Letter Sequence Supplement |
---|
EPID:L-2017-LLA-0421, ITAAC Closure Verification Evaluation Form (Vef) 5149 for ITAAC 3.2.00.01c.ii (Index No. 742) for Vogtle Unit 4 (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
|
MONTHYEARML18019A3622018-01-25025 January 2018 (LAR 17-037) Acceptance Letter Project stage: Acceptance Review ML18066A7172018-03-0707 March 2018 COL Docs - RAI Transmittal for Vogtle 3 & 4 LAR 17-037 (RAI LAR 17-037-1) Project stage: RAI ND-18-0417, Supplement to Request for License Amendment and Exemption: Changes to Tier 2 Departure Evaluation Process2018-04-0606 April 2018 Supplement to Request for License Amendment and Exemption: Changes to Tier 2 Departure Evaluation Process Project stage: Supplement ML18102B6832018-04-12012 April 2018 COL Docs - RAI Transmittal for Vogtle 3 & 4 LAR 17-037 (RAI LAR 17-037-3) Project stage: RAI ML18113A7802018-04-23023 April 2018 COL Docs - RAI Transmittal for Vogtle 3 & 4 LAR 17-037 (RAI LAR 17-037-4) Project stage: RAI ML18121A4372018-05-0101 May 2018 COL Docs - RAI Transmittal for Vogtle 3 and 4 LAR 17-037 (RAI LAR 17-037-5, -6, -7, and -8) Project stage: RAI ML18128A3692018-05-0808 May 2018 COL Docs - RAI Transmittal for Vogtle 3 and 4 LAR 17-037 (RAI LAR 17-037-9) Project stage: RAI ND-18-0608, Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S2)2018-05-11011 May 2018 Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S2) Project stage: Supplement ND-18-0646, Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S3)2018-06-18018 June 2018 Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S3) Project stage: Supplement ND-18-0830, Unit 4 - ITAAC Closure Notification on Completion of ITAAC 3.2.00.01c.ii (Index Number 742)2018-06-27027 June 2018 Unit 4 - ITAAC Closure Notification on Completion of ITAAC 3.2.00.01c.ii (Index Number 742) Project stage: Request ND-18-0831, Unit 4 - ITAAC Closure Notification on Completion of ITAAC 3.2.00.01d (Index Number 743)2018-06-28028 June 2018 Unit 4 - ITAAC Closure Notification on Completion of ITAAC 3.2.00.01d (Index Number 743) Project stage: Request ML18200A1682018-07-19019 July 2018 ITAAC Closure Verification Evaluation Form (Vef) 4369 for ITAAC 3.2.00.01d (Index No. 743) for Vogtle Unit 3 Project stage: Request ML18200A1672018-07-19019 July 2018 ITAAC Closure Verification Evaluation Form (Vef) 5149 for ITAAC 3.2.00.01c.ii (Index No. 742) for Vogtle Unit 4 Project stage: Request ND-18-1006, Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S4)2018-08-0303 August 2018 Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S4) Project stage: Supplement ND-18-1067, Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S5)2018-08-10010 August 2018 Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S5) Project stage: Supplement ML18256A4002018-09-0707 September 2018, 12 September 2018, 20 September 2018, 26 September 2018 Non-Concurrence Process NCP-2018-008, Vogtle Units 3 and 4, License Amendment Request 17-037, Changes to Tier 2* Departure Evaluation Process Project stage: Request ND-18-1180, Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S6)2018-09-13013 September 2018 Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S6) Project stage: Supplement ML18235A0322018-09-20020 September 2018 Exemption - Vogtle Electric Generating Plant, Unit 4 LAR 17-037 Project stage: Other ML18207A2622018-09-20020 September 2018 Safety Evaluation - Vogtle Electric Generating Plant, Units 3 and 4 LAR 17-037 Project stage: Approval ML18235A0362018-09-20020 September 2018 Attachment to Amendment No. 141 - VEGP Unit 4 LAR 17-037 Project stage: Acceptance Review ML18235A0352018-09-20020 September 2018 Amendment No. 141 - Vogtle Electric Generating Plant, Unit 4 LAR 17-037 Project stage: Other ML18235A0342018-09-20020 September 2018 Attachment to Amendment No. 142 - VEGP Unit 3 LAR 17-037 Project stage: Acceptance Review ML18235A0292018-09-20020 September 2018 Issuance of Amendments 142 and 141 and Granting of Exemptions Changes to the Tier 2* Departure Evaluation Process (LAR 17-037) Project stage: Request ML18235A0302018-09-20020 September 2018 Cover Letter - Vogtle LAR 17-037 - Issuance of Amendments 142 and 141 and Granting of Exemptions Re Changes to the Tier 2* Departure Evaluation Process Project stage: Approval ML18235A0312018-09-20020 September 2018 Exemption - Vogtle Electric Generating Plant - Unit 3 LAR 17-037 Project stage: Other ML18235A0332018-09-20020 September 2018 Amendment 142 - Vogtle Electric Generating Plant, Unit 3 LAR 17-037 Project stage: Other 2018-06-18
[Table View] |
|
---|
Category:Letter type:ND
MONTHYEARND-24-0103, Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests2024-04-26026 April 2024 Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests ND-24-0114, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-04-0101 April 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-24-0046, (Vegp), Unit 3, Condition Prohibited by Technical Specification Limiting Condition of Operation 3.1.6 Control Bank Overlap Limits Exceeded Due to Inadequate Procedure Guidance2024-03-18018 March 2024 (Vegp), Unit 3, Condition Prohibited by Technical Specification Limiting Condition of Operation 3.1.6 Control Bank Overlap Limits Exceeded Due to Inadequate Procedure Guidance ND-24-0059, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-03-0404 March 2024 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0693, Combined License (COL) License Condition 2.D.(4)(d) Completion of Initial Criticality and Low-Power Tests2024-02-15015 February 2024 Combined License (COL) License Condition 2.D.(4)(d) Completion of Initial Criticality and Low-Power Tests ND-23-0690, Combined License (COL) License Condition 2.D.