ML17303B031

From kanterella
Jump to navigation Jump to search
Insp Rept 50-528/88-01 on 880104-0212.Violations Noted.Major Areas Inspected:Engineering,Maint,Surveillance Testing, Operations & QA & Administration
ML17303B031
Person / Time
Site: Palo Verde 
Issue date: 03/30/1988
From: Burdoin J, Caldwell C, Mendonca M, Narbut P, Parkhill R, Richards S
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML17303B029 List:
References
50-528-88-01, 50-528-88-1, NUDOCS 8804190113
Download: ML17303B031 (74)


See also: IR 05000528/1988001

Text

e

U.

S.

NUCLEAR REGULATORY COMMISSION

REGION V

Report

No:

50-528/88-01

Docket No.

50-528

License

No.

NPF-41

Licensee:

Arizona Nuclear

Power Project

P.

0.

Box 52034

Phoenix, Arizona, 85072-2034

Facility Name:

Palo Verde Nuclear Generating Station - Unit 1

Inspection at:

Corporate

Engineering Offices, Phoenix,

Arizona

Palo Verde Site, Wintersburg,

Arizona

Inspection

Conducted:

January

4 through February 12,

1988

Inspectors:

.

Me

nc

, Te

Leader

Date Signed

R

Park ill,. Assista t Team Leader

P.

ar

u

, Sr.

sident

spector

Date Signed

~i~r/t'~

Date Signed

Burdoin,

Reac or Inspectore~

C. Caldwell,

Reactor 'Inspector

Consultants:

S.

Kobylarz, Westec Services,

Inc.

S. Klein, Westec Services,

Inc.

Da e Signed

a /~Y$

Date Signed

Approved by:

S.

A. Richards,

Chief,

Engineering Section

~Summer:

33oS

Date Signed

Ins ection Janu'ar

4 throu

h Februar

12

1988

Re ort Nos.

50-528/88-01

involved the areas

of Engineering,

Maintenance,

Surveillance Testing,

Operations,

and equality Assurance

and Administration.

During this inspection,

inspection

modules

25578,

25583,

30703,

35701,

37700,

37701,

37702,

38701,

8804190ii3

SS0330

PDR

ADOCK 05000528

9

DCD

1

41400,

41700;

41701,

42700,

56700,

61700,

61725,

61726,

62700,

62702,

62703,

62704,

62705,

71707,

71710,

73051,

73055,

92700,

and 92701 were used.

Results:

The following findings and conclusions

were identified:

Understandin

Control

and

Im lementation of Plant Desi

n

Re uirements

The team noted several

examples of problems in which the licensee

appeared

to

have

a less

than adequate

understanding

of the plant design.

Specific

concerns

in this regard involve both an inadequate

licensee

understanding

of

the plant design basis

and an inadequate

implementation of design requirements

into plant modifications

and activities.

Summar

of Violations Identified,

Of the areas

inspected,

three apparent violations of NRC requirements

were

identified,

as

summarized

below:

A.

Failure to comply with certain as-built requirements

of prescribed

documented

instructions,

procedures,

or drawings.

B.

Failure to comply with prescribed

procedures

in making temporary

modifications to install

a tank to supply hypochlorite for the emergency

spray pond.

C.

Failure to comply with ASHE requirements

in determining the size of

pressure relief valves for the surge tanks in the essential

chilled water

system.

It should

be noted that several

areas

of potential violation of NRC

requirements remain unresolved,

pending completion of additional

licensee

review of the specific problems

involved.

Further actions in this regard

will be the subject of future correspondence,

following a review of additional

licensee

information'on these

items.

DETAILS

1.

Persons

Contacted

. See Enclosure l.

2.

Desi

n Basis

Documentation

and

En ineerin

Activities

A.

General

Observations

The design portion of the inspection

focused

on

a review of design

change

packages

and original design basis documentation'elated

to

the selected

safety systems.

The team

was impressed with the

ability of the engineering staff to provide rapid responses

to

detailed technical

questions,

and

a capability to rapidly access

design basis

documentation

and analyses.

ANPP maintains

a

calculation index which facilitated this retrieval process.

Based

on the results of the design inspection,

the team determined

that the selected

safety

systems

(essential

chilled water, essential

cooling water,

and essential

spray systems)

are functional.

However, the team found that design analyses

were not adequately

verified to assure

a comprehensive

and complete evaluation of system

and equipment performance.

In many cases,

calculations to support

the established

size of safety related

components

and equipment

were

not complete,

or missing in their entirety.

The team found that the

observations

identified in the design inspection

are indicative of a

problem in the implementation of the

ANPP Technology Transfer

Program.

