..

,

,

,

Revised the flexiblanket detail to incorporate

-

the third layer, Sheet 3, Detail-3-4,

,

Revised the air drop into the center of a cable

-

tray detail,-Sheet-3,LDetail 3-4.3 and

-

Detail 3-4.4.

-

. Revised the detail associated with the

transition from conduit pre-shape to ~

.i

.

.

Flexiblanket, Sheet 3.-Detail 3-5.2.and 3-5.2a.

Revised the detail for the installation of.

-

conduit preshapes on conduits, 3-inch and

-!

larger, Sheet 4 Detail 4-1.

Revised.the detail for air drops protected with

-

Flexiblanket, 2-inch and larger, Sheet 4,

Detail 4-2.

Revised the conduit details associated with:

-

conduits less--that 2Ein. to incorporate.the

required upgrades, Sheet 4. Detail 4-1.1~.

Detail revised to incorporated the upgrade for

-

flex conduit and air drops less than 2 in.,

'

Sheet 4, Detail 4'.2.-l.

Revised the detail for conduits protected.by--

-

pre-shape fire barrier material mounted adjacent

to a concrete surface, Sheet 4, Detail 4-3.1,.

Provided a revision to-the detail for oversized

-

conduits mounted adjacent to a concrete surface,

Sheet 4, Details'4-6 and 4-7.

Revised the cable tray detail to incorporate the

-

longitudinal seam upgrade, Sheet 5,

.

Details 5-1.1 and 5-1 22

.

provided a revision to the cable tray radial'

-

bend oetail, Sheet 5, Detail 5-6,

-

- Revised the details associated with banding.

cable-tray Tee f.ections, Sheet 5-7 , 5-8, 5-9.-

and 5-10.

provided a revision to the detail for cable-tray

-

butt joints. Sheet 5, Detail 5-11.

.

An f . bu'.

_

_ _ ,

_

!

,

-t

-3-

.

-

Provided a detail associated with the transition

of cables exiting from.the end.of a cable tray

'

to an air. drop, Sheet 5 , Detail 5-12.

t

-

Provided a detail for. installing stress skin -

!

overlay on cable tray splice plates, Sheet 5, .

Detail 5-14.

'

!

-

Provided a detail for the stress skin upgrade'to

.

LDBs, Sheet 6, Detail 6-1.

.

b

P

P

s

T

k

!

I

1

i

i

!

<

'

l

i

1

'

.

ATTACHMENT 9

THERM 0 - LAG CONFIGURATIONS NOT BOUND U BY TESTING PROGRAM

Auxiliary Building Elevation 810', Room X-207

Configuration 1 - T'ree :able tray vertical stack assembly. This fire

barrier configuration encloses one 30-inch and two 24-inch cable trays

in a box assembly. The fire barrier box assembly encloses these trays

for a straight run of approximately 6 feet.

The box assembly is

approximately 5 feet in height. Cable trays T230ACA75 and T230ACG75 are

protected by Thermo-Lag as they enter and exit the fire barrier box

assembly. One side of the fire barrier box assembly is attached to the

concrete wall with Hilti-Bolts.

Penetrating the concrete wall inside

the fit e barrier box assembly is 40 conduit sleeves which exit the ca'le

a

spreading room and air drop their cables into the cable trays which are

enclosed by the box assembly. The-fire barrier box is constructed out

of 1/2-inch prefabricated Thermo-Lag 330-1 panels supported by a Uni-

Strut frame. The joints and seams are stitched and reinforced with

stress skin,

The top and bottom sections of the box that extend from

the tray to the wall use the score and fold method and are shaped

accordingly. The bottom panel is tie wired to every other rungs of the

bottom tray and the sides were banded through the side of Thermo-Lag

side panels to the tray:. (DCAs 103472 and 103489)

Configuration 2 - Two 24-inch tray vertical stacked configuration

similar to Configuration 1 above.

This box assembly contains nine

conduit , sleeves which exit the cable spreading room and air drop their

cables into the trays within the box.

