MONTHYEARML18270A3642018-09-27027 September 2018 Topics NRC Staff Would Like Exelon to Address at Calvert Cliffs 50.69 LAR Pre-submittal Meeting Project stage: Meeting ML18276A0712018-10-0404 October 2018 Exelon'S Presentation for October 4, 2018 Public Pre-Submittal Meeting on Planned Calvert Cliffs 10CFR50.69 LAR Project stage: Meeting ML18292A8202018-10-24024 October 2018 October 4, 2018, Summary of Pre-Application Meeting with Exelon Generation Co., LLC on Planned Submittal of Licensing Action for Calvert Cliffs Nuclear Power Plant, Units 1 and 2, Risk-Informed Categorization and Treatment Project stage: Meeting 2018-10-04
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24250A1062024-09-0606 September 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24108A1352024-05-20020 May 2024 Email to Christian Williams Re Decision on the Exemption Request for Calvert Cliffs ML24108A1312024-05-15015 May 2024 Email to Christian Williams Re Availability of Environmental Assessment for the Calvert Cliffs Exemption ML24131A0612024-05-10010 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) NRC-2024-0085, Response from State of MD Regarding Review of EA for Calvert Cliffs Exemption Request2024-05-0909 May 2024 Response from State of MD Regarding Review of EA for Calvert Cliffs Exemption Request ML24122B5072024-05-0101 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-591, Revision 0 ML24131A1212024-04-29029 April 2024 Email to State of MD Requesting Review of the EA for Calvert Cliffs Exemption Request ML24012A0492024-01-11011 January 2024 Request for Additional Information Regarding Final Response to Generic Letter 2004-02 ML23311A1682023-11-0707 November 2023 NRR E-mail Capture - Constellation - Fleet Request - Acceptance of Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections (L-2023-LLR-0053 and L-2023-LLR-005 ML23311A1692023-11-0707 November 2023 NRR E-mail Capture - Constellation - Fleet Request - Acceptance of Proposed Alternative for Examinations of Exam Categories B-B, B-D, and C-A SG Pressure Retaining Welds and Full Penetration Welded Nozzles (L-2023-LLR-0055 and L-2023-LLR-00 ML23304A0152023-10-30030 October 2023 NRR E-mail Capture - Final RCI - Constellation Energy Generation, LLC - Calvert Cliffs 1 & 2 - Exemption from Security Rule (L-2023-LLE-0033) ML23181A0732023-06-30030 June 2023 NRR E-mail Capture - Acceptance Review for Calvert Cliffs TSTF-59A ML23160A0222023-06-0606 June 2023 NRR E-mail Capture - Calvert Cliffs - Long Term Coupon Surveillance Program RAI ML23156A0102023-06-0404 June 2023 NRR E-mail Capture - Calvert Cliffs - RAI License Amendment Request for Emergency Desiel Generator ML23080A0672023-03-21021 March 2023 NRR E-mail Capture - Acceptance Review for Calvert Cliffs Unit 1 - LAR to Modify the Long-Term Coupon Surveillance Program ML23080A1002023-03-21021 March 2023 NRR E-mail Capture - Acceptance Review for Calvert Cliffs Repair Replacement of Saltwater System Buried Piping ML23026A1332023-01-26026 January 2023 NRR E-mail Capture - Acceptance Review for Calvert Cliffs Deletion of License Condition for Decommissioning Trust LAR ML22354A2622022-12-20020 December 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Request to Use Certain Provisions of the 2019 Edition of the ASME BPV Code, Section XI ML22342B1462022-11-21021 November 2022 NRR E-mail Capture - Acceptance Review for TSTF 295A ML22325A0052022-11-18018 November 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-273-A, Revision 2 ML22255A0132022-09-0909 September 2022 NRR E-mail Capture - NRC Acceptance Review of Braidwood, Byron, Calvert Cliffs, Ginna - License Amendment Request to Adopt TSTF-577 ML22200A0782022-07-19019 July 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request to Use Honeywell Mururoa V4F1 R Supplied Air Suits ML22271A0772022-05-0606 May 2022 NRR E-mail Capture - Final RAIs 9.1.2021 Constellation Relief Request ML22129A0132022-05-0606 May 2022 NRR E-mail Capture - Draft RAIs for Requests for Alternatives I4R-17, I4R-23, ISI-05-018, I6R-10 ML22091A2392022-04-0101 April 2022 NRR E-mail Capture - Calvert Cliffs - Formal RAI for Proposed Alternative for Examinations of Certain Pressurizer Welds ML22091A0852022-04-0101 April 2022 NRR E-mail Capture - Braidwood and Byron - Final RAI Regarding Proposed Alternative for Various Pressurizer Welds (EPID L-2021-LLR-0035 and 0036) ML22091A2402022-03-23023 March 2022 NRR E-mail Capture - (External_Sender) Salem Generating STATION-INCIDENTAL Take of Atlantic Sturgeon Collected on 03/22/2022 ML22075A1912022-03-16016 March 2022 NRR E-mail Capture - Acceptance for Review of Proposed Alternative Repair Method for Buried Class 3 Saltwater System Piping ML22088A1562022-03-0202 March 2022 NRR E-mail Capture - Byron, Braidwood, Calvert Cliffs, and Ginna - Non-acceptance of Application to Revise Technical Specifications 5.6.5.b, the Core Operating Limits Report (COLR) ML22059B0602022-02-28028 February 2022 Change to Review Schedule Regarding Proposed Alternative for Various Pressurizer Welds ML22060A0172022-02-23023 February 2022 NRR E-mail Capture - Calvert Cliffs Nuclear Power Plant, Units 