Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
I
(1 point)
Given the following:
The plant is at 100% RTP
At TIME0, an inadvertent turbine trip occurs
At TIME=2 minutes, Intermediate Range N-35 indicates 5.0 E-7 AMPS
Which ONE of the following is the MINIMUM additional time expected for the POWER
ABOVE PERMISSIVE P6 status light to EXTINGUISH on the lR N-35 Drawer?
A.
8lOminutes
B.
11l3minutes
C.
14l6minutes
D.
17l9minutes
Page 1 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
2
(1 point)
Given the following:
RCS Temperature: 170°F and stable
RCS Pressure: 350 psig and stable
Subsequently PT-501, PZR PRESSURE, fails, due to a loss of electrical power.
Which ONE of the following correctly completes the statement below?
lAW AOP-020, LOSS OF RESIDUAL HEAT REMOVAL (SHUTDOWN COOLING) the
OATC is FIRST required to
A.
close PCV-455C, PZR PORV
B.
close RC-536, PORV BLOCK VALVE
C.
place the associated LTOPP Arming Switch to the NORMAL position
D.
take Manual Control of PC-444J, PZR PRESS and restore RCS pressure to
350 psig
Page 2 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
3
(1 point)
Given the following:
The crew is performing EQP-ES-i .2, POST LOCA COOLDOWN AND
DEPRESS U R IZATI ON
All reactor coolant pumps have been stopped
SIG narrow range levels are 30% and stable
Which ONE of the following correctly completes the statements below?
While Natural Circulation is occurring
(1)
will be at or trending to saturation
temperature for the associated steam generator pressure.
If the RCS level lowers to the point that steam voiding has begun to occur in the RCS
hot legs, the steam generators will
f2)
A.
(l)Thot
(2) stop removing heat due to the interruption of natural circulation flow
B.
(i)Tc01d
(2) stop removing heat due to the interruption of natural circulation flow
C.
(I) hot
(2) continue removing heat by reflux boiling
D.
(i)T0iu
(2) continue removing heat by reflux boiling
Page 3 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Exctmination
Question:
4
(1 point)
Given the following:
EOP-E-1, LOSS OF REACTOR OR SECONDARY COOLANT is being performed
CV Pressure is 12 psig, slowly rising
RTGB Annunciator APP-002-E1, CV SRY PMP COOL WTR LO FLOW, alarms
Which ONE of the following correctly completes the statements below?
lAW APP-002-E1, the control room
(II
required dispatch an operator to
locally check flow on FIC-657,CCW SPRAY PMP FLOW IND & LO ALARM.
The CV spray pumps
(2)
required to be stopped immediately.
A.
(1) is
(2) are
B.
(1) is
(2) are NOT
C.
(1)isNOT
(2) are
D.
(1)isNOT
(2) are NOT
Page 4 of 75
Question:
5
(1 point)
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Given the following:
The plant is at 25% RTP, returning to power following a trip
APP-036-D8, PROCESS MONITOR HI RAD is received
The OATC observes the following:
The OATC is required to,
(2)
AOP-014, COMPONENT COOLING WATER SYSTEM MALFUNCTION
AOP-018, REACTOR COOLANT PUMP ABNORMAL CONDITIONS
A.
(1) #1 Seal failure has occurred
(2) lAW AOP-018, determine total affected RCP #1 Seal leakoff flow rate,
before taking further action
B.
(1) #1 Seal failure has occurred
(2) lAW AOP-O1 8, trip the reactor, then trip the affected RCP and go to EOP-E
0, REACTOR TRIP OR SAFETY INJECTION
C.
(1) Thermal barrier has a leak
(2) lAW AOP-014, check FCV-626, THERM BAR FLOW CONT valve closed.
If it is not closed, the OATC is required to close FCV-626
D.
(1) Thermal barrier has a leak
(2) lAW AOP-014, check FCV-626, THERM BAR FLOW CONT valve closed.
If it is not closed, the OATC is required to close CC-735, THERM BAR OUT
ISO valve immediately
Which ONE of the following correctly completes the statements below?
Li)
Page 5 of 75
Robinson Nuclear Plant
ILC-J7RNPRO NRC Examination
Question:
6
(1 point)
Given the following:
The crew is responding to a loss of charging lAW AOP-003-1
LOSS OF
CHARGING OR LETDOWN, due to NO charging pumps running.
Letdown has been isolated
APP-O01-D1, RCP THERM BAR COOL WTR LO FLOW, is EXTINGUISHED
CCW Heat Exchanger outlet temperature is 104°F
RCP #1 Seal Leakoff flows are approximately 2.5 GPM
Pressurizer level is 37% and slowly lowering
It has been 15 minutes since all Charging has been lost
lAW AOP-003-1 which ONE of the following identifies the NEXT required action, AND
the reason for this action?
A.
Attempt to restore at least one Charging Pump because RCP Thermal Barrier
cooling is sufficient.
B.
Isolate the RCP Seal Injection lines to the RCPs to avoid damage to the RCP
Seals when one Charging Pump is restored.
C.
Trip the Reactor and stop the RCPs because CCW Heat Exchanger outlet
temperature is too high to properly cool the Thermal Barrier.
D.
Trip the Reactor and stop the RCPs because the RCP #1 Seal Flows are
abnormal.
Page 6 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
7
(1 point)
Initial conditions:
RHR Train A is in service
Subsequently, the Instrument Air line to FCV-605, RHR HX BYPASS FLOW, ruptured
causing a total loss of operating air to the valve.
ASSUME NO OPERATOR ACTION
Which ONE of the following correctly completes the statements below?
FCV-605 will fail to the
(II
position.
RHR flow through the RHR Heat Exchangers will
(2)
from steady state to
steady state.
A.
(1) open
(2) remain the same
B.
(1) open
(2) lower
C.
(1) close
(2) rise
D.
(1) close
(2) remain the same
Page 7 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
8
(1 point)
Given the following
The plant is at 100% RTP
RCS pressure is currently 2220 PSIG and RISING
The LOWEST RCS pressure observed by the OATC was 2207 PSIG
The OATC is verifying that PC-444J, MASTER PRESSURE CONTROLLER is
operating properly in AUTO
Which ONE of the following correctly completes the statement below?
Proper operation of PC-444J in AUTO would be represented by the Spray Valves
PCV-455A & PCV-455B
(1)
and Control Group Heaters are
(2)
A.
(1) throttled
(2) at 50% fire
B.
(1) throttled
(2) at 25% fire
C.
(1) CLOSED
(2) at 50% fire
D.
(1) CLOSED
(2) full ON
Page $ of 75
Question:
(1 point)
9
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Given the following:
An ATWS has occurred
The BOP manually tripped the turbine
Operators have been dispatched to locally trip the reactor
The OATC is taking immediate action lAW FRP-S.1, RESPONSE TO NUCLEAR POWER
GENERATION
- ATWS and observes:
ROD SPEEcj
I
Which ONE of the following correctly completes the statements below?
The OATC
(1)
required to take further action IMMEDIATELY to insert rods into the
core.
Control rods will insert at the current indicated speed until Tave reaches AT LEAST
(2)
A.
(1) is
(2) 548.6°F
B.
(1) is
(2) 552.6°F
C.
(1)isNOT
(2) 548.6°F
D.