Configuration 3 - This assembly at the time of the inspection was not

completed.

This configuration will enclose JB 2990 and a cable tray

together.

Auxiliary Building Elevation 790', Room X-174

Cordiquration 4 - This fire barrier assembly enclosed two cable trays

(1220ABC0e ana T230ACA24), en 18-inch end 12-inch, instalied parallel

running horizontally down the corridor.

This fire barrier enclosure is

approximately 60 feet in length. The enclosure is constructed in such a

manner that the trays have a Thermo-Lag partitien (except at the tray

'

splice plates) separating the trays within the enclosure. The common

f

enclosure top and bottom is fabricated out of Thermo-Lag 330-1 panels

with the bottom panels being secured to the rungs of the trays with tie

wire.

This tie wire attachment is applied to every other rung, with at

least two ties per rung.

The seams of this configuration are provided

with stress skin overlays and the butt joints are stitched then overlaid

4

with stress skin (DCA 102471).

Safeguards Building, Elevation 810', Room 2-083

'

Configuration 5 - This configuration

. ncists of two vertical 24-inch

wide cable tray which air drop their cat Ns 'nto conduit sleeves which

t

- _ _ _ . - - - - - - _ _ _ _ _ _ _ _ _

-

.

. .

-

.

..

,

.

t

-2-

i

!

penetrate the concrete wall interfacing with Room 2-082.

The two cable

trays are independently protected with Thermo-Lag to the point that they

terminate and the cables air drop. At this point, a Thermo-lag box

(5 feet x 3 feet x 10 inches) enclosure has been constructed to enclose

,

the air drop cables and the conduit sleeves.

The box is secured to the

!

wall with Hilti-Bolts and the joints and corners have been upgraded with

stress skin overlays (DCAs 101986, 103034, and 104124).

Configuration 6 - This configuration consists of two JBs, installed up

against a concrete wall, boxed together.

Between the JBs, only a single

layer of Thermo-Lag panel is installed.

The remaining exposed sides of

,

the JBs are protected with two layers of Thermo-Lag fire barrier panel

material. The joints and seams have been overlaid with stress skin and

,

trowel grade material .

The banding application could not be applied

circumferentially around the JBs.

The banding is attached to steel

angles which are bolted to the wall above and below these JBs

-

(DCA 103634).

Safeguards Building, Elevation 810', Room 2-082

Configuration 7 - This configuration consists of cables air dropping out

of several embedded wall conduit sleeves and entering three short run

.

horizontal cable trays above the two service water lines running down

the corridor.

These cables exit these horizontal trays and air drop

into a 30-inch tray which runs under the service water lines. The

,

cables leaving the sleeves are protected with Flexiblanket 660 fire

barrier material. When these cables enter the three horizontal trays

installed above the service water piping, they are protected in the

trays by Thermo-Lag 330-1 fire prefabricated panel system.

These trays

'

are protected independently.

As these cables exit the tray segments

above the service water piping, they are protected by Flexiblanket 660

fire barrier material.

The cables enter the 30-inch tray though the top

of panel of the Thermo-Lag fire barrier system installed on this tray.

4

In order to accommodate the air drop cables entering the 30-inch tray, a

j

12-inch wide x 43-inch long openint was cut into the top tray panel.

A

i

6-inch high curb constructed out of Thermo-Lag 330-1 prefabricated

panels was installed around the opening and this opening was filled with

Thermo-Lag 660 trowel grade material (DCA 10301).

i

'l

Safeguards Building, Elevation 831', Room 2-088

I

Configuration 8 - This configuration consists of enclosing two JBs

installed on a common support in one fire barrier enclosure.

Each JB is

enclosed in the first layer of Thermo-Lag 330 panel material separately

and the second layer was applied using the score and fold method to

enclose both JBs.

The joints and seams were either overlaid with stress

skin or are stitched (DCA 103184, 103192, and 103A81).

1

4

i

!