MONTHYEARML23180A1512023-06-29029 June 2023 LLC, Request for Exemption to the Reporting Requirements of 10 CFR 50.46(a)(3) ML21102A3072021-04-15015 April 2021 OEDO-21-00155 - Lessons-Learned from the Design Certification Review of the NuScale Power, LLC, Small Modular Reactor ML21050A4312021-02-19019 February 2021 LLC - Lessons-Learned from the Design Certification Review of the NuScale Power, LLC Small Modular Reactor ML20247J5642020-09-11011 September 2020 Standard Design Approval for the NuScale Power Plant Based on the NuScale 600 Standard Plant Design Certification Application ML20231A8042020-08-28028 August 2020 Final Safety Evaluation Report for the NuScale Standard Plant Design ML20224A4602020-08-25025 August 2020 OEDO-20-00292-Response to the Advisory Committee on Reactor Safeguards Letter on NuScale Power, LLC, Report on the Safety Aspects of the NuScale Small Modular Reactor ML20231A5982020-08-25025 August 2020 OEDO-20-00285_NuScale Area of Focus - Boron Redistribution ML20210M8902020-07-29029 July 2020 Area of Focus - Boron Redistribution ML20195A5872020-07-13013 July 2020 LLC - Submittal of Draft Operator Licensing and Examination Standard for NuScale Small Modular Reactors ML20195C7662020-07-13013 July 2020 LLC Request for Standard Design Approval Based on the NuScale Standard Plant Design Certification Application ML20192A3262020-07-10010 July 2020 LLC, Submittal of Environmental Report: Revision Status ML20198M3932020-07-0202 July 2020 LLC Submittal of Revised Packing Slip for Submittal of the NuScale Standard Plant Design Certification Application, Revision 4.1, Dated June 19, 2020 ML20174A3472020-07-0101 July 2020 OEDO-20-00220 - Area of Focus - Probabilistic Risk Assessment and Emergency Core Cooling System Valve Performance ML20184A2872020-07-0101 July 2020 LLC Submittal of Presentation Materials Entitled ACRS Full Committee Presentation: NuScale Topic - Boron Redistribution and General Design Criterion 33, PM-0720-70785, Revision 0 ML20181A4322020-06-22022 June 2020 Final SER for NuScale TR-0516-49416 NON-Loss-of-Coolant Analysis Model, Rev 3 (Letter) ML20181A2702020-06-22022 June 2020 Final SER for NuScale TR-0516-49422 Loss-of-Coolant Analysis Model, Rev 2 (Letter) ML20198M3922020-06-19019 June 2020 LLC - Submittal of the NuScale Standard Plant Design Certification Application, Revision 4.1 ML20171A7312020-06-19019 June 2020 LLC, Submittal of Riser Flow Hole Methodology and Associated Changes to Final Safety Analysis Report Incorporating Its Use ML20157A2232020-06-0303 June 2020 Letter to NuScale Requesting -A for TR-0716-50350 ML20150C5172020-05-29029 May 2020 LLC Submittal of Presentation Materials Entitled NRC Public Meeting Presentation: Boron Redistribution and Associated Design and DCA Changes, PM-0620-70336, Revision 0 ML20150E1772020-05-29029 May 2020 LLC - Submittal of Presentation Materials Entitled ACRS Full Committee Presentation: NuScale Topic - Extended Dhrs Operation and RCS Boron Redistribution (Closed Session), PM-0620-70243, Revision 0 ML20150C8812020-05-29029 May 2020 LLC Submittal of Presentation Materials Entitled ACRS Full Committee Presentation: NuScale Topic - Boron Redistribution and Associated Design and DCA Changes, PM-0620-70244, Revision 0 ML20149M1192020-05-28028 May 2020 LLC Summary of Impacts to Erai 8930 Response and Discussion on the Exemption from General Design Criterion 33 ML20141L8082020-05-20020 May 2020 LLC Submittal of Containment Response Analysis Methodology Technical Report, TR-0516-49084, Revision 3 ML20141N0122020-05-20020 May 2020 LLC Submittal of Changes to Final Safety Analysis Report, Section 6.2, Containment Systems, Section 6.3, Emergency Core Cooling System, and Technical Report TR-0516-49084, Containment Response Analysis Methodology Technical