(1)isNOT
(2) 552.6°F
Page 9 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
10
(1 point)
Given the following:
The crew is operating in EOP-E-3, STEAM GENERATOR TUBE RUPTURE
The RCS has been cooled to target temperature
The crew is preparing to initiate an RCS depressurization
Which ONE of the following correctly completes the statements below?
lAW EOP-E-3, the RCS depressurization is initiated in order to
(1)
lAW EOP-E-3, if normal PZR spray is not available, the NEXT RCS depressurization
method to be used is
(2)
A.
(1) refill the Pressurizer, ONLY
(2) Aux Spray
B.
(1) refill the Pressurizer, ONLY
(2) one PZR PORV
C.
(1) refill the Pressurizer AND minimize break flow
(2) one PZR PORV
D.
(1) refill the Pressurizer AND minimize break flow
(2) Aux Spray
Page 10 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
11
(1 point)
Given the following:
The plant is at 100% RTP
A major piping rupture occurs on the 72 steam header
Which ONE of the following correctly completes the statements below?
S/G levels will INITIALLY
(1)
A
Safety Injection will automatically occur.
A.
(1) RISE
(2) High Steam Flow
B.
(1) RISE
(2) High Steam Line Differential Pressure
C.
(1) LOWER
(2) High Steam Flow
D.
(1) LOWER
(2) High Steam Line Differential Pressure
Page 11 of75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Excimination
Question:
12
(1 point)
Given the following:
The crew was operating in EOP-ECA-O.2, LOSS OF ALL AC POWER RECOVERY
WITH SI REQUIRED, following an Extended Loss of AC Power (ELAP)
The PEAK CV pressure during the ELAP was 4.5 psig
Current conditions:
The crew has just been directed to reset the Safety Parameter Display System
(SPDS) and initiate monitoring of the Critical Safety Function Status Trees
(CSFSTs)
CURRENT CV pressure is 3.5 psig and slowly lowering
Which ONE of the following correctly completes the statements below based on the
current plant conditions?
ERFIS
(11
use adverse containment setpoints when evaluating the CSFSTs
via SPDS.
lAW OMM-022, EMERGENCY OPERATING PROCEDURES USERS GUIDE,
adverse containment setpoints are
(21
to be used.
A.
(1)does
(2) required
B.
(1)does
(2) NOT required
C.
(1)does NOT
(2) required
D.
(1)does NOT
(2) NOT required
Page 12 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
13
(1 point)
Given the following:
The plant was at 100% RTP
An electrical fault in the 115 KV switchyard causes both East and West 115 KV
Busses to deenergize
Assume NO OPERATOR ACTIONS for the first two minutes of this event.
Which ONE of the following correctly completes the statements below?
A Blackout signal will be sensed on 480V Bus E-2
(1)
The B MDAFW pump will receive an automatic start signal
(2)
seconds
after the loss of 480V Bus E-2.
A.
(1) ONLY
(2) 39.5
B.
(1)ONLY
(2) 49.5
C.
(1) AND 480V Bus E-1
(2) 39.5
D.
(1) AND 480V Bus E-1
(2) 49.5
Page 13 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
14
(1 point)
Given the following:
Battery chargers A and B are in service
Battery chargers A-i and B-i are in standby
12:00 MCC-5 is de-energized
13:01 APP-036-D3, BATT A/B LO VOLT, alarm is illuminated
There are multiple indications of loss of control power to components
At 13:05, MCC-5 is re-energized.
Which ONE of the following correctly completes the statements below?
Battery charger(s)
(1)
will need to be manually restarted.
The Design Basis of the A and B battery chargers is to be able to fully recharge its
associated battery in
hours.
A.
(i)A-i ONLY
(2) 10
B.
(i)A&A-i
(2) 10
C.
(1) A & AI
(2) 24
D.
(i)A-I ONLY
(2) 24
Page 14 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
15
(1 point)
Given the following:
Following a plant trip from 4% power at 1200, the crew has just transitioned out of
EOP-E-0, REACTOR TRIP OR SAFETY INJECTION, into an optimal recovery
procedure.
The following parameters are observed at 1300:
Loop ATcold
445°F
Loop B Tcold
330°F
Loop C Tcold
445°F
RCS pressure
1800 psig
CV pressure
I psig
CV sump level
380 inches
CVrad level
1OR/hr
NRIevel
10%
8%
6%
pressure
1055 psig
1075 psig
1095 psig
Which ONE of the following identifies the HIGHEST priority Functional Response
Procedure whose entry condition has been met?
A.
FRP-J.2, RESPONSE TO CONTAINMENT FLOODING
B.
FRP-J.3, RESPONSE TO HIGH CONTAINMENT RADIATION LEVEL
C.
FRP-P.1, RESPONSE TO IMMINENT PRESSURIZED THERMAL SHOCK
D.
FRP-H.4, RESPONSE TO LOSS OF NORMAL STEAM RELEASE
CAPABILITY
Page 15 of75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
16
(1 point)
Given the following:
The plant is at 25% RTP
APP-009-F8, 4KV BUSES LO FREQ, is in alarm
The crew enters AOP-026, GRID INSTABILITY
Frequency is now at 58.3Hz
Which ONE of the following correctly completes the statements below?
lAW AOP-026, The crew is required to
(1)
trip the reactor.
For the given conditions, the reason for the AOP steps to trip the RCPs is to
(2)
A.
(1) immediately
(2) prevent damage to RCP motor wind ings
B.
(1) direct the load dispatcher to raise frequency, but if not corrected within 5
minutes, then
(2) prevent damage to RCP motor wind ings
C.
(1) immediately
(2) preempt the low frequency automatic RCP trip
D.
(1) direct the load dispatcher to raise frequency, but if not corrected within 5
minutes, then
(2) preempt the low frequency automatic RCP trip
Page 16 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
17
(1 point)
lAW EOP-ECA-1 .2, LOCA OUTSIDE CONTAINMENT, which ONE of the following
correctly completes the statements below?
The crew is required to FIRST close
valves.
The crew is required to monitor for
to determine if the break has been
isolated.
A.
(1) Sl-870 A & B, BIT OUTLET
(2) RVLIS level rising
B.
(1) RHR-744 A & B, RHR RETURN TO COLD LEGS
(2) RVLIS level rising
C.
(1) Sl-870 A & B, BIT OUTLET
(2) RCS pressure rising
D.
(1) RHR-744 A & B, RHR RETURN TO COLD LEGS
(2) RCS pressure rising
Page 17 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
18
(1 point)
Given the following:
The crew is operating in EOP-ECA-1.1, LOSS OF EMERGENCY COOLANT
RECIRCULATION
It has been 15 hours1.736111e-4 days <br />0.00417 hours <br />2.480159e-5 weeks <br />5.7075e-6 months <br /> since the reactor trip
RVLIS Full Range is 80%
RCS subcooling is 600 F
Total SI flow is 650 GPM
The crew is at a step to determine if SI can be terminated
Which ONE of the following correctly completes the statement below?
lAW EOP-ECA-1 .1, the crew is required to...
REFERENCE PROVIDED
A.
maintain 650 GPM SI flow.
B.
reduce SI flow to 115 GPM.
C.
reduce SI flow to 140 GPM.
D.
stop ECCS pumps and establish normal charging flow.
Page 18 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
19
(1 point)
Given the following:
The plant is at 75% RTP
The crew is performing GP-005, POWER OPERATION, raising power to 100%
The OATC withdraws control rods 5 steps for temperature control
When the IN-HOLD-OUT lever is released, it returns to the HOLD position
Outward rod motion CONTINUES
Which ONE of the following correctly completes the statements below?