(3)(e) Completion of Pre-Critical Tests2024-02-0808 February 2024 Combined License (COL) License Condition 2.D.(3)(e) Completion of Pre-Critical Tests ND-24-0019, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-02-0101 February 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0912, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-01-0202 January 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0881, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-12-0404 December 2023 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0817, Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a)2023-11-17017 November 2023 Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a) ND-23-0823, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-11-0303 November 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0723, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-10-0404 October 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0697, Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-09-0505 September 2023 Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0669, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-08-0707 August 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0205, Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests2023-07-28028 July 2023 Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests ND-23-0608, ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72) ND-23-0618, Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797)2023-07-20020 July 2023 Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797) ND-23-0609, Notification of Completion of All ITAAC2023-07-20020 July 2023 Notification of Completion of All ITAAC ND-23-0607, ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13) ND-22-0796, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813) ND-23-0459, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587) ND-23-0162, ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165) ND-23-0575, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588) ND-23-0439, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265) ND-23-0552, Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624)2023-07-18018 July 2023 Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624) ND-23-0483, ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4) ND-23-0586, ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159)2023-07-17017 July 2023 ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159) ND-23-0610, ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603)2023-07-17017 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603) ND-23-0573, ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497) ND-23-0406, ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498) ND-22-0816, ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19)2023-07-15015 July 2023 ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19) ND-23-0603, ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831) ND-23-0446, ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250) ND-23-0594, ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629) ND-23-0601, ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719) ND-23-0606, ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557) ND-23-0499, ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700) ND-23-0476, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355) ND-23-0588, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78) ND-23-0121, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667) ND-23-0122, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668) ND-23-0597, ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530) ND-23-0002, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270) ND-23-0543, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622) ND-23-0394, ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703) ND-23-0461, ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652) ND-22-0980, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75) ND-23-0111, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646) ND-23-0587, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595) ND-23-0589, ITAAC Closure Notification on Completion of ITAAC 2.6.03.04a (Index Number 601)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.03.04a (Index Number 601) 2024-04-26
[Table view] Category:License-Application for Facility Operating License (Amend/Renewal) DKT 50
MONTHYEARNL-24-0286, Emergency Request to Revise Technical Specification 3.7.9 for a One-Time Change to Support a Unit 1 Nuclear Service Cooling Water Transfer Pump Repair2024-07-20020 July 2024 Emergency Request to Revise Technical Specification 3.7.9 for a One-Time Change to Support a Unit 1 Nuclear Service Cooling Water Transfer Pump Repair NL-24-0234, Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown2024-06-28028 June 2024 Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown NL-24-0087, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks2024-06-21021 June 2024 License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks NL-22-0267, License Amendment Request to Revise Diesel Generator Frequency and Voltage Ranges for Technical Specification 3.8.1, AC Sources – Operating, Surveillance Requirements2024-03-20020 March 2024 License Amendment Request to Revise Diesel Generator Frequency and Voltage Ranges for Technical Specification 3.8.1, AC Sources – Operating, Surveillance Requirements NL-23-0666, License Amendment Request: Remove Combined License Appendix C (LAR 23-008)2023-08-28028 August 2023 License Amendment Request: Remove Combined