ML18102A778

From kanterella
Jump to navigation Jump to search
Forwards Insp Rept 50-311/96-81 on 961202-13.No Violations Noted
ML18102A778
Person / Time
Site: Salem PSEG icon.png
Issue date: 01/21/1997
From: Wiggins J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Eliason L
Public Service Enterprise Group
Shared Package
ML18102A779 List:
References
NUDOCS 9701270181
Download: ML18102A778 (7)


See also: IR 05000311/1996081

Text

Mr. Leon R. Eliason

Chief Nuclear Officer & President

Nuclear Business Unit

January 21, 1997

Public Service Electric and Gas Company

P.O. Box 236

Hancocks Bridge, New Jersey 08038

SUBJECT:

SALEM SAFETY SYSTEM FUNCTIONAL INSPECTION REPORT 96-81

Dear Mr. Eliason:

On January 8, 1996, the NRC completed a Safety System Functional Inspection (SSFI) at

your Salem Unit 2 facility, examining the component cooling (CC) system. The enclosed

report presents the results of that inspection.

We conducted this SSFI inspection to independently assess the scope, depth and quality of

your efforts covered by your Updated Final Safety Analysis Report Project Plan. Other

NRC activities have included our overall review of the Project Plan and inspections

conducted in the May to October 1 996 time period to monitor and assess your

implementation of that Plan. We will finalize our views on the adequacy of your activities

after we meet with you. That meeting will provide you an opportunity to describe the

results of your overall efforts in the licensing and design bases areas. We anticipate

scheduling that meeting in February, 1997.

The team noted that significant improvements were made to the component cooling

system during the current outage. These improvements included the completion of a

system flow balance, resolution of instrument calibration errors, and the completion of a *

significant amount of corrective and preventive maintenance activities. Also, the team

noted that your Updated Final Safety Analysis Report Project Plan review effort identified

and resolved a number of licensing basis discrepancies. However, the team identified two

design basis issues that call into question the system's ability to perform its safety

function.

A single failure of the CC room ventilation could adversely affect 2 CC pumps, leaving only

one CC pump available for long term operation. For certain accident scenarios, your

Emergency Operating Procedures (EOPs) rely on having at least two CC pumps functional.

Therefore, the EOP need for two pumps appears inconsistent with the ventilation system

design. The second issue is related to the operation of the CC pumps during certain

postulated accident conditions. The EOPs require that operators manually start a single CC

pump following certain accidents. For a short period of time, after switching emergency

core cooling pump suction from the refueling water storage tank to the containment sump,

the CC pump may operate at flow rates beyond its current design limit. Operating a CC

pump at high flow rates is inconsistent with its design basis and our review of your prior

analysis of this condition raised several questions. In addition, the team also identified

weaknesses in the quality of several other engineering calculations and analyses associated

with the CC system.

9701270181 970121

PDR

ADOCK 05000311

Q

PDR

270012

. "*

_ ....

Mr. Leon R. Eliason

2

It also appears that a number of the design and analysis issues discussed in this report

have strong connections to the existing restart concern associated with emergency diesel

generator (EOG) loading. You should carefully review the results of this report and factor

the insights gained from that review into your short and long term approach to the EOG

loading issue. In addition, as discussed during our January 8, 1997 exit meeting, you

should consider the need for measuring the extent to which the identified design and

analysis issues affect the condition of other important plant systems, structures and

components, along with the need for a prioritized plan to address those conditions.

At the February 1997 meeting, along with your discussion of the integrated results of your

licensing and design bases conformance activities, you should also be prepared to discuss

the impact of the SSFI findings on any conclusions reached as a result of those activities.

In addition, you should address: (1) your plans for any "extent of condition" reviews; (2)

the impact of this report's results on the EOG loading issue; and, (3) whether any of the

report results constitute new or revised restart items.

Since the final resolution of the SSFI findings are pending further evaluation by your staff

and by the NRC, this inspection report does not address enforcement actions. Inspection

findings that are candidates for enforcement are identified in this report as unresolved

items . .You will be notified in future correspondence of our decision on any enforcement

actions.