The Rods Out Motion LightII status (illuminated or extinguished) will be
determined by the
Li)
lAW AOP-001, MALFUNCTION OF REACTOR CONTROL SYSTEM, the NEXT
required action for the OATC is to
(2)
A.
(1) Power Cabinet
(2) trip the reactor and GOTO EOP-E-0, REACTOR TRIP OR SAFETY
INJECTION
B.
(1) Logic Cabinet
(2) place the rod bank selector switch in AUTO to attempt to stop the
continuous rod withdrawal
C.
(1) Power Cabinet
(2) place the rod bank selector switch in AUTO to attempt to stop the
continuous rod withdrawal
D.
(1) Logic Cabinet
(2) trip the reactor and GOTO EOP-E-0, REACTOR TRIP OR SAFETY
INJECTION
Page 19 of75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
20
(1 point)
Given the following:
LT-459, CH
I PRZR LEVEL is selected for control
The REFERENCE LEG for LT-459 develops a slow and small leak
Which ONE of the following correctly identifies the indications the OATC observes at
the RTGB over the first minute of this event?
(ASSUME NO OPERATOR ACTION)
LI-459
LI-460
PZRLVL
PZRLVL
Indication
Indication
Level
A.
Rises
Lowers
Rises
B.
Lowers
Rises
Rises
C.
Rises
Lowers
Lowers
D.
Lowers
Rises
Lowers
Page 20 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
21
(1 point)
Given the following:
A tube leak developed in the C S/G
The plant has been taken offline lAW AOP-035, SIG TUBE LEAK
Plant cooldown lAW AOP-035 is in progress and the crew is at the step to refill the
affected SIG
Which ONE of the following correctly completes the statements below?
AOP-035 directs the operators to feed the C SIG to
(1)
lAW AOP-035-BD, feed flow rate is initiated slowly to the affected SIG
(2)
A.
(1)70%
(2) to minimize the rate of dilution effects during SIG backfill
B.
(1)78%
(2) to minimize the rate of dilution effects during SIG backfill
C.
(1)70%
(2) to minimize the possibility of a rapid depressurization and reinitiation of
break flow
D.
(1)78%
(2) to minimize the possibility of a rapid depressurization and rein itiation of
break flow
Page 21 of75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
22
(1 point)
Given the following:
The plant is operating at 39% RIP
Condenser Vacuum is degrading
APP-008-A5, CONDENSER LO VACUUM has just illuminated
The crew has entered AOP-012, PARTIAL LOSS OF CONDENSER VACUUM OR
The BOP subsequently reports:
Turbine is at 280 MWe gross
Condenser Backpressure is 4.0 INHG
Which ONE of the following correctly complete the statements below?
lAW AOP-012, the crew is required to...
AOP-007, TURBINE TRIP BELOW P-8
EOP-E-0, REACTOR TRIP OR SAFETY INJECTION
REFERENCE PROVIDED
A.
trip the Reactor and go to EOP-E-0.
B.
restore compliance with the Condenser Backpressure Limit by reducing
backpressure.
C.
trip the Turbine and go to AOP-007.
D.
restore compliance with the Condenser Backpressure Limit by raising turbine
load.
Page 22 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
23
(1 point)
Given the following:
R-14C, PLANT VENT LOW RANGE GAS MONITOR is in alarm
The crew is in AOP-005, RADIATION MONiTORING SYSTEM
The on-shift RC Tech reports that gas samples indicate A Waste Gas Compressor
is the source of the activity
A clearance is prepared containing the following Waste Disposal (WD) system valves,
all of which are proposed to be closed:
WD-1611, WASTE GAS COMPRESSOR A SUCTION
WD-1 670, WASTE GAS COMPRESSOR A DISCHARGE
WD-1 665, WASTE GAS COMPRESSOR A RECIRC
WD-1669, WASTE GAS COMPRESSOR A NITROGEN SUPPLY
WD-3335, WD-2063A ISOLATION
Which ONE of the following correctly completes the statements below?
The proposed clearance
(jJ
completely isolate the A Waste Gas
Compressor from the Gaseous Waste Disposal System.
lAW AD-OP-ALL-0200, CLEARANCE AND TAGGING, electrical power sources to the
A Waste Gas Compressor are tagged
the mechanical isolation points.
REFERENCE PROVIDED
A.
(1) does
(2) after
B.
(1) does
(2) prior to
C.
(1) does NOT
(2) prior to
D.
(1)doesNOT
(2) after
Page 23 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Exctmination
Question:
24
(1 point)
Given the following:
The plant is in mode 1 at 100% power
A confirmed bomb threat is received at 2105
The caller specified that the bomb is located in the control room
The control room is evacuated at 2110
lAW AOP-004, CONTROL ROOM INACCESSIBILITY, the reactor is required to be
tripped from
Li)
Subsequently,
The time is now 2145
The operator in the Charing Pump Room informs the SM that:
1) N-51 indicates 3 x 10 cps and slowly lowering
2) PZR pressure is 2225 psig
3) PZR level is 45%
lAW AOP-004, ATTACHMENT 1, AUXILIARY BUILDING OPERATOR, the operator in
the charging pump room is required to
Which ONE of the following correctly completes the statements above?
A.
(1) the 4KV room or South Cable Vault
(2) start an additional charging pump from the Charging Pump Room
B.
(1) the 4KV room or South Cable Vault
(2) raise the running charging pump speed to maximum using local controls
C.
(1) the Control Room upon evacuation
(2) start an additional charging pump from the Charging Pump Room
D.
(1) the Control Room upon evacuation
(2) raise the running charging pump speed to maximum using local controls
Page 24 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
25
(1 point)
Given the following:
The plant is operating at 100% power
Letdown flow is 45 gpm
The A Charging Pump is operating in AUTO
The B Charging Pump is operating in MANUAL
Subsequently:
R-9, Letdown Line Area Monitor, alarms
The alarm is determined to be valid
The crew enters AOP-005, RADIATION MONITORING SYSTEM
Attachment 9, AREA MONITOR R-9
- LETDOWN LINE AREA
Which ONE of the following correctly completes the statements below?
lAW with Attachment 9 of AOP-005, the operator
Li)
required to isolate
letdown flow.
AOP-005, Attachment 9 actions are taken to
(21
A.
(i)is
(2) filter airborne radioactive material prior to release from the Auxiliary
Building
B.
(1)i5NOT
(2) filter airborne radioactive material prior to release from the Auxiliary
Building
C.
(1)is
(2) reduce the contribution to background radiation levels in the Auxiliary
Building
D.
(i)i5NOT
(2) reduce the contribution to background radiation levels in the Auxiliary
Building
Page 25 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
26
(1 point)
Given the following:
The plant was at 100% RTP
A reactor trip occurred
The turbine fails to trip in auto and manual and the BOP reports it will not runback
The MSIVs fail to close
The crew is responding in FRP-P.1, RESPONSE TO IMMINENT PRESSURIZED
THERMAL SHOCK
RCS temperatures continue to lower
ALL S/Gs indicate 0% Narrow Range
Which ONE of the following correctly completes the statements below?
lAW FRP-P.1, the crew is required to maintain
Once RCS temperature is stable, the crew is required to perform a soak for
C2)
A.
(1) total feed flow> 300 gpm
(2) 28 minutes
B.
(1) total feed flow> 300 gpm
(2) 60 minutes
C.
(1) approximately 60 gpm feed flow to each S/G
(2) 28 minutes
D.