This'program

was instituted to assure that design basis

documentation

developed

by Bechtel for Palo Verde is effectively

transferred

to the cognizance of ANPP engineer ing personnel.

The

team found that

ANPP had not adequately

reviewed design basis

analyses

to assure that

a complete

and accurate

design basis is

available for use in future plant design modification efforts.

Based

on the

number of observations

identified related to Bechtel

calculations,

the objectives of the Technology Transfer

Program

may

not have

been achieved.

Although ANPP has not made significant

permanent

design

changes

to the plant, the team was concerned that

future modifications

may be compounded

in difficulty and complexity

by the lack of design information.

Specific examples of these

observations

are described

in Section

B

below.

B.

Desi

n Activities

The team reviewed mechanical

and electrical

design related to three

critical safety systems:

Essential

chilled water

(EC)

Essential

cooling water

(EW)

Essential

spray pond (SP)

The

EC supplies chilled water to a number of safety related

room

coolers

from a chiller which rejects

heat to the essential

cooling

water system

(EW).

The

EW provides cooling water to the essential

chiller

and the shutdown heat exchanger.

Heat from this equipment

is rejected to the essential

spray pond by the essential

cooling

water heat exchanger.

The essential

spray

pond serves.

as the

ultimate heat sink for Palo Verde Nuclear Generating Station.

None

of these

systems

operate

during normal

power operation.

. However, in

the event of a design basis accident,

heat

loads are rejected

from

the containment

sump to the shutdown heat exchanger

and then to the

essential

spray

pond via the essential

cooling water

heat exchanger.

The team reviewed design documentation

related to these

systems

including design

change

packages

(DCPs),

system descriptions,

P8IDs,

specifications,

line lists,

and design

analyses

to assess

the

capability of these

systems

to perform their safety functions.

For

the electrical ancillary support systems,

the team reviewed the

design analyses

for the sizing of the Class lE station batteries

and

the emergency

diesel

generators,

the

AC and

DC voltage studies,

and

the protective device setting

and coordination studies.

The review

focused

on the adequacy of the methodology,

the accuracy of the

design data,

and the validity of the the design

assumptions

utilized

in the calculations.

As part of the Technology Transfer

Program,

ANPP conducted

reviews of design documentation

received

from

Bechtel.

The team assessed

the effectiveness

of these

reviews

as

an

adjunct to the design inspection.

The team identified a number of observations

which indicated

weaknesses

in several

areas

of engineering activities.

These

include missing or inadequate

design analyses

and inadequacies

in

the verification of design analyses.

The following observations

are

illustrative.

ANPP has not made significant design

changes

to the Palo Verde plant

configuration.

Consequently,

the team did not review plant design

modifications originated

by ANPP engineering.

However, the team did

review a number of design calculations

and analyses

prepared

by

Bechtel substantiating

the original plant design basis.

The team

identified weaknesses

related to the use of unverified assumptions

and methodology

used in the calculations.

In some cases,

there were

no calculations

or documented

rationale to substantiate

system

parameters

.or equipment sizes.

The team noted

a general

lack of

awareness

by ANPP engineers

of the specific design

assumptions

utilized in the calculations.

The team attributes this lack of

awareness

to a shortcoming of the Technology Transfer

Program.

(1)

Missin

Calculations

a.

Sur

e Tank Pressure

Relief Valves

The essential

chilled water and

EW surge

tanks are

supplied nitrogen through

a pressure

regulating valve to

maintain nitrogen pressures

between

2 and

5 psig for the

essential

cooling water tank and

25 and

55 psig for the

EC..

A relief valve is provided

on the essential

chilled

water tank to protect the tank from pressures

which might

exceed its design pressure

of 100 psig.

Similarly, the

essential

cooling water surge tank is provided with a

relief valve to prevent exceeding

the design pressure

of

15 psig.

Section III of the

ASME B8PV Code, Article ND-7412,

requires

pressure relief valve capacity to include

consideration

of a fully open pressure

reducing device.

The licensee

had not considered

or done calculations

which

demonstrate

that the relief valves provided for the

essential

chilled water and essential

cooling water surge

tanks"are

sized to accommodate

flows resulting from the

failure of the upstream regulating valve in the wide open

position.

Failure of the regulating valve could impose

pressures

exceeding

design pressure

on the surge tanks if

the relief valve cannot

accommodate

the resultant 'nitrogen

flows.

In response

to the team's

concern,

ANPP engineering

personnel

developed preliminary- (checked,

but unverified)

calculations to confirm the capacity of these relief

valves to meet the code requirement.

