ML18102A780

From kanterella
Jump to navigation Jump to search
Insp Rept 50-311/96-81 on 961202-13.No Violations Noted. Major Areas Inspected:To Conduct Independent Insp to Determine If Plant,Unit 2 CC Sys Would Perform Intended Safety Function
ML18102A780
Person / Time
Site: Salem 
Issue date: 01/21/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML18102A779 List:
References
50-311-96-81, NUDOCS 9701270185
Download: ML18102A780 (74)


See also: IR 05000311/1996081

Text

Docket No:

License No:

Report No:

Licensee:

Facility:

Location:

Dates:

Inspectors:

Approved by:

9701270185 970121

PDR

ADOCK 0500031l

G

PDR

.

. . ..~.,*---*:--/ :..::.: -*.

.. -.. ~ . -.. :-

.' . ." *-:.

U.S. NUCLEAR REGULATORY COMMISSION

50-311

DPR-75

50-311196-81

REGION I

Public Service Electric & Gas Company

Salem Nuclear Generating Station, Units 2 .

Hancocks Bridge, New Jersey 08038

December 2-13, 1996

J. Trapp, Team Leader, DRS

S. Klein, Reactor Engineer, DRS

G. Morris, Reactor Engineer, DRS

L. Prividy, Sr. Reactor Engineer, DRS

W. Sherbin, Contractor

S. Stewart, Sr. Resident Inspector, DRP

James T. Wiggins, -Director

Division of Reactor Safety, Region I

  • .. ,: '-*

TABLE OF CONTENT$

EXECUTIVE: SUMMARY ...... ** . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iv

03

Operations Procedures and Documentation . . . . . . . . . . * * * . * . . . . . . . . . . . 1

03. 1 Emergency Operations Procedures and Single Failures * * . * . . . . . . . . . 1

03.2 Operating and Abnormal Procedures * * . . . . * * * . * * . . * . * * . . * . * . * * 4

05

Operator Training and Qualification . * . . * . * . * * . * * * * * * * * * * * * * * * * * * * * * . 5

05.1 .. Training Material and Simulator Fidelity *.***** ** * * * * * * * * * * * * * * * * 5

__ , -.*

M 1

Conduct of Maintenance . . . . . . . . . . . . . . . . . . . .. . . . . . . . * . . . . . . . . . . . 6

M 1. 1 System Flow Balance Test * . . * * * * * * * * * * * * * * * * * * :. ; * * * * * * * * * ** * 6

M1 .2 Pump and Valve Testing ................... * ...*

  • ~~-~~~~~:-........ -~-~~~-~::9-

M1 .3 Maintenance and Testing of Heat Exchangers **** -** O..~'. * * * . * . . . . 12 *

M1 .4 -Testing of Instrumentation and Controls (l&C) *.. ~ : * * * * * * * * * . * . * 15

  • *M2
  • Maintenance and Material Condition of Facilities and Equipment * . * * * * * * * * 16

M2.1 >CC Radiation Monitors .. ~ .....* *. ~ **....*... * * ~~- ... _* .*... * ~ .. : *. .

1*6

M2.2 Root Cause Evaluations and Corrective Actions for System Failures * * * 17

-

.

M3

Maintenance Procedures and Documentation ....***. ~ . . * * * * * . * * * . . . * 18

M3.1 Ventilation System Testing and Documentation ****** -* * * . * * * * * . . 18

-... M3.2 Test Procedure Acceptance Criteria . . * . . * * * * * * * . * * * * * * * * * * * . * 19

E1

Conduct of Engineering . . * . . * * . * . . . . * * . . . . * * * * * . * * * * * . . . . . . . . * . 22

E1 ;-1' Component Cooling Pump Runout and NPSH * * * . * * * . * * * . * * * * . . . 22

E 1*.2

CC Pump Room Ventilation * . * . . . . * * * . * * * * * . . * * * * * . * * * * * * * . 26

E1 .3 Pump Seal Water Cooling . * *. * . . * * * * . * * * . * * . * * * * * * * * . . * . * * * 27

E1 .4 Electrical Protective Devices .......***. * * . . .. . . * * * * * * * * . . . . . . 28

E1 .5 Setpoint Control . * * * . * . * * . . . . . * . . . . * * * . * . . . . * * * . * . . . . . . 33

E1 .6 Equipment Power Supplies * . * . . . . . * . . . . . * . . * * * . . * * * . * . . . * * 34

E3

Engineering Procedures and Documentation * . * . . . * * . * * * * * * * * * * . . . * . * 36

E3.1

.Electrical Calculations * * . * * * * . * . . . * * * * * * * * * * * * * * * * * * . * . * * 36

E3.2

Technical Standards . * . . * * * * . . * * . . . * * * * . * * * * * * * * * . * . . . . * 38

E3.3

Drawing Control ...................... ~ ... -. . . . . . . . . . . . . 40

E3.4 Configuration Baseline Document * . . * . . . * . * * . * * * * * * * . . . . . * * * 41

ii

ES

TABLE OF CONTENTS (CONT'D)

Miscellaneous Engineering Issues * * * * * * . * * * * . * * * * * * * * * * * * * * * * * * * * 42

ES. 1

Post Accident Sampling System Heat Exchangers

. . * * * * * * * * * * * * * 42

E8.2

Licensing Basis Verification * * * * * . * * * * . . * . * * * * . . . * . . * * * * * * * * 43

E8.3

Licensing Basis Updates . * * * * * * * . * * * * * . * . * * * * * * * * * * * * * * * * * 45 *

E8.4

Probabilistic Safety Assessment * * * * * * * * . * . . * * * * * * * * * * * * * * * * 46

. *;_-;_

  • X 1

Exit Meeting Summary * * * * * * .* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * 4 7

--. ..-

iii

Report Details

The objective of this inspection was to conduct an independent inspection to determine if

the Salem Unit 2 component cooling* (CC) system would perform its intended safety

function. The scope of the inspection included verifying that the system had a technically

sound design and licensing basis, system components were tested to demonstrate design

requirements, and operating practices and procedures were consistent with the design.

The team used the guidance provided in NRC Inspection Manual Chapter 93801, Safety

System Functional Inspection (SSFI), to conduct this inspection activity.

The team noted that significant improvements were made to the CC system during the

current outage. These improvements included the completion of a system flow balance,

resolving instrument calibration errors, and the completion a significant number of

corrective and preventive maintenance activities. The team found that the licensing basis

CC description was, with a few exceptions, consistent with the actual CC system's design

and operation. However, the team did identify two design issues regarding the CC pump

room ventilation and the maximum acceptable flow limit for the CC pump, where operating

practices were inconsistent with system design information. The resolution of these issues

was ongoing at the conclusion of this inspection. The team concluded that contingent

upon the satisfactory resolution of the SSFI findings and the licensee's already identified

CC system restart issues, the Salem Unit 2 CC system would perform its intended safety

function.

I. Operations

03

Operations Procedures and Documentation

03.1

Emergency Operations Procedures and Single Failures

a.

Inspection Scope

The team reviewed the PSE&G contingencies for emergency operations to verify

that plans and emergency operating procedures were consistent with the design

bases for the CC system.

b.

Findings and Observations

CC Pump Operability Requirements

The Salem Updated Final Safety Analysis Report (UFSAR), Section 9.2.2.3, states

that "In the event of a_ loss-of-coolant accident (LOCA), one pump and one heat

exchanger are capable of fulfilling system requirements." Salem Unit 2 Technical

Specification 3. 7 .3 requires two independent CC loops to be operable in Modes 1,

2, 3, and 4 *

2

In early 1995, PSE&G identified that certain emergency scenarios could place a

single running CC pump in a runout (excessive flow) condition. Specifically, if a

standby CC pump was out-of-service for any reason and a LOCA occurred

coincident with a loss of offsite power and failure of a vital bus (which fails a

second CC pump), two residual heat removal (RHR) heat exchangers would

automatically be placed in service with only one operable component cooling pump. *

This alignment resulted in a single CC pump providing flow to two RHR heat

exchangers. The licensee determined that this condition could be resolved by

operating two CC pumps when two RHR heat exchangers were inservice. As an

interim measure, in March 1995, PSE&G operations established an operating policy

wherein if any one of the three CC pumps were not available, the technical ': :- : * *

specification action statement for an inoperable CC loop would be entered. The

operating policy provided added assurance that two CC pumps would always be

available.

  • :

The EOPs could have been revised to include contingencies for single CC pump

operation; however, to reduce decisional steps and to allow for simplification of the

EOPs for the LOCA, the initial availability of two CC pumps was assumed.

Minimizing operator decision steps in the EOPs assured completion of the

realignment of valves from the refueling water storage tank (RWST) injection phase

to containment sump recirculation phase within an established time limit that

assured adequate core cooling. Appropriate contingencies for loss of a vital bus

and accompanying equipment were included in the EOPs.

CC Pumo Room Ventilation (For additional information see Section E1 .2)

The team reviewed the EOPs and the need for two operable CC pumps in the

accident mitigation strategy. The EOPs were found consistent with the PSE&G

operating policy. However, the team questioned PSE&G on the need for the CC

pump room ventilation and whether the ventilation system controls were adequate

to support three CC pump availability under normal and accident conditions.

The 21 CC pump room ventilation equipment (2VHE-33) and the 23 CC pump are

provided power from electrical Train C. The 22/23 pump room ventilation

equipment (2VHE-34) and the 22 CC pump are provided electrical power from

Train B. The 22/23 CC pump room ventilation equipment (2VHE-34) is common for

both the 22 and 23 CC pumps. Electrical Train A provided power to the 21 CC

pump. A failure of Train C electrical power would prevent operation of the 21 CC

pump ventilation equipment (2VHE-33) and the 23 CC pump. A failure of the 22/23

room ventilation equipment (2VHE-34) or electrical Train B would result in the

failure of room cooling for both the 22 and 23 CC pumps. The failure of the room

ventilation* equipment may fail the associated CC pump. The team identified that,

during certain accident scenarios and conditions, the EOPs require at least 2

operable CC pumps. If less than 2 CC pumps are operable, then the EOP

instructions cannot be completed to ensure adequate CC will be available .

3

PSE&G reviewed the team's concerns and determined that plant operations prior to

the decision to administratively require three CC pumps for technical specification

operability could have resulted in operations outside of the plant's design bases.

Specifically, for periods prior to 1995, when the 21 CC pump was out-of-service,

the postulated single failure of the 22/23 CC pump room cooler could have resulted

in a condition where no CC pumps would be available for accident mitiga~ion. The

postulated single failure of the 22/23 CC room cooler was a condition that had not

been evaluated by PSE&G and was a condition that alone could have prevented the

fulfillment of the safety function of the CC system. PSE&G made a notification of

their determination to the NRC in accordance with 10 CFR 50. 72(b)(2)(iii),- on

November 25, 1996.

.*.~-.. * : * *.

The team was informed that PSE&G was considering a licensing bases change to .

revise the requirement for CC pump operability to capture the need to have three.

pumps operable during plant operations. Resolution of ventilation concerns would

be required to support the change. PSE&G made resolution of the ventilation issue

a Mode 6 (Refueling) prerequisite.

CC Pump Runout (For additional information see .Section E1 .1).

The team observed that, even if standby electrical power w:re

0

availabl:~ {~:~he .three

CC pumps and to the room ventilation equipment, an EOP directed alignment allows

one CC pump to be placed in an apparent runout condition for a short time during a

postulated LOCA event coincident with a loss of offsite electric power. In the

Salem EOPs, one CC pump is started in the initial steps following the reactor trip at

the onset of the postulated event. During the change from the injection to the

recirculation lineups, in Salem procedure EOP-LOCA-3, the CC valves from the two

RHR heat exchangers are automatically opened prior to start of a second CC pump.

The second pump was manually started following the valve alignment change. The

entire change from injection lineup to the recirculation lineup is designed to be

completed in less than 12.5 minutes following receipt of the RWST low level alarm

at 15.2 feet. PSE&G operations had demonstrated that the second pump would be

started in less than eight minutes from the onset of the runout condition. PSE&G

personnel stated that single pump operations for a short period of time had been

evaluated; however, the team questioned the flow rate limit that had been used in

the evaluation.

The team was concerned that a single CC pump operating with both RHR heat

exchangers in service would result in CC pump flows in excess of that previously

evaluated and could result in pump damage. The team was also concerned that the

overall electric loadin9 of the emergency diesel generator supplying power to the CC

pump, when in the runout alignment, may be higher than previously evaluated. In

response to these issues, PSE&G initiated an action request (AR) and initiated both

an engineering review of the issue and a root cause evaluation .

... :_ ..... _.

'-.*-.

4

c.

Conclusions

PSE&G had identified that emergency operations for some postulated events could

result in operation beyond the design of the CC pumps. As an interim measure, in

1995, PSE&G operations initiated a policy to ensure that at least two CC pumps

were operable during plant operation. The policy to ensure that at least 2 CC

pumps would always be available failed to appropriately account for a single failure

of CC pump room ventilation. The failure of the 22/23 CC pump room cooler, ,vvhen

the 21 CC pump was out of service, could have resulted in no available CC puinps

during some postulated accident conditions. The failure to have considered. thisj .. _.~*

design deficiency remains unresolved pending NRC review of this issue for potential

enforcement action (URI 50-311/96-81-01).

-

The team identified that the operating policy of having three operable CC pti111ps .. ,.

failed to properly consider the affect of a loss of cc pump room ventilation orl'pump

operability. The failure of the EOPs to account for a* single failure of CC pump room

ventilation is an NRC unresolved item pending the completion of the licensee's

corrective actions and the review of this issue by the NRC for potential enforcement

action (URI 50-311/96-81-02).

  • , *-"

The team identified that the EOPs allowed a CC pump to operate at flow rates

beyond its documented design limits for a short period of time. The failure to

provide a technically sound basis for operating a CC pump in this manner remains

unresolved pending the completion of the licensee's corrective action and the

review of this issue by the NRC for potential enforcement action (URI 50-311/96-

81-03).

03.2 Operating and Abnormal Procedures

a.

Inspection Scope

The team reviewed the CC system operating and abnormal procedures to verify the

procedures instructions properly reflected the system design.

b.

Observations and Findings

The team found that current revisions of operating procedures were in place to

support CC system operations. The procedures had been recently revised and

included enhancements such as basis sections for each procedure to describe

commitments and reasons for various steps, and detailed sections for contingency

actions when abnormal procedures were used *


--


------

5

The team identified a procedure discrepancy concerning when to trip rea~t~r coolant

pumps (RCPs) on loss of all component cooling. The discrepancy involved whether

to immediately trip all RCPs on loss of CC, as stated in the CC abnormal procedure,

or to allow five minutes for CC restoration as specified in the RCP abnormal

procedure. PSE&G personnel stated that 10 minutes of RCP operations without CC

was allowed by the technical manual for the pumps, however a previous

commitment to the NRC stated that the pumps would be conservatively tripped

immediately on total component cooling water loss. PSE&G prepared an action

request to resolve the discrepancy.

c.

Conclusions

Operating procedures related to normal and abnormal operations of the component

cooling water system had been recently upgraded by PSE&G, and the ~ea.m _

_~,>, - *

considered the improvements to be a good initiative. The team conCluded that the

CC procedures were generally of good quality and appropriately reflected the CC

system design and licensing basis. However a discrepancy was identified on when

to trip reactor coolant pumps on total loss of CC.

05

Operator Training and Qualification

05.1 Training Material and Simulator Fidelity

a.

Inspection Scope

The team reviewed operator training for the component cooling system to verify

that appropriate design information was provided to the operators. The review

included an assessment of the technical completeness and accuracy of appropriate

training materials and examination tools. The fidelity of the plant simulator

regarding the CC system was also reviewed.

b.

Findings and Observations

PSE&G performed a crew readiness assessment in January 1996 to evaluate the

preparedness of the reactor operators for resumption of plant operations. The

examination was conducted in three parts, a written examination, simulator.

scenarios, and a plant walkthrough evaluation. After a detailed evaluation of the

examination results, PSE&G concluded that no specific weaknesses existed in

operator knowledge regarding CC system operations and design. Therefore, no CC

specific training was required before restart.

A CC lesson plan had* been prepared and was awaiting final supervisory review* and

approval. The team reviewed the training plan and found that design information

had been appropriately included. At the time of this inspection, the lesson plan had

not been used. The requalification examination bank for written evaluation and job

performance measures was reviewed by the team, and CC design and operations

information was appropriately included .

.::*

6

The team reviewed simulator fidelity for full power CC operations, abnormal

operations, and response to the loss of offsite power and loss of coolant combined

with loss of offsite power events. In each case, the simulator appropriately

modeled CC system performance and provided effective training for these events.

The team was informed that extensive training on recently revised EOPs had been

conducted and had included CC operations. Simulation of remote shutdo~n panel

operations was not provided, and training on these operations was done by in-plant

discussions and walkthroughs.

The team found that the operating, abnormal, and emergency operating procedures

in use at the training facility were current and of high quality. Instructors were**

knowledgeable of CC specific operations and training provided to evaluattitthe_

operations.