(1) approximately 60 gpm feed flow to each S/G
(2) 60 minutes
Page 26 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
27
(1 point)
Given the following:
A reactor trip occurred due to a loss of off-site power
The crew is in EOP-ES-0.2, NATURAL CIRCULATION COOLDOWN
ONE CRDM fan is in operation
All RCS loops are determined to be ACTIVE
Natural Circulation conditions have been established
Which ONE of the following correctly completes the statements below?
lAW EOP-ES-0.2, the MAXIMUM cooldown rate is
(1)
/60 minutes.
RCS Core T is expected to
(2)
over the next hour.
A.
(1)70°F
(2) lower
B.
(1)70°F
(2) rise
C.
(1)100°F
(2) lower
D.
(1)100°F
(2) rise
Page 27 of 75
Question:
28
(1 point)
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Given the following:
The plant is at 100% RIP
Picture
above indicates a B RCP #2 seal leak.
lAW AOP-018, REACTOR COOLANT PUMP ABNORMAL CONDITIONS,
if TOTAL seal leakage exceeds a MINIMUM value of
(2)
a plant trip is
required.
A.
(1)1
(2) 5.7 gpm
B.
(1)1
(2) 8.0 gpm
C.
(1) II
(2) 5.7 gpm
D.
(1) II
(2) 8.0 gpm
II.
Which ONE of the following correctly completes the statements below?
Page 28 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
29
(1 point)
Given the following:
The plant is at 100% power
A loss of the startup transformer occurs
Which ONE of the following correctly completes the statement below?
At the INSTANT that the startup transformer loss occurs, Component Cooling Water
pump(s)
(1)
LOST power.
A.
A ONLY has
B.
B ONLY has
C.
A & C have
D.
A & B have
Page 29 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
30
(1 point)
Which ONE of the following correctly completes the statement below?
The MINIMUM instrumentation and VCT level SETPOINT to initiate automatic
swapover of the charging pump suction to the RWST is as follows:
LT-112
(1)
LT-115,
(2)
and lowering.
A.
(1)OR
(2) 12.4 inches
B.
(1)OR
(2) 14.4 inches
C.
(1)AND
(2) 12.4 inches
D.
(1)AND
(2)14.4 inches
Page 30 of 75
Robinson Nuclear Plant
ILC-i 7 RN? RO NRC Examination
Question:
31
(1 point)
Given the following:
The crew is performing GP-007, PLANT COOLDOWN FROM MODE 3 TO
MODE 5
RCS temperature is at 22OF
Which ONE of the following correctly completes the statements below?
lAW the TRM...,
(1)
of CVCS Heat Tracing is(are) required to be OPERABLE.
ONE of the purposes of the CVCS Heat Tracing is to maintain
(2)
during
large volume borations.
A.
(1) ONLY one channel
(2) VCT temperature
B.
(1) ONLY one channel
(2) solution solubility of Boric acid
C.
(1)two channels
(2) VCT temperature
D.
(1)two channels
(2) solution solubility of Boric acid
Page 31 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
32
(1 point)
Given the following:
The RCS is 205 °F.
GP-007, PLANT COOLDOWN FROM MODE 3 to MODE 5 is in progress.
RHR pump A is in service providing cooling
Subsequently;
The following alarm actuates, APP-001-F7, RHR PMP MOTOR OVLDITRIP
Which ONE of the following correctly completes the statements below?
An A RHR Pump overload condition would be indicated by breaker status lights being
Green light LIT and Red light
(1)
Prior to attempting to start the B RHR Pump lAW AOP-020, LOSS OF RESIDUAL
HEAT REMOVAL (SHUTDOWN COOLING), the COMPLETE set of valve controllers
required to be closed is
(2)
HIC-142, PURIFICATION FLOW
A.
(1)LIT
(2) FC-605 and HIC-758, ONLY
B.
(J)LIT
(2) FC-605, HIC-758 and HIC-142
C.
(1)OFF
(2) FC-605 and HIC-758, ONLY
D.
(1)OFF
(2) FC-605, HIC-758 and HIC-142
Page 32 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
33
(1 point)
Given the following:
RCS temperature is 150°F
The A Train of RHR is in operation
Which ONE of the following correctly completes the statement below?
lAW OP-201, RESIDUAL HEAT REMOVAL SYSTEM, whenever actions are taken to
introduce dilute boron sources RHR flow must be a MINIMUM of
to
ensure the assumptions of the boron dilution analysis are satisfied.
A.
2800 gpm
B.
3350 gpm
C.
3500 gpm
D.
3750 gpm
Page 33 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
34
(1 point)
Initial conditions:
The plant was at 100% RTP when a LOCA occurred
The crew is performing EOP-E-0, REACTOR TRIP OR SAFETY INJECTION and is
at the step to reset SPDS
MANUAL monitoring of the Critical Safety Function Status Trees (CSFST) is
required
Current conditions:
Containment pressure is 6 psig and slowly rising
RCS pressure is 885 psig and stable
CETs are 690°F and stable
RVLIS full range is 38% and slowly rising
Which ONE of the following correctly completes the statements below?
The terminus for Critical Safety Function 2, CORE COOLING, is
Li)
Assuming that the CORE COOLING CSFST is the HIGHEST terminus upon exiting
EOP-E-0, OMM-022 directs that the CSFSTs be monitored
(2)
OMM-022, EMERGENCY OPERATING PROCEDURES USERS GUIDE
A.
(1) YELLOW
(2) continuously
B.
(1) YELLOW
(2) once every 10-20 minutes
C.
(1) ORANGE
(2) continuously
D.
(1) ORANGE
(2) once every 10-20 minutes
Page 34 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
35
(1 point)
Given the following:
The plant was operating at 100% RTP
A Steam Line Break on B S/G occurred inside the CV
CV Pressure peaked at 18 psig and is currently lowering slowly
RCS Pressure lowered to 1550 PSIG and NOW is 1715 PSIG and stable
The OATC identifies APP-003-C3, PRT HI PRESS is in alarm and PRT level has
risen 2%
Which ONE of the following correctly completes the statements below?
The PRT High Pressure condition
(1)
due to CVC-382, RCP SEAL RETURN
LINE RELIEF lifting.
With NO operator action taken to mitigate the condition, P1-472, PRT PRESSURE, on
the RTGB will reach a MAXIMUM of
before the rupture disk fails.
A.
(1) is NOT
(2) 115 psig
B.
(1)is
(2) 115 psig
C.
(1)is
(2) 100 psig
D.
(1)isNOT
(2) 100 psig
Page 35 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
36
(1 point)
Given the following:
The plant is at 100% RTP
C COW Pump is running, A and B CCW pump are in standby
The OATC has been directed to start CCW Pump A and secure COW Pump C
lAW OP-306, COMPONENT COOLING WATER SYSTEM
When CCW Pump C was stopped, APP-0O1-F5, COW PMP LO PRESS, was
received and cleared
Which ONE of the following correctly completes the statements below?
The C CCW Pump is
(1)
low pressure auto start.
The B COW Pump is
(2)
low pressure auto start.
A.
(1) locked out from
(2) locked out from
B.
(1) available for
(2) locked out from
C.
(1) locked out from
(2) available for
D.
(1) available for
(2) available for
Page 36 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
37
(1 point)
Which ONE of the following correctly completes the statements below?
The PZR Safety Acoustic Monitors are powered from
(1)
The PZR Safety Acoustic Monitors have to be manually reset at
(2)
A.