License Appendix C (LAR 23-008) NL-23-0360, Supplement to License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel2023-05-0505 May 2023 Supplement to License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel NL-23-0217, License Amendment Request to Revise Technical Specification Surveillance Requirement 3.4.14.1 and Proposed Inservice Testing Alternative ALT-VR-022023-05-0101 May 2023 License Amendment Request to Revise Technical Specification Surveillance Requirement 3.4.14.1 and Proposed Inservice Testing Alternative ALT-VR-02 NL-23-0152, License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-144832023-04-11011 April 2023 License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-14483 NL-23-0136, License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006)2023-04-0505 April 2023 License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006) NL-22-0764, – Units 1 & 2, License Amendment Request to Revise Technical Specification 1.1 and Add 5.5.23 to Use Online Monitoring Methodology2022-12-21021 December 2022 – Units 1 & 2, License Amendment Request to Revise Technical Specification 1.1 and Add 5.5.23 to Use Online Monitoring Methodology ND-22-0894, License Amendment Request for Technical Specification SR 3.0.3 for Never-Performed Surveillances (LAR-22-005)2022-12-19019 December 2022 License Amendment Request for Technical Specification SR 3.0.3 for Never-Performed Surveillances (LAR-22-005) NL-22-0897, Supplement to Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A,2022-12-0909 December 2022 Supplement to Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, ML22286A1252022-11-16016 November 2022 Issuance of Amendments Nos. 217 & 200 Regarding Revision to Technical Specifications to Adopt TSTF-283-A, Revision 3, Modify Section 3.8 Mode Restriction Notes NL-20-0170, Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC2022-10-14014 October 2022 Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC NL-22-0208, License Amendment Request for Alternative Source Term, TSTF-51, TSTF-471, and TSTF-4902022-06-30030 June 2022 License Amendment Request for Alternative Source Term, TSTF-51, TSTF-471, and TSTF-490 NL-22-0288, License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel2022-06-30030 June 2022 License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel NL-21-0994, Adoption of TSTF-283-A, Revision 3, Modify Section 3.8 Mode Restriction Notes2021-12-22022 December 2021 Adoption of TSTF-283-A, Revision 3, Modify Section 3.8 Mode Restriction Notes NL-21-0989, License Amendment Request to Relocate Augmented Piping Inspection Program Details2021-12-22022 December 2021 License Amendment Request to Relocate Augmented Piping Inspection Program Details NL-21-0925, Adoption of TSTF-269-A, Revision 2, Allow Administrative Means of Position Verification for Locked or Sealed Valves2021-12-22022 December 2021 Adoption of TSTF-269-A, Revision 2, Allow Administrative Means of Position Verification for Locked or Sealed Valves NL-21-0930, Joseph F. Farley Nuclear Plant, Units 1 & 2 and Vogtle Electric Generating Plant, Units 1 and 2 - Supplement to Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspections2021-10-21021 October 2021 Joseph F. Farley Nuclear Plant, Units 1 & 2 and Vogtle Electric Generating Plant, Units 1 and 2 - Supplement to Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspections NL-21-0845, License Amendment Request: Revise Technical Specification 3.7.2 Limiting Condition for Operation to Remove One Main Steam Isolation Valve System2021-09-30030 September 2021 License Amendment Request: Revise Technical Specification 3.7.2 Limiting Condition for Operation to Remove One Main Steam Isolation Valve System NL-21-0385, Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements2021-09-29029 September 2021 Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements NL-21-0658, Joseph Farley, Units 1 and 2, Vogtle, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for for Steam Generator Tube Inspections2021-09-17017 September 2021 Joseph Farley, Units 1 and 2, Vogtle, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for for Steam Generator Tube Inspections NL-21-0613, Supplement to License Amendment Request to Revise Technical Specification 5.7, High Radiation Area, .2021-06-30030 June 2021 Supplement to License Amendment Request to Revise Technical Specification 5.7, High Radiation Area, . NL-21-0160, License Amendment Request to Remove Table of Contents from Technical Specifications2021-06-22022 June 2021 License Amendment Request to Remove Table of Contents from Technical Specifications NL-21-0042, Units 1 and 2, Vogtle Electric Generating Plant - Units 1 and 2, Voluntary License Amendment Request to Use Beacon Power Distribution Monitoring System2021-06-0909 June 2021 Units 1 and 2, Vogtle Electric Generating Plant - Units 1 and 2, Voluntary License Amendment Request to Use Beacon Power Distribution Monitoring System NL-20-0173, License Amendment Request to Revise Technical Specification Surveillance Requirement 3.3.5.2 Allowable Values2021-03-30030 March 2021 License Amendment Request to Revise Technical Specification Surveillance Requirement 3.3.5.2 Allowable Values NL-21-0065, License Amendment Request to Revise Technical Specification 5.7, High Radiation Area, Administrative Controls2021-03-25025 March 2021 License Amendment Request to Revise Technical Specification 5.7, High Radiation Area, Administrative Controls NL-20-0949, License Amendment Request to Revise, Technical Specifications to Adopt TSTF-541, Revision 22020-10-30030 October 2020 License Amendment Request to Revise, Technical Specifications