_ . .

  • * * 'f/i*:

c.

Conclusions

M1

The team found that PSE&G had translated appropriate CC design information into

materials used for training and evaluating licensed operators. The simulator

provided an effective tool for training and evaluating CC operations during normal

~nd accident conditions. The procedures and lesson plans used for CC training *

were of high quality and appropriately complete for evaluation of operator -

knowledge and abilities on the CC system *

II. Maintenance

Conduct of Maintenance

M1.1 System Flow Balance Test

a.

Inspection Scope

b.

The team reviewed a special flow balance test that was conducted to verify that the

CC system would perform consistent with assumptions in the accident analysis.

The test procedure was reviewed to verify that proper acceptance criteria were

established for assuring adequate CC flow to safety-related equipment during

postulated accident conditions.

Observations and Findings

On July 18, 1996, PSE&G initiated performance improvement request (PIR)

960709221 to identi~y and resolve a concern regarding whether the required

component cooling flow through the residual heat removal heat exchanger (RHRHX)

during a LOCA alignment would be obtained. PSE&G concluded that t.he best

alternative to resolve the concern was to perform a special test in accordance with

Procedure No. TS2.SE-SU.CC-0001 (0), CC System Flow Balance. in a 10 CFR

50.59 evaluation of this procedure, which was conducted in October 1996, PSE&G

described the limiting LOCA alignment for the CC system as follows: one CC pump,

one CC heat exchanger, one RHR heat exchanger, all the emergency core cooling

-.

--..;:

... *.~*.:

..

. 7

system pumps, and the non-isolated, non-safety loads. The non-isolated, non-

safety loads for Unit 2 include: the positive displacement charging pump, the seal

water heat exchanger, the waste gas compressors, and radiation monitor system

(RMS) heat exchangers.

The two main purposes of the flow balance test were:

To ensure that the CC system safety-related components would receive

design flow in the limiting LOCA alignment with one train of the CC system

available.

To benchmark a CC system hydraulic flow model that had been developed

by a contractor and was being reviewed by PSE&G.

The CC system manager and the *cognizant mechanical design engineer presented

the results of the flow balance test to the Salem Unit 2 test review board during a

November 21, 1996 meeting which was observed by the team. PSE&G identified

the m_ajor test deficiencies. as follows:

The 21 and 22 RHR control room CC flow indicators read approximately .

1000 gpm higher than the temporarily installed ultrasonic flow measuring

instruments.

The CC flows for the 21 and 22 centrifugal charging pumps mechanical seal

heat exchangers were 9.5 and 10.8 gpm respectively compared to the

required test acceptance value of 11.5 gpm. The team also noted that

UFSAR Table 9.2-3 specified the CC flow to these components as 14 gpm

(max). The cognizant mechanical design engineer indicated that the pump

manufacturer had confirmed the minimum CC flow requirement to be 6 gpm.

On this basis the test results were considered acceptable. PSE&G stated

that UFSAR Table 9.2-3 and applicable plant procedures would be updated

accordingly.

During the latter portion of the flow balance test, lower than required flow

readings were observed using the local flow indicator (2FIC643A) for the 21

safety injection (SI) pump seal water heat exchanger. PSE&G attributed the

problem to a malfunction of 2FIC643A since initial flow readings from this

instrument for a comparable system alignment resulted in flows greater than

the required flow of 11.5 gpm. Work order (WO) 961031116 was issued to

troubleshoot and repair 2FIC643A.

During the initial flow balance of the system in accordance with Sectio~ 5~ 1

of Procedure No. TS2.SE-SU.CC-0001 (0), the CC flow to the 24 reactor

coolant pump thermal barrier as read on local flow indicator (2Fl620) was 38

gpm versus the required flow of 40-42 gpm. The cognizant design engineer

stated that 38 gpm was acceptable with the pump manufacturer.

8

During discussions between the team and the cognizant mechanical design

engineer, it was apparent that allowances for instrument error and CC pump

degradation had been considered to establish reasonable acceptance criteria for the

flow balance test. For example, the required CC flow to support operability of the

21 SI pump was 10 gpm (UFSAR Table 9.2-3). The cognizant mechanical design

engineer indicated that 5% of full instrument range ( +/- 1 gpm) was required to

account for instrument error and a 3-4% flow allowance was needed to account for

a 10% degradation in pump head. Therefore, the acceptance criteria for the 21 SI

pump CC flow was established as 11.5 gpm in the flow balance test procedure.

PSE&G had discussed this general approach for establishing CC flow acceptance

criteria in Action Request 961003083 which was issued to resolve the minimum

required CC flow to the 21 and 22 centrifugal charging pumps mechanical seal heat

exchangers. However, there were no documented calculations to support the CC*

flow acceptance criteria used in the flow balance test procedure. Pending PSE&G's

completion and documentation of the calculations. su.pporting the test acceptance

criteria and review by the NRC for potential enforcement action, this issue is

unresolved (URI 50-311196-81-04).

The team also noted that documented calculations had not been completed for the

required CC flow values to be incorporated into CC system procedures, such as the

CC pump surveillance test procedures, S2.0P-ST.CC-0001(Q), -0002(0), and -

0003(0), The team noted that an allowance for repeatability between surveillance

tests should be considered in establishing the acceptance criteria, This

consideration was illustrated by the following anomaly which could not be explained

by the CC system manager or the cognizant mechanical design engineer. CC flow

provided to the 21 RHR pump seals met the test acceptance criteria during the

performance of the flow balance test (11.5-13.0 gpm measured in October 1996

with 21 CC pump) while the flow recorded during a later troubleshooting procedure

did not (10.5 gpm measured in December 1996 with 23 CC pump). The team

noted that this anomaly was exacerbated by the fact that the 23 CC pump was the

strongest (i.e., highest developed head for a given flow) of the 3 CC pumps.

Therefore, the 23 CC pump should have provided more flow than the 21 CC pump

for the comparable CC system alignment.

c.

Conclusions

It was apparent that PSE&G had attempted to include reasonable acceptance criteria

into the flow balance test. However, final conclusions regarding the results of the

flow balance test could not be made pending completion of the calculations required

to properly document the CC flow acceptance criteria specified in Procedure No.

TS2.SE-SU.CC-0001_(Q).

9

M1 .2 Pump and Valve Testing

a.

Inspection Scope

Testing was reviewed to verify adequate pump and valve performance to support

system operability. The review included PSE&G's implementation of the inservice

test (IST) program and corrective actions taken to resolve deficiencies found during

IST program Audit 95-0125.

b. *

Observations and Findings

Pumps

The team reviewed PSE&G's actions regarding periodic testing of CC pumps. **Based

on a review of test records, the team noted that PSE&G was adequately testing the

CC pumps in accordance with the Salem IST program requirements. * The team also

noted that PSE&G had made a number of changes to improve pump testing in

response to the findings of Audit 95-0125. For example, AR 9507221196 had .

been issued to resolve a significant pump testing problem. The CC pump test

procedure had been written such that flow was not closely controlled which. *

resulted in questionable repeatability of test results for trending pump performance.

The team verified that the CC pump test procedures were corrected to ensure

adequate test repeatability.

Notwithstanding the changes made to improve the pump testing at Salem, the team

noted that several substantial CC pump testing activities, which the licensee had

identified as needing to be addressed, were not done at the time of this inspection.

The first activity involved elevated vibration readings for the three CC pumps which

have recently been observed. PSE&G has issued a troubleshooting procedure per

WO 960928055 to evaluate this problem. Also, after the documented pump

acceptance criteria has been developed based on the flow balance test, the pump

test procedures would need to be revised and pump baseline testing needed to be

reperformed.

Relief Valves

The team reviewed PSE&G's program for testing relief valves in the CC system.

The review included PSE&G's preliminary response to Generic Letter (GL) 96-06,

Item 3, regarding potential overpressurization of piping caused by thermal expansion

of trapped fluid between closed valves.

In the Salem IST prog.ram basis data sheets, PSE&G documented the basis for all

CC relief valves concerning their inclusion or exclusion from the American Society

of Mechanical Engineers (ASME)Section XI IST program. The team had the

following comments upon reviewing these data sheets:

10

PSE&G concluded that the CC excess letdown heat exchanger outlet relief

valve (2CC112) did not provide a safety function. PSE&G considered that

this thermal relief valve was not required to be in the scope of the IST

program because inadvertent opening of this relief valve combined with

subsequent failure to reclose would not prevent the excess letdown heat

exchanger from performing its function. However, the team determined that

2CC112 does perform a safety function since it is relied upon to provide

thermal relief protection for CC piping between containment isolation valves

2CC113 and 2CC115. Hence the relief valve should be periodically tested to

provide ongoing assurance regarding its operational readiness. The team

noted that the piping between 2CC113 and 2CC115 was identified by

PSE&G in their preliminary response to GL 96-06 as requiring relief

protection. PSE&G indicated that, even though relief valve. 2CC112 was not

currently in the IST program, it had been tested satisfactorily on

September 27, 1996. PSE&G stated that 2CC112 would be included in a

periodic surveillance test program.

PSE&G had appropriately included in the IST program the relief valves (21,

22, 23, and 24CC129) which protect the CC piping associated with thermal

barrier cooling for the reactor* coolant pumps, and the vacuum breaker

(2CC148) and relief valve (2CC147) for the CC surge tank. The team also

verified satisfactory testing of these valves.

Manual Valves

The Salem EOPs included steps to isolate both the boric acid evaporator and the

spent fuel pool heat exchangers from component cooling following certain

postulated accidents. These steps were intended to prevent runout of the single CC

pump started at the onset of the event. The team indicated that the manual

isolation valves specified by the EOPs were not included in the inservice testing

program and, therefore, could not be credited as operational. The team considered

that operation of the valves could not be assured if periodic testing and monitoring

was not accomplished. Further, for some interim period prior to shutting the valves

but after a CC pump was started, the pump could be in a runout condition. PSE&G

responded to the concern by demonstrating that in some* scenarios, runout of the

operating CC pump would result in the CC low header pressure alarm which could

cause the reactor operator to isolate the non-safeguards CC header using valves

CC-30 and CC-31, which were included in the IST program. This action could not

be expected to be accomplished until some time after the CC pump had been

operating in a runout condition. PSE&G had not evaluated this condition.

11

The team observed that no CC system manual valves were included in the scope of

the Salem IST progra*m. However, as stated above, the Salem EOPs included * .*

specific operating instructions regarding manual valves to isolate both the boric acid

evaporator and the spent fuel pool heat exchangers from component cooling.

PSE&G issued AR 961202179 to address the apparent inconsistency between the

EOPs and the IST program regarding manual valves. PSE&G committed to resolve

this inconsistency by establishing a periodic surveillance test for the applicable

manual valves.

Power Ooerated Valves

The team reviewed testing of several power operated valves in the Salem IST

program including MOVs and the CC surge tank vent which is a solenoid, air >

operated globe valve. The team also reviewed testing of the service water system

solenoid air operated valves (21 and 22SW129) that supply cooling water to the CC

pump room coolers. PSE&G had appropriately included power operated valves for

the CC system in the IST program.

Valves 21 and 22SW129 were being adequately stroke time tested in accordance

with Procedure S2.0P-ST.SW.0014(Q), Rev.3, lnservice Testing, Room Cooler*

Valves. In reviewing the testing of MOVs, the team noted that PSE&G recently

reviewed the thrust limits for the RHR heat exchanger outlet valves (21 and

22CC16) to be consistent with their response to GL 95-07, Pressure Locking and

Thermal Binding of Gate Valves. The team verified that the maximum thrust limits

for these MOVs would be limited to minimize valve closure thrusts and thus prevent

thermal binding upon opening. Maximum closure thrust values (28,611 lbs for

21CC16 and 26,566 lbs for 22CC16) not to be exceeded during testing were

established in the Managed Maintenance Information System. Diagnostic test

procedures required adherence to these limits while testing these MOVs.

Check Valves

The team reviewed the acceptance criteria that was included in Procedure S2.0P-

ST .CC-0001 (Q), 21 CC Pump lnservice Testing, for determining the acceptability of

the backflow check function of the CC pump discharge check valve 21 CC1. The

procedure requires 2 of 3 of the following indications for an acceptable test: (1) an

audible "clapping shut" when stopping the 21 CC pump; (2) decreased pressure

observed at the pump discharge pressure gage; and (3) no reverse flow observed at

the 21 CC pump. The team considered these criteria to be appropriate and noted

no test failures for the CC pump check valves.

,* .. -

12

c.

Conclusions

Although the licensee had identified that several substantial punip testing activities

remained to be completed, the team concluded that PSE&G was adequately

implementing pump and valve testing for CC as required by the IST program. The

team identified instances where controls were not in place for periodically testing

certain manual valves used in the EOP valves. PSE&G agreed to include these

valves in a periodic surveillance test program.

M1 .3 Maintenance and Testing of Heat Exchangers

a.

Inspection Scope

b.

The team reviewed CC heat exchanger maintenance and testing actions being-taken*.

regarding GL 89-13, Service Water System Problems Affecting Safety-Related

Equipment, as described in PSE&G correspondence NLR-N90021, dated

January 26, 1990, which was later revised in NLR-N90165, dated August 31,

1990.

PSE&G uses thermal performance testing to confirm that the component cooling

heat exchangers (CCHX) can transfer required heat loads to the ultimate heat sink

during a postulated accident. The results of this testing are used as input to a

computerized model of the CCHX to confirm that the heat exchanger

manufacturer's design data sheet performance can be achieved. The team sampled

the results of CCHX thermal performance testing ancl the related computer model

input and output.

Observations and Findings

CC Heat Exchangers

The CC heat exchangers are performance tested periodically in accordance with

Procedures S2.0P-PT.SW-0026(Q) and -0027(0), Revision 5, 21 and 22

Component Cooling Heat Exchanger Heat Transfer Performance Data Collection.

Testing is performed while shutdown in Mode 4 with the last test having been

performed in October 1994 for both CCHX. The Component Performance group is

responsible for reviewing the test data, calculating the heat transfer capability of the

heat exchanger, and providing the results to the system manager for review and_

approval.

The team reviewed the heat exchanger thermal performance test results obtained in

October 1994. PSE&G calculated fouling factors based on test data to predict heat

removal at design conditions. The predicted heat removal was multiplied by 0.95 to

account for uncertainty (i.e., a 5% instrument measurement uncertainty value was

assumed) and then compared to the heat removal requirements specified under

service conditions in the heat exchanger vendor data sheet.

13

Based on the review of the thermal performance test results, PSE&G concluded that

the CC heat exchangers would remove the required heat load under accident

conditions. However, the team questioned the technical basis for the 5%

assumption used to account for instrument measurement uncertainty. PSE&G

stated that the 5% measurement uncertainty value was based on "equivalent"

instrumentation, which was not identical to that used for the test. Hence, there

was no specific documented technical basis for the assumed measurement

uncertainty. The team determined that if the measurement uncertainty was greater

than about 11 %, the heat exchangers may not meet their required thermal

performance under accident conditions.

Also, in light of clogged tubes reported from recent heat exchanger inspections, the

team questioned how PSE&G calculated essentially clean heat exchangers with zero

fouling factors on both tube and shell sides from the 1994 thermal performance

testing results. For example, a review of the inspection and cleaning in March 1996

of the 21 CC heat exchanger performed under WO 960608023 indicated that "10%

of the inlet tubes and 75% of the return tubes were clogged." Assuming similar

heat exchanger condition during the 1994 performance test, it is not clear how the

thermal performance tests for heat exchangers in service, prior to cleaning, would

have zero fouling factors, when tube clogging was actually observed.

CCHX Thermal Performance Computer Model

The team found cases where computer model predicted near zero or negative

fouling for the CC heat exchanger. For these cases, the heat exchanger

performance calculated by the model was better than that predicted by the

manufacturer's data sheet for a clean heat exchanger.

The team questioned the potential for non-conservative prediction of heat exchanger

performance by the model. A non-conservative heat exc_hanger performance model

would indicate less tube fouling than may actually* be present in the heat exchanger.

Therefore, an unacceptably fouled heat exchanger, that would be unable to perform

its design function, may not be detected by conducting the performance test. In

response to the team's questions, the licensee stated that the computer program

was established to provide the most realistic assessment of cooler cleanliness and

intentionally removes inherent conservatism in the theoretical calculations used in

the model.

The licensee also ran an additional case using the model in which the

manufacturer's design data sheet performance factors (temperatures, flows, and

fouling) were input. Results showed that the model predicted approximately 12 %

better performance (overall heat transfer coefficient, U) than the data sheet

performance. Although the model only predicts a 5% better heat load capability,

the 12% over prediction in "U" is significant because this is the value used by

Westinghouse in their accident analyses .

c.

14

In response to the team's questions, the licensee contacted the manufacturer to

obtain further information on whether the model's performance predictions were

consistent with and applicable to the Salem Unit 2 CCHX.