(1) Distribution Panel A
(2) Instrument Cabinet A
B.
(1) Distribution Panel A
(2) Cabinet ARP-1
C.
(1) Instrument Bus 1
(2) Instrument Cabinet A
D.
(1) Instrument Bus I
(2) Cabinet ARP-1
Page 37 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
38
(1 point)
Given the following:
The plant is at 100% RTP
Rod control in manual
Which ONE of the following will cause the Channel 2 OTL\\T trip SETPOINT to lower?
A.
N-42 upper detector fails high.
B.
Output of T-ave Median Selector fails high.
C.
RCS wide range pressure channel fails low.
D.
Power reduction to 50% with normal pressure and temperature.
Page 38 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
39
(1 point)
Given the following:
The plant is at 100% RTP
PZR Pressure Channel PT-456 has failed HIGH
The appropriate OWP has NOT been implemented
Which ONE of the following correctly completes the statement below?
The remaining actuation logic for the LO PRESS SI is
(jj
and the
LO PRESS SI Block Permissive is
(2)
A.
(1)1/2
(2) 1/2
B.
(1)2/2
(2) 2/2
C.
(1)1/2
(2) 2/2
D.
(1)2/2
(2) 1/2
Page 39 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
40
(1 point)
Given the following:
The plant is recovering from a reactor trip and safety injection due to a SBLOCA in
containment
HVH-1, 2, 3 and 4 Normal Inlet dampers are to be opened lAW OP-921,
CONTAINMENT AIR HANDLING
Which ONE of the following correctly completes the statements below?
In order to re-open the HVH unit Normal Inlet dampers the
(1)
must be reset.
The dampers are repositioned from a keyswitch
A.
(1) Safety Injection signal ONLY
(2) on the RTGB
B.
(1) Safety Injection and Containment Isolation PHASE A signals
(2) on the RTGB
C.
(1) Safety Injection signal ONLY
(2) in the Unit 2 cable spread room
D.
(1) Safety Injection and Containment Isolation PHASE A signals
(2) in the Unit 2 cable spread room
Page 40 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
41
(1 point)
Which ONE of the following correctly completes the statements below?
lAW EOP-ES-1 .3, TRANSFER TO COLD LEG RECIRCULATION,
after stopping a CV Spray Pump, the CV Spray Pump discharge valves are CLOSED
to prevent possible
LIJ
Sl-863A and Sl-863B can be OPENED when
based on the valves
electrical interlock.
A.
(1) contamination of the RWST
(2) RHR pump discharge pressure is <210 PSIG
B.
(1) contamination of the RWST
(2) Sl-862A and Sl-862B are CLOSED
C.
(1) gas binding of the SI system
(2) RHR pump discharge pressure is <210 PSIG
D.
(1) gas binding of the SI system
(2) Sl-862A and Sl-862B are CLOSED
Page 41 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
42
(1 point)
Given the following:
The plant is at 99.5% RIP
The OATC performed a small dilution for Tavg control
Turbine is in OPER AUTO
The following indications are noted in the Control Room over a 20 minute period:
Power Range Nls are increasing
Tavg is lowering
Steam flow and feed flow are slightly elevated
The FWUFM 4 minute average power is 2349 MWt and slowly rising
Which ONE of the following correctly completes the statements below?
(1)
event is in progress.
The crew is required to FIRST reduce power
A.
(1) A main steam line leak
(2) lAW OMM-001-2, SHIFT ROUTINES AND OPERATING PRACTICES
B.
(1) An inadvertent RCS dilution
(2) lAW OMM-001-2, SHIFT ROUTINES AND OPERATING PRACTICES
C.
(1) A main steam line leak
(2) lAW AOP-038, RAPID DOWNPOWER
D.
(1) An inadvertent RCS dilution
(2) lAW AOP-038, RAPID DOWNPOWER
Page 42 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
43
(1 point)
Given the following:
The plant is at 100% RTP
Control Rods are in Manual
PT-446, MS TURB FIRST STAGE PRESS TRANSMITTER, the selected turbine
first stage pressure transmitter, INSTANTANEOUSLY fails to zero
(ASSUME NO OPERATOR ACTION)
Which ONE of the following correctly completes the statements below regarding the
Steam Generator Water Level Control System?
INITIALLY Feed Flow will
(II
At the end of the transient (STEADY STATE TO STEADY STATE), Feed Flow will be
(2)
its original value.
A.
(1) lower
(2) less than
B.
(1) lower
(2) equal to
C.
(1) remain unchanged
(2) less than
D.
(1) remain unchanged
(2) equal to
Page 43 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
44
(1 point)
Given the following:
The plant is in Mode 3
B MDAFW Pump is running
A feedline break occurs between FCV-1 425, MDAFW PUMP B FCV, and V2-20B,
The break is isolated and a clearance is hung to isolate the section of piping, Single
Valve isolation
Which ONE of the following correctly completes the statement below?
When the break is isolated, the crew will be able to feed
with the A
MDAFW pump.
A.
SIG A ONLY
B.
S/GBONLY
C.
S/Gs A and B ONLY
D.
S/Gs A, B, and C
Page 44 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
45
(1 point)
Given the following:
The plant is at 100% RTP
Emergency Diesel Generator (EDG) A is started and paralleled to the 480V Bus
E-1 for surveillance testing
EDG A is loaded to 1100 KW
A lagging power factor (+VARS) has been established
Which ONE of the following correctly completes the statement below?
(1)
the voltage control potentiometer will cause the generator to pick up a
larger share of the
(2)
load.
A.
(1) Lowering
(2) reactive
B.
(1) Raising
(2) reactive
C.
(1) Lowering
(2) real
D.
(1) Raising
(2) real
Page 45 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
46
(1 point)
Given the following:
The plant is in Mode 3
DC Distribution Panel B was de-energized due to a fire
Which ONE of the following correctly completes the statements below?
Control Power has been lost to 41 60V Busses
(1)
Control Power to the 41 60V Busses
be restored using a safety switch in
the 4160V Switchgear Room.
A.
(1)1&2
(2) can
B.
(1)1&2
(2) can NOT
C.
(1)3&4
(2) can
D.
(1)3&4
(2) can NOT
Page 46 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
47
(1 point)
Due to an accident coupled with a Loss of Offsite Power, Emergency Diesel Generator
(EDG) A has operated at 110% of the maximum continuous load rating for the last 30
minutes.
Which ONE of the following correctly completes the statement below?
The EDG A is loaded to
(1)
, and can remain at this load for an additional
(2)
A.
(1)2200KW
(2) 30 minutes
B.
(1)2200KW
(2) 90 minutes
C.
(1)2750KW
(2) 30 minutes
D.
(1)2750KW
(2) 90 minutes
Page 47 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
48
(1 point)
Given the following:
The plant was at 100% RTP
A LOCA coincident with a loss of Off-Site Power occurred
Safety Injection has been reset
The BOP observes APP-010-A1, EMERG GEN NB AUTO-TRIP alarms and the
following indications:
..
E1ERGS B
TO J SE?
0KB 50278
..
Which ONE of the following correctly completes the statements below?
Breaker 52117B, EMERG DGATO BUS El tripped on
(1)
IF the BOP places the BKR 52117B control switch on the RTGB to TRIP, BKR 52/17B
(2)
automatically re-close.
Over Power, 51V-A-ADG, OVERCURRENT RELAY
Over Current, AMPTECTOR ON 52/17B
A.
(1) Over Power
(2) will
B.
