Brown Ferry, Units 1, 2 & 3 - Letter Acknowledging Receipt of Request for Adjudicatory Hearing, NPDES Permit No. AL0022080
ML18283A844
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 07/15/1977
From: Little J
US Environmental Protection Agency, Region 4
To: Sanger H
Office of Nuclear Reactor Regulation, Tennessee Valley Authority
References
NPDES AL0022080
Download: ML18283A844 (4)


Text

DISTRIBUTION AFTER ISSUANCE F OPERATING LICENSE

~ OOCKET NUM U.S NUCI.EAR REGULATORV COMM N R NRC rORM 195 I1-7)I xk94 FILE NUMB NRC DISTRIBUTlON FoR PART 50 DOCKET MATERlAL TO: "ROM:U~S ~ Environ+ Protect+ Agency OATE OF OOCUMENT Atlanta, Georgia 7/15/77 Mr. Herbert Sanger John Ao Little OATS R ECEI V E 0 9/1/77 C3NOTORIZEO PROP INPUT FORM NUMBER OF COPIES RECEIVED BETTE R QORIGINAL QVNCLASSIFIEO gCOPV DESCRIPTION ENCLOSURE Acknowledgement of receipt of Mr. Sanger's Request for Adjudicatory Hearing with respect to the Browns Ferry Nuclear Plant~ ~ +~ ~

PLANT NIXIE: Browns Ferry Units 1-2-3 RJL 9/1/77 SAFETY FOR ACTION/INFORMATION BRANCH CHIEF: 7 INTERNAL 0 IST Rl BUTION C PDR I It: E (2)

OELD HANAUER CHECK STELLO EISENHUT SHAO BUTLER GRIMES J. OLLINS EXTERNAL DISTRIBUTION CONTROL NUMBER LPDR:

TIC gr j~

NSIC 16 CYS ACRS SENT CATE 0 Y

'7P+gop P+

/ ~

1 yf05tqp rp

~ni

~c ~nox<

UNITED STATES ENVIRONMENTALPROTECTION AGENCY.

REGiON IV 345 COVRTLAND 5TREET ATLANTA, GEORGlA 30308 3U> ".s-;7-,

" ': -::-..:5'0-4'6 ..

I(, --,*

5a S. Sanger 496 P'I'erbert General Counsel Tennessee Valley Authority 400 Commerce Street Knoxville, Tennessee 37902 .Be Re: Request XZ ~

for Adjudicatory Hearing Browns Ferry Nuclear Plant HPDES Permit No. AL0022080

Dear Hr. Sanger:

This writing will acknowledge receipt of your Request for Adjudi-catory Hearing with respect to the above-referenced facility. Your Request is being considered in accordance with the regulations of. this Agency. \

Prior to a decision by this Agency concerning a grant or denial of your Request for Adjudicatory Hearing, all contested provisions of the NPDES Permit are stayed in accordance with 40 C.F.R. 5125.35 and.

40 C.F.R. 5125. 36.

It is the understanding of this Agency based on your Request and on personal communication with the staff of the Tennessee Yalley Authority at a meeting held in Atlanta earlier this month, that the cooling towers at the Browns Ferry facility are not performing up to design specifications. moreover, your Request indicates that on July 10; 19?7, subsequent to our Atlanta meeting, one of the towers was taken out of service due to a structural failure and that similar failures remain a real possibility for the other'towers at Browns Ferry.

As the contested provisions of your NPDES Permit have been stayed by the submission of your Request, the temperature limitations contained in the Permit are not currently applicable to the Browns Ferry facility.

However, in accordance with the relief sought in your Request, at any time the ambient upstream temperature exceeds SloF. you will be

expected to comply viith the limits of 90oF. maximum temperature and 5oF. maximum temperature rise, both as measured at the dovin-- .

" stream .edge of the assigned mixing zone. "

You.should be prepared

'to discuss and present a strategy for the long-term resolution of

.. -'.these difficulties by October 31; 1977.. A final decision on 'your Request'for Adjudicatory- Hearing ivill be'ade after these discussions..

Since ly, t

, P<y~fy John Alee Little Acting Regi onal Admi ni strator cc: James llarr Alabama Hater Improvement Comm.