to Adopt TSTF-541, Revision 2 ML20224A4642020-08-11011 August 2020 Southern Nuclear Operating Co, Inc - Supplement to License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions ML20192A1402020-06-30030 June 2020 Southern Nuclear Operating Co., Inc. - License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions ND-20-0093, Supplement to Request for License Amendment: Tornado Missile Protection for Main Steam Vent Stacks and Wall 11 (LAR-19-014S1)2020-02-14014 February 2020 Supplement to Request for License Amendment: Tornado Missile Protection for Main Steam Vent Stacks and Wall 11 (LAR-19-014S1) ND-19-1483, Request for License Amendment: Reconciliation of Environmental Conditions Inputs to Civil Structural Design Licensing Basis (LAR-19-019)2019-12-13013 December 2019 Request for License Amendment: Reconciliation of Environmental Conditions Inputs to Civil Structural Design Licensing Basis (LAR-19-019) NL-19-0963, Removal of the Main Steam and Main Feedwater Valve Isolation Times from Technical Specifications Using Consolidated Line Item Improvement Process2019-12-11011 December 2019 Removal of the Main Steam and Main Feedwater Valve Isolation Times from Technical Specifications Using Consolidated Line Item Improvement Process NL-19-1063, Units 1 and 2 and Vogtle Electric Generating Plant, Units 1 and 2 - Application to Revise Technical Specifications to Adopt TSTF-569, Revise Response Time Testing Definition2019-12-10010 December 2019 Units 1 and 2 and Vogtle Electric Generating Plant, Units 1 and 2 - Application to Revise Technical Specifications to Adopt TSTF-569, Revise Response Time Testing Definition NL-19-0006, Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program2019-07-15015 July 2019 Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program NL-19-0635, End State Revision from Hot Shutdown to Cold Shutdown for Several Technical Specifications2019-07-0909 July 2019 End State Revision from Hot Shutdown to Cold Shutdown for Several Technical Specifications NL-18-1302, License Amendment Request for Technical Specification Improvement to Revise Actions for One Steam Supply to Turbine Driven Auxiliary Feedwater Pump Inoperable Using the Consolidated Line ...2018-12-19019 December 2018 License Amendment Request for Technical Specification Improvement to Revise Actions for One Steam Supply to Turbine Driven Auxiliary Feedwater Pump Inoperable Using the Consolidated Line ... ML18226A0942018-08-0909 August 2018 Edwin I. Hatch, Units 1 and 2; and Vogtle, Units 1 and 2 - License Amendment Request to Revise Technical Specification 5.2.2.g and Update Emergency Plan Minimum On-shift Staff Tables NL-18-1043, License Amendment Request: Supplement to Request to Incorporate Seismic Probabilistic Risk Assessment Into the Categorization Process2018-08-0606 August 2018 License Amendment Request: Supplement to Request to Incorporate Seismic Probabilistic Risk Assessment Into the Categorization Process ND-18-0417, Supplement to Request for License Amendment and Exemption: Changes to Tier 2 Departure Evaluation Process2018-04-0606 April 2018 Supplement to Request for License Amendment and Exemption: Changes to Tier 2 Departure Evaluation Process ND-18-0199, Supplement to Request for License Amendment and Exemption Regarding Technical Specifications for Reactor Coolant System Vacuum Fill and Inspections, Tests, Analyses, and Acceptance Criteria for Containment Floodup (LAR-17-027S3)2018-02-14014 February 2018 Supplement to Request for License Amendment and Exemption Regarding Technical Specifications for Reactor Coolant System Vacuum Fill and Inspections, Tests, Analyses, and Acceptance Criteria for Containment Floodup (LAR-17-027S3) NL-17-1199, Submittal of License Amendment Request to Revise Technical Specification Section 5.5.17 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2017-09-12012 September 2017 Submittal of License Amendment Request to Revise Technical Specification Section 5.5.17 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies ML17208B0182017-08-31031 August 2017 Issuance of Amendments Regarding Technical Specification Requirements for Diesel Fuel Oil (TSTF-374) NL-17-1088, Submittal of License Amendment Request, Relocation of the Emergency Operations Facility2017-08-30030 August 2017 Submittal of License Amendment Request, Relocation of the Emergency Operations Facility NL-16-2382, License Amendment Request to Modify Approved 10 CFR 50.69 Categorization Process2017-06-22022 June 2017 License Amendment Request to Modify Approved 10 CFR 50.69 Categorization Process NL-17-1026, Revision to Technical Specifications Pages for Limiting Condition for Operation 3.7.142017-06-0202 June 2017 Revision to Technical Specifications Pages for Limiting Condition for Operation 3.7.14 NL-17-0236, License Amendment Request to Revise Technical Specification Surveillance Requirement 3.3.1.32017-05-24024 May 2017 License Amendment Request to Revise Technical Specification Surveillance Requirement 3.3.1.3 NL-17-0058, Request to Revise Technical Specifications LCO 3.7.9 for a Change to Support Nuclear Service Cooling Water Transfer Pump Repairs2017-03-24024 March 2017 Request to Revise Technical Specifications LCO 3.7.9 for a Change to Support Nuclear Service Cooling Water Transfer Pump Repairs NL-16-2631, Exigent Request to Revise Technical Specifications LCO 3.7.9 for a One-Time Change to Support Unit 2 Nuclear Service Cooling Water Transfer Pump Repair2016-12-13013 December 2016 Exigent Request to Revise Technical Specifications LCO 3.7.9 for a One-Time Change to Support Unit 2 Nuclear Service Cooling Water Transfer Pump Repair 2024-07-20