(1) Over Power
(2) will NOT
C.
(1) Over Current
(2) will
D.
(1)OverCurrent
(2) will NOT
TEL
EMER2 DIESEL
TOlERATOR A
STOP
SORT
O I
ELERO DOS
TO BUS El
BAR 50178
CLOSE I [1
OPERO DIESEL
ONERATOR B
STOP
SORT
O
TRIP
005Ea
Page 4$ of 75
Robinson Nuclear Plant
ILC-17RNPRO NRC Examination
Question:
49
(1 point)
Given the following:
The crew has entered AOP-035, S/G TUBE LEAK based on multiple indications of
A S/G tube leakage
The crew has performed an OST-051, Reactor Coolant System Leakage
Evaluation, and determined unidentified leakage of 0.04 gpm
Chemistry has confirmed the primary to secondary leak rate is 0.04 gpm
Which ONE of the following correctly completes the statements below?
lAW AOP-035 a
(1)
event has occurred.
AOP-035-BD states that radiation monitor R-24A is NOT a reliable indicator when less
than
(2)
power.
A.
(1) PSAL-3
(2) 40%
B.
(1) PSAL-3
(2) 50%
C.
(1) PSAL-1
(2) 40%
D.
(1) PSAL-J
(2) 50%
Page 49 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
50
(1 point)
Given the following:
The plant is in MODE 3
A release is in progress from A Waste Gas Decay Tank
R-14C, PLANT VENT LOW RANGE GAS MONITOR, FAIL light illuminates due to
low counts
Which ONE of the following correctly completes the statements below?
RCV-014, WASTE GAS RELEASE ISOLATION will
LIJ
The R-14 Skid
(2)
shift to the Intermediate/Mid Range.
A.
(1) remain OPEN
(2) will
B.
(1) remain OPEN
(2) will NOT
C.
(1) automatically CLOSE
(2) will
D.
(1) automatically CLOSE
(2) will NOT
Page 50 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
51
(1 point)
Given the following:
The plant is at 100% RTP
OST-021, DAILY SURVEILLANCES is in progress
The following data is recorded for SW temperature
HVH-1
HVH-2
HVH-3
HVH-4
Tl-1662A, B, C, D
96°F
96°F
98°F
97°F
High Accuracy
95°F
95°F
97°F
96°F
Temperature
Instrument
Which ONE of the following correctly completes the statement below?
Entry into Tech Spec LCO 3.7.8 required actions
(1)
required based on
TI-i 662A, SWBP A TO HVH 1 TEMP INDICATOR
TI-I 662B, SWBP B TO HVH 2 TEMP INDICATOR
TI-i 662C, SWBP C TO HVH 3 TEMP INDICATOR
TI-I 662D, SWBP D TO HVH 4 TEMP INDICATOR
A.
(1)is
(2) the highest TI-1662 reading
B.
(1)is
(2) the highest High Accuracy Temperature Instrument reading
C.
(1) is NOT
(2) the average of the TI-i 662 readings
D.
(1)isNOT
(2) the average of the High Accuracy Temperature Instrument readings
Page 51 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
52
(1 point)
Initial conditions:
SW-739, CCW HEAT EXCHANGER A RETURN, and SW-740, CCW HEAT
EXCHANGER B RETURN, are initially throttled open to LESS THAN POSITION
I
Subsequently:
SW-739 & SW-740 are throttled CLOSED an additional 1/2 turn.
Which ONE of the following correctly completes the statement below?
As a result of these manipulations, from steady-state to steady-state...
Service Water Header PRESSURE will
(1)
CCW Heat Exchanger Outlet TEMPERATURE will
A.
(1) lower
(2) lower
B.
(1) lower
(2) rise
C.
(1) rise
(2) lower
D.
(1) rise
(2) rise
Page 52 of 75
Question:
53
(1 point)
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Given the following:
The plant is at 100% RTP
APP-002-F7, INSTR AIR HDR LO PRESS was received 10 minutes ago
The crew is progressing in AOP-017, LOSS OF INSTRUMENT AIR
The following indications are observed:
lAW AOP-017, the crew is required to trip the reactor, based on
(1)
(2)
a concurrent use procedure.
A.
(1) SGWLC being adversely affected
(2) is NOT
B.
(1) SGWLC being adversely affected
(2) is
C.
(1) IA header pressure exceeding the trip limit established by the AOP
(2) is NOT
D.
(1) IA header pressure exceeding the trip limit established by the AOP
(2) is
Which ONE of the following correctly completes the statements below?
Page 53 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
54
(1 point)
Given the following:
The plant was at 100% RTP
A reactor trip and loss of offsite power occurred
Which ONE of the following correctly completes the statement below?
Two minutes into the event, Instrument Air Compressor(s)
have power
available.
A.
A and D
B.
and B
C.
B and Primary Air Compressor
D.
D and Primary Air Compressor
Page 54 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examincttion
Question:
55
(1 point)
Which ONE of the following conditions concerning the Personnel Air Lock would
REQUIRE entering an LCO Action Statement?
A.
Both air lock doors fail acceptance test criteria while the plant is in MODE 6.
B.
Welding cables are laid through both airlock doors while the plant is in MODE
5.
C.
The outer door is opened for a normal entry into Containment while the plant is
in MODE 3.
D.
The inner and outer doors are opened simultaneously for a normal entry into
Containment while the plant is in MODE 4.
Page 55 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
56
(1 point)
During a power ascension in accordance with GP-005, POWER OPERATION, Power
Range NIs and Calorimetric power indicate 28% power.
Which ONE of the following is the expected RCS Core Delta T for the indicated power
level?
A.
8.1°F
B.
8.7°F
C.
16.1°F
D.
21.0°F
Page 56 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
57
(1 point)
Given the following:
The plant is at 100% RTP
Several alarms illuminate and the OATC observes LT-460 indication off scale LOW
(ASSUME NO OPERATOR ACTIONS)
Which ONE of the following correctly completes the statements below?
Over the first minute of this event...
Charging pump speed will
(1)
and
Letdown will
(2)
A.
(1) RISE
(2) remain in service
B.
(1) RISE
(2) automatically isolate
C.
(1) LOWER
(2) remain in service
D.
(1) LOWER
(2) automatically isolate
Page 57 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
58
(1 point)
Which ONE of the following correctly completes the statements below?
APP-005-A2, IR HI LEVEL ROD STOP actuates when
(1)
lRNls are at
current equivalent to 20% power.
If IR LOGIC TRIP DEFEAT TRAIN A and TRAIN B pushbuttons are pushed
sequentially, IR LOGIC TRIPS
(2)
blocked.
A.
(1)2of2
(2) are
B.
(1)2of2
(2) are NOT
C.
(1)lof2
(2) are
D.
(1)lof2
(2) are NOT
Page 58 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
59
(1 point)
Given the following:
You have been assigned to perform OST-OJO, POWER RANGE CALORIMETRIC
DURING POWER OPERATION DAILY
Indicated power level values are:
N-41: 97.2%
N-42: 99.7%
N-43: 99.3%
N-44: 100.6%
Calculated power level is 99.5%
Which ONE of the following statements is correct?
A.
N-41 adjustment is REQUIRED, ONLY.
B.
N-44 adjustment is REQUIRED, ONLY.
C.
N-41 and N-44 adjustment is REQUIRED.
D.
NO adjustment is REQUIRED based on data recorded.
