Amendment 142 - Vogtle Electric Generating Plant, Unit 3 LAR 17-037
ML18235A033
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 09/20/2018
From: Jennifer Dixon-Herrity
NRC/NRO/DLSE/LB4
To:
City of Dalton, GA, Georgia Power Co, MEAG Power, Oglethorpe Power Corp, Southern Nuclear Operating Co
HABIB D/415-1035
Shared Package
ML18235A029, ML18256A400 List:
References
EPID: L-2017-LLA-0421, LAR 17-037
Download: ML18235A033 (2)


Text

SOUTHERN NUCLEAR OPERATING COMPANY, INC.

GEORGIA POWER COMPANY OGLETHORPE POWER CORPORATION MEAG POWER SPVM, LLC MEAG POWER SPVJ, LLC MEAG POWER SPVP, LLC CITY OF DALTON, GEORGIA VOGTLE ELECTRIC GENERATING PLANT, UNIT 3 DOCKET NO.52-025 AMENDMENT TO FACILITY COMBINED LICENSE Amendment No. 142 License No. NPF-91

1. The Nuclear Regulatory Commission (the Commission) has found that:

A. The application for amendment by Southern Nuclear Operating Company (SNC),

dated December 21, 2017, as supplemented by letters dated April 6, May 11, June 18, August 3, August 10, and September 13, 2018, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Commission's regulations set forth in 10 CFR Chapter I; B. The facility will be constructed and will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations, and all applicable requirements have been satisfied.

2. Accordingly, the license is amended to authorize changes to the Updated Final Safety Analysis Report (UFSAR) as described in the licensees application dated December 21, 2017, as supplemented by letters dated April 6, May 11, June 18, August 3, August 10, and September 13, 2018. The license is amended by adding License Condition 2.D.(13), as indicated in the attachment to this license amendment. Paragraph 2.D(8) of Facility Combined License No. NPF-91 is hereby amended to read as follows:

(8) Incorporation The Technical Specifications, Environmental Protection Plan, and ITAAC in Appendices A, B, and C, respectively of this license, as revised through Amendment No. 142, are hereby incorporated into this license.

3. This license amendment is effective as of the date of its issuance and shall be implemented within 45 days of the date of issuance. As part of implementation, SNC shall fully implement the procedural guidance described in Enclosures 1U and 8U to the license application dated December 21, 2017, as supplemented by letters dated April 6, May 11, June 18, August 3, August 10, and September 13, 2018, and the NRC Staff Safety Evaluation, Section 3.1, page 14, before completing implementation of this license amendment. The licensee shall submit the changes authorized by this amendment with the next update of the UFSAR in accordance with 10 CFR 50.71(e).

FOR THE NUCLEAR REGULATORY COMMISSION:

/RA/

Jennifer Dixon-Herrity, Chief Licensing Branch 4 Division of Licensing, Siting, and Environmental Analysis Office of New Reactors Date of Issuance: September 20, 2018

Attachment:

Affected pages of the Facility Combined License