CC Pump and Heat Exchanger Room Coolers

In a revised response to GL 89-13, dated August 31, 1990, PSE&G committed to

periodically inspect and clean the two CC pump room coolers. PSE&G viewed this

revised commitment as an acceptable alternative to the thermal performance testing

option of GL 89-13. As a result of this revised commitment, PSE&G no longer

committed to "trending important system parameters".

Based on a review of preventive maintenance WO 960528046 for inspection and

cleaning of the 22 CC pump room cooler performed in April 1996, the team was

concerned that the present method of inspecting and cleaning the room coolers may

not demonstrate adequate thermal performance of the CC room coolers. The cooler

inspection was performed in accordance with Procedure SC.MD.PM.SW-0006(0),

Revision 4, Service Water Room Coolers Internal Inspection. The specific concerns

were:

Comments in WO 960528046 indicated that silt, waterbox debris, and failed

lining were present in the heat exchanger waterbox. However, acceptance

criteria were not included for determining the as-found acceptability of the

cooler regarding fouling factors and service water flow rates. This was

inconsistent with PSE&G's response to GL 89'." 13 which stated in part that

"Procedures will include acceptance criteria and recommended actions for

acceptable results." Also, no technical justification for the inspection

frequency of the room coolers existed.

PSE&G did not periodically verify adequate service water or air flow through

the room coolers. This concerned the team since silting was known to exist

in service water lines and room cooler waterboxes and the manual damper

(2-VHE-747) supplying air to the 22 CC pump room was found closed during

a plant walkdown.

Conclusions

The team concluded that the computerized model used to predict CCHX

performance, based on test data, may not be conservative. PSE&G is in contact

with the heat exchanger manufacturer to resolve this issue. The team concluded

that the lack of a specific documented technical basis for the 5 % instrument

measurement uncertainty assumption used in CC heat exchanger performance

calculations was an unresolved item pending further evaluation of this issue by

PSE&G and review by the NRC for potential enforcement action (URI 50-311/96-81-

05). The lack of acceptance criteria for assessing the as-found condition of the

room coolers and for establishing adequate service water and air flow rates in CC

room cooler maintenance procedures was considered to be an unresolved item

pending PSE&G's evaluation and review by the NRC for potential enforcement

action (URI 50-311196-81-06).

15

M1 .4 Testing of Instrumentation and Controls (l&C)

a.

Inspection Scope

The team witnessed testing that was performed to resolve a discrepancy with

residual heat removal (RHR) heat exchanger CC flow measurement found during the

system flow balance test.

b.

Observations and Findings

CC RHR Heat Exchanger Outlet Flow Indication '(2Fl-601 A and Bl and Flow Element

(2FE-601A and Bl

CC flow is measured through each RHR heat exchanger by a transmitter which

senses the differential pressure (DP) between the inner and outer radius t_aps _th~t

are* located* on* a 12-inch, 90°* elbow installed in the* CC piping. The flow element

was original plant equipment specified by Westinghouse to develop a DP of 137 .

inches of water which would correspond to a full scale flow of 10,000 gpm on the

Control Room console indicators (2Fl-601 A and B). * During the performance of the

flow balance test, a discrepancy of CC flow to the RHR heat exchangers was

observed. The Control Room console indicators read about 1000 gpm higher than

temporarily installed ultrasonic flow meters (USFMs) which were used during the

test to more accurately measure flow through both RHR heat exchangers. PSE&G

reported this discrepancy to the NRC on Novembe~ 29, 1996, in Licensee Event

Report 96-028.

PSE&G performed a troubleshooting procedure authorized by W0961112091 to

accomplish an insitu calibration of the elbow flow meters for the 21 and 22 trains.

This procedure confirmed the problem was associated with the lack of initial field

calibration of the elbow flow meters. The team witnessed portions of the

troubleshooting procedure and verified the following:

The test equipment for flow (Panametrics Transport PT868 Flowmeter) and

DP had been calibrated to kf!OWn standards prior to the test.

Each transducer with mounting hardware was installed in accordance with *

the USFM vendor instruction manual and located at optimum locations (i.e.,

in straight run of pipe with more than 10 pipe diameters upstream and 5 pipe

diameters downstream).

The team confirmed with the cognizant l&C engineer that Calculation No. SC-

CC002-01, Revision 1, 1 /2 Component Cooling RHR Outlet Flow Indication and

Alarms, was the calculation of record and would be revised to include the correct

design inputs for incorporation into the channel calibration procedures for CC flow

through each RHR heat exchanger.

16

c.

Conclusions

The team concluded that appropriate measures had been taken to control the

collection of test data for the insitu calibration of the elbow flow meters. PSE&G

was taking appropriate actions to correct the elbow flow meter design inputs and

revise the CC RHR heat exchanger outlet flow indication and alarm channel

calibration procedures.

M2

Maintenance and Material Condition of Facilities and Equipment

M2.1 CC Radiation Monitors

a.

Inspection Scope

The team reviewed design and operations for containing radioactive contamination

that could enter the CC system.* *

  • ** * *
  • . ** *
  • * * * * * * *
  • *

b.

Observations and Findings

The Salem UFSAR, Section 9.2.2.3, states, "Since heat is transferred from the

component cooling water to the service water, the component cooling system

serves as an intermediate system between the reactor coolant and the service water

systems and insures that any leakage of radioactive fluid from the components

being cooled is contained within the plant." Further, in Section 11.4.2.2, the

UFSAR states that "Component cooling liquid monitors (2R-17A,B), continuously

monitor the component cooling water for radiation."

During system walkdowns, the team was informed by PSE&G that the CC radiation

monitors had been out-of-service since some time in 1995 due to problems with the

radiation monitoring computer. The CC radiation monitors are non safety-related

and are not used to determine offsite radioactive releases. PSE&G returned the

monitors to service on December 9, 1996. During the period that the monitors

were out-of-service, the reactor had been defueled leaving the spent fuel pool heat

exchanger as the only active CC load. No significant leakage of component cooling

either into or out of the system had been suggested by surge tank level changes.

Routine, weekly samples of component cooling water had been completed and had

included evaluation of gross activity. During two periods when component cooling

pumps were secured for maintenance, low levels of activity were detected in the

CC system. The likely source of the leakage was the spent fuel pool heat

exchanger. PSE&G informed the team that inspection of the heat exchanger did not

identify leaking tubes and no activity was detected when the CC pumps were

running. Also, no leakage of chromates into the spent fuel pool had been detected

by chemistry sampling of the pool.

17

c.

Conclusions

The team identified a discrepancy between the UFSAR requirement for CC radiation

monitors to continuously monitor CC for radiation and station practice wherein the

monitors had been out of service for over one year. The team was concerned that

the licensee appeared to not repair these radiation monitors in a timely manner given

the length of time the monitors were out-of-service and the function they provide

(i.e. prompt identification of leakage into the system from radioactive systems

served). These radiation monitor issues are unresolved pending further NRC review

for potential enforcement action (URI 50-311/96-81-07).

M2.2 Root Cause Evaluations and Corrective Actions for System Failures

a.

Inspection Scope

The teani reviewed corrective actions and root cause evaluations *for CC equipment" **

problems that had been identified by PSE&G.

b.

Observations and Findings

The team reviewed 1994, 1995, and 1996 corrective maintenance work orders

(WO) concerning pumps, various check valves, and several power operated valves

in the CC system. Based on this review, the team observed the following:

Increasing vibration levels had been noted for the CC pumps during inservice

testing. PSE&G was taking appropriate actions to address this problem even

though the vibration levels had not reached the alert level. WO 960928055

had been recently issued to perform a troubleshooting procedure for

gathering and analyzing pump vibration levels while operating different

pumps in paraliel.

Several check valves (2CC186 and 2CC119) had frequent local leak rate test

failures. However, PSE&G took appropriate action to correct these failures.

These valves were included in a comprehensive root cause analysis report

issued by the check valve performance group in April 1996 in response to

repeated failures of containment isolation valves identified in CR

96031914 7. Also, the CC pump discharge check valves had performed well

with no corrective maintenan.ce required during the last 3 years.

WO 950924133 had been issued to correct a bent spring rod pipe support

(2P-CCH-332) near the excess letdown heat exchanger containment isolation

valve. The team verified that the cause of this problem was adequately

assessed and not attributed to any hydraulic disturbance such as water

hammer. PSE&G had determined the cause of the damaged support to be

from an associated maintenance activity where the rod was bumped by a

heavy load.

18

High valve factors were determined for MOV 2CC117 during initial testing

that was performed in response to GL 89-10. PSE&G attributed the problem

to carbon steel wedge shoes without hard facing on the valve internal wear

surfaces causing high frictional forces. PSE&G implemented design change

2E0-2340 to provide replacement wedge shoes with hard facing that

improved the valve performance.

c.

Conclusions

The team concluded that PSE&G was taking good corrective actions to identified

CC equipment problems.

M3

Maintenance Procedures and Documentation

M3.1 Ventilation System Testing and Documentation

a.

Inspection Scope

The team reviewed testing and documentation aspects of the ventilation system to

determine its capability and readiness in supporting the operability of the CC

system.

b.

Observations and Findings

Separate room coolers are located in the motor driveri auxiliary feedwater pump

area for providing cooling for each of the two CC pump rooms. Air is cooled by a

fan coil unit_ and independently ducted to each CC pump room. Return air from the

pump rooms passes through a louvered fire damper mounted in the fire door of each

CC pump room. The return air discharges through this louver to a hallway on the

84 foot elevation of the Auxiliary Building. When in standby, the room coolers are

started on high temperature by individual room thermostats.

The team observed the following design and configuration deficiencies during plant

walkdowns:

The louvered fire damper in the fire door (Door C8-2) for 21 CC pump room

was closed. The team noted that an analysis had not been performed

regarding the impact on return air flow and room temperature with this

louver closed. PSE&G also informed the team that two design information

items concerning the ~oom coolers were not available: (1) PSE&G could not

determine design information concerning the louvered fire damper, such as

free area with the louver open; and (2) no air flow calculation existed for the

room cooler to determine if the louver in the fire door was adequately sized

to pass design air flow. The team concluded that the closed louvered fire

damper may have prevented the CC room coolers from performing their

design basis function .


---

-

19

In addition to the closed fire damper, the manual damper designated 2-VHE-

747 located in the supply air duct of the room cooler designated 2VHE33

was closed. Also, manual damper designated 2-VHE-749 located in the

supply air duct of room cooler designated 2VHE34 was closed. The team

noted that these dampers and associated duct were shown on auxiliary

building ventilation drawing 205337-A-8763-20 as supplying 600 cfm of air

to the 22 CC pump room and 1350 cfm of air to the auxiliary feed pump

area, respectively.

PSE&G could not account for the position of the dampers described above .

Therefore, the team questioned if PSE&G had administrative controls

regarding ventilation damper positions to support equipment operability in

safety-related systems. PSE&G indicated that there were no existing

controls. AR 961121961121204 was issued for the Operations Manager to

determine what controls should be implemented for ventilation system

equipment to assure that the plant is o"pe*rated c"o"r'1sistent with desigh

assumptions.

c.

Conclusions

The team concluded that these deficiencies demonstrated inadequate configuration

control of ventilation equipment needed to support CC system operability. This

issue remains unresolved pending further NRC review for potential enforcement (URI

50-311/96-81-08).

M3.2 Test Procedure Acceptance Criteria

a.

Inspection Scope

The team reviewed the maintenance and surveillance test procedures and results of

selected electrical equipment required to support the CC system. The 125 Volt

batteries are required to support control of the CC system pumps, the on-site power

supply and power the pilot solenoid valves. The emergency diesel generators

(EDGs) supply power for the CC system pumps and motor operated valves.

b.

Observations and Findings

1.

Salem UFSAR, Section 8.3.2.1 states that three 125 Volt batteries are

provided for the control power for the vital buses and power for the 125 Volt

de distribution cabinets. Technical Specification 4.8.2.3.2g describes the

requirements for a battery capacity discharge test to demonstrate at least

80% of the manufacturer's rating every 60 months. Technical Specification

4.8.2.3.2h further states that the test frequency shall be increased to 12

months if the battery shows signs of degradation including a drop of more

than 10% capacity from the previous test .

20

Salem Nuclear Generating Station implements the requirements of these

technical specifications by Procedure SC.MD-FT.125-0002(0), Rev. 4, dated

November 15, 1995, 125 Volt station Batteries Performance Discharge Test.

The team reviewed the latest battery capacity test data for the safety-related

125 Volt batteries. The team noted that procedure SC.MD-FT.125*.0001 (0),

Rev. 0, dated November 5, 1992, 125 Volt Station Batteries Performance

Discharge Test, was the controlling procedure at the time of those tests~

The team confirmed both procedures referenced Institute of Electrical and

Electronics Engineers (IEEE) Standard 450-1987, Recommended Practice for

Maintenance, Testing, and Replacement of Large Lead Storage Batteries.

Attachment 11 to procedure SC.MD-FT.125.0001 (0), required that the

capacity of the battery be calculated at the completion of the test in

accordance with procedure steps 5.4.37 or 5.5.18. The team noted that the

required calculation of battery capacity was defined in the body of the

  • procedure *{steps 5.4.37 and 5.5.18) as the ratio of the time to reach" low

battery voltage to two hours (the time used to establish the discharge rate.)

The team confirmed this method of calculating battery capacity was in

agreement with the method contained in IEEE:..450-1987, Section 6.5, *

Determining Battery Capacity. The team found that the tests for batteries

2A and 2B (performed in May 1993 and April 1993 respectively) were

stopped at two hours instead of proceeding to the low battery voltage point

as implied by procedure steps 5.4.37 and 5.5.18. The licensee indicated the

tests were stopped at two hours because that duration was required by

other steps in the test procedure (5.4.33 and 5.5.17 .)

The team noted that

since the test was not properly completed, no calculation could be performed

in accordance with procedure steps 5.4.37 or 5.5.18. However, the data

sheets indicated the batteries had 100% capacity.

The team confirmed the batteries had at least 100% capacity as stated by

reviewing the recorded test data. However, the team was concerned that

there was no documented true battery capacity established in the 1993

tests, there was no value to compare with the next battery capacity test for

degradation.

In response, the licensee had the battery manufacturer estimate the probable

capacity from the 1993 test data. The results showed the battery capacities

were 11 5 % for battery 2A e1nd 112.5 % for battery 2B.

The team noted the latest revision to the battery test procedure (SC.MD-

FT.125.0002(0), Rev. 4, dated November 15, 1995), was changed, in part,

to incorporate a change to the Technical Specification Surveillance

Requirement 4.8.2.3.2 (approved by the NRC on September 19, 1995.) Part

of the Technical Specification change incorporated a requirement to increase

the frequency of the battery performance tests from 60 months to 12

months if degradation in battery capacity of more than 10% was found from

the previous test. The team found that the revised procedure failed to

incorporate an acceptance criteria for battery degradation. The team also

21

found that the discussion in the body of the procedure on degradation in the

form of notes (Procedure pages 21 and 48) indicated a frequency change to

every 18 months was appropriate for a greater than 10% capacity drop from

the previous test.

In response to these concerns, the licensee issued AR 961206169 to review

this item and revise the procedure.

2.

The team reviewed the battery charger maintenance procedure S2.MD-

ST.125-0001 (0), Rev. 0, dated July 27, 1996, 125 Volt Battery Chargers.

The 125 Volt battery chargers had been replaced under change 2EC-3332/1

because of maintenance problems with the original chargers. The original

chargers were rated for 250 Amps and the new chargers were rated for 300

Amps. Because of ampacity concerns of the ac power input cables, both the

original and the new chargers required the current limit to be set at a

maximum of 210 Amps. The team.found that the current* battery charger *

current limit as-found test contained a caution and required the electrician to

. adjust the controls to ensure the current drawn by the charger would not

3.

exceed 210 Amps. This instruction would inhibit recording the true as-found

current limit if it had drifted above 210 Amps because the test would not

permit loading the battery charger above 210 Amps. In response to the

team's observation, the licensee initiated an AR to review this item .

The team reviewed the Diesel Generator Speed/Load Control System

Alignment procedure, SC.MD-CM.DG-0006 (Q), Rev. 8, dated

June 12, 1996, to determine the setpoint for the EOG governor motor

operated potentiometer (MOP) allowable frequency range. This setpoint was

critical because the EOG loading calculation (ES-9.0002) is based on the EOG.

frequency not increasing above 60.5 Hertz. This restriction was further

emphasized in a recent request to change the Technical Specification

4.8.1.1.2 from 61.2 to 60.5 Hertz max. License Change Request S95-36

was sent to the NRC on November 25, 1996. However this was a re-write

of license change request (LCR) 94-40 which was initiated in response to

Incident Report 94-301, dated October 13, 1994, which first documented

the potential for EOG overloading because EOG frequency in excess of 60.5

Hertz conditions. The team found that even though the new procedure had

an acceptable as-left criteria of 59.80-60.20, there were no acceptance

criteria for the as-found condition (procedure step 5.5.1.) The team

observed that the as found condition of EOG 2C was recorded at 60.22 Hz.

when tested on May 11, 1996, following the installation of a new MOP.