Page 59 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
60
(1 point)
Given the following:
A GP-006-1, NORMAL PLANT SHUTDOWN FROM POWER OPERATION TO
HOT SHUTDOWN is in progress to support a scheduled refueling outage
The turbine is tripped
Tavg is being controlled at 547°F by the Steam Dumps in Pressure Control Mode
Subsequently, P1-464, STEAM HEADER PRESSURE fails high.
Which ONE of the following correctly completes the statements below?
Steam Dump
(1)
will OPEN.
At a condenser vacuum SETPOINT of
(2)
the Steam Dumps will NO
LONGER be armed.
A.
(1) Bank 1 ONLY
(2) 19.7 HG
B.
(1) Bank I ONLY
(2) 21.0 HG
C.
(1) Banks I and 2
(2) 19.7 HG
D.
(1) Banks 1 and 2
(2) 21.0 HG
Page 60 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
61
(1 point)
Which ONE of the following is the power supply for HVE-3, CV AIR IODINE REMOVAL
Fan?
A.
MCC-5
B.
MCC-6
C.
MCC-9
D.
MCC-1O
Page 61 of75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
62
(1 point)
Given the following:
The plant is in MODE 5
The equipment hatch is removed lAW OMM-033, IMPLEMENTATION OF CV
CLOSURE
A Containment Purge is in progress lAW OP-921, CONTAINMENT AIR HANDLING
R-14C, PLANT VENT LOW RANGE GAS MONITOR is Out of Service (OOS)
HVE-1A, CV PURGE FAN is in operation
Containment radiation monitors are all trending up slowly
Which ONE of the following correctly completes the statements below?
To commence the Purge operation
(11
MUST be in operation.
IF R-1 1, CV AIR & PLANT VENT PARTICULATE alarms, HVE-IA
automatically stop.
A.
(1) both R-1J AND R-12
(2) will
B.
(1) either R-1 I OR R-1 2
(2) will
C.
(1) both R-11 AND R-12
(2) will NOT
D.
(1) either R-11 ORR-12
(2) will NOT
Page 62 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
63
(1 point)
Given the following:
The plant is at 100%
A seismic event has occurred several minutes ago
APP-036-B6, SPENT FUEL PIT LO LEVEL, has just illuminated
SFPC Pump B is aligned for service
lAO reports leakage is coming from UPSTREAM of SFPC-796, SFPC PUMP B HI
LEVEL SUCTION
Which ONE of the following correctly completes the statements below?
lAW AOP-036, SEP EVENTS, spent fuel pool cooling
(1)
be restored by
placing SFPC Pump A in service.
Subsequently,
Maintenance has repaired the leaking pipe
OP-913, REFUELING WATER PURIFICATION PUMP OPERATION, is being used
to restore spent fuel pool (SFP) to normal level
lAW AOP-036, the addition of 550 lbs of boric acid for every foot level added to the
(2)
required.
A.
(1) will
(2) is
B.
(1) will
(2) is NOT
C.
(1)wiIINOT
(2) is
D.
(1)wiII NOT
(2) is NOT
Page 63 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
64
(1 point)
Given the following:
The plant is at 100% power
FCV-478, S/G A FWRV (Feedwater Regulating Valve) is failing open
Which ONE of the following correctly completes the statements below?
Operators will FIRST receive
(1)
Subsequently:
All operator actions to control FCV-478 have failed
- A Feedwater Isolation occurs
Assuming no additional operator actions, the FIRST automatic reactor trip signal that
occurs is
t2)
APP-006-A3, S/G A LVL DEV
APP-006-D2, S/G A NAR RANGE HI LEVEL
A.
(1) APP-006-A3
(2) Turbine Trip
B.
(1) APP-006-A3
(2) Steam Generator LO-LO level
C.
(1) APP-006-D2
(2) Turbine Trip
D.
(1) APP-006-D2
(2) Steam Generator LO-LO level
Page 64 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Exctrnination
Question:
65
(1 point)
Given the following:
The plant is at 100% RIP
A release of Waste Condensate Tank (WCT) D is in progress.
Annunciator APP-036-E7, RAD MONITOR TROUBLE, is received.
The BOP Operator reports the FAIL light for R-18, LIQUID WASTE DISPOSAL
MONITOR, is illuminated.
Which ONE of the following correctly completes the statement below?
RCV-018, LIQUID WASTE RELEASE ISOLATION VALVE will...
A.
NOT automatically close. The release must be manually terminated.
B.
NOT automatically close. The release may continue lAW APP-036-E7
Annunciator Procedure.
C.
automatically close when the monitor FAIL light is illuminated. The release can
NOT continue under the current release permit.
D.
automatically close when the monitor FAIL light is illuminated. The release can
continue lAW APP-036-E7 Annunciator Procedure, RCV-01 8 must be
manually bypassed.
Page 65 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
66
(1 point)
Given the following
You are OATC on shift and require a short term relief to meet with the PGM
Which ONE of the following correctly completes the statements below?
lAW AD-OP-ALL-I 000, if you are relieved for GREATER THAN
(I)
, then a
Narrative Log Entry, formal turnover and shift turnover sheet, and the logs signed over
MUST occur.
lAW AD-OP-ALL-I 000, if you return to the Control Room 15 minutes after being
relieved, a briefing
required.
A.
(1) 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />
(2) is
B.
(1) 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />
(2) is NOT
C.
(I) 20 minutes
(2) is
D.
(1) 20 minutes
(2) is NOT
Page 66 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
67
(1 point)
Given the following:
The plant is at 100% RTP for the past three weeks
Chemistry has just provided the following results from a Reactor Coolant System
sample that was taken 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> ago:
RCS Chloride: 0.1 ppm
RCS Oxygen: 0.15 ppm
Which ONE of the following correctly completes the statements below?
The
concentration exceeds the TRMS 3.5, REACTOR COOLANT
OXYGEN AND CHLORIDE CONCENTRATION limit.
lAW TRMS 3.5 CONDITION A, action to restore compliance with the TRMS must be
initiated with a COMPLETION TIME of
(2)
A.
(1) Oxygen
(2) 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />
B.
(1) Oxygen
(2) immediately
C.
(1) Chloride
(2) 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />
D.
(1) Chloride
(2) immediately
Page 67 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
68
(1 point)
Given the following:
Core Reload is in progress lAW GP-O1O, REFUELING
Consider the following list of responsibilities:
1) Maintains and evatuates the 1/M plot during core loading
2) Determines fuel movement sequence
3) Advises the Refueling SRO that conditions are acceptable or unacceptable for
authorizing gripper unlatching for fuel assembly insertion into the core
Which ONE of the following correctly completes the statement below?
lAW OMM-OO1-18, OUTAGES, the Reactivity Monitor stationed in the Control Room is
responsible for....
A.
I ONLY
B.
2 ONLY
C.
1AND3
D.
2AND3
Page 68 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
69
(1 point)
Given the following:
The plant is in Mode 3
Preparations for a post trip startup lAW GP-003, NORMAL PLANT STARTUP
FROM HOT SHUTDOWN TO CRITICAL are in progress
The Outside AO has been directed to perform Section 6.14. BLOWDOWN TO THE
FLASH TANK WITH HEAT RECOVERY BYPASSED of OP-406, STEAM
GENERATOR BLOWDOWN IWET LAYUP SYSTEM
lAW AD-OP-ALL-0203, REACTIVITY MANAGEMENT, which ONE of the following
correctly completes the statements below?
A Dedicated Licensed Operator
(1)
requited to be present in the field with
the AO when performing this task.
