Forwards Info Re Status of Unimplemented USIs for Facilities Per Generic Ltr 89-21.Licensee 890417 Submittal Re USI A-44 on Station Blackout Under Review.Usi A-47 Will Be Resolved Via Response to Generic Ltr 88-19
ML20012E948
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 03/22/1990
From: Clark R
Office of Nuclear Reactor Regulation
To: Hunger G
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
References
REF-GTECI-A-44, REF-GTECI-A-47, REF-GTECI-EL, REF-GTECI-SY, TASK-A-44, TASK-A-47, TASK-OR GL-88-19, GL-89-21, TAC-74538, NUDOCS 9004090140
Download: ML20012E948 (4)


Text

.

March 22,. 1990 00chet No's. !0 352 1%TR1 T p_N w/ enclosure' i

[ NRC' PDR '

Fj RClark i

l and 50 353 GSuh

{

Mr. George A. Hunger, Jr.

Local PDR OGC t

Director-Licensing,ic Company PDI-2 Reading EJordan MC 5-2A 5 Philadelphia Electr SYarge ACRS'10)

Nuclear Group Headquarters BBoger KEccleston r

Correspondence Control Desk WButler P.O. Box 195 M0'Brien Wayne, Pennsylvania 19087-0195 i

Dear Mr. Hunger:

$UBJECT: UNIMPLEMENTEDUNRESOLVEDSAFETYISSUES(TACNO.74538) l RE:-

LIMERICK GENERATING $TATION, UNITS 1 AND 2 On October 19, 1989 thestaffissuedGenericLetter(GL)89-21whichrequested information concerning the status of implementation of unresolved safety issues (US!s) at Liwerick Generating Station, Units 1 and 2.

Based on your l

response to this GL dated Noveml>er 30, 1989, our review of NRC records and discussions with your staff, the NRC staff has concluded that only two USIs i

have not been implemented at Limerick Units 1 and 2.

The status of these two USIsislistedintheenclosuretothIsletter. The results of the staff's assessment of USI implementation were presented to the Commission at a meeting i

on February 14, 1990.

If you have questions or comments concerning the above, please do not hesitate to contact us.

Sincerely,

{

Original signed by Richard J. Clark Richard J. Clark, Project Manager Project Directorate 1-2 1

Division of Reactor Projects 1/11 Office of Nuclear Reactor Regulation

Enclosure:

As stated i

cc w/ enclosure:

I l

See next page

]i r

[74538]

I PDI-?/P PDI-2/D l

i RClark.

3j')D**d WButler ni pnun unu PDC

g.

p.

    • *.,9 h

UNITEO STATES

[4 sW NUCLE AR REGULATORY COMMIS$lON

'l 5

wAsmwotow, p. c. tons

+

'g....+

March 22,1990 l

1 Docket Nos 50 352 and 50 353

(.

Mr. George A. Hunger, Jr.

Director Licensing, MC 5 2A 5 Philadelphia Electric Company Wuclear Group Headquarters L

Correspondence Control Desk P.O. Box 195 Wayne, Pennsylvania 19087 0195

Dear Mr. Hunger:

SUBJECT:

UNIMPLEMENTEDUKRESOLVEDSAFETYISSUES(TACNO.74538)

RE:

LIMERICK GENERATING STA110N, UNITS 1 AND 2 On October 19, 1989 the staff issued Generic Letter (GL) 89-21 which requested information concerning the status of implementation of unresolved safety issues (US1s) at Linerick Generating Station Units 1 and 2.

Based on your response to this GL dated November 30, 1989, our review of NRC records and discussions with your staff, the NRC staff has concluded that only two U$1s have not been implemented at Limerick Units 1 and 2.

The status of these two U515islistedintheenclosuretothIsletter. The results of the staff's assessment of U$1 implementation were presented to the Comission at a meeting on February 14, 1990, If you have questions or comments concerning the above, please do not hesitate to contact us.

Sincerely, J

?

J Clark, Project Manager roject D rectorate 1-2 Division of Reactor Projects 1/11 Office of Nuclear Reactor Regulation

Enclosure:

As stated

- cc w/ enclosure see next page n.

m

+ - -

s.r--

  • - - - - - - = - -

e' i

ENCLO50Rt LIMERICK GENERATING STATION, UNITS 1 AND 2 UNIMPLEMENTED U$1'$

Expected Imp 1tinented U$1 Title Date Remarks A 44 Station Blackout To be deterrtined Licensee's 4/17/89 submittal under staff review.

A-47 Safety,1mplication of To be determined Response to GL Control Systems in LWR 88-19 due 3/90.

Nuclear Power Plants e

i m

}

t

, o.

Mr. George A. HunkerPhiladelphia Elec ric Company Units 1 & 2 Jr.

Limerick Generating Station l

l CCt Troy B. Conner, Jr., Esquire Mr. Thomas Geivsky, Director Conner and Wetterhahn Bureau of Radiation Protection I

1747 Pennsylvania Ave., N.W.

PA Dr; Box 2063t. of Environmental Resources l Washington, D. C.

20006 P. 0.

l Harrisburg, Pennsylvania 17120 Mr. Rod Krich 52A 5 Philadelphia Electric Company Single Point of Contact

(

955 Chesterbrook Boulevard P. O. t.ex 11880 Wayne, Pennsylvania 19087-5691 Harrisburg, Pennsylvania 17108 1880

}

Mr. Graham M. Leitch, Vice President Mr. Philip J. Duca i

Limerick Generating Station Support Manager Post Office Box A Limerick Generating Station i

Senatoga, Pennsylvania 19464 P. O. Box A Senatoga, Pennsylvania 19464 Mr. Marty J. McCormick, Jr.

l Plant Manager Mr. Gary Edwards Limerick Generating Station Superintendent-Technical i

P.O. Box A Limerick Generating Station

$anatoga, Pennsylvania 19464 P. O. Box A Senatoga, Pennsylvania 19464 l

Mr. Larry Doerflein i

U.S. huclear Regulatory Comission Mr. Gil J. Madsen l

Re ion 1 47fAllendaleRoad Regulatory Engineer Limerick Generating Station King of Prussia, PA 19406 P. 0. Box 1.

Senatoga, Pennsylvania 19464 Mr. Thous Kenny Senior Resident Inspector

}

115 Nuclear Ergulatory Comission l

P. O. Box 596 i'

Pottstown, Pennsylvania 19464 i

Mr. John Doering Projectliarager t

Limerick Generating Station P. O. Box A l

Senatoga, Pennsylvania 19464 Mr. Larry Hopkins

[

l Superintendent-Operations Limerick Fenerating Station P. O. Box A t

$anatoga, Pennsylvania 19464 1