The calculation

determined that for both tanks,

the relief valve was

adequately

sized to accommodate

the flow resulting from a

failure of the regulating valve in the wide open position.

However, the calculation determined

the

Cv (flow

coefficient) for the relief valve based

on the design flow

identified on the relief valve data sheet.

This flow was

in gpm representing

the liquid flow through the valve at

design conditions.

ANPP engineering

personnel

advised

that the valve vendor

had indicated (in a telephone

conversation) that the

g'as flow calculated

using this

Cv

was conservative.

This is

a potential violation of. the

ASME code

and is identified, as inspection

item

50-528/88-01-01.

Desi

n Pressures

and

Tem eratures

The team reviewed the Line Designation List for Palo Verde

which identifies the design pressures

and temperatures

for

system piping.

The licensee

could find no calculations

or

documented

rationale to substantiate

the design pressures

and temperatures

identified for the selected

safety

systems.

In response

to the team's

concern,

ANPP prepared

and"submitted

a written "sequence

of events" outlining the

methodology

used to develop the design pressures

and

temperatures

for PVNGS systems.

This procedure

included

a

calculation which attempted to confirm the design pressure

and temperature

for the

EC.

However, the calculation did

not include considerations

such

as

an evaluation of worst

case

operating

modes

and static

heads

due to components

which might be located at elevations

lower than the

essential

chilled water

pump.

The calculation

was not

signed,

checked,

or verified.

The team was unable to

confirm that design pressures

identified for systems

listed in the Line Designation List assure that piping

systems

and components

are adequately

designed to meet

system

demands.

ANPP stated that calculations to support the design

pressures

and temperatures

for the selected

safety systems

under review (EC,

EW, and

SP) will be developed.

In

addition,

ANPP will prepare

design pressure/temperature

calculations for any system which is modified prior to the

modification if the modification affects these

parameters.

Subsequently,

the team reviewed

a calculation submitted

by

ANPP to document the rationale supporting design pressures

and temperatures

for the essential

spray pond system'SP)

and

had

no questions

on that do'cument.

This observation

is not safety significant since the

design pressures

established

for the systems

reviewed

appear

to be sufficiently conservative.

However, the team

considered

the lack of substantiation

for design

conditions to be

a weakness

in design

development

which

could impact future modifications

made to the'lant.

This

observation

(and others described

below) contributed to

the team's

concern that

ANPP may not be adequately

reviewing design basis

documentation

to assure

that

critical design parameters

are supported

by design

analyses.

This observation

remains

open pending

completion of the calculations

committed to by ANPP.

The prelimjnary schedule

was January

29,

1988 for SP

(completed), April 1, 1988 for EW, and July 1,

1988 for

EC.

This is considered

an unresolved

item and is

identified as inspection

item 50-528/88-01-02.

Seismic

Desi

n of Electrical

Cables in Vertical"Cable

~Tra

s

During the system

walkdown portion of the SSFI, the team

noted that only nylon ties appeared

to be, used to support

electrical

cables in vertical cable trays.

The utility

was asked to provide an analysis

which justified that

cables

in vertical cable trays are supported

such that

they could adequately

withstand

a safe

shutdown earthquake

without resulting in any significant loading

upon the

cable terminations.

Such

an analysis

should also include

consideration

of nylon tie wrap aging effects.

The team

reviewed the installation specification governing the

support of conductors

in vertical

raceways

and

observed'hat

the instructions

were generalized

and could not be

solely relied upon to determine

a worst case'lant

configuration.

In addition, the team confirmed via the

utility that support blocks,

Kel lum grips

and cable

clamps,

as referenced

in the installation specification,

were not utilized in the vertical cable trays,

but instead

applied only to cables

in vertical conduit.

The utility,

in an outline of a plan to resolve the concern;- dated

February

15, 1988,

committed to perform the requested

analysis within a ten-week schedule.

Before performing

the subject analysis,

the utility intends to determine

plant vertical tray configurations followed by

establishment

of worst case

models.

This approach is

considered

by the team to be acceptable

with the

understanding

that the final analysis

when completed will

be reviewed

by the Structural

and Geosciences

Branch of

NRR.

This issue constitutes

an unresolved, item and is

identified as inspection

item 50-528/88-01-03.

Class

1E Batter

Room Ventilation

The team observed that the Class

1E battery

room 'normal

and emergency

exhaust ventilation ducts

draw room air from

approximately the middle of the

room height.

This

arrangement

could allow for the potential build-up of

hydrogen gas,'hich

is released

from the battery primarily

during equalize

charging,

in the

room volume above the

exhaust

duct register.

The licensee

has provided the team

with an evaluation which documents that the ventilation

system provides

good air mixing action which would result

in the purging of potential

hydrogen entrapment

areas.