The setting was returned to 60.03 Hz. The team confirmed the settings for

EDGs 2A and 2B were found and left within the allowable as-left tolerance

during their last preventive maintenance.

The licensee indicated that an AR would be initiated to revise that section of

the procedure addressing as-found frequency of installed MOPs .

c.

22

Conclusions

The team concluded that the failure to incorporate the latest technical specification

surveillance criteria in the battery surveillance performance test procedure was a

procedure weakness. The licensee stated that the procedure would be revised to

properly reflect the technical specification requirement.

The team concluded that the licensee had failed to follow their battery performance

test procedure for calculating the capacity of batteries 2A and 28 in 1993 because

of an inadequate test procedure.

The team also concluded that the errors found in the battery charger test procedure

and the EOG speed control alignment procedures had minor safety significance.

The licensee has initiated actions to correct these procedure deficiencies.

The* above issu*es are unresolved pending the completion* of the licensee's corrective

action and the NRC review of this issue for potential enforcement action (URI 50-

311196-81-09).

Ill Engineering

E1

Co.nduct of Engineering

E1 .1

Component Cooling Pump Runout and NPSH

a.

Inspection Scope

The team reviewed several design calculations, engineering evaluations, and other

design documents to assess the design basis and supporting analysis for the CC

system.

b.

Observations and Findings

Calculations

Calculation S-C-CC-MDC-0879, Revision 1, dated June 28, 1992, Maximum and

Minimum CC Pump Flow Requirements and NPSH, established the CC pump

minimum permissible flow, runout flow, and evaluated required and available NPSH

during runout conditions. The team reviewed this calculation in detail and identified

the following weaknesses:

1 .

The calculation (Sheet 1 l refers to an attached pump curve to establish the

recommended minimum flow rate of 1000 gpm for the CC pumps. However,

the pump curve is a generic Goulds pump "catalog cut" without any specific

customer designation. It was not clear that this curve is applicable to the

Salem CC pumps .

--

-


~

23

2.

Using the accident alignment for the CC system provided in TS2.SE-SU.CC-

0001 (0), Revision 0, CC System Flow Balance, with the minimum flow

requirements provided in UFSAR Table 9.2-3, and assuming isolation of CC

flow to the spent fuel pool heat exchanger and boric acid evaporator early in

the injection phase (in accordance with the EOPs) of a postulated large break -

LOCA, the team determined that total CC pump flow may be as low as 771

gpm. Consequently, the 1100 gpm minimum CC pump flow requirement

established in the calculation may not be satisfied during the injection phase

of a postulated LOCA.

3.

The calculation assumes (Sheet 2) that "CC pump runout flow is 20% higher

than the flow corresponding to its best efficiency point (BEP)." The

calculation states that this assumption is consistent with "normal industry

practice." In addition, the required pump NPSH at runout (5700 gpm) is

extrapolated (Sheet 7) from the manufacturer's design pump curve.

However, the p*ump curve* only shows retju"ired NPSH for Hows* up to 5000 *

gpm. It is not obvious from the curve that required NPSH could be limited to

the 23 feet value determined in the calculation.

4.

No documented basis was provided for the minimum surge tank water level

(El. 126'-0") used in the calculation to determine NPSH available to the

pump. Although a setpoint calculation exists for the surge tank levels,

PSE&G was unable to correlate the levels in the setpoint calculation (SC-

CC003-01, Revision 0) to the low level elevation specified in the calculation.

Licensee Identified Pump Runout Issue

The calculation states (Sheet 1) that "None of the operating modes of the CC

system require flow in excess of the design flow," and " ... there is no expected

scenario that would lead to pump runout condition ... " However, in 1994 PSE&G

identified the potential for CC pump runout during a postulated LOCA and failure of

a vital bus (PR 940805141). Consequently, PSE&G contracted an external

engineering organization to perform an additional analysis of the CC pump capability

to operate under runout conditions (Evaluation of Component Cooling Pump at

Runout Condition, dated November 7, 1994). That analysis also used

extrapolations of the manufacturer's pump curves to conclude that the pump could

operate "reliably at runout flow conditions for an indefinitely long period." The

report also stated that the CC pump will operate at runout until another CC pump is

restored to service or until an RHRHX can be isolated. Subsequently, PSE&G

developed administrative guidance to require three CC pumps to be operable

assuring the availability of two CC pumps assuming the single active failure of one

CC pump.

24

SSFI Identified Pump Runout Issue

The team identified other cases where the potential exists for the CC pump to

operate at or near runout conditions which had not been adequately evaluated to

assure the pump manufacturer's NPSH requirements would be satisfied. For

example:

In the event of a postulated LOCA, (using current EOPs) one CC pump is

started during the injection phase, and the RHRHX outlet valves

(21CC16&22CC16) automatically open during recirculation on low level in

the RWST, running out the pump for approximately 10 minutes.

When a CC pump is started in EOP-TRIP-1, the spent fuel pool heat

exchanger and boric acid evaporator may still be aligned for service. Recent

flow balance test results indicate that CC pump flow may be near runout

(5*500-5'600 gpm) until flow to these loads is.isolated.

A Westinghouse analysis (PSEB0-96-040, Revision 1, dated

September 3, 1996, Single Train Cooldown Analysis Report) indicates that

CC flow rates through the CCHX and RHRHX are based on one CC pump

operating near runout.

In response to these issues, the licensee contacted* the pump manufacturer to

obtain further information related to CC pump performance under runout conditions.

In a letter to PSE&G, dated December 11, 1996, the manufacturer stated that:

The minimum flow for this pump is 600 gpm for a maximum of 60 minutes.

Maximum continuous flow is 5600 gpm. Based on testing done on same

size pumps, a maximum flow rate of 6370 gpm may be tolerated for up to

10 minutes. However, NPSH required is 26 pounds per square inch absolute

(psia) and brake horsepower is 362 hp.

At the time of the inspection, PSE&G did not have a formally documented hydraulic

analysis or a field benchmarked and issued flow model that establishes the

maximum possible CC pump flow that could be achieved for all worst case system

alignments. Except for the estimates and extrapolations reflected in this calculation

and the independent analysis, there was no documented hydraulic analysis to

establish the maximum possible CC pump flow that could be achieved, or to

confirm that the manufacturer's NPSH requirements would be satisfied.

25

CC Flow Diversion

The team also noted that when the outlet valves open on both RHRHXs (on low

RWST level) and the CC pump is at runout, CC flow may be diverted from safety-

related components (e.g., SI, charging, and RHR pumps) to the RHRHXs. There

was no documented analysis or testing to assure that adequate CC flow would be

supplied to the safeguards pumps during these conditions. In addition, with two

RHRHXs operating, more heat may be rejected to the CC system. There was no

documented analysis to establish what flow would be supplied to the RHRHXs, and

that the CCHXs could maintain CC supply temperatures below the design limit

(126°F).

EOG Loading

The pump manufacturer determined that the CC pump motor would be required to

produce* approximately 362 brake horsepower at pump runout conditions. This is

an increase of approximately 62 brake horsepower above that assumed in the EOG

loading calculation for a CC pump motor. The team noted that the impact of the

increased horsepower *requirement on the EOG loading had not been evaluated.

Summary

In summary, the team found that there was no documented analysis to confirm

that:

Minimum CC pump flow will be greater than 600 gpm in all cases, e.g.,

during injection.

The maximum flow will not be exceeded in any mode of operation or system

alignment.

Sufficient NPSH is available to support operation at the maximum permissible

runout flow rate. It is not clear that operation at this flow rate, even for a

short duration, will not result in cavitation that could compromise the

capability of the CC pump to continue performing its safety function.

The emergency diesel generator has adequate capability to accommodate the

increased loading from a CC pump operating at the specified runout flow.

Adequate CC flow is supplied to safeguards pumps when the outlet valves

on both RHRHXs are open at low RWST level; or, that sufficient flow would

be supplied to both RHRHXs to maintain CC supply temperatures at or below

126°F.

The licensee has issued AR 961212085 to evaluate CC pump operation at the

maximum flow rate of 6370 gpm .

26

c.

Conclusions

The team identified a condition where the operation of the CC pumps appeared

inconsistent with documented design limits. The team concluded that the CC

-pumps would probably be at or near runout conditions when the RHRHX outlet

valves are automatically opened during a postulated LOCA. CC pump operation at

runout during these conditions had not been adequately analyzed by PSE&G.

Consequently, the CC pumps may be adversely affected if sufficient NPSH is not

available, and the pumps are subjected to the effects of cavitation. An unresolved

item for this issue is described in Section 03.1 of this inspection report.

E1 .2

CC Pump Room Ventilation

a.

Inspection Scope

  • At the completion* of the inspection, PSE&G' had not issued a verified analyses of

CC room temperatures under design basis conditions with postulated single failures

  • of the auxiliary building ventilation room coolers. The team was informed of

preliminary room .temperature results by PSE&G. The team reviewed an interim

design calculation completed to establish the maximum outside air temperature that

would permit simultaneous operation of the 22 and 23 CC pumps assuming failure

of ~he 22/23 pump room cooler during Mode 6 (refueling operations).

b.

Observations and Findings

There was no documented analysis to demonstrate that sufficient cooling would be

provided to the 22/23 CC pumps to permit satisfactory pump operation with the

22/23 CC pump room cooler (2VHE34) out-of-service. In response to the team's

concerns, PSE&G performed a preliminary analysis to determine CC room

temperatures under design basis accident conditions assuming the single failure of

these room coolers. The analysis -assumed the door to the pump room with the

failed room cooler is open. Preliminary results indicated temperatures as high as

138°F in the room with the failed room cooler, which was in excess of current

room temperature design limits. PSE&G is evaluating the permanent removal of the

22/23 CC pump room door, and is developing analyses of room temperatures for

these accident conditions.

The team also reviewed interim design calculation S-2-ABV-MDC-1666, Revision 0,

Maximum Outside Air Temperature for Mode 6 Entry. The calculation was

developed in response to the team's concern with the single failure of CC room

ventilation equipment. * This calculation was performed using a GOTHIC computer

model. Since the room coolers are thermostatically controlled to start at 100°F,

and calculated temperatures in the areas never reached 100°F, without modeling

the coolers, no room cooler operation was assumed in the analysis. The doors of

the 22/23 CC pump room were removed in the model. The calculation determined

that the maximum permissible outside air temperature for operation under these

conditions is 67°F. The interim analysis was performed to allow refueling activities

to proceed prior to the final resolution of this issue.

    • .: .. ':..*.

27

c.

Conclusions

Since the analyses of cooling available to the 22/23 CC pump room for design basis

accident conditions had not been completed, the team was unable to assess the licensee's

evaluation. PSE&G is continuing efforts to complete and verify these calculations and to

resolve the issues related to the single failure of the room coolers and its impact on CC

system performance. The team found the interim design calculation on 22/23 CC pump

room temperatures was acceptable in that it adequately represented the scenario described

. for Mode 6 operation. An unresolved item for the ventilation system issues is described in *

Section 03.1 of this inspection report.

E1 .3

Pump Seal Water Cooling

a.

.,

. .. * .... * ... " .. *.

!* :.

  • ...... ,,

.*. '*

  • * . * * *
  • The*team reviewed the technical basis for assuring that ade*quate CC water flow will be

provided . to emergency core cooling pump seal water coolers following the initiation of an

accident .. *

b.

Observations and Findings

A Westinghouse letter BURL-3824, dated May 14, 1980, ESF Pump Operation Without CC

indicates that the centrifugal* charging, safety injection, and RHR pumps can be operated

without CC being supplied to the seal water heat exchangers for 15-20 minutes following

an accident or blackout provided that lube oil cooling* (service water) is automatically

started within 50 seconds. A memorandum attached to the letter recommended that

procedures should be changed to start a CC pump in the event of a small break LOCA that

could result in extended RWST drawdown time beyond the 15-20 minute criterion. The

team questioned whether this issue had been addressed to assure that adequate cooling

water is supplied to the safety-related pump seal coolers*within the prescribed 20 minutes.

The licensee had issued PIR 950814345, dated February 1996, which raised similar

questions on this issue. However, resolution of this PIR was .not completed and the

licensee was not viewing closure of the PIR as a restart issue.

PSE&G engineers stated that, a CC pump will be started within 20 mi~utes after the

initiation of any accident event, including any size LOCA. PSE&G is further evaluating the

time required to start a CC pump using the current EOPs*to confirm that a CC pump can be

started within the required 20 minute time frame.

c.

Conclusions

The licensee's operations staff indicated that the EOPs would direct the operators to

manually start a CC pump in less than 20 minutes after the initiation of any accident event.

However, PSE&G was unable to provide documentation to support this assessment.

Consequently this item remains unresolved pending the completion of the PSE&G

evaluation and NRC review for enforcement action (URI 50-311/96-81-10).

28

E1 .4

Electrical Protective Devices

a.

Inspection Scope

The team reviewed the electrical protective devices selected for CC system pumps

and MOVs to ensure that the components were adequately protected and the

device setpoints were appropriate. The team also reviewed the calculations, single

line drawings and MCC pan descriptions and performed walkdowns of associated

MCC pans to verify the as-built CC system MOV power supplies and protective

devices.

b.

Observations and Findings

...... }; .. ,

. CC MOV !hermal Overloa~ ff<?U H:eaters ...

.. * ..

Heater Selection

The team reviewed calculation ES-18.006, Rev. 0, dated June 16, 1994,

Selection of TOL Heater Elements for Safety Related MOVs, to confirm the

design was in conformance with the licensee's commitn:ients to Regulatory

Guide 1 . 106. The calculation indicated a change from using option 1 a of the

Regulatory Guide, continuously bypassed except during testing, to option 2,

trip setpoints established with all uncertainties in favor of completing the

safety-related function.

The team identified that the calculation incorrectly used the manufacturer's

data for the trip characteristics for the TOL relays. The manufacturer's

information that was included as a reference was incomplete in that it did

not include the current range tables required for proper selection of the

heater elements. The calculation did correctly include information that

indicated the trip point was 125% of the heater element minimum current,

but never defined minimum current. The licensee incorrectly used digits

included as part of the heater model number as the trip point. The team

noted that the licensee's technical standard for TOL sizing was issued one

month after the calculation had been issued and correctly addressed the

manufacturer's heater selection criteria for trip point determination.

The team questioned the source of the MOV motor data because the

referenced motor curves listed in the calculation spreadsheet were not

included in the referenced motor data packages. PSE&G was able to find

motor data sheets for the CC system valves in question under another

vendor document not referenced in the calculation.

29

The team noted that the calculation methodology adjusted the thermal

withstand data for the MOV motors based on applied voltage. Motor thermal

withstand is not directly affected by applied voltage. In addition, the

calculation also adjusted the motor time current characteristic curves for

voltage. This unrealistic double compensation for voltage was a

conservative error. However, the team did find that the calculation failed to

address the ambient temperature of the MOVs which could affect their

thermal withstand capability. The motor data that the licensee found

indicated the motors were rated for 40 degrees centigrade (°C). The

calculation indicated some of the MOV motor ambient could be as high as

50°C.

The team observed that the time current characteristic curves for the heater

elements selected for 6 of the 14 CC valves would not provide locked rotor

protection. This failure to meet one of the goa_ls of the calculation was not

  • * addressed. *

The team observed that the calculation did not address the position of the

TOL adjustment knob, located on the face of the TOL relay. This adjustment

could affect the trip point by + /-10 % . This was also was not addressed in

the assumptions. The team walked down several CC system motor control

. center (MCC) compartments and confirmed the adjustment knobs were set at

100%. Therefore, this did not affect the results of the calculation.

The calculation was based on un-compensated TOL relays and adjusted the

trip curves for a 50 °C ambient. The team's walkdown confirmed that there

was a mix of un-compensated and ambient compensated TOL relays.

The licensee documented the calculational weaknesses identified by the

team in AR 961212226. The AR was designated as requiring completion

prior to Mode 4, hot shutdown.

Heater Design Control

The team observed that design change DCP 2EC-3249, approved

July 9, 1994, was initiated to provide adequate protection for the power

conductors feeding the safety-related valves. This was to be accomplished

by resizing the thermal overload relay heaters, breaker sizes and removing

the jumpers around the TOL contacts. Calculation ES-18-006 was the base

design document for the TOL heater selection.

The team identified inconsistencies between the calculated TOL heater size,

the heater size listed on the 230 Volt MCC one line diagrams and the heater

size listed in the Maintenance Management Information System (MMIS) data

base. These inconsistencies affected 3 of the 14 CC system MOVs. In

addition, the team identified an additional MOV which did not have any TOL

data listed in .MMfS and two MOVs that had two different TOL heater sizes

listed for the~same valve.