The OATC
authorize the performance of this reactivity manipulation
without CRS/Reactivity Manager oversight.
A.
(1)is
(2) can
B.
(1) is NOT
(2) can
C.
(1)is
(2) can NOT
D.
(1)isNOT
(2) can NOT
Page 69 of 75
Robinson Nuclear Plant
fiX-i 7 RNP RO NRC Examination
Question:
70
(1 point)
Given the following:
The plant is in MODE 3 at 547°F
A transient causes RCS pressure to rapidly increase
Which ONE of the follow
correctly completes the statements below?
(1)
If the RCS Pressure Safety Limit is exceeded, the MAXIMUM amount of time to
restore compliance per Tech Specs is
(2)
A.
(1)<2485PS1G
(2) one hour
B.
(1)<2735PS1G
(2) one hour
C.
(1)<2485PS1G
(2) five minutes
D.
(1)<2735PS1G
(2) five minutes
A/AJ&
In
/N/S74-72O//
1Z:7
SVITE
- -
Rs
r
(L
t.
Page 70 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
71
(1 point)
Initial conditions:
The plant is at 100% RTP
Which ONE of the following activities requires entry into a Technical Specifications
LCO action statement?
(CONSIDER EACH OF THE BELOW CHOICES INDEPENDENTLY OF EACH OTHER)
A.
Charging Pump A removal from service for oil change.
B.
Boric Acid Transfer Pump B recirc valve leak repair.
C.
CCW Pump A mechanical seal repair.
D.
CCW Pump B breaker repair.
Page 71 of75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
72
(1 point)
Given the following:
GP-007, PLANT COOLDOWN FROM HOT SHUTDOWN TO COLD SHUTDOWN
is in progress
You have been assigned by the WCC SRO to hang a clearance on the RCS Filter
for replacement
RCS Filter radiation levels are 1100 mrem/hr at 30 cm from the filter housing
Which ONE of the following correctly completes the statements below?
lAW AD-RP-ALL-201 7, the radiation area is required to be classified as a
lAW AD-HU-ALL-0005, the Independent / Concurrent Verification
(2)
be
waived.
AD-RP-ALL-2017, ACCESS CONTROLS FOR HIGH, LOCKED HIGH, AND VERY
AD-HU-ALL-0005, HUMAN PERFORMANCE TOOLS
A.
(1) Locked High Radiation Area
(2) can
B.
(2) can
C.
(1) Locked High Radiation Area
(2) can NOT
D.
(2) can NOT
Page 72 of 75
Robinson Nuclear Plant
ILC-i 7 RNP RO NRC Examination
Question:
73
(1 point)
Given the following:
A LOCA has occurred
Both SI pumps have tripped
All RCPs have been stopped
The crew is performing FRP-C.1, RESPONSE TO INADEQUATE CORE COOLING
Subsequently, RWST level lowers to 27%
Which ONE of the following correctly completes the statement below?
The EARLIEST the crew is required to transition to EOP-ES-1 .3, TRANSFER TO
COLD LEG RECIRCULATION is
A.
immediately
B.
when APP-002-B3, RWST LO-LO LVL alarms
C.
when all actions of FRP-C.1 have been completed
D.
when at least 1 RCP has been started lAW FRP-C.1
Page 73 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
74
(1 point)
Which ONE of the following correctly completes the statement below?
With respect to Fire Protection Procedures, specific room guidelines for the Fire
Brigade to fight a fire in the Auxiliary Building are located in
A.
FP-OO1, FIRE EMERGENCY
B.
AOP-041, RESPONSE TO FIRE EVENT
C.
OMM-002, FIRE PROTECTION MANUAL
D.
OMM-003, FIRE PROTECTION PRE-PLANS
Page 74 of 75
Robinson Nuclear Plant
ILC-1 7 RNP RO NRC Examination
Question:
75
(1 point)
Given the following:
The plant is in Mode 6
During testing of RTGB annunciators several annunciators were not received
The crew has entered AOP-054, LOSS OF CONTROL ROOM ANNUNCIATORS
Which ONE of the following correctly completes the statements below?
The crew will direct the Outside AO to check Breaker 12, Lundell AC, on Instrument
Bus
(1)
The OAO reports the breaker is tripped, and that there are no apparent signs of
damage or abnormal odors.
The breaker can be reset one time
(2)
, with CRS approval.
A.
(1)2
(2) IMMEDIATELY
B.
(1)3
(2) following a Live-Dead-Live check lAW OP-603-2, ELECTRICAL LIVE-
DEAD-LIVE CHECKS
C.
(1)2
(2) following a Live-Dead-Live check lAW OP-603-2, ELECTRICAL LIVE
DEAD-LIVE CHECKS
D.
(1)3
(2) IMMEDIATELY
Page 75 of 75
Examination KEYfor: ILC-i 7 RNP RO NRC Exan;in
Question
Answer
Nuntber
1
B
2
C
3
D
4
B
5
C
6
A
7
C
8
D
9
D
10
C
11
A
12
C
13
A
14
D
15
A
16
C
17
D
18
B
19
D
20
A
21
C
22
A
23
B
24
D
25
D
Printed 10/25/2017 10:26:32 AM
Page 1 of3
Examination KEYfor: IIX-17RNPRO NRCExamin
Question
Answer
Number
26
D
27
C
28
D
29
C
30
C
31
D
32
B
33
A
34
C
35
C
36
A
37
C
38
A
39
B
40
C
41
C
42
A
43
B
44
C
45
B
46
C
47
D
48
C
49
C
50
D
Printed 10/25/2017 10:26:32 AM
Page 2 of3
Examination KEYfor: ILC-1 7 RNP RO NRC Exarnin
Question
Answer
Nuntber
51
D
52
D
53
B
54
B
55
D
56
C
57
D
58
C
59
A
60
C
61
A
62
C
63
D
64
A
65
A
66
A
67
B
68
C
69
D
70
D
71
D
72
A
73
A
74
D
75
A
Printed 10/25/2017 10:26:33 AM
Page 3 of3
500
400
300
200
100
0
FIGURE 1
MINIMUM ECCS FLOW RATE VERSUS TIME AFTER TRIP
Page 1 of I
Rev. 2
EOP-ECA-J.1
LOSS OF EMERGENCY COOLANT RECIRCULATION
Page 32 of 38
FLOW
RATE
(GPM)
600
10
100
1000
10000
TIME
(MINUTES)
6.0
r
ci
5.0
ci
ci
4.0
ci
C
ci
- 0C
8 3.0
Note: Zero load condenser
backpressure limit applies
down to 10% rated turbine
speed
ATTACHMENT 3
9.0
8.0
7.0
CONDENSER BACKPRESSURE LIMIT
Siemens Curve
Number: CT-27466C
2.0
1.0
0.0
Backpresssre Limit
0
100
200
300
400
500
600
700
800
900
Gross Load (MWe)
8
7
I
6
I
5
cwwol6I3
I
4
I
3
2
I
IWD152R191
er a;;
TANKS
l_WO_IZN_II4j
_D_25O3R.l&S
B
-
-w
_____________
_flO72
- t:ns
ITh_ThM
l52Rl35
I
___
%
___
______
m
____ ____
7) >
W5C GS COPRSSOR
PKG
A
___
________
__
_]
-
E
,e
NOTE
I
cv
CWDAS M4L11Efl
lff5
wo
V
- -
-
STATION
Lzz__zzi
-
8
7
5
I
4
I
3
I
2
I