[Table view] |
Text
B. H. Whitley Southern Nuclear Director Operating Company, Inc.
Regulatory Affairs 42 Inverness Center Parkway Birmingham, AL 35242 Tel 205.992.7079 Fax 205.992.5296 April 6, 2018 Docket Nos.: 52-025 ND-18-0417 52-026 10 CFR 50.90 10 CFR 52.7 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Units 3 and 4 Supplement to Request for License Amendment and Exemption:
Changes to Tier 2* Departure Evaluation Process (LAR-17-037S1)
Ladies and Gentlemen:
Pursuant to 10 CFR 52.98(c) and in accordance with 10 CFR 50.90, Southern Nuclear Operating Company (SNC) requested an amendment to the combined licenses (COLs) for Vogtle Electric Generating Plant (VEGP) Units 3 and 4 (License Numbers NPF-91 and NPF-92, respectively) by SNC letter ND-17-1726, dated December 21, 2017 [ADAMS Accession Number ML17355A416],
to apply the existing departure evaluation process for Tier 2 departures in the evaluation of certain Tier 2* departures. In this same letter SNC also requested an exemption from certain change requirements in 10 CFR Part 52, Appendix D, to allow departures from Tier 2* information evaluated against criteria proposed in a new License Condition without a license amendment by expanding the applicability of the existing Tier 2 departure evaluation process.
This supplement provides information in response to a Request for Additional Information (RAI),
(LAR 17-037-1) from the NRC Staff, which was transmitted by electronic mail (email) on March 7, 2018 [ADAMS Accession Number ML18066A717], to support review of LAR-17-037. The responses to the RAI questions also consider feedback provided by the NRC staff during a public phone call on March 29, 2018.
Enclosures 1 through 8 were provided with the original LAR-17-037, SNC letter ND-17-1726. to this letter provides the SNC responses to Questions 1 through 3 of RAI LAR-17-037-1.
The information provided in this License Amendment Request (LAR) supplement does not impact the scope, technical content, or conclusions of the Significant Hazards Consideration Determination, the Environmental Considerations, or markups to the licensing basis documents of the original LAR-17-037 provided in Enclosures 1 and 3 of SNC letter ND-17-1726.
U.S. Nuclear Regulatory Commission ND-18-0417 Page 2 of 4 This letter has been reviewed and confirmed to not contain security-related information. This letter contains no regulatory commitments.
In accordance with 10 CFR 50.91, SNC is notifying the State of Georgia of this LAA supplement by transmitting a copy of this letter and its enclosure to the designated State Official.
Should you have any questions, please contact Wesley Sparkman at (205) 992-5061.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 6th of April 2018.
Respectfully submitted, Brian H. Whitley Director, Regulatory Affairs Southern Nuclear Operating Company Enclosures 1-8) (Previously submitted with the original LAA, LAR-17-037, in letter ND 1726)
- 9) Vogtle Electric Generating Plant (VEGP) Units 3 and 4 - Response to NRC Request for Additional Information (RAI) Regarding the LAR-17-037 Review (LAR-17-037S1)
U.S. Nuclear Regulatory Commission ND-18-0417 Page 3 of 4 cc:
Southern Nuclear Operating Company / Georgia Power Company Mr. S. E. Kuczynski (w/o enclosure)
Mr. M. D. Rauckhorst Mr. D. G. Bost (w/o enclosure)
Mr. M. D. Meier (w/o enclosure)
Mr. D. H. Jones (w/o enclosure)
Mr. J. B. Klecha Mr. G. Chick Mr. D. L. McKinney (w/o enclosure)
Mr. T. W. Yelverton (w/o enclosure)
Mr. B. H. Whitley Ms. C. A. Gayheart Mr. C. R. Pierce Ms. A. G. Aughtman Mr. D. L. Fulton Mr. M. J. Yox Mr. J. Tupik Mr. W. A. Sparkman Ms. A. C. Chamberlain Ms. A. L. Pugh Mr. F. J. Redwanz Document Services RTYPE: VND.LI.L00 File AR.01.02.06 Nuclear Regulatory Commission Mr. W. Jones (w/o enclosure)
Ms. J. Dixon-Herrity Mr. C. Patel Ms. J. M. Heisserer Mr. B. Kemker Mr. G. Khouri Ms. S. Temple Mr. F. Brown Mr. T.E. Chandler Ms. P. Braxton Mr. T. Brimfield Mr. C. J. Even Mr. A. Lerch State of Georgia Mr. R. Dunn
U.S. Nuclear Regulatory Commission ND-18-0417 Page 4 of 4 Oglethorpe Power Corporation Mr. M. W. Price Mr. K. T. Haynes Ms. A. Whaley Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinghouse Electric Company, LLC Mr. L. Oriani (w/o enclosure)
Mr. G. Koucheravy (w/o enclosure)
Mr. M. Corletti Mr. M. L. Clyde Ms. L. Iller Mr. D. Hawkins Mr. J. Coward Other Mr. S. W. Kline, Bechtel Power Corporation Ms. L. A. Matis, Tetra Tech NUS, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.