In accordance with 10 CFR 2. 790 of the Commission's regulations, a copy of this letter

and its enclosure will be placed in the NRC Public Document Room.

Docket No. 50-311

Enclosures:

Sincerely,

.* James T. Wiggins, Director

Division of Reactor Safety

1 . NRC Region I SSFI Report No. 50-311 /96-81

2. Slides from Exit Meeting

o

I

Mr. Leon R. Eliason

3

cc w/encl:

L. Storz, Senior Vice President - Nuclear Operations

E. Simpson,. Senior Vice President - Nuclear Engineering

E. Salowitz, Director - Nuclear Business Support

C. Schaefer, External Operations - Nuclear, Delmarva Power & Light Co.

D. Garchow, General Manager - Salem Operations

J. Benjamin, Director - Quality Assurance & Nuclear Safety Review

D. Powell, Manager, Licensing and Regulation

R. Kankus, Joint Owner Affairs

A. Tapert, Program Administrator

R. E. Selover, Esquire

M. Wetterhahn, Esquire

P. MacFarland Goelz, Manager, Joint Generation

Atlantic Electric

Consumer Advocate, Office of Consumer Advocate

William Conklin, Public Safety Consultant, Lower Alloways Creek Township

Public Service Commission of Maryland

State of New Jersey

State of *Delaware

--*

Mr. Leon R. Eliason

Distribution w/encl:

Region I Docket Room (with concurrences)

J. Wiggins, DRS

Kay Gallagher, DRP

Nuclear Safety Information Center (NSIC)

L. Nicholson, DRP

S. Barber, DRP

R. DePriest, DRP

G. Kelly, DRS

N. Della Greca, DRS

G. Morris, DRS _

S. Klein, DRS

L. Prividy, DRS

J. Trapp, DRS

D. Screnci, PAO

NRC Resident Inspector

PUBLIC

DRS Files

Distribution w/encl: (Via E-Mail)

L. Olshan, NRR

W. Dean, OEDO

J. Stolz, PDl-2, NRR

M. Callahan, OCA

Inspection Program Branch, NRR (IPAS)

R. Correia, NRR

R. Frahm, Jr., NRR

DOCUMENT NAME: A:\\SAL9681.INS

4

To receive a copy of this document, indicate in the box: *c* = Copy w' out attachment/encl

OFFICE

RI/DRS

NAME

JTrapp

DATE

01/17/97

01 t- /97

"E" = Copy with attachment/enclosure "N" = No copy

RI/DRS

RI/

JWiggins

01121191

01 / /97

OFFICIAL RECORD COPY

EXECUTIVE SUMMARY

Salem Nuclear Generating Station, Unit 2

NRC Inspection Report 50-311 /96-81

The objective of this inspection was to conduct an independent inspection to determine if

the Salem Unit 2 component cooling (CC) system would perform its intended safety

function.

Operations

The team identified an operating procedure weakness in that under certain *

conditions, a single active failure of certain equipment is not supported by the

emergency operating procedures (EOPs). The single failures identified by the team

were the failure of the 22/23 CC pump room ventilation (2VHE-34) or the failure of

the Train C electrical power. The loss of Train C electrical power would prevent the

operation of the 21 CC pump room ventilation (2VHE-33) and the 23 CC pump. A

single failure of this equipment could adversely affect the performance of two CC

pumps leaving only one CC pump available. For certain accidents, the EOPs require

two CC pumps be operating. The licensee failed to evaluate this vulnerability in

1995 when administrative controls were developed requiring 3 operable. CC pumps

(Section 03.1 ).

'

The CC system normal and abnormal operating procedures were recently upgraded

and were of good quality (Section 03.2).

The procedures and lesson. plans used for CC training were of high quality and

appropriately complete for evaluation of operator knowledge and abilities on the

system (Section 05.1 ).

Maintenance

The team identified that Publip Service Electric and Gas (PSE&G) had no

documented calculations to support the CC flow acceptance criteria used in the

flow balance test. Final conclusions regarding the results of the flow balance test

could not be made pending completion of these documented calculations (Section

M1 .1 ).