The mechanism for air mixing in the

room is provided by

the air flow from a supply air register which is located

in approximately the center of the battery

room.

Supply

air is provided from a Class

lE ventilation

system.

However, during

a kalkdown of the battery

rooms the team

observed

possible

areas

of entrapment

formed by structural

steel

members at the ceiling where it was not completely

obvious that adequate air mixing would occur.

The team questioned

whether actual

hydrogen level readings

have

been taken at the ceiling to verify the hydrogen

removal capability.

Apparently, to date,

the only

measurements

for hydrogen

have

been

made at or near

the

batteries

and not at the ceiling.

Two of the

120

VDC vital battery

rooms

have

emergency

lighting batteries

also housed in the room.

The team

identified that the emergency lighting batteries

were not

considered

in the calculation for hydrogen

(H~) generation

during design of the ventilation system for the 120

VOC

vital batteries.

In addition, the calculations

had never

been verified to determine if excessive

H~ pocketing

has

been occurring.

6

The licensee

re-performed

the

H~ calculations

and

found that it would take

92 hours0.00106 days <br />0.0256 hours <br />1.521164e-4 weeks <br />3.5006e-5 months <br /> to reach

a 2X

concentration

in the battery

rooms without any

ventilation.

This was quite different from their

original calculation which did not include the

emergency lighting battery

Hz generation.

The licensee

committed to perform a test of actual

Hydrogen levels in the battery

rooms while charging

the batteries.

Work Request 221481

was prepared to

monitor the buildup of,hydrogen in all areas

of the

battery

rooms during float and equalizer charging.

'his

will determine

the potential for H~ pocketing.

This issue will remain open pending confirmation. from the

licensee that the aforementioned

tests

have

been

completed

and the results

support the current design configuration.

This is identified as inspection

item 50-528/88-01-04.

Batter

Room Minimum Desi

n Ambient Tem erature

Battery sizing is based

on a minimum cell operating

temperature

to ensure that the battery

has

adequate

capacity to satisfy the design basis

requirement.

The

team found that the licensee

did not have

a design

calculation which documents that the Essential

HVAC system

for the battery

room could maintain

a minimum 60

F design

ambient temperature,

which is the design input temperature

in the battery sizing analysis

associated

with a loss of

offsite power.

Also, the team found that the minimum

design

ambient temperature,

calculated

as

59

F in the

analysis for the normal battery

room

HVAC system during

plant start-up (Calculation 13-MC-HJ-001,

sheet

15 of 34),

did not satisfy the calculation Design Criteria, Part

II.B, which required

60 F.

However, the design margin

available in the Class lE batteries

compensates

for'he

weakness

in the minimum'design

ambient temperature

analysis.

The identified weaknesses

are

examples of

inadequate

design verification and the failure of the

Technology Transfer

Program to assure

rigorous design

analyses

which form the basis for the safety-related

design of the plant.

This item will remain

open pending confirmation from the

licensee that

a calculation,

which 'demonstrates

that the

essential

HVAC system

can maintain the required 60'F

during

a

LOP,

has

been formally issued

and supports

the

current design configuration.

Additionally., the licensee

should assure that the normal battery

room

HVAC system

has

been formally updated,

and its design basis

has

been met.

This is identified as inspection

item 50-528/88-01-05.

(2)

Inade

uate Calculations

Diesel Generator Sizin

A review of the data utilized in the Diesel Generator

Sizing calculation for the

pumps

and drive motors for the

Essential

Spray

Pond,

Essential

Cooling Water,

and

EC

indicated that incorrect and non-conservative

data

was

utilized in the diesel

generator

load analysis for the

plant conditions

under review.

Forced

Shutdown

(FSD) and

LOCA/LOP plant conditions'were

analyzed to determine the

required size for the diesel

generator.

The team found that the applicable

brake

horsepower

(Bhp)

requirement,

based

on the required

system flow for the

plant condition under review was not always utilized.

Also, the team found that the

Bhp or flow requirement

was

derived from a document

found to be not up to date,

such

as the System Description,

even though it was

a controlled

design basis

document.

Furthermore,

worse

case

load data

was apparently

not utilized in the calculation

even though

the applicability of the calculation

was for all three

Palo Verde Units.

The calculation

showed the Essential

Cooling Water

Pump

EWA(B)-POl "Load Size" brake

horsepower

(Bhp)

requirement

as

665 Bhp, with a "Maximum" requirement

of 690 Bhp.

665 Bhp on the

pump characteristic

curves correlates

with a flow requirement of 14,550

gpm (which is listed as the rated capacity in the

system description which is shown

as

a reference

, document for this data).