Mr. S. Roetger, Georgia Public Service Commission Ms. S. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Balch Bingham Mr. R. Grumbir, APOG NDDocumentinBox@duke-energy.com, Duke Energy Mr. S. Franzone, Florida Power & Light
Southern Nuclear Operating Company ND-18-0417 Enclosure 9 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Response to NRC Request for Additional Information (RAI)
Regarding the LAR-17-037 Review (LAR-17-037S1)
(This Enclosure consists of six pages, including this cover page.)
ND-18-0417 Response to NRC Request for Additional Information (RAI) Regarding the LAR-17-037 Review (LAR-17-037S1)
The following are questions provided by the NRC Staff [Request for Additional Information (RAI)
LAR 17-037-1] regarding the review of Southern Nuclear Operating Company (SNC) License Amendment Request (LAR)17-037, which was submitted by SNC letter ND-17-1726 on December 21, 2017.
Question 1 Section VIII.B.6.a of 10 CFR Part 52, Appendix D, states that an applicant who references this appendix may not depart from Tier 2* information, which is designated with italicized text or brackets and an asterisk in the generic DCD, without NRC approval. Additionally, General Design Criterion 1 of 10 CFR Part 50, Appendix A, Quality standards and records requires, in part, that structures, systems, and components important to safety be designed, fabricated, erected, and tested to quality standards commensurate with the importance of the safety functions to be performed.
In the technical evaluation, the licensee states that SNC performed an analysis of the Tier 2*
matters listed in 10 CFR Part 52, Appendix D, Section VIII paragraphs B.6.b and B.6.c. The Reviewers Aid included as Enclosure 5 also addresses matters based on Section VIII.B.6.b and VIII.B.6.c. The DCD contains additional text designated as Tier 2* that may not clearly fall under the matters listed in Section VIII.B.6.b and VIII.B.6.c, but is still subject to the requirements of Section VIII.B.6.a. Specifically, the CVS piping inside containment is non-ASME Code piping subject to additional requirements for design, fabrication, examination, inspection, and testing. These additional requirements are designated Tier 2* and support the basis for satisfying GDC 1. The licensee should describe how a potential change to the treatment of this non-ASME Code piping would be handled by the proposed process.
Additionally, the licensee should consider if there are any other topics designated as Tier 2*
information in the DCD that may not be adequately covered by the specified criteria.
SNC Response to RAI Question 1 As a point of clarification,Section VIII.B.6.a of 10 CFR Part 52, Appendix D, referenced in Question 1 is only applicable to applicants who reference Appendix D, not COL holders that reference Appendix D. Instead, Paragraph VIII.B.6.b, which contains similar requirements, is applicable to licensees.
The UFSAR text regarding the CVS piping in the UFSAR referred to in the question (Subsection 5.2.1.1) is designated in the AP1000 DCD Introduction [ADAMS Accession Number ML11171A303], Table 1-1, Index of AP1000 Tier 2 Information Requiring NRC Approval for Change, as ASME Code Piping Design Restrictions. SNC utilized this DCD Introduction table to ensure that all Tier 2* text was properly identified and evaluated. This Tier 2* category is listed in the 10 CFR Part 52, Appendix D, paragraph VIII.B.6.c.(2) as American Society of Mechanical Engineers Boiler & Pressure Vessel Code (ASME Code) piping design and welding restrictions, and ASME Code Cases. (Note that although the UFSAR Tier 2* text refers to ASME B31.1 Code and the 10 CFR Part 52, Appendix D, paragraph VIII.B.c.(2) refers to ASME Boiler and Pressure Vessel Code, SNC considers paragraph VIII.B.c.(2) as the applicable reference.) Furthermore, SNC interprets the term code in the new evaluation Criteria to include ASME B31.1.
Page 2 of 6
ND-18-0417 Response to NRC Request for Additional Information (RAI) Regarding the LAR-17-037 Review (LAR-17-037S1)
SNC evaluated the Tier 2* text regarding the CVS piping in UFSAR Subsection 5.2.1.1. This Tier 2* text involves two types of information. One set of text involves Tier 1 information. SNCs evaluation of this text concluded that the Design Commitments in Tier 1 (specifically for CVS Section 2.3.2, item 14) adequately capture the necessary safety significant requirements. This item requires that the nonsafety-related piping located inside containment and designated as reactor coolant pressure boundary, as identified in Tier 1, Table 2.3.2-2 (pipe lines with "No" in the ASME Code column), is designed to withstand a seismic design basis event and maintain structural integrity. Hence, any departures from these Tier 1 Design Commitments would require prior NRC approval. Furthermore, changes that would relax the manner in which Code requirements are met, such as non-conservative changes to the loading combinations and stress limits described in UFSAR Subsection 5.2.1.1 Tier 2* text would require prior NRC review and approval per the requirements of 10 CFR Part 52, Appendix D, paragraph VIII.B.5.b.(2) because adverse changes in design requirements tied to code requirements are treated as adverse effects on design function potentially affecting the frequency of occurrence of an accident. As described in NEI guidance 96-07, Guidelines for 10 CFR 50.59 Implementation, Revision 1, while a minimal increase in the likelihood of occurrence of a malfunction of an SSC important to safety is permitted, licensees must still meet applicable regulatory requirements and other acceptance criteria to which they are committed (such as contained in regulatory guides and nationally recognized industry consensus standards, e.g., the ASME B&PV Code).