30

The team identified the following examples where the TOL calculation and

the TOL heaters installed in the plant did not agree:

CC118

CC136

CC190

C2.68A

C2.60A

C5.92A

Installed

C3.01

C3.56A

C6.30A

In response to the difference between the calculation and the installed

heaters, the licensee* performed an extent of condition evaluation and found

28 other discrepancies in safety-related systems. The licensee identified that

a change document (CD) No. 509/0 had been written against calculation

ES-18.006, as a result of design change 2EC-3249. The CD was issued to

revise the calculation for 30 heaters, including_ 2 of the 3 CC system MOVs

  • identified above: The CD did not address one of the* cc system MOVs

,identified .as having a discrepancy. In addition, the team noted that for one

. CC system MOV, discrepancies in heater size existed between the installed

  • heater, calculation, and the CD.

The CD failed to provide a technical justification for the change in TOL heater *

size. The team found that 10 of the 30 TOL heater changes involved

reducing the size of the heaters without any design calculation. Smaller size

heaters could result in premature tripping of the safety-related MOVs. This

was in direct conflict with the one of the stated goals of modification

_ 2EC-3249 to remain in conformance with Regulatory Guide 1 . 106 by

selecting heaters based on the conservative methodology.

2.

CC MOV Molded Case Circuit Breaker (MCCB) Magnetic Setting

. The team noted that the time current curves developed as part of calculation

ES-18.006 to demonstrate adequate protection for the MOV and the

connected power cables did not include the MCCB that forms part of the

combination motor starter with the TOL and the contactor. The TOL

manufacturer's information included as a reference to the calculation stated

that short circuit protection must be provided for the TOL and its associated

controller [contactor]. Selected MCCB curves were included in Calculation

ES-13.006(0), Rev. 2, dated October 18, 1995, Breaker and Relay

Coordination. The team noted that the MCC one line diagrams indicated a

variety of MCCBs had been used in the MCC compartments supplying the

CC system valves. These included thermal-magnetic (T /M) breakers that

respond to both overload and fault conditions and adjustable magnetic-only

(MAG) MCCBs that respond only to fault (instantaneous) conditions. The

team found examples where four CC valves with the same size MOV motors

and TOL heaters (C5.92A) were protected by 15 Amp T/M MCCB

(2CCV117, 2CCV131 ), a MAG set at 42 Amps (2CCV17) and a MAG set at

128 Amps (2CCV18). The team identified the 128 Amp setting was

excessive because the ratio of protection of the MCCB to the TOL was

,

.. *

31

greater than 20 and should normally be in the range of 7 to 10. This high

. setting provided insufficient protection for the combination starter. The team

also found that Calculation ES-13.006, Attachment E2, page 109, plotted

this breaker at 42 Amps, not 128 Amps.

In addition, the team found two pairs of valves (21 CC3, 22CC3 and 2CC30,

2CC31) with TOL size C10.48 heaters and 52 Amp RMS inrush currents that

had instantaneous MAG settings of 68 and 75 Amps, respectively. Standard

industry practice (e.g., ANSI C37 .96-1976, AC Motor Protection) would

maintain a ratio between inrush and MAG breaker setpoint of 175 -200%.

These low settings below 150% could result in premature tripping of the

MCCB resulting in failure of the valve to perform its intended safety function.

The licensee responded that they had never experienced a trip of the MCCB

during valve testing. Nevertheless, the licensee agreed that setpoint to

locked rotor ratios of less than 150% was not. prudent and initiated a change

to these four MCCB setpoints to reduce the* risk of premature failure*:

3.

. CC Pump Overcurrent Relay

The team reviewed the CC pump overcurrent relay setpoints as documented

in the maintenance department's relay test orders and compared those

values with the relay settings depicted in calculation ES-13.006(0), Breaker

and Relay Coordination, Rev. 2, dated October 18, 1995, and Drawing

203117, Rev. 24, dated March 11, i 996. The team observed that the relay

settings were consistent between the two documents. However, the team

noted the CC pump motor data (full load and locked rotor amps) contained

on the drawing differed slightly from the motor outline drawing 209C219,

Rev. 6, and the motor nameplate data. The team noted that the coordination

curves used generic motor data for motor acceleration, and the time current

plots failed to contain any motor thermal capability information. The team

reviewed the assumed motor acceleration data to verify the use of generic

curves was acceptable. The calculation assumed all pumps accelerated in

one second, but the overcurrent relays for all the safety-related 4160 Volt

motors (except 21 AFW) were set to allow locked rotor current for

approximately 15 seconds. The team reviewed traces of the

January 23, 1996, loss of offsite power loading test of EOG 2A and

confirmed the CC pump accelerated to full speed within one second with an

average voltage of 4200 Volts applied. The team also estimated the

acceleration of the CC pump with a minimum specified 70% voltage would

be less than four seconds. Therefore the use of generic motor accelerating

curves was acceptable for the CC pump motor.

The calculation did not include motor thermal damage capability curves.

Therefore, it was not possible to determine if the relays provided sufficient

running or locked rotor protection. The team reviewed the motor

specification 78-1303, dated July 26, 1978, and specification 85001, dated

December 13, 1985, and confirmed that motor thermal capability information

should have been available. The licensee was not able to find motor thermal

32

damage criteria in its document files. The motor manufacture was also

unable to find Salem specific CC pump motor information. However, the

motor manufacturer was able to find motor data for a motor similar to the CC

pump motor supplied to another nuclear facility. The team found the thermal

damage curve for the similar motor was not fully protected in the locked

rotor condition by the settings used for the Salem CC pump motor

overcurrent relays. However, as noted above, the relay setting would ,allow

greater than 15 seconds locked rotor condition prior to tripping. This

discrepancy would only affect the CC pump motor if it had failed to start and

was not considered an operability concern by the team because in order for

the relay to malfunction the CC pump would have already failed to start for

another unrelated reason. The licensee considered the existing relay setting

provided adequate motor protection during normal operation. The team

noted that the long time overcurrent setting would permit a 200% overload

and would not inhibit operation of the CC pumps. The licensee considered

some potential' rnotor *damage *under *a* 1ocked rotor condition to *be

acceptable.

c.

Conclusions

The team concluded that there. were significant weaknesses in the calculation for

the selection of the thermal overload relays for the CC system MOVs. The selection

of the new TOL heaters involved a lack of design and calculation control. The lack

of quality in the calculation indicated that the calculation preparer and the reviewer

failed to fully understand the operation of the equipment or the referenced

manufacturer's information.

The design change to place the TOL heaters in service resulted in the installation of

TOL heaters without a documented design basis. The team concluded that the

licensee had not maintained document control of the TOL relay heaters associated

with the CC system and other safety-related systems because heater sizes existed

in MOV circuits that were not based on the existing calculated basis. The team also

concluded the change document to the design calculation did not provide any

documented basis to accept the irn~talled TOL heaters for 30 safety-related MOVs.

The team found inappropriate design control in the selection of the molded case

circuit breakers associated with the CC system valves. The team identified four

magnetic trip MCCBs that had the potential for a premature trip (Valves 21 CC3,

22CC3, 2CC30 & 2CC31 ). The licensee completed corrective actions to reset

these breakers prior to the conclusion of this inspection with minor modifications to

S-96-025 and S-96-026.

The team also identified some minor weaknesses in the documentation and

assumptions made in the calculation for the selection of the CC pump motor

overcurrent relays .

E1 .5

a.

33

The team concluded that these issues remain unresolved pending the completion of

the licensee's corrective actions and the review of these issues by the NRC for

potential enforcement action (URI 50-311196-81-11 ).

Setpoint Control

Inspection Scope

The team reviewed selected instrument setpoint calculations to ensure that the

setpoints had a technically sound basis.

b.

Observations and Findings

1.

2RM17 - Surge Tank Vent Isolation Radiation Monitors

The UFSAR, Section 9.2.2.4:3; indicates that the CC surge tank is open to

.the atmosphere, but if high radiation is detected in the recirculation system,

the vent line is automatically closed.- The inspectors questioned the setpoint

basis for the radiation monitor alarm and safety function and were informed

that the setpoint was established to detect when the concentration of

. radioactive material in the component cooling system was approximately that

of primary coolant. The basis for the setpoint was to ensure that gaseous .

releases via the waste gas header were low.' In response to the team's

questions, the licensee's engineers stated that the radiation monitors

associated with the CC surge tank vent line appear to be set substantially

above the setpoints documented in either the Westinghouse Precautions

Limitation and Setpoint Document, Table 4.5, (Rev. 7, August 1979) (VTD-

304209) or the CC system configuration baseline document, DE-CB.CC-

0023(0), Rev. 1, Table T-1. Both of these documents indicated a setpoint

was 0.5 decade above minimum sensitivity. UFSAR Section 11.4 describes

these process radiation monitors, and UFSAR Table 11.4.2 indicated the

setpoint for 2-R17 A and 2-R178 was 1.0 E(-)7 micro curies per cubic

centimeter. Maintenance Procedure S2.IC-CC.RM-0027(0), Rev. 3,

December 11, 1996, which indicated a trip setpoint of 1.8E4 counts per

minute. PSE&G informed the team that an evaluation of the radiation

monitors setpoints and their bases would be conducted.

2.

2Ll-628A.C Cooling Component Cooling Surge Tank Level Alarms

The team reviewed Calculation SC-CC003-01, Rev. 1, Setpoint Relationships

- CC Surge Tarik Level, dated April 23, 1996, which established the

uncertainties associated with the high and low level alarms for the CC

system surge tank. The range for the alarms were established by the

Westinghouse Precautions Limitations and Setpoints document (Rev. 7,

34

August 1979) (VTD-304209) for the prime purpose of detecting leakage into

or out of the CC system. The team noted that the calculation concluded that

the process limits were not defined and required future configuration to

assure the existing setpoints were adequate for the alarm limits. The team

found that no action had been established to resolve this (or other) open

items from the setpoint calculations.

c.

Conclusions

The team concluded that the design basis documentation for the CC system

radiation monitors were inconsistent. The team also determined that the CC

radiation monitor setpoints may be inappropriately set to high. These radiation

monitors are not safety-related and are not used to calculate offsite radioactive

releases.

The'team* also identified *that' the design 'basis setpoint calculation for the *surge tank

level alarms .contained missing information that was identified in the body of the

calculation, but had not bee_n included in a system to track its resolution.

The calculation deficiencies are an unresolved item pending the completion of the

licensee's corrective action, including an evaluation to determine if the radiation

monitor setpoint was consistent with the UFSAR, and the review of these

deficiencies by the NRC for potential enforcement action (URI 50-311/96-81-12).

E1 .6

Equipment Power Supplies

a.

Inspection Scope

The team reviewed the power supplies for selected CC system and supporting

system components to confirm proper electrical train separation.

b.

Observations and Findings

1.

CC Pumps

The team reviewed the 4160 Volt and 230 Volt MCC one line diagrams. The

team confirmed the three CC pumps were powered from individual safety-

related 4160 Volt ac busses .. These busses are fed from the preferred offsite

power supply and can be fed from the onsite emergency diesel generators if

required. The pumps are automatically loaded on the EDGs following a

LOOP and are manually loaded on the EDGs following a LOCA and

appropriate load shedding. The team questioned the emergency operating

procedure (EOP) guidance for the restoration of the CC system. *The team

noted that procedure 2-EOP-APPX-1, Rev.20, dated October 14, 1996,

Step 5, required load shedding the 21 cooler and three fans (21 switchgear

supply fan, 21 auxiliary building exhaust fan and the 21 containment fan

, cooling unit) prior to starting the 21 CC pump. The team noted the

.. : corresponding section in the EOG loading calculation (ES-9.002) did not

c.

2.

3 .

35

account for these load changes at the 600-second mark, but instead load

shed the containment. spray pump (317 kW) at the time 21 CC pump was

  • added at 59 minutes. The team therefore questioned the availability of the

onsite power supply for CC pump 21 at the assumed 10-minute switchover

point.

The licensee agreed that the EOG loading calculation failed to address this

.scenario and issued an AR (961223215) to resolve this issue. This will

-remain -an unresolved item pending the licensee's incorporation of this

scenario into the EOG loading analysis and the review of this issue by the

NRC for potential enforcement action (URI 50-311196-81-13).

CC Motor Operated Valves

The team confirmed the motor operated valve~ were powered from 230 Volt

ac vital motor control centers (MCCs)* powered from the* A and C safety * *

. divisions. The one exception found by the team was the flow control valve

  • for the number 22 RHR heat exchanger (22CC16), which was powered from

the B safety division. This .arrangement of power supplies permits isolation

of the two CC flow headers and allows CC flow to both safety divisions of

the CC system on loss of any one power supply.

CC Instruments

The team reviewed selected CC system instruments powered from the 11 5

Volt instrument buses and confirmed that those instruments were powered

from redundant vital instrument buses.

4.

Supporting Systems Power Supplies

The team reviewed the power supply for the fan units cooling the CC pump

rooms 21 and 22 and confirmed they were powered from safety related 230

Volt ac MCCs. The team noted that the number 22 pump (Train 8) room

also contains the number 23 CC pump (Train C) and was cooled by fan unit

2VHE34 powered from Train 8. However, the team found that the number

21 CC pump (Train A) was cooled by fan unit 2VHE33 powered from Train

C. Therefore loss of Train C could result in loss of both the number 21 and

23 CC pumps. The effect of single failures on multiple CC pumps are also

discussed in section 03.1, E1 .1, E1 .2 of this inspection report.

Conclusions

The team concluded that proper train separation had been provided for the CC

system components. However, the team concluded that the emergency power

supply for the 21 CC pump to support EOP APPX-1, step 5, had not been included

in the EOG loading analysis. Also, the team concluded that the association of two

fan units for the three CC pumps provided the opportunity for an additional single

failure not previously analyzed by the licensee.

-

--~ ------------

36

E3

Engineering Procedures and Documentation

E3.1

Electrical Calculations

a.

Inspection Scope

The team reviewed selected design basis calculations and analyses for the ac and

de electrical systems that support CC system operation. The de system is required

for pump control, pilot solenoid valve power and control, control center low voltage

control, and EOG control and loading. The ac system is required for CC pump

power and MOV power and control.

b.

Observations and Findings

1.

CC Control Circuit Voltage Drop

The team observed that calculation ES-15.006(0), Rev. 2, dated

January 23, 1995, 230 Volt Vital AC Bus Control Power Circuit Voltage

Drop Study, did not address the MOV control circuit voltage drop for all

circuits including 7 of the 14 CC system MOV circuits. The licensee

responded that the calculation was based on the "worst case" circuits; The

team noted that the calculation failed to document and verify this

assumption. In response to the SSFI team finding, the licensee reviewed the

circuit lengths of the missing circuits and confirmed that these circuits were

enveloped by other analyzed circuits with similar size one motor starters .

. Therefore the voltage drop assumptions for the CC system MOVs were

acceptable.

2.

Load Flow CC Pump Starting Capability

The team observed that calculation ES-15.004(0), Rev. 2, dated

October 7, 1996, Load Flow and Motor Starting, was based on a degraded

voltage condition of 0.932 Per Unit (PU). This value was less than the

present degraded voltage setpoint and adds conservatism to the analysis.

However, the team noted that the CC pump motor was not included in the

analysis which included other safety-related 4160 Volt motors. The licensee

responded that the 300 horsepower (hp) CC pump motor would be

enveloped by the larger motors (400 and 600 hp) on the 4160 Volt buses.*

Therefore the calculation was also acceptable for the CC pump motor. The

calculation had not documented this engineering judgement .

37

3.

Battery Charger Recharge Load on the EOG

The CC pumps are automatically loaded onto the EOG following a loss of

offsite power (LOOP) and manually loaded onto the EDGs following a safety

injection signal coincident with a LOOP. The team observed that calculation

ES 9.002(0), Rev. 2, dated October 14, 1994, Emergency Diesel Generator

Loading, indicated very little margin between the required load and the 2

hour EOG rating.

The team observed that the calculation included detailed loading analysis for

all three EDGs for several different cases including LOOP, LOOP/LOCA with

all EDGs available, and LOOP/LOCA with one EOG not available. The loading

analysis for the 28 EOG was the most limiting because the calculated margin

below the 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> EOG rating was 68 kilowatts (kW) at a nominal frequency

of -60 hertz (Hz).

The team reviewed the calculation of the battery charger contribution to the

EOG loading. This calculation was based on measured battery charger

output during normal plant operation. The team observed the calculation

incorrectly adjusted the measured output of the battery charger resulting in

an incorrect conclusion that the input power was less than the output power.

The licensee had previously acknowledged this error and had appropriately

issued a change against the calculation prior to this inspection.

In addition, the team noted that the calculation was based on a 250 Amp

charger and the chargers had been replaced with 300 Amp chargers under

design change (DCP) 2EC-03332, approved April 1, 1996. The EOG loading

calculation had been identified as a document that required change as part of

that modification ancl included a change document (CD E511 /0} against the

calculation identifying the change details.