These

Bhps were then

converted to a motor input

kW requirement

(based

on

the motor efficiency related to 690 horsepower

(hp),

or 0.945,

which is conservative).

Nevertheless,

the

calculation

goes

on to establish

Forced

Shutdown

(FSD) and

Loss of Coolant Accident/Loss of Offsite

Power

(LOCA/LOP)

kW requirements,

based

on the "Load

Size" or normal,

and the

"Maximum" required

Bhps,

as

525

kW and 545

kW respectively,

which apply to both

plant conditions.

In this case

the calculation

methodology of a normal

and

maximum load for each

plant condition is erroneous.

The Flow Diagram for

the

EW shows the flow for a "Normal" and

a "LOCA"

shutdown condition to be the

same,

and flow during a

"FSD" to be much higher.

The hydraulic analysis for

this, system,

13-MC-EW-001, Revision 1, calculates

the

FSD flow as 17,280

gpm,

and the

LOCA/LOP flow as

15,980

gpm.

These

flows are the only flows

.

applicable for each of the plant conditions.

On this

basis,

the team calculates .that the

kW required for

FSD is 550

kW, and for LOCA/LOP 545

kW.

This

compares with the licensee

calculated

loads

as

follows:

Team Calculation

Licensee Calculation

Forced

Shutdown

550

kW

525

kW

545

kW, maximum

LOCA/LOP

545

kW

525

kW

545

kW, maximum

Therefore,

the

use of incorrect design flows for the

plant conditions analyzed resulted in a 4X to 5X

error in understating

the required motor kilowatts

(kWs) due to the erroneous

methodology.

The Essential

Spray

Pond

Pump required flow, based

on

the hydraulic analysis for the system,

13-MC-SP-302,

Revision 0, is 16,540

gpm for both

FSD and

LOCA/LOP

conditions.

This corresponds

to approximately

589

Bhp on the

pump test data sheet

M095-103-1.

However,

the calculation utilized 580 Bhp as the

pump

requirement,

in spite of the .fact that the System

Description, which was

shown as

a reference for this

data,

showed

589 Bhp as the

pump requirement.

The

Bhp requirement for the Essential

Chilled Water

pump used in the calculation,

13.3 Bhp, disagrees

with the data

on pump curve N-872, Revision 0, which

shows

14 Bhp required at the operating point, 400

gpm.

The flow requirement,

400 gpm, correlates

well

with the flow data indicated

on the Flow Diagram

13-M-ECF-001, Revision 1, which shows the

maximum

flow to be 397

gpm.

The team

was concerned that in the three (3) cases

where

the team reviewed the data utilized in the calculation,

discrepancies

and/or errors

were found, raising concerns

regarding the overall validity of the calculated results.

'As

a result of the team's

concern,

the licensee

reviewed

the calculation

and data for all motor drives greater

than

100 hp.

The results of the analysis

confirmed the team's

observation,

and found, for example, that for the Unit 2

diesel

generator,

the

LOCA/LOP load increased

3.8X (or

207.2

kW) and the

FSD load increased

2.2X (or 120.9

kW).

Nevertheless,

the resulting design margin available in the

diesel

generators

during LOCA/LOP, based

on the continuous

rating,

was at least 14.5X.

The .team also noted that the licensee's

engineers

had

initiated two (2) revisions to the diesel

generator

loading analysis

(Calculation

Change Notices),

but failed,

in the process,

to review the analysis

provided by the

original architect-engineer,

and detect the errors in the

data

and calculations

as identified by the team.

This item remains

open pending confirmation from the

licensee that the subject calculation

has

been formally

revised

and supports

the plant's current design

configuration.

This is identified as inspection

item

50-528/88-01-06.

Cl'ass

lE Batter

Sizin

The team reviewed the Class lE Battery and Battery Charger

Sizing Calculation 13-EC-PK-100,

Revision 5, for

conformance with acceptable

design criteria and the

validity of the assumptions

and the data utilized in the

calculation.

The team found that

a calculation assumption utilized

erroneous

methodology

and data which,

as

a result,

understated

the average

inverter load on the battery.

Also, other

data utilized in the calculation for auxiliary

relay cabinet loading was found to be incomplete

and,

therefore,

understated.

The "average floating voltage" of the duty cycle for

the battery

was

used to establish

the average

inverter load.

The concept of a battery

on float

during a design discharge

is incorrect since the

battery is not on float charge for this condition.

The initial .battery voltage

on discharge

was

considered

to be 130.2 volts (which is the minimum

recommended float voltage for the battery).

The

initial battery voltage cannot

be more than the

battