MONTHYEARML18233A4752018-08-24024 August 2018 Summary of Safety Inspection of the Service Water Reservoir Dam (CAC Nos. 001370/05000338 and 001370/05000339; EPID L-2017-LNS-0015) Project stage: Other ML19225B0702019-08-16016 August 2019 Redacted, Transmittal Letter for Dam Inspection Report (CAC Nos. 001370/05000348/L-2017-LNS-0015 and 001370/05000364/L-2017-LNS-0015) Project stage: Other ML19232A0402019-08-23023 August 2019 Transmittal Letter for the Federal Energy Regulatory Commission (FERC) Dam Inspection Report (CAC No. 001370/05000395/L-2017-LNS-0015; EPID L-2019-LRO-0063) (Redacted Version) Project stage: Other ML19246A1532019-09-12012 September 2019 Redacted, Transmittal of Dam Inspection Report (CAC No. 001370/05000400/L-2017-LNS-0015) Project stage: Other ML20006D5902020-01-0202 January 2020 Redacted - Comanche Peak Nuclear Power Plant, Unit Nos. 1 and 2 - Transmittal of Dam Inspection Report Project stage: Other ML21272A3022021-12-0606 December 2021 Summary of Safety Inspection of the Service Water Reservoir Dam (CAC Nos. 001370/05000338 and 001370/05000339; EPID L-2017-LNS-0015)(Public Version) Project stage: Other ML22006A0122022-01-19019 January 2022 Redacted Cover Letter McGuire Dam Safety Inspection 2021, Public Project stage: Other ML22041A0052022-02-11011 February 2022 Transmittal of Dam Inspection Report (EPID L-2017-LNS-0015) (Public) Project stage: Other ML22047A2272022-02-18018 February 2022 Dam Inspection Cover Letter (Public - Redacted) Project stage: Other ML22077A8022022-03-22022 March 2022 Summary of the Dam Safety Inspection for Catawbas Standby Nuclear Service Water Pond Dam (CAC Nos. 001370/05000413 and 001370/05000414; EPID L-2017-LNS-0015) (Redacted Letter) Project stage: Other ML22059A0972022-03-24024 March 2022 Summary of Safety Inspection of the Service Water Reservoir Dam (CAC Nos. 001370/05000395; EPID L-2017-LNS-0015) (Public) Project stage: Other ML23333A0872023-12-13013 December 2023 Transmittal of Dam Safety Inspection Report - Public Project stage: Other ML24344A1902024-12-23023 December 2024 Summary of Safety Inspection of the Service Water Reservoir Dam (CAC Nos. 001370/05000395; EPID L-2017-LNS-0015) (Nonproprietary Cover Letter) Project stage: Other ML24341A1252024-12-23023 December 2024 Summary of Safety Inspection of the Service Water Reservoir Dam (CAC Nos. 001370/05000338 and001370/05000339; EPID L-2017-LNS-0015) Cover Letter (Public Version) Project stage: Other 2022-01-19
[Table View] |
Text
CEII - DO NOT RELEASE CEII - DO NOT RELEASE August 16, 2019 Ms. Cheryl A. Gayheart Regulatory Affairs Director Southern Nuclear Operating Co., Inc.
3535 Colonnade Parkway Birmingham, AL 35243
SUBJECT:
JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 AND 2 - TRANSMITTAL OF DAM INSPECTION REPORT (CAC NOS. 001370/05000348/L-2017-LNS-0015 AND 001370/05000364/L-2017-LNS-0015)
Dear Ms. Gayheart:
Enclosed is a copy of the Dam Safety Inspection Report prepared by the Federal Energy Regulatory Commission (FERC) for the U.S. Nuclear Regulatory Commission (NRC). This report contains the results of an inspection conducted on April 23, 2019, of the Category I Cooling Water Storage Pond Dam at the Joseph M. Farley Nuclear Plant, Units 1 and 2. Based on observations made during the field inspection, review of data submitted by the owner, and discussions with the NRC staff and licensee representatives, FERC found that the Cooling Water Storage Pond dam embankment and appurtenances were in satisfactory condition and adequately maintained for service, stability, and longevity.
The information in the report is considered Critical Energy Infrastructure Information (CEII).
Thus, the Enclosure is official use only and is being withheld from public disclosure.
The enclosure transmitted herewith contains Critical Energy Infrastructure Information. When separated from enclosure, this transmittal document is decontrolled.
C. Gayheart CEII - DO NOT RELEASE CEII - DO NOT RELEASE If you have any questions regarding this matter, I may be reached at 301-415-1009, or via e-mail at Shawn.Williams@nrc.gov.
Sincerely,
/RA John G. Lamb for/
Shawn Williams, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-348 and 50-364
Enclosure:
FERC Dam Safety Inspection Report cc w/o encl: Listserv
Package ML19218A230; Letter ML19218A239 (Non-Public; FERC Report ML19218A238 (Non-Public); Redacted Letter ML19225B070 (Public)