In general, PSE&G was adequately implementing testing required by the surveillance

testing program. However, the team identified several valves where controls were

not in place to ensure that they would be periodically tested (Section M1 .2). Also,

an error was noted in the battery surveillance test procedure and the 1993 battery

test data was not properly evaluated to determine battery degradation (Section

M3.2) *

iv

-: .-,-- ..

PSE&G did not provide an adequate documented technical basis for justifying the

5 % instrument measurement uncertainty assumption used in CC heat exchanger

performance calculations. Acceptance criteria for assessing the as-found condition

of the CC room coolers had not been established and room cooler service water and

air flow rates were not being monitored for assuring equipment operability (Section

M1.3).

The team concluded that PSE&G failed to repair the CC radiation monitors in a

timely manner since they had been out of service for over a year (Section M2.1 ).

Good corrective actions were being taken to identified CC equipment problems

(Section M2.2).

The team identified several CC pump room dampers that were closed which was

inconsistent with information on applicable ventilation system drawings. These

deficiencies demonstrated inadequate configuration control of ventilation equipment

needed to support CC system operability (Section M3.1 ).

The CC heat exchanger thermal performance computer model is not conservative

(Section M1 .3).

Engineering

The team identified a c*ondition where the operation of the CC pumps appears

inconsistent with documented design limits. The team concluded that the CC

pumps will probably be at or near runout conditions when the residual heat removal

heat exchanger outlet valves are automatically opened on low refueling water

storage tank level during a postulated loss of coolant accident. Component cooling

pump operation at runout during these conditions has not been adequately analyzed

by the license~. Consequently, the CC pumps may be adversely affected if

sufficient net positive suction head (NPSH) is not available, and the pumps are

subjected to the effects of cavitation (Sections 03.1 and E1 .1 ).

In general, design basis information and calculations were available and retrievable.

However, the team identified weaknesses in several calculations. The most

significant weaknesses were noted in the CC pump NPSH, thermal overload heater

sizing, and molded case circuit breaker overcurrent setting calculations. In these

cases, inadequacies in calculation methodology or assumptions invalidate the

conclusion of the calculation. In addition, the team also noted that the licensee ~

failed to document a number of engineering judgements and assumptions. In these

cases, the missing engineering judgements and unsubstantiated assumptions did not

invalidate the results of the calculations (Sections E1.1, E1 .4, E3.1, and E3.4).

v

The design change to place the thermal overload (TOL) heaters in service resulted in

the installation of TOL heaters without an adequate documented design basis. The

team concluded that the licensee had not maintained document control of the TOL

relay heaters associated with the CC system and other safety-related systems. - The

team identified heaters existed in motor operated valve (MOV) circuits that were not

based on the existing calculated basis. The team also concluded that a change

document to the design calculation did not provide an adequate documented basis

for the installed TOL heaters for 30 safety-related MOVs (Section E1 .4).

The team concluded that the design basis documents for the CC system radiation

monitor setpoints were inconsistent. The team also determined that the CC ;, *. -

radiation monitor setpoints may be inappropriately set to high. These radiation* __

monitors are not safety-related and are not used to calculate off site radioactive*

releases (Section E1 .5).

The team concluded that the licensing basis descriptions for the CC system were,

with a few minor exceptions, consistent with the actual plant design. The team -

concluded that the CC UFSAR Macro-Review was a *good initiative and identified

and corrected several updated final safety analysis report (UFSAR) discrepancies

(Section E8.2).

The team noted that the EOPs provide instructions to isolate component cooll-ng

water from the post accident sampling system (PASS) heat exchangers during

accident conditions. The PASS heat exchangers are provided cooling water using

temporary hoses from the demineralized water system. Operation of PASS using

demineralized water during postulated accident conditions is inconsistent with the

design and licensing basis (Section 8.1-).

The team concluded that the development of the technical standards program was a

positive initiative. However, the team noted that the standards did not include a

technical justification for acceptance of existing conditions in the plant. The team

considered this to be a program weakness. In addition, the team identified one case

where work in progress, during the development of the technical standards, was

not coordinated with the developing standard (Section E3.2).

The team concluded that the CC system drawings were generally accurate. Jhe

licensee initiated actions to correct the minor discrepancies identified by the team

(Section E3.3) *

vi