Following a loss of offsite power and prior to the diesel generators supplying

power to the battery chargers, the batteries begin to discharge to supply the

de loads. Calculation ES-4.006(0), Rev. 0, 125 Volt de Component Study

and Voltage Drop, indicates the initial battery voltage could drop to 113.16

volts and the battery cable resistance is less than .0007 ohm. When volt(!ge

is returned to the battery charger, its output voltage will attempt to return to

132 Volts direct current (Vdc), resulting in the charger going into current

limit. The team found that the calculated battery charger load on the EDGs

neglected any battery recharging current, following a partial battery

discharge, that could result in the battery chargers going into a current limit

mode. This additional load was not included in either the original calculation

or in the two changes that were outstanding against the calculation .

c.

"~38

The team considered the lack of adequate justification for not including the

battery recharging current in the battery charger load in the diesel generator

load calculation to be an unresolved item pending the licensee's evaluation of

this issue and the NRC review for potential enforcement action. (URI 50-

311196-81-14).

4.

DC System Time Constant

The team observed that calculation ES-4.003(0), Rev. 1, dated

January 18, 1996, 125 Volt DC Short Circuit and System Voltage Drop,

included as .an attachment a letter from the manufacturer of the battery main

fuses. This letter provided confirmation for the de interrupting rating for the

fuses. The team noted the letter included a statement that the rating was

only applicable if the de system time constant was within the requirements

of the Underwriters Laboratory (UL) standard {UL-198L, DC Fuses for

  • lndustrial""Use) used to test* the fuses. The* licensee* could *not produce any

evidence that the circuit time constant was ever reviewed to address the

  • fuse manufacturer's caution. The fuses in question were the main fuses

from the battery. They would* only be called on to operate for a major fault

on the de bus. While the team does not consider this to be an operability

concern, the team did considered this to be an undocumented engineering

judgement. The licensee initiated an action request (AR 961130114) against

the calculation to document the time constant of the de system .

Conclusions

The team concluded that the licensee failed to document a number of engineering

judgements and assumptions. The calculation review and approval process also

failed to identify and correct the lack of rigor in documenting assumptions and

engineering judgements. While the missing engineering judgements and

unsubstantiated assumptions did not invalidate the results of these calculations,

other unsubstantiated assumptions, used in the CC NPSH and TOL heater

calculations, did invalidate the calculation results.

E3.2

Technical Standards

a.

Inspection Scope

As part of the team's review of issues identified during this inspection, the team

reviewed the guidance available to the engineering staff in the form of technical

standards.

b.

39

Observations and Findings

1.

Low Voltage Circuit Breakers and Combination Starters

The team reviewed technical standard ND.DE-TS.ZZ-2012(0), Rev. 0, dated

July 7, 1994, Low Voltage Circuit Breakers and Combination Starters during

the review of the selection* of thermal overload relays and molded case

circuit breakers for the CC system motor operated valves. The team noted

the technical standard was generally consistent with present engineering

practice endorsed by recent IEEE standards (IEEE-741-1990). However, the

section on MCCB selection recommended an instantaneous setting range of

185% to 235% of the motor's locked rotor current. While this range of

settings would have avoided the risk for premature tripping of CC system

MOVs, it did not address the TOL manufacturer's requirement for short

circuit protection for the combination starter components. This requirement,

contained* in the licensee's vendor technical *data (VTD) number 317-235-01'

(GE.instruction GEH-5091 ), and included as a reference to Calculation ES-

18.006, Rev. 0, June 6, 1994, indicated the importance of providing short

.Circuit protection for the thermal .overload relay.

The team also noted that Attachment 4 to the standard listed a number of

TOL heaters as non-safety related. Two of those heaters were used in the

CC system and included in the ES-18.006 calculation. The licensee could

not identify the bases for the non-safety related label, but did confirm that

the TOL heaters of concern in the CC system were listed in the Salem Unit 2

. Bill of Material as safety-related.

2.

Medium Voltage Motor Protection

The team reviewed technical standard ND.DE-TS.ZZ-2014(0) , Protective

Relaying for 4.16 kilo Volts (kV) and 7 .2 kV Susses, Rev. 1, dated

December 13, 1995, as part of the review of the protection* for the CC pump

motors. The team noted that the standard's recommendations for the long

term and instantaneous relay settings agreed with industry recommendations

(ANSI C37 .96) and the actual settings on the CC pump motor overcurrent

relays generally agreed with the standard. The team noted that the

standard's recommendation for the time dial selection correctly stated that it

should be picked to lie between the motor acceleration curve and the motor

thermal damage curve. This information was missing from the Salem

calculation ES-13.006, Rev. 2, dated October 18, 1996, and contributed to

the discrepancy noted in Section E1 .4 of this report. The standard did not

address selection guidelines for using generic motor data. The Salem

calculation assumed the same one second motor acceleration curve for all

4. 16 kV motors without any basis. The team confirmed this was a good

value for a 100% voltage start of the CC pump required by the Salem motor

specifications number 78-1303, Rev. 0, dated July 26, 1978, and number

I

L

40

85001, Rev. 0, dated December 13, 1985, from a review of the EOG loading

. test data but also noted that the service water pump required two seconds

to come up to speed. This did not address minimum voltage starting at 70%

voltage with the potential for a longer acceleration time.

3.

Electrical Installation

The team reviewed technical standard SC.DE-TS.ZZ-2034(0), Rev. 3, dated

July 30, 1996, following a walkdown of the electrical distribution equipment

associated with the CC system. The team observed numerous examples of

power cables, in the 84 foot elevation de equipment area, that were

unsupported for distances of six feet or more, including the ac power feeds

to the new 300-amp battery chargers recently installed under DCP-2EC-

3332, Rev. 0, dated April 1, 1996. The team noted that the standard,

paragraph 5.2.27, specified that the maximum. free air length [of cable]

  • should be nominally 3'-0"*or twice the*min'imum bend .. radius,'whichever is

greater and that this paragraph had not been changed in the latest revision.

The licensee responded to these discrepancies between the recently issued

technical standards and the existing plant conditions by stating that the

intent of the standards was for new work. Although the new battery

charger did not change the ac power cables, the team felt the cables should

have been supported between the raceway and the new chargers to the

recent guideline. The licensee prepared an Action Request (961212228) to

address the generic concern of these discrepancies.

c.

Conclusions

The team concluded that the development of the technical standards program was a

positive initiative by the licensee. However, the team noted that the standards did

. not include a technical justification for the acceptability of existing conditions in the

plant. The team considered this to be a program weakness. .In addition, the team

identified one case where work in progress, during the development of the technical

standards, was not coordinated with the technical standard the licensee was

developing at the same time. The licensee issued an Action Request to address the

practice of not evaluating existing conditions.

E3.3

Drawing Control

a.

Inspection Scope

The team conducted walkdowns of the CC system to verify that plant drawings

were consistent with the installed plant equipment.

41

b.

Observations and Findings

The team noted several minor discrepancies with component description on the

labels attached to CC components. For example, the team noted that the label on

  • the steam generator blowdown cooler inlet valve was incorrectly labeled as the

outlet valve. The licensee appropriately issued ARs to track the resolution of these

deficiencies.

The piping and instrument diagrams (P&ID) for CC were generally accurate. The

team noted that the labels on the steam generator blowdown cooler heat

exchangers were not consistent with the P&ID. The licensee revised the P&ID

(Sheet 2, Rev. 33) to properly document the component identification numbers.

The team also noted that the P&IDs did not indicate identification numbers for

instrumentation located on the post accident sample .coolers. The licensee issued

an AR to track and resolve this discrepancy.

The team identified that DCP 2SC-2154 did not update the P&ID to remove FM

601 A&B and DCP 2EE-0248 did not update the instrument loop diagram for FIC

642A&B. In response~ the licensee issued ARs 961130118 and 961206159 to

address these and related drawing errors.

Section. E1 .4 of this report also addresses discrepancies between the 230 Volt vital

MCC bus one line diagram and the installed TOL heater and related design

documents.

c.

Conclusions

The team concluded tha*t the CC system drawings were generally accurate. The

licensee initiated actions to correct the minor discrepancies identified by the team

for both the. drawings and plant equipment labels. *

E3.4

Configuration Baseline Document

a.

Inspection Scope

The team reviewed selected sections of the Configuration Baseline Document (CBD)

for the component cooling system. The team also sampled several design

calculations, engineering evaluations, and other design documents to assess the

accuracy of the CBD and its supporting design inputs.

b.

Observations and Findings

The CBDs were developed and issued final for use during the 1988 to 1992 time

frame. However, in some cases CBDs were found to be impacted by processes

outside of the design change process (e.g., revisions to calculations and engineering

evaluations). These types of changes to the CBD were incorporated without design

verification. In a memorandum, dated July 1, 1996, all licensing and engineering

personnel were directed to use qualified source documents (calculations,

42

engineering evaluations, etc.) in CBDs rather than the CBDs themselves to make

engineering decisions. The CBDs were to be used as a "Road Map" to identify

these source documents. The CBD validation effort is in process to fully validate

the design basis information contained in those documents.

The CBD provided a comprehensive index of CC design basis calculations. In

general the team found that calculations were readily available and, in the case of

those maintained on the Document Management System (OMS), easily retrieved.

c_.

Conclusions

The team concluded that the CBD was a good source of design information and was

properly controlled by the licensee. The team found that CC design calculations

were referenced in the CBD. Calculations on the OMS were readily available.

ES

Miscellaneous* Engineering Issues

E8.1

Post Accident Sampling System Heat Exchangers

a.

Inspection Scope

The team reviewed the interface between CC and the PASS to verify that operating

practices were consistent with the licensing basis.

b.

Observations and Findings

. _ The UFSAR, Sec~ion 9.3.6.1, states that, "The PASS provides the capability to

obtain, under accident conditions, a containment air grab sample, liquid and stripped

gas reactor coolant grab samples ... " Secti_on 9.3.6.2 states that, "Ten gallons per

minute of component cooling water is supplied to the sample cooler rack to cool

reactor*coolant samples. n

Emergency Operating Procedure, 2-EOP-TRIP-1, Reactor Trip or Safety Injection,

Step 17, provides instructions requiring the closure of the boric acid evaporator CC

outlet valve (2CC48). Isolating the boric acid evaporator also isolates CC water

from the PASS heat exchangers. The boric acid evaporator CC outlet valve remains

closed throughout the duration of an accident. Therefore, in accordance with _the

current EOPs, CC is not available to provide PASS heat exchanger cooling flow

during an accident.

In response to this concern, the licensee provided procedure SC.CH-AB.CC1155(Q),

Revision 0, Temporary Cooling of PASS Cooler Rack 811, which is used to restore

cooling to the PASS cooling rack (Panel 811 ). The team reviewed this procedure

and found that it provides for installation of temporary hoses to supply cooling

water (demineralized water) to the PASS when component cooling water is not

available. However, this temporary installation is not consistent with the

description of the cooling water supply provided in the UFSAR or with NUREG 0737

evaluations for the PASS. The licensee issued AR00961212177 to track the

resolution of this discrepancy.

43

c.

Conclusions

The team concluded that providing PASS heat exchanger cooling water from the

demineralized water system is inconsistent with the UFSAR. This issue remains

unresolved pending: (1) the completion of the licensee's evaluation, including an

assessment to determine if the operating procedure change for using deminerlized

water instead of CC was conducted in a manner consistent with 1 OCFR 50.59 and

50. 71 (e); and, (2) review by the NRC for potential enforcement action

(URI 50-311196-81-15).

E8.2

Licensing Basis Verification *

a.

Inspection Scope

The team compared the UFSAR description of the CC (Section 9.2.2, Component

Coating System) and suppc>rt systems with the design 'basis information to verify

that the UFSAR descriptions were accurate. The team also reviewed the licensee's

  • UFSAR Project Macro review of the CC system to verify that the licensee had

adequately reviewed the UFSAR.

b.

Observations and Findings

The team identified examples where the description material in the UFSAR did not

Clearly reflect the CC system design. For example:

Section 9.2.2.8.1,. states in part that "The reactor coolant pump bearing

temperature alarm is set at 175 degrees Fahrenheit." The next paragraph

which also discusses the reactor coolant pump bearing temperature alarm

states that "The maximum test temperature of 185 °F is also the suggested

alarm setpoint ... ". The team found that these two statements were not

consistent.

Section 9.2.2.3, states in part that "The operation of the system is

monitored with the following instrumentation: 3. A temperature indicator in

the outlet line from each heat exchanger". The team noted that the steam

generator blowdown sample heat exchangers did not have a temperature

indicator in the outlet line.

Section 11.4.2.2, states in part that "These channels (CC radiation monitors

2-R17 A,8) continuously monitor the component cooling water for radiation."

The team noted that plant procedures do not require one or both CC

radiation monitors to be continuously inservice when the CC system is in

operation. The team also noted that both CC radiation monitors* had been

out-of-service for an extended duration at the start of this inspection (See

Section M2.1 ).

The team reviewed the UFSAR Macro-Review for the CC system. The Macro-

Review was one part of the licensee initiative to validate the information provided in

44

the UFSAR. The CC Macro-Review was conducted by one engineer during a one

week duration. The CC Macro-Review verified 57 UFSAR attributes and identified 6

discrepancies. The identified discrepancies were generally descriptive errors that

did not adversely affect the CC system function. For example, the Macro-Review

identified that the UFSAR incorrectly stated that CC provides makeup water for the

waste gas compressor seals. The Macro-Review correctly identified that the CC

system is not capable of performing this function. The identified discrepancies for

  • . the CC system were all appropriately placed in the corrective action program.

The attributes were verified by identifying a document which substantiated the

statement in the UFSAR. It was not the intent of the Macro-Review to conduct an

in-depth validation of the supporting documentation. For example, if the attribute

was each CC heat exchanger is designed to remove 1 /2 the decay heat 20 hours2.314815e-4 days <br />0.00556 hours <br />3.306878e-5 weeks <br />7.61e-6 months <br />

after plant shutdown, then the calculation validating this information would be

referenced in the Macro-Review. The engineer conducting the Macro-Review would

  • *not *necessarily revrew the talcl..llation to verify that the* assumptions were valid and.

the calculation was based on sound engineering principles.

The team compared the administrative guidance provided in procedure S2.SE-

DD.ZZ-0008(Z), System Engineering Final System Readiness Review UFSAR Macro-

Review Desk Guide, with the CC Macro-Review. The team noted a few examples

where the attributes recommended for selection by the desk guide, such as

setpoints, were not selected for verification during the CC Macro-Review. For

example, the RCP bearing alarm setpoint was not selected. The team also noted

one example, regarding the absence of the outlet temperature indicator on the

steam generator. blowdown sample heat exchanger, where the attribute was

selected; however, the Macro-Review did not identify the discrepancy between the

pl~nt and UFSAR description. *

The team reviewed the auxiliary building UFSAR project Vertical Slice to determine

if the single failure of the CC room ventilation issue identified during this inspection

was identified during the Vertical Slice. The team concluded .that this issue was not

explicitly identified during the Vertical Slice review. However, the licensee had

initiated a single failure evaluation to review ventilation systems for single failures.

The licensee's ventilation engineers stated that the preliminary evaluation had

identified that a single ventilation failure would affect multiple CC pumps.

c.

Conclusions

The team concluded that the CC licensing basis descriptions (UFSAR) were, with a

few minor exceptions,* consistent with the actual plant design. The team concluded

that the CC UFSAR Macro-Review was a good initiative and identified and corrected

several UFSAR discrepancies. However, the team noted that there are significant

scope and methodology differences between the Vertical Slice/Macro-Review and

an SSFI. Therefore, it was not the primary purpose of the Vertical Slice/Macro-

Reviews, to identify design issues, such as, the ventilation and pump runout issues

that were identified during* this inspection.

-.

45

E8.3

Licensing Basis Updates

a.

Inspection Scope

The team reviewed the timeliness for two licensing basis changes.

b.

Observations and Findings

During the team's review of the EDG loading Calculation ES-9.002, the team noted

the analysis concluded that the load margin must be maintained by restricting the

frequency of the EDG to no greater than 60.5 Hz. A maximum frequency would

limit the maximum pump and fan speeds and limit their driven load. This then

would limit the increase in load to below the EOG' s 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> limit. The calculation

referenced an incident report (94-301, dated October 13, 1994) and a licensing

change request (LCR) 94-40 which addressed the change in the EOG technical

speeification. Technical Specification 4:8:1. l prese-ntly liniits the acceptable

frequency range to 58.8 - 61.2 and the proposed change would set the allowable

range to 58.8 - 60.5 Hz. The LCR 94-301 had not been issued but had been

replaced by LCR S95-36. LCR S95-36 had been sent. to the NRC for approval on

September 26, 1996. The team was concerned with the delay in issuing the LCR

which supports the EDG operability. In response to the team's concern, the

licensee indicated the delay was due to combining the original LCR 94-40 with

another LCR into the new LCR S95-36. There was no explanation why this new

LCR was not released until September 1996.

The team reviewed the licensee's EDG governor test and setup procedure SC.MD-

CM-OG-0006(0), Rev. 8, dated June 12, 1996~ and noted that the allowable

frequency range of the latest governor setup procedure would have supported the

proposed technical specification. (Refer to Section M3.2 of this report for a

discussion on the as-found acceptance criteria.)