Report ML20141M7642020-05-20020 May 2020 LLC Submittal of Nuclear Steam Supply System Advanced Sensor Technical Report, TR-0316-22048, Revision 3 ML20141L7872020-05-20020 May 2020 LLC, Submittal of Second Updates to Standard Plant Design Certification Application, Revision 4 ML20141L8162020-05-20020 May 2020 LLC, Submittal of Long-Term Cooling Methodology, TR-0916-51299, Revision 3 ML20141M1142020-05-20020 May 2020 LLC Submittal of NuScale Instrument Setpoint Methodology Technical Report, TR-0616-49121, Revision 3 ML20141L8042020-05-20020 May 2020 LLC Submittal of Technical Specifications Regulatory Conformance and Development, TR-1116-52011, Revision 4 ML20128J3162020-05-18018 May 2020 OEDO-20-00167 - Response to the ACRS Letter on Combustible Gas Monitoring ML20133K0882020-05-12012 May 2020 LLC, Submittal of Presentation Materials Entitled Public Meeting Presentation: Topic - Emergency Core Cooling System (ECCS) Boron Distribution (Closed Session), PM-0420-69512, Revision 0 ML20133J9142020-05-11011 May 2020 LLC Submittal of Presentation Materials Entitled Public Meeting Presentation: Topic - Emergency Core Cooling System (ECCS) Boron Distribution, PM-0420-69511, Revision 0 ML20112F4552020-05-0101 May 2020 LLC, Design Certification Application Phases 5 and 6 Review Status ML20107F8492020-05-0101 May 2020 OEDO-2000140 - NuScale Area of Focus - Helical Tube Steam Generator Design ML20104A0792020-04-27027 April 2020 OEDO-20-00115 - Safety Evaluation Report for Topical Report TR-0516-49416, Revision 2, Non-Loss-of-Coolant Accident Analysis Methodology ML20099H0802020-04-0808 April 2020 LLC - Submittal of Presentation Materials Entitled NRC Public Meeting: Revisions to Nuscale'S EPZ Sizing Methodology Topical Report, PM-0420-69598, Revision 0 ML20098G2372020-04-0707 April 2020 Nuscale Power, LLC Submittal of Remaining Closure Items for the Emergency Core Cooling System Valve Failure Mode Effects Analysis Audit Items ML20097F1922020-04-0606 April 2020 Nuscale Power, LLC Submittal of Presentation Materials Entitled ACRS Full Committee Presentation: Nuscale Topic - Hydrogen/Oxygen Monitoring, PM-0420-69518, Revision 0 ML20094H6742020-04-0303 April 2020 LLC Submittal of Presentation Materials Entitled ACRS Full Committee Presentation NuScale Topic-Probabilistic Risk Assessment with a Focus on Emergency Core Cooling System Analysis PM-0420-69559, Revision 0 ML20092L8992020-04-0101 April 2020 LLC - Submittal of Updates to Standard Plant Design Certification Application, Revision 4 ML20072M6682020-03-30030 March 2020 Response to NuScale Letter Dated February 24, 2020, on Planned SDA Application Content ML20072H3332020-03-0909 March 2020 LLC - Submittal of Presentation Materials Entitled Public Meeting Presentation: Topic - Emergency Core Cooling System (ECCS) Boron Distribution, PM-0320-69218, Revision 0 ML20057D9002020-03-0606 March 2020 Submittal of Errata to Final SE for NuScale Power, LLC TR-1010-859-NP-A, Quality Assurance Program Description for the NuScale Power Plant ML20062F7262020-03-0505 March 2020 Request for Withholding Information from Public Disclosure for Nuscale Power, LLC Letter Public ML20069A1572020-03-0404 March 2020 LLC - Submittal of Presentation Materials Entitled ACRS Full Committee Presentation: NuScale Topical Report-Rod Ejection Accident Methodology, PM-0320-69146, Revision 0 ML20069A1772020-03-0404 March 2020 LLC - Submittal of Presentation Materials Entitled ACRS Full Committee Presentation: NuScale Topical Report-Non-Loss-of-Coolant Accident, PM-0320-69141, Revision 0 ML20069A9632020-03-0404 March 2020 LLC Submittal of Presentation Materials Entitled ACRS Full Committee Presentation: NuScale Topical Report, Loss-of-Coolant Accident Evaluation Model, PM-0320-69138, Revision 0 ML20066G2802020-03-0303 March 2020 LLC, Submittal of Presentation Materials Entitled ACRS Subcommittee Presentation: NuScale Topic - Hydrogen Monitoring, PM-0220-69071, Revision 0 ML20066G2882020-02-28028 February 2020 LLC Submittal of Presentation Materials Titled ACRS Full Committee Presentation: NuScale - Steam Generator Design (Closed Session), PM-0220-69053, Revision 0 2023-06-29