Thus, a non-conservative change to loading combinations and stress limits would be incompatible with the more than minimal standard. This same requirement would apply to departures from other UFSAR Tier 2* text that similarly involve regulatory requirements and other acceptance criteria to which SNC is committed.
The second set of Tier 2* text in UFSAR Subsection 5.2.1.1 related to CVS piping inside containment involves requirements that were not included in Tier 1. This text requires that dimensional fabrication, assembly, erection, inspection, examination, and testing requirements as defined in Chapters IV, V, and VI of the ASME B31.1 Code are applicable and used for the B31.1 (Piping Class D) CVS piping systems, valves, and equipment inside containment. SNCs evaluation of this text determined that it did not require any new evaluation Criterion. The basis for this conclusion is that any departure that reduces commitments to B31.1 Code in this text would require prior NRC review and approval based on the departure evaluation criteria in 10 CFR Part 52, Appendix D, paragraph VIII.B.5.b.(2), because non-conservative changes in fabrication, assembly, erection, inspection, examination, and testing requirements tied to code requirements are treated as potentially affecting the likelihood of malfunction (see similar basis discussion in above paragraph).
After initial full power operation, this Tier 2* text reverts to Tier 2 text in accordance with 10 CFR Part 52, Appendix D, paragraph VIII.B.6.c.
Question 2 Section VIII.B.6.b of 10 CFR Part 52, Appendix D, states that an applicant who references this appendix may not depart from the following Tier 2* matters without prior NRC approval, of which one of these matters is titled piping design acceptance criteria. The licensee states that SNC performed an analysis of the Tier 2* matters listed in 10 CFR Part 52, Appendix D, Section VIII paragraphs B.6.b and B.6.c.
Page 3 of 6
ND-18-0417 Response to NRC Request for Additional Information (RAI) Regarding the LAR-17-037 Review (LAR-17-037S1)
In the LAR 17-037 submittal, Page 9 of Enclosure 1 indicates that Criterion 2 was developed as a screening criterion as a result of the analysis performed of these Tier 2* matters, which included, among other things, piping design acceptance criteria. The bases for Criterion 2 provides a list of three design processes:
- a. Diverse Actuation System
- b. Protection and Safety Monitoring System
- c. Human Factors Engineering Notably missing from this list is piping design acceptance criteria, one of the topics identified on Page 9 of Enclosure 1. Please elaborate on how piping design acceptance criteria will be treated by the proposed process.
SNC Response to RAI Question 2 Piping design acceptance criteria (DAC) are called out in various locations within the UFSAR (e.g., Subsections 3.6.2 and 3.9.3) as Tier 2* text. This Tier 2* text describes a design process that is used to implement an industry standard (e.g., ASME Code). Hence, any departures that result in a material change to this piping DAC would meet Criterion 2 and require prior NRC approval. LAR-17-037 submittal, Page 9 of Enclosure 1 properly includes piping design acceptance criteria under Criterion 2. However, as noted in the question, the bases discussion regarding Criterion 2 does not list piping design acceptance criteria. Enclosure 1 of the original LAR-17-037 is revised as follows to correct this inconsistency (revised text is shown in blue underlined font):
- 1. Under Section 3, Technical Evaluation, on Pages 10 and 11 of 19, under Criterion 2 (Design Processes) Bases add the following new bullet as the second bullet:
- Piping design acceptance criteria (multiple system sections in the plant-specific Tier 1; plant-specific Tier 2 DCD, Subsections 3.6.2 and 3.9.3);
- 2. Under Section 3, Technical Evaluation, on Pages 10 and 11 of 19, under Criterion 2 (Design Processes) Bases after the paragraph entitled Protection and Safety Monitoring System (PMS) add the following:
Piping Design Acceptance Criteria (DAC)
This UFSAR Tier 2* text describes a design process for piping design that is used to implement an industry standard (ASME Code). For example, as explained in UFSAR Section 3.6.2.1.1, this text defines the process for determining pipe break locations in piping designed and constructed to the requirements for Class 1 piping in the ASME Code,Section III, Division 1.
Departures related to this design process may not be easily evaluated against the eight criteria of paragraph B.5.b; therefore, some departures may not receive prior NRC approval as required. The application of proposed Criterion 2 assures that any material departure related to piping DAC receives prior NRC approval.
- 3. Under Section 3, Technical Evaluation, on Page 13 of 19, in the second full paragraph, revise the last sentence to read as follows:
Page 4 of 6
ND-18-0417 Response to NRC Request for Additional Information (RAI) Regarding the LAR-17-037 Review (LAR-17-037S1) are related to the Diverse Actuation System (DAS), Protection and Safety Monitoring System (PMS), piping design acceptance criteria, and Human Factors Engineering (HFE).