The team also noted that a proposed 1995 LCR S95-31, Component Cooling - Add

Third Pump, has not been submitted to the NRC. In addition, actions had not been

initiated to reflect this administrative control requirements in the UFSAR or technical

specification bases. The licensee's system readiness review indicated that the

resolution of this item was scheduled for prior to plant restart.

c.

Conclusions

The team concluded that PSE&G was untimely in submitting their licensing change

request for the EDG frequency limit requirement. In addition, incorporation of the 3

operable CC pumps administrative requirement into the licensing basis was also

untimely.

46

E8.4

Probabilistic Safety Assessment

a.

Inspection Scope

The team reviewed the Salem Probabilistic Safety Assessment (PSA) fault trees to

verify that the CC system design was properly modeled in the PSA fault trees. The

team also verified that dependencies between CC and other safety-related systems

were *consistent with the design information.

b.

Observations and Findings

The team noted that the PSA description of the CC system operation and fault tree

was not consistent was the system design basis. The licensee's PSA engineers

made the following changes to address the team's findings:

.*

Separate. CC fault tre*es* were developed for GC normal operation and CC .

operation when entering cold leg recirculation following a loss of coolant

.*accident. The cold leg recirculation fault trees included separating the two *

  • CC headers as required by the emergency operating procedures.

The Human Error Probability for the operator action to transfer to cold leg

recirculation was recalculated to reflect the train separation.

A new operator action was created to repre~ent restarting a CC pump and

un-isolating the CC heat exchanger service water after a loss of offsite

power and a safety injection signal both occur.

The team also noted that the PSA model incorrectly assumed that the CC to the

charging pump seals was not required for pump operation. In response to this

finding, the licensee's PSA group created a new event tree to model the response to

a loss of all CC as an initiating event. This had previously been excluded as an

initiating event because of the incorrect assumption that the charging pumps were

not dependant on CC. There is a potential that the loss of CC will result in a loss of

the charging pumps and reactor coolant pump thermal barrier cooling. Under certain

conditions, this could result in a RCP seal LOCA.

The preliminary CC model update resulted in a core damage frequency (CDF)

change from approximately 4.4E-5/year to 8.13E-5/year. The new model assumed

that a loss of the 22/23 CC pump room cooler would result in both CC pumps *

failing to function. The licensee's engineering staff was conducting an analysis to

determine what action*s could be implemented to break the dependency between the

CC pump room coolers and CC pumps. A decrease in CDF will be achieved if

corrective actions eliminate this dependency.

The PSA group with the assistance of operations staff reviewed the PSA

descriptions for several safety-related systems to determine if the modeling errors

identified were prevalent throughout the PSA. The operations staff review did not

identify any other significant discrepancies.

47

c.

Conclusion

The team concluded that there were CC modeling errors that adversely affected the

calculated plant CDF. The licensee corrected the identified errors and performed a

review to identify similar errors in the individual plant evaluation (IPE). The team

determined that the licensee's actions to resolve this issue were appropriate.

V. Management Meetings

X1

Exit Meeting Summary

The team discussed the team findings with the licensee staff and management

before leaving the site on December 13, 1996. The team presented the inspection

results to members of licensee management at the conclusion of the inspection on

January 8, 1997. The exit meeting was open for public observation. The slides

used* at the. exit meeting* are provided* as *Enclosure 1 *to this report. *The licensee

acknowledged the findings presented.

No proprietary material was knowingly retained by the team* or disclosed in this

  • inspection report. The SSFI team question data base that was developed by the

licensee will be maintained onsite as a quality controlled record .

I L

l

48

PARTIAL LIST OF PERSONS CONT ACTED

V.J. Chandra, Engineering

T. DelGaizo, Contractor

D. Dodson, Licensing

J. Dunn, Westinghouse

L. Ford, System Manager

M. Hoskins, Engineering

K. King, Engineering

D. Lounsbury, Operations

W. Maher, Engineering

D. McHugh, Senior Engineer

G. Overbeck, Director System Engineering

D. Powell, Licensing

J. Raymond, Westinghouse

Drawings

49

DOCUMENTS REVIEWED

205331 A8763-46, Rev. 46, dated 7/3/96, No. 2 Unit Component Cooling, Sheet 1 of 3

205331 A8763-32, Rev. 32, dated 6/21/96, No. 2 Unit Component Cooling, Sheet 2 of 3

205331 A8763-35, Rev. 35, dated 6/27/96, No. 2 Unit Component Cooling, Sheet 3 of 3

205337 A8763-19, Rev. 35, dated 12/5/96, No. 2 Unit Auxiliary Building Ventilation,

Sheet 2

205337 A8763-2.1, Rev. 21, dated 12/29/96, No. 2 Unit Auxiliary Building Ventilation,

Sheet 3

207491 A8803-24, Rev. 24, No. 1 Unit-Auxiliary Building Component Cooling Piping,

Plans Elev. 45', 55', 64', 100', & 122'

205328-SH1, Rev. 46, Chemical & Volume Control System P&ID

205328-SH2, Rev. 53, Chemical & Volume Control System _P&ID

205328-SH3, Rev. 39, Chemical* & Volume Control System P&ID

.205342-SH3, Rev. 62, Service Water Nuclear Area P&ID

205342-SH4, Rev. 51, Service Water Nuclear Area P&ID

209C219, Rev. 6, CC Pump Motor Outline Drawing

203828, Rev. 20, SWP 21 125V DC Schematic

203834, Rev. 17, SWP 22 125V DC Schematic

220942, Rev. 16, SW Inlet Control Valves to CC HT EX 21 & 22

322509, Rev. 21, 2B Ventilation 230 V Vital CC One Line*

322510, Rev. 20,-2c Ventilation 230 V Vital CC One Line

211517, Rev. 9, .21 CC Pump 125V Schematic

211518, Rev. 4, 22 CC Pump 125V Schematic

-

-

211520, Rev. 4, 23 CC Pump .125V Schematic

211516, Rev. 4, 21 CC Pump 28V Schematic

211519, Rev. 9, 22 CC Pump 28V Schematic

211521, Rev. 7, 23 CC Pump 28V Schematic

601685, Rev. 4, 2CC17, 21CC3, 2CC30 MOV 230/115V Schematic

601683, Rev. 5, 22CC3, 2CC18, 2CC31 MOV Schematic

211527, Rev. 16, 2CC117, 2CC136 MOV Schematic

211528, Rev. 24, 2CC118, 2CC113, MOV & SOV Schematic

216911, Rev. 14, 2CC131 MOV Schematic

218846, Rev. 15, 2CC187 MOV Schematic

21884 7, Rev. 16, 2CC190 MOV Schematic

224384, Rev. 9, 2CC215 SOV Schematic

211526, Rev. 4, 2CC117, 2CC136 28V Control

211 530, Rev. 14, 22CC 16 MOV Schematic

211529, Rev. 15, 21CC16 MOV Schematic

601686, Rev. 1, 22CC3, 2CC18, 2CC31 28V Control

601684, Rev. 0, 2CC17, 21 CC3, 2CC30 28V Control

211524, Rev. 10, 2CC149 28V Control

242625, Rev. 4, RM System Alarms - Sheet 1

242626, Rev. 3, RM _System Alarms - Sheet 2

211522, Rev. 11, 21 Surge Tank and Header Pressure Alarms

211523, Rev. 10, 22 Surge Tank and Header Pressure Alarms

50

220178, Rev. 18, Interface Racks 41 & 126

236256, Rev. 7, Safeguard Equipment Control System

236259, Rev. 8, Safeguard Equipment Control System

236262, Rev. 8, Safeguard Equipment Control System

211357, Rev. 9, 28V DC Oneline

220804, Rev. 8, 2ADE 28V Distribution Cabinet Oneline

220805, Rev. 9, 2BDE 28V Distribution Cabinet Oneline

220806, Rev. 7, 2CDE 28V Distribution Cabinet Oneline

223720, Rev. 22, 125V DC Oneline

220812, Rev. 21, 2A 115V AC Vital Instrument Bus Oneline

220813, Rev. 20, 2B 115V AC Vital Instrument Bus Oneline

220814, Rev. 18, 2C 115V AC Vital Instrument Bus Oneline

222483, Rev. 29, 2A West Valve 230V Control Center Oneline

222484, Rev. 30, 28 West Valve 230V Control Center Oneline

222485, Rev. 37, 2C West Valve 230V Control Center Oneline

  • 222505*, Rev. 23,* 2A East Valve 230V Control *center Orieline

222507, Rev. 24, .2.C East Valve 230V Control Center Oneline

203063, Rev. 31, 460V & 230V Vital and Non-Vital Oneline

601400, Rev. 13, 2A-230V AC Vital Bus Oneline

601401, Rev. 13, 2B-230V AC Vital Bus Oneline

601402, Rev. 11, 2C-230V AC Vital Bus Oneline

203061, Rev. 30, 4160V Vital Buses Oneline

601701, Rev. 13, Salem-Hope Creek 500kV, 138kV, 4.16kV One Line

203117, Rev. 24, 4160V Vital Buses Relay Settings

EOG 2A, 11 /23/96, Loading Test Visicorder Plot

203666, Rev. 9, Safeguards Emergency Loading Sequence SH1

203667, Rev. 7, Safeguards Emergency Loading Sequence SH2

203668, Rev. 6, Safeguards Emergency Loading Sequence SH3

203669, Rev. 7, Safeguards Emergency Loading Sequence SH4

203670, Rev. 11, Safeguards Emergency Loading Sequence SH5

203673, Rev. 6, Safeguards Emergency Loading Sequence SH6

228477, Rev. 14, Control Console Component Coding Water

622031 D, Rev. 0, Loop Diagram Vent Valve 2CC149

6220290, Rev. 1, Loop Diagram Excess Letdown Ht Ex Outlet 2CC113 (3 sheets)

6220300, Rev. 1, Loop Diagram Excess Letdown Hx Ex Inlet 2CC215 (3 sheets)

622013, Rev. 2, Loop Diagram, 2FT601 A (3 sheets)

622014, Rev. 2, Loop Diagram, 2FT601 B (3 sheets)

622017, Rev. 1, Loop Diagram, 2F1 C613

622020, Rev. 1, Loop Diagram, 2F1 C622

622019, Rev. 1, Loop Diagram, 2FIC619

622018, Rev. 1, Loop Diagram, 2FIC616

622021, Rev. 0, Loop Diagram, 2FIC645

622022, Rev. 0, Loop Diagram, 2FIC646

622027, Rev. 0, Loop Diagram, 2FIC643A

622028, Rev. 0, Loop Diagram, 2FIC643B

622032, Rev. 0, Loop Diagram, 2FIC642A

622033, Rev. 0, Loop Diagram, 2FIC642B

622034, Rev. 0, Loop Diagram, 2FIC625

..

51

622015, Rev. 1, Loop Diagram, 2LT628A (2 sheets)

622016, Rev. 0, Loop Diagram, 2LT628B (2 sheets)

622023, Rev. 1, Loop Diagram, 2PC600A

622024, Rev. 1, Loop Diagram, 2PC600B

622000, Rev. 0, Loop Diagram, 2TE672P

622001, Rev. 0, Loop Diagram, 2TE672Q

622006, Rev. 0, Loop Diagram, 2TA8463

622002, Rev. 0, Loop Diagram, 2TE672U

622003, Rev. 0, Loop Diagram, 2TE672V

622007, Rev. 0, Loop Diagram, 2TA8464

622004, Rev. 0, Loop Diagram, 2TE672L

622005, Rev. 0, Loop Diagram, 2TE672M

622008, Rev. 0, Loop Diagram, 2TA8465

622035, Rev. 1, Loop Diagram, 2TIC627 A

622010, Rev. 0, Loop Diagram, 2TE602C

  • * 622011, Rev: 3, Loop Diagram, 2TE602A (2 sheets)

622026, Rev. 1., .Loop Diagram, 2TA9286Z

622036, Rev. 1, Loop Diagram, 2TIC627B

622009, Rev. 0, Loop Diagram, 2TE602D

622012, Rev. 2, Loop Diagram, 2TE602B (2 sheets)

622025, Rev. 2, Loop Diagram, 2TA9264Z

622037,. Rev. 1, Loop Diagram, 2TIC623

622038, Rev. 1, Loop Diagram, 2TIC624

21839-A-8902, Rev. 19, Salem Unit 2 Auxiliary Building Component Cooling Piping,

Mechanical Arrangement, Plans and Elevations

21839-S-8902, Rev. 20, Salem Unit 2 Auxiliary Building Component Cooling Piping,

Mechanical Arrangement, Plans and Elevations

Calculations and Engineering Evaluations

S-C-CC-MDC-0879, Revision 1, 6/23/92, Maximum and Minimum CC Pump Flow

Requirements and NPSH

S-C-CC-MDC-0860, Revision 0, 3/5/92, CC System Design Temperatures

S-C-CC-MDC-0575, Revision 0, 7/16/90, 11 and 21 CCW Heat Exchanger Data Sheet

Revision for Titanium Tubes

S-2-CC-MDC-0559, Revision 0, 6/28/90, 22 CCW Heat Exchanger Performance Evaluation

S-2-ABV-MDC-1622, Revision 0 IR1, 10/24/96, Auxiliary Building Pump Room

Temperatures

S-2-ABV-MDC-1666, Revision 0, 12/9/96, Interim Design Calculation-Maximum Outside

Air Temperature for Mode 6 Entry

S-C-VAR-MEE-1146, Revision 0, 11/1/96, Review Component Cooling & Service Water

System Piping Classifications - Salem

S-C-CC-MEE-0606-0, 7 /29/91, Service Water Pipe Cracks in Component Cooling (CC) Heat

Exchanger 12/22 Cubicle

S-C-CC-MEE-0596-0, 7/15/91, Containment Isolation Valves for Component Cooling

System

S-C-CC-MEE-0880-0, 2/25/94, Evaluation of Component Cooling System Operability with

Valves CC125 & CC146 Open

52

S-C-CC-ME-0605, 7/29/91, Component Cooling (CC) System Surge Tank Relief Valve

CC147 Set Pressure

S-C-CC-ME-0602-0, 7 /29/91, Component Cooling System* Isolation Following Thermal

Barrier Rupture

.

S-C-N21 O-MSE-269, 7 /31 /84, Potential Overpressurization of the Component Cooling

Water System

Westinghouse Calculation 3/10/67, Relief Valves for IPP#2, ACS (applicable to PSE&G)

S-C-4kV-JDC-959, Rev. 4, 6/18/93, Degraded Vital Bus UV Setpoint

ES-4.003(0), Rev. 1, 1 /18/96, 125 Vdc Circuit and System Voltage Drop

ES-4.004(0), Rev. 3, 5/29/96, 125 Vdc Battery and Battery Charger Sizing

ES-4.006(0), Rev. 0, 1 /18/96, 125 Vdc Component Study and Voltage Drop

ES-9.002(0), Rev. 2, 10/14/94, Emergency Diesel Generator Loading

ES-13.005(0), Rev. 5, 3/27/96, Penetration Overcurrent Protection

ES-13.006(0), Rev. 2, 10/18/95, Breaker & Relay Coordination Study

ES-15.004(0), Rev. 1, 10/7/96, Load Flow & Motor Starting.

ES-15J)06(0); Rev. 2, 1 /23195, *23ov Vitat* MCC Power Circuit Voltage Drop

ES-15.008(0), Rev. 2, 12/22/95, Degraded Grid Study

ES-18.006(0), Rev. 0, 6/6/94, Selection of TOL Heater Elements

SC-CC001, Rev. 1, 6/14/94, CC Ht Ex Outlet Temp Setpoint

SC-CC002, Rev. 1, 4/27/96, CC RHR Outlet Flow Setpoint

SC-CC003, Rev. 1, 4/23/96, CC Surge Tank Level Setpoint

S-2-CC-MDC-0898(003) and (004), MOV Capability Assessments for 21 and 22 CC16

Correspondence and Other Documents

DE-CB.CC-0023(0), Revision .2, 1 /5/94, Configuration Baseline Documentation for

Component Cooling Water

NLR-190194, 5/17 /90, B. A. Preston to V. Polizzi, Licensing Position on Passive Failures

Associated with the Salem Service Water System

NLR-194224, 6/14/94, D. A. Smith to H.G. Berrick, Service Water and Component Cooling

Water Design Bases Accident Conditions

LR-196102, 7/25/96, Updated Licensing Position on Passive Failures.Associated with the

Salem Generating Station Service Water System

Westinghouse PSE-89-744, 11/8/89, Salem CCW Calculation Summaries

TS2.SE-SU.CC-0001 (0), Revision 0, 1 OCFR50.59 Applicability Review, CC System Flow

Balance

Westinghouse PSE-84-802 (Re-ISSUED), 7 /26/84, Component Cooling Water System

Potential Overpressurization Notification

Westinghouse BURL-4031, 10/21 /81, Reactor Coolant Pump CC & Seal Injection Water

Loss

Westinghouse PSEB0-96-040, 9/3/96, Single Train Cooldown Analysis Report, Revision 1

Westinghouse PSE-94-605, 5/25/94, Revision 1 of Salem CCWHX SWS Flow Margin

Report (Post-LOCA Mode)

Westinghouse 20223, 5/26/89, Type 93A Reactor Coolant Pump for Surry Units 1 and 2

Estimated Flow Through Thermal Barrier Cooling Water Outlet Caused by Rupture of One

Heat Exchanger Tube

VTD No. 322553, dated 11/21/96, Evaluation of Component Cooling Pump at Runout

Condition, Revision 1, November 7, 1994 (MPR Associates, Inc.)