[Table view] |
Text
LO-0419-65210 April 30 , 2019 Docket No.52-048 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738
SUBJECT:
NuScale Power, LLC Submittal of Updated Planning Information Regarding Future Applications to the Nuclear Regulatory Commission
REFERENCE:
Letter from NuScale Power, LLC to NRC entitled "NuScale Power, LLC Response to NRC Regulatory Issue Summary 2017-18 , 'Process for Scheduling and Allocating Resources for Fiscal Years 2020 through 2022 for the Review of New Licensing Applications for Light-Water Reactors and Non-Light-Water Reactors ,"' dated February 5, 2018 (ML18036B047)
In the referenced letter, dated February 5, 2018 , NuScale Power, LLC (NuScale) responded to NRC Regulatory Issue Summary (RIS) 2017-18. In part, the subject RIS states that the NRC is seeking new or updated information on schedules for submitting certain applications and on the status of a variety of licensing and design-related activities for Small Modular Reactors (SMR). This response included the status of the design , analyses , testing , licensing , and project planning for the NuScale SMR at that time.
The purpose of this letter is to provide updated planning information regarding future applications to the NRC for the NuScale SMR. NuScale's updated plans include an application for a standard design approval. The scope of this application is planned to include a revised Final Safety Analysis report (FSAR), consistent with the scope of Part 2 Tier 2 of the NuScale Design Certification Application (DCA), and the associated changes to topical and technical reports addressing updates to the NuScale plant design.
NuScale plans for pre-application to focus on FSAR content and to obtain NRC agreement with the proposed approach. One goal of pre-application engagement is to achieve a more efficient review, of about 24 months. Efficiencies in review will be supported by: 1) eliminating extraneous detail from the current FSAR, using risk insights where appropriate; and 2) marking the FSAR to distinguish between changes that clearly require NRC re-review, and changes that do not automatically require re-review on the basis of 10 CFR 50.59 criteria. In addition , NuScale plans to revisit risk-informed initiatives that were discontinued for the purpose of maintaining schedule during the DCA. For example , defining "credible" in terms of risk. Such a definition would bring clarity and consistency to the review, and would allow NuScale to benefit from the safety of its design.
NuScale is currently planning to use the application process under 10 CFR Part 52 Subpart E, Standard Design Approval. NuScale requests the NRC to initiate a project number for this application process. NuScale intends to submit an application in second quarter calendar year 2021 , and is planning to initiate pre-application meetings with the NRC in the third quarter of 2019.
NuScale Power, LLC 1100 NE Circle Blvd , Suite 200 Corvallis, Oregon 97330 Office 541.360-0500 Fax 541.207 .3928 www.nuscalepower.com
LO-0419-65210 Page 2 of 2 04/30/19 If you have any questions , please contact Michael Melton, Nu Scale Licensing Manager, at 240-833-3007 or at mmelton@nuscalepower.com.
Sincerely, Distribution: Robert Taylor, NRC , OWFN-8H12 Samuel Lee, NRC , OWFN-8H12 NuScale Power, LLC 1100 NE Circle Blvd , Suite 200 Corvallis, Oregon 97330 Office 541.360-0500 Fax 541.207 .3928 www.nuscalepower.com