1 and 2 - Withdraw of Draft RAI Regarding Proposed Alternative for Various Pressurizer Welds ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML21281A1402022-01-14014 January 2022 Acceptance for Review of Proposed Alternative ISI-05-018 for Examinations of Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles ML21301A0672021-10-28028 October 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-541 ML21295A5712021-10-22022 October 2021 NRR E-mail Capture - Acceptance for Review of Proposed Alternative ISI-05-019 for Pressure Testing of Certain Portions of ASME Section XI Class 2 Auxiliary Feedwater Piping ML21287A0322021-10-13013 October 2021 Request for Additional Information Re Proposed Alternative for Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds ML21286A5902021-10-0505 October 2021 Acceptance for Review of Proposed Alternative ISI-05-017 for Examinations of Examination Category C-B Steam Generator ML21287A0932021-10-0505 October 2021 Request for Additional Information: Calvert Cliffs 1 & 2 LAR to Revise Spent Fuel Pool Cooling - Shutdown Cooling Systems Licensing Basis (EPID L-2021-LLA-0112) (Email) ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21214A0202021-08-0909 August 2021 License Amendment Request to Change Spent Fuel Pool Cooling Design Basis ML21215A3502021-08-0303 August 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-554 ML21201A0482021-07-19019 July 2021 Acceptance of Requested Licensing Action to Change Spent Fuel Pool Cooling Design Basis ML21180A1562021-06-28028 June 2021 Request for Additional Information Regarding License Amendment Request Concerning Containment Sump ML21152A1232021-06-0101 June 2021 Acceptance for Review of Proposed Alternative ISI-05-016 Involving Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds (EPID L-2021-LLR-0037) (Email) ML21154A0132021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0112021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0142021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21117A0442021-04-26026 April 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting 2024-09-06
[Table view] |
Text
From: Marshall, Michael To: "Villar, Enrique:(GenCo-Nuc)"
Subject:
FYI: Topics NRC Staff Would Like Exelon to Address at Calvert Cliffs 50.69 LAR Pre-submittal Meeting (L-2018-LRM-0059)
Date: Thursday, September 27, 2018 7:42:00 AM Hello Rick, Two of the benefits of pre-submittal meetings are making sure the NRC staff and licensee have a shared understanding of (1) the content needed in a submittal for acceptance and (2) the level of detail needed in a submittal to minimize the need for RAIs. In order for Exelon to gain the maximum benefit from the pre-submittal meeting, the following topics should be addressed in Exelons presentation to the NRC staff at the October 4th public pre-submittal meeting:
- Describe the integrated, systematic process being used to support the risk-informed categorization and treatment of SSCs.
- Describe whether the case studies in the EPRI report are bounding for Calvert Cliffs.
- Describe how the proposed approach addresses the discussion in Section II.1.2 of the statements-of-consideration for 10 CFR 50.69.
- Identify any differences between the approved Limerick 50.69 LAR and the planned Calvert Cliffs 50.69 LAR.
- Identify which portions of the EPRI report (or information in the EPRI report) will be included in the submittal.
- Identify which portions of the EPRI report that Exelon will be using as the technical justification for the planned amendment.
- Describe whether the alternative approach described in the EPRI report can be considered a bounding approach.
- For the PRAs used in the case studies, state whether the PRAs have been used to support NRC approval of licensing actions comparable to the planned 50.69 LAR.
- For the SPRAs used in the case studies in the EPRI report, describe whether peer-review findings have been appropriately addressed for risk-informed licensing actions and whether SPRA peer-review findings have been closed out using an NRC-approved process.
- Discuss the relevance of the Near Term Task Force 2.1 evaluations in determining the appropriate tier for the proposed alternative approaches considering the differences in scope and purpose.
- Discuss why correlated failures that are evaluated for Tier 2 plants are not considered for Tier 1 plants (i.e., why Tier 2 evaluations are not performed for Tier 1).
- Describe how risk significant SSCs identified by fire PRA will be addressed considering the incorporation of a new approach that relies on fire PRA models to identify SSCs that are important to safety.
- Describe - how Exelon will address the potential hazard changes that may change the current proposed Tier 1 classification in the future and therefore, the categorization approach with respect to seismic risk.
If Exelon plans to use any presentation material during the public meeting, please provide a
copy of the presentation material to me at least two days prior to the meeting.
Best Regards, Michael L. Marshall, Jr.
Senior Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation 301-415-2871