53

Bechtel Letter GSA-3679, 2/14/91, SWS Heat Exchanger Performance Evaluation -

Computer Runs with Dummy Values

DES-93-0300, 12/30/93

PIR 00950814345 CR

PIR 00960216322

PIR CR 00960925135

Letter LR-N96228, 9/25/96, PSEG to NRC LCRS95-36

~etter LR-N95042, 4/4/95, PSEG to NRC LCR 93-27

Letter NLR-N94169, 9/13/94, PSEG to NRC LCR 93-27

Letter NLR-N94108, 6/28/94, PSEG to NRC LCR 93-27

Letter NLR-N93196, 1/21/94, PSEG to NRC LCR 93-27

Letter 95-1158, 9/19/95, NRC to PSEG 125V DC TS 3.8.2.3

Letter, 12/6/96, C&D to PSEG 1993 Performance Test Evaluation

.Performance Improvement Request 960709221, Concern with Setting CC Flow through

RHRHX, issued July 18, 1996

PSE&G *Audit No. *95..:0125 of tn*service Testing Program*

Nuclear Training Center Lesson Plan 0299-095.04H-PANFLO-OO, Panametrics Ultrasonic

Portable Flowmter

.

..

.

.

.

Panametrics* Letter, dated November 22, 1996, forwarding .Certificate of Calibration for PT

868 Instruments - Serial Numbers 702, 157 and 158

.

Performance Improvement Request 961026073, Discrepancy with RHR HX CC Flow

Measurement

PSE&G Letters NLR-N90021, dated January 26, 1990, and NLR-N90165, dated

August 31, 1990, regarding Commitments to Generic Letter 89-13

Action Request 96031914 7 Regarding Repeat' Failures of Containment Isolation Valves

Action Request 961121204 Regarding Corrective Actions to Control Configuration of

Ventilation System Equipment

Action Request 961202179 Regarding Corrective Actions to Address the Manual Valves

Inconsistency between EOPs and the IST Program

Configuration Baseline Documentation

DE-CB-CC-0023(0), Rev. 0, 1 /15/94, CC System Configuration Baseline Document

Vendor Technical Document

304209, Rev. 7, August 1979, Westinghouse Precautions Limitations & Setpoints

317235, Rev. 1, 4/4/95, General Electric Thermal Overload Relay Data

317227, Rev. 1, 4/4/95, Reliance Motor Data 10 HP

317229, Rev. 1, 4/4/95, Electric Apparatus Motor Data 10 HP

317233, Rev. 1, 4/4/95, Limitorque Motor Data 0.2 HP

175421, Rev. 1, 9/12/94, Westinghouse CC Pump and Motor Data

910-142A-2, Two Channel Transport Model 2 PT868 Portable Flowmeter

54

Technical Standards

ND.DE-TS-ZZ-2012(0), 7/13/94, Low Voltage Circuit Breakers & Combination Starters

.ND.DE-TS.ZZ-2014(0), 12/13/95, Protective Relaying for 4.16kV & 7.2kV Buses

SC.DE-TS.ZZ-2034(0), 7/30/96, Construction of Electrical Installation

OPS Procedure

Emergency Operating Procedures

CC Abnormal and Normal Operation Procedures

2-EOP-APPX-1, Rev. 20, Component Cooling Water Restoration

Miscellaneous

SWEC TOL Walkdown, 11 /95 - 3/96, Fuse & breaker Verification Data Sheets

MMIS Component Data; CC system 230V *Mcc Pan Data Records

Specification

S-C-1978-DSP-1303, Rev. *o, 7126178, Spare Motors (78-1303)

S-C-1970-EGS-0048, Rev. 0, 6/25/70, Alternating Current Motors (70001-A)

S-C-EOOO-:-EGS-0115, Rev. 0, 12/13/85, Alternating Current Motors (85001)

Work Order 960214251, 6/25/96, 2C EOG MOP Replacement

960805170, 8/8/96, 2A EOG Governor Corrective Maintenance

960214210, 7/9/96, 2B EOG MOP Replacement

931124002, 5/11 /93, 2A 125V Station Battery Performance Test

950521003, 11 /14/94, 2C 125V Station Battery Performance Test

931124004,.5/12/93, 2B 125V Station Battery Performance Test

880412133, 10/18/88, .2A 125V Station Battery Replacement

880412134, 9/17/88, 2B 125V Station Battery Replacement

950725034, Rebaseline 21 CC Pump per Procedure S2;0P-ST.CC-0001 (0)

960202028, Rebaseline 22 CC Pump per Procedure S2.0P-ST.CC-0002(0)

950622037, Rebaseline 23 CC Pump per.Procedure S2.0P-ST.CC-0003(0)

960928055, Authorizing Troubleshooting Procedure to Collect Data for Evaluating

Electrical Vibration Levels for 21 , 22, -23 CC Pump

961112091, Authorizing Troubleshooting Procedure to Collect Data for Calibrating RHR HX

CC Flow Elbow Meters

960608023, Regarding Inspection and Cleaning of 21 CC Heat Exchanger

960528046, Regarding Inspection and Cleaning of 22 CC Pump Room Cooler

950924133, Correct Bent Spring Rod Pipe Support 2P-CCH""332

960919250, Replace CC Surge Tank Vacuum Breaker Valve 2CC148

960422158, Perform Set Pressure Test on Relief Valve 2CC112

  • .*"
  • ,

55

Modifications

2EC-3585/Pkg 1, 1 OCFR50.59 Safety Evaluation for CCW Letdown Temperature Control

Valve (CC71)

2EC-3249, 7/8/94, Cable Protection (TOL Replacements)

2EC-3332, 4/1 /96, 125V Battery Charger Replacement

2EZ-1478, 7/13/93, Valve 2CC71 Temperature Interlock

2EC-1015, 10/20/82, Addition of motor operators to CC Valves

2EC-0348, 8/3/83, Addition of motor operators to CC Valves

2EC-1014, 10/12/82, Addition of motor operators to CC Valves

Design Change 2E0-2340, Regarding Replacement Wedte Shoes for MOV 2CC117

Design Change 2E0-2425, Regarding Replacement of 1-inch Globe Valves 2CC281 and

282.

Evaluations .

s..:C-230-EEE-0753, 5/18/93, 230V Motor Operation During Degraded Grid

S-C..:230-EEE-0790-2, 7 /20/93, Motor Starting & Running During LOCA Block Start

UFSAR

8.3, Opsit~ Power System

9.2.2, Component Cooling System ..

11 .4~2.2, Process Radiation Monitor

Chapter 1 5, Accident Analysis

Technical Specification :

2/4.8. 1, AC Sources

3/4.8.2, Onsite Power Distribution

Procedures

S2.IC-CC.RM-0027(0), Rev. 3, 12/11 /96, 2R178 CCW Process Radiation Monitor

SC.MD-ST.ZZ-0005(0), Rev. 2; 5/2/96, MCCB Maintenance

SC.MD-PT.230-0001 (0), Rev. 1, 5/22/96, TOL Overcurrent Trip Testing

SC.MD-CM-DG-0006(0), Rev. 8, 6/12/96, DG Speed/Load Control System Alignment

SC.MD-ST.125-0004(0), Rev. 8, 5/16/96, 125V Station Batteries 18-Month Service Test

SC.MD-FT.125-0002(0), Rev. 4, 11 /15/95, 125V Station Batteries Performance Discharge

Test

82.MD-ST.125-0001 (0), 7/27/96, 125V Battery Charger Maintenance

TS2.SE-SU.CC-0001 (0), CC System Flow Balance

S2.0P-ST.CC-0001 (0), -0002(0), -0003(0), lnservice Testing - 21, 22, 23 Component

Cooling Pumps

S2.0P-ST.SW.0014(0), lnservice Testing, Room Cooler Valves

S2.0P-PT.SW-0026(Q) and -0027(0), 21 and 22 CC Heat Exchanger Heat Transfer

Performance Data Collection

Opened

50-,311/96-81-01

50-311 /96-81-02

£?0-311 /9 6-81-03

50-31 1,196-81-04

50-.311196-81-05

50-311196-81-06

50-311196-81-07

50-311196-81-08

50-311196-81-09 .

50-311/96-81-10

50-311/96-81-11

50-311196-81-12

50-311196-81-13

50-311/96-81-14

50-311196-81-15

56

ITEMS OPENED, CLOSED, AND DISCUSSED

CC pump room ventilation deficiency prior to 1995

.

Current EOPs are inconsistent with single CC pump room ventilation

failure

Current EOPs allow CC pump to runout which is not supported by

pump design documentation

No documented basis for CC flow balance acceptance criteria

No documented basis for CC heat exchanger performance test

assumptions and analysis

Lack of acceptance criteria for CC room ventilation coolers

CC radiation monitors not restored in a timely manner

CC pump room ventilation damper position is not controlled

Battery surveillance -test inadequacies

CC supply to pump seal water cooling heat exchangers

Inadequacy in TOL heater calculation and control

Inadequacy in setpoint calculations .for radiation monitors and surge

tank level alarm

EOG loading study discrepancy* with loading CC pump

EOG loading study discrepancy with battery charger

PASS operation inconsistent with UFSAR

BEP

CBD

cc

CCHX

EOPs

ESQ

ft

gpm

hp

LOCA

NPSH

NRC

PASS

PSE&G

  • psia

RHR

_

RHRHX

RWST

SFP HX

SGS

SI

UFSAR

OF

MCCB

TOL

oc

MAG

CV

SW

A

v

kV

kW

w

C&D

RM

CBD

ac

de

0/L

EOG

MCC

LCR

VTD

MOP

PU

LOOP

57

LIST OF ACRONYMS USED

best efficiency point

Configuration Baseline Documentation

Component Cooling Water System

Component Cooling Heat Exchanger

Emergency Operating Procedures

Emergency Safeguards

feet

gallons per minute

horsepower

Loss of Coolant Accident

Net Positive Suction Head

United States Nuclear Regulatory Commission

Post Accident Sampling System

Pubtic Service* Bectrlc & Gas * *

pounds per square inch absolute

Residual Heat Removal .System

. Residual Heat Removal Heat Exchanger

Refueling Water Storage Tank

  • Spent Fuel Pool Heat Exchanger

Salem Generating Station

Safety Injection

Updated *Final Safety Analysis Report

degrees Fahrenheit

molded case circuit breaker

thermal overload relay

degrees Centigrade

magnetic only (instantaneous) MCCB

chemical and volume control system

service water system

ampere

volt

kilo Volt

kilo Watt

Westinghouse

C&D Charter Power Systems

radiation monitoring system

Configuration Baseline Document

alternating current

direct current

one line

emergency diesel generator

motor control center

Licensing Change Request

Vendor Technical Document

motor operated potentiometer

per unit

loss of offsite power

.

"

ENCLOSURE 1

.

.

...... *

EXIT MEETING *S*LIDES.- * * * * * * *

  • * * * *

SALEM UNIT 2

SAFETY SYSTEM

FUNCTIONAL INSPECTION

. .

.

.

. .. *.

. .

. .

.

COMPONENT COOLING

WATER.

NRC INSPECTION

50-311 /96-81

DECEMBER 2-13, 1996

OBJECTIVE

Determine if the system will perform its

intended safety function

SCOPE

Verify the system has a technically sound

d*esi"gri and* l"icensing basis

  • * * *

Verify that system components are tested

to demonstrate design requirements

Verify that system operating practices are

consistent with the design

Review licensee's efforts to validate

licensing basis

1

OVERALL CONCLUSIONS

Significant CC system improvements

were made during the current outage

The licensing basis descriptions {FSAR)

were, with some exceptions, consistent

with actual plant conditions

  • * * * ** ** Design issues were identi.fied by* the* team

that raise questions regarding CC system

capabilities

Contingent upon the satisfactory

resolution of the SSFI findings,

The SSFI team has concluded that the

Unit 2 CC system can perform its

intended safety function

2

- - - - - - - -

..

CC PUMP ROOM VENTILATION

Operating Practice Are Inconsistent with

Design

Historically, the single failure of CC room

ventilation was not properly addressed

Current EOPs do not support CC system

  • opetation with a single *venti'lation *.

component failure

N.o CC ventilation design analysis to

support current EOPs

.

This issue should have been identified in

1995 when administrative requirements

were changed

Based on the SSFI finding, an AR was

issued to track the resolution of this issue

3

  • ,

Ventilation Configuration Control is

Inadequate

No ventilation damper administrative

controls

Dampers found mis-positioned

Ventilation Testing... * * * * * **

The CC pump room ventilation testing

does not measure design parameters

necessary to demonstrate function

4

...........

CC PUMP OPERATION

Operating Practices Inconsistent With Design

EOPs allow a CC pump to operate beyond

its measured pump curve

The calculation for CC pump runout/NPSH

in:chJded some unsu*bsta**ntiated

=**

..... '*

  • assumptions * * *

An adequate analysis was not completed

to support the runout of the CC pump

Based on the SSFI finding, an AR was

issued to track the resolution of this issue

5

.:.- .

.,

ENGINEERING DESIGN EVALUATIONS

Calculations

Calculations were generally easily

retrievable and available

.... . =.: ***=*--:-*e*: . .---*T*he,*brea:ker ._overcutretit r.-el-a*y,setting:for****** * * * ._ .. ,,~

4 *MoVs Were not *conservative* and*

required resetting

Multiple inconsistencies were noted in the

MOV thermal overload calculation

The setpoint calculation and actual CC

radiation monitor setting were not

appropriate

The setpoint calculation for the surge

tank level alarm was not complete

6

.,

ENGINEERING QUALITY VERIFICATION

Licensing Basis Validation

The PASS system is not operated in

accordance with the FSAR description

Several other minor descriptive FSAR

  • * * * ** * * ***** *. * .. *d*iscrepanc1e*s.' *were***i*denti*f-ied** .* * * **

= =*~ *.**

    • ... - * **

.. *. * * * ... ** .. : *

Minor discrepanci~s were noted between

the implementation of the FSAR project

CC Macro Review and the administrative

guidelines

The CC Macro review fulfilled its intended

function

Two changes to the TS were not

submitted in a timely manner

7

.,

Probabilistic Safety Assessment

Dependencies between the CC

pumps/charging pumps and ventilation

were not modelled correctly

.*'*- .... *.* ..... ** ... Th:~se .. errors. irDP.~.G~e..d .. th~ G~!~~_l9_ted _99re .. . ...

.

damage frequency. . * * .** *.

. *

    • * *.* *
  • * * ***
    • * =

8

.,

.,

SURVEILLANCE AND TESTING

Test Program Scope

In general, CC system components were

included in the test program

One exception was the Spent Fuel Pool

  • **. :, -. :and* Bori*c. ***Acid .-*Evaporato*r .manual .. ,.:., .... >

., .*:: * '; ..... :-*

isolation valves

Procedures

In general, the surveillance test

procedures reviewed were appropriate

One exception was the battery

performance test procedure acceptance

criteria were not consistent with the TS

9

  • ""

.......

, .

Acceptance Criteria

The basis for the CC flow balance test

acceptance criteria was not documented

The basis for the CC heat exchanger

performance test acceptance criteria was

        • * ** ., __ : ....... * ...... ** ... *not.-:documented:-. * :*_ **- ,. *-. * ..... , *.* *: .*- *- .* *.: :: -

._-*, .. ,: *. * *** * * * -* * *.: **; *.* *

Test Program Implementation

In. general, the test program

implementation was good

-

The 1993 battery surveillance test data

were not properly evaluated .

10

OPERATIONS

Procedures

Operating procedures were generally of

high quality and consistent with the CC

system design

~_ .. ,:, -* ..... = .*. ***:=.*Exception *n*oted we*-re*-the * EO*Psrr.elated to--**.:.**.-* .. -**

. ventilation failures or cc pu'tnp runoLit ..

. .

and the RCP trip criteria was inconsistent

between Abnormal Procedures

Training

The CC training material was of high

quality

The simulator properly reflected the CC

design with the exception of the CC

radiation monitor setpoints

11

"-.

l

'

....

Equipment Configuration Control

The CC radiation monitors have been out-

of-service for nearly 1 year

CC system drawings are generally

accurate

    • ..:*:-:*.*:***:.'\\ ......... ,. .. : ....... .:.:=** ..

-

- ........ ,,.*_ .. * ......
  • _. ................. - .. **: .:* .. :*, :* .;
  • .*
  • . *.~*** ... * .... *****

'* ** .. ::.

Corrective actions *reviewed* for cc**

system component failures were.

appropriate

12