MONTHYEARML19256G2531979-12-20020 December 1979 Notifies That NRC Guides & Criteria Cannot Be Adequately Incorporated Into Site Emergency Plan Before 800101.Requests Delay in Submittal Data for Revised Emergency Plan Until 800131 Project stage: Other ML19260D3701980-02-0404 February 1980 Forwards Estimate of Evacuation Times for Areas Near Facility,In Response to NRC Project stage: Other ML19321B1811980-07-21021 July 1980 Advises That 800718 Emergency Plan Upgrading Per NUREG-0654 Will Be Delayed Until 801001.Requests Rept from 800422-23 Emergency Preparedness Team Review Project stage: Other ML19331D7121980-08-28028 August 1980 Notifies That Final Version of Upgraded Emergency Plan Will Be Submitted by 810102 Project stage: Other ML19332A5901980-09-12012 September 1980 Informs of Util Concept of Physical Means for Alerting & Providing Clear Instructions to Populace within Plume Exposure Emergency Planning Zone.Design Concept Is to Provide Tone Alert Receivers for All Establishments in Zone Project stage: Request ML19345B0031980-11-0707 November 1980 Forwards Summary of 801104 Meeting W/Util Re Proposed Sys to Provide Prompt Notification in Event of Emergency.Meeting Satisfies Request for NRC Response to Util Project stage: Meeting ML19345B0061980-11-0707 November 1980 Summary of 801104 Meeting W/Util in Bethesda,Md Re Licensee Proposal for Sys Providing Prompt Notification of Public in Event of Emergency.Plan Is Predicated on NOAA Willingness to Participate Project stage: Meeting ML20037C2381981-01-15015 January 1981 Forwards Facility Emergency Planning Info for Placement in Lpdr.W/O 8101070522 Project stage: Other ML20003E7541981-04-0303 April 1981 Provides Info Re Schedules for Implementation of Emergency Response Facilities.Conceptual Design Description for Technical Support Ctr & Emergency Operations Facilities Will Be Submitted by 810601 Project stage: Other ML20037D1681981-05-0505 May 1981 Approves Ga State & Local Plans for Emergency Preparedness. Approval Subj to Implementation of Alert & Notification Sys That Meets Criteria of App 3 to NUREG-0654/FEMA-REP-1, Revision 1 by 810701 Project stage: Other ML19352A8691981-05-29029 May 1981 Submits Info in Response to Generic Ltr 81-10 Re Conceptual Design Description of Emergency Offsite Facility. Functional Design Criteria for Emergency Response Facilities Available in Central Files Only Project stage: Other ML20039C1771981-12-0303 December 1981 Requests Review of Encl Matl to Assess Util Capability for Providing Prompt Alerting & Notification of Response Organizations & Population Project stage: Approval ML20039E0361981-12-31031 December 1981 Discusses Proposed Improvements for Meteorological Measurements & Assessment Capabilities of Radiological Releases.Effluent Transport & Diffusion Estimates Will Be Provided by 830630 Project stage: Other 1980-09-12
[Table View] |
Similar Documents at Hatch |
|---|
|
Text
Gec'q:a Power Cornpany 333 Pecmont Avenue At anta Georg.a 30308 Te:ephore 404 526-6526 P Of ce Box 4545 At:anta. Georgia 30302 GeorgiaPower the SCdhem eit<tnc system W. A. Wldner wce Pres. cent and General Manager April 3,1981 Nuclear Generaton I
s s
h' Director of Nuclear Reactor Regulation United States Nuclear Regulatory Commission l6
- 3198g, Washington, D. C.
20555
\\
g#
~ k.
NRC DOCKETS 50-321, 50-366
' s'; w s.-
OPERATING LICENSES DPR-57, NPF-5 EDWIN I. HATCH NUCLEAR PLANT UNITS 1, 2 SCHEDULE FOR EMERGENCY RESPONSE FACILITIES Gentlemen:
In response to your letter of February 18, 1981, Georgia Power Company submits the following information concerning our schedules for implementation of Emergency Response Facilities (ERFs).
We plan to submit our conceptual design description for the Technical Support Center (TSC) and the Emergency Operations Facility (EOF) to you by June 1,1981. A description of TSC instrumentation, instrument quality, instrument accuracy and reliability will reflect the specifications at the time we submit the information. However., implementation of the I
specified instrumentation will be subject to commercial availability of such equipment. Other ERF related documentation requested in your letter will also be submitted to you by June 1,1981.
We intend to have emergency response facilities fully operational t;y October 1,1982. Facilities and staffing plans will be in place, but it is too early to predict if instrumentation will be fully operational by tne specified date. However, we will maintain October 1,1982 as our target date for full operability of ERF instrumentation. Review of staffing levels and schedules is in progress. Staffing and task descriptions for ERFs will be submitted with our June 1,1981 response.
Please contact this office if you require further information.
Very truly yours,
.. l ' d '., c h t..< u c
W. A. Widner 45 PLS/mt lo f
.-