- 4. Under Section 3, Technical Evaluation, on Page 14 of 19, after the second full paragraph (i.e., before the paragraph starting Tier 1 DCD, Section 3.2.) add the following text:
Various system ITAAC in the plant-specific Tier 1 DCD address piping design in accordance with ASME Code. For example, plant-specific Tier 1 Section 2.1.2, Reactor Coolant System, item 2.b reads as follows:
The piping identified in Table 2.1.2-2 as ASME Code Section III is designed and constructed in accordance with ASME Code Section III requirements.
The Tier 2* text in plant-specific Tier 2 DCD Subsections 3.6.2 and 3.9.3 define the processes (i.e., piping design acceptance criteria) necessary to implement the Tier 1 requirement. These processes define, for example, how to determine pipe break locations for ASME Code Class 1, 2 and 3 piping systems.
The design reports used to close out the ITAAC are referenced in ITAAC close-out documentation and available for NRC review. After initial full-power operation, the piping design acceptance criteria reverts to Tier 2 text in accordance with 10 CFR Part 52, Appendix D, paragraph VIII.B.6.c.
Question 3 Section VIII.B.6.b of 10 CFR Part 52, Appendix D, states that an applicant who references this appendix may not depart from the following Tier 2* matters without prior NRC approval, of which one of these matters is titled Motor-operated and power operated valves. 10 CFR Part 50 Appendix A, General Design Criteria 1, 2, 4, 14, and 15 provide requirements related to the design of these valves. 10 CFR Part 50 Appendix B additionally provides requirements related to quality assurance in the design, fabrication, construction, and testing of safety-related valves.
The screening criteria provided in LAR 17-037 use the phrase used to implement an industry standard or endorsed regulatory guidance or construction materials that deviate from a code or standard credited to determine whether the Tier 2* change process may be departed from.
In the case of the design and qualification provisions for motor-operated valves (MOVs) and power-operated valves (POVs), the Tier 2* information contained in the AP1000 DCD was not considered part of a code, standard, or endorsed regulatory guidance at the time, but subsequent to the certification of the AP1000 design, became classified as such. Furthermore, the applicant states in Enclosure 5 of LAR 17 037 that the topic of MOVs and POVs is adequately addressed in Tier 1 and by paragraph VIII.B.5. Please provide additional basis for supporting this conclusion, including the means by which the qualification of MOVs and POVs will be accomplished. The licensee should elaborate on how they would evaluate changes to the provisions for MOVs and POVs- specifically if changes would be made pursuant to 10 CFR Part 52, Appendix D, Section VIII paragraph B.5.
Page 5 of 6
ND-18-0417 Response to NRC Request for Additional Information (RAI) Regarding the LAR-17-037 Review (LAR-17-037S1)
SNC Response to RAI Question 3 The basis for excluding MOV/POV design and qualification provisions from the new evaluation criteria is based on the following. Plant-specific Tier 1 DCD requires that safety-related MOVs/POVs (identified in Tier 1 tables) must be able to perform their active safety-related function to change position as indicated in the Tier 1 table. These Tier 1 requirements specify that tests or type tests of motor-operated valves will be performed that demonstrate the capability of the valve to operate under its design conditions. The design and qualification conditions that need to be tested are described in Tier 2* text in UFSAR Subsection 5.4.8.
These design and qualification requirements are tied to the ASME QME-1-2007 Edition, Qualification of Active Mechanical Equipment Used in Nuclear Power Plants (Reference 8 in UFSAR Subsection 5.4.16) by text in UFSAR Subsection 5.4.8.3 that states Requirements for qualification testing of power-operated active valves are based on QME-1 (Reference 8).
If a change were proposed to reduce or adversely alter the design and qualification provisions outlined in UFSAR Subsection 5.4.8 that are based on QME-1, such as removing the requirement for the design conditions applicable to MOVs to include differential pressure, the change would require prior NRC review and approval under 10 CFR Part 52, Appendix D, paragraph VIII.B.5.b.(2) because non-conservative changes in design requirements tied to code requirements are treated as potentially affecting the likelihood of malfunction. As described in NEI guidance 96-07, Guidelines for 10 CFR 50.59 Implementation, Revision 1, while a minimal increase in the likelihood of occurrence of a malfunction of an SSC important to safety is permitted, licensees must still meet applicable regulatory requirements and other acceptance criteria to which they are committed (such as contained in regulatory guides and nationally recognized industry consensus standards). Because the Tier 2* text in UFSAR Subsection 5.4.8 contains design and qualification acceptance criteria tied to code requirements, any non-conservative change to the Tier 2* text would trigger the paragraph VIII.B.5.b.(2) criterion.
Hence, SNC concluded that no new evaluation Criterion was necessary to address changes to this text.
After initial full-power operation, this Tier 2* text reverts to Tier 2 text in accordance with 10 CFR Part 52, Appendix D, paragraph VIII.B.6.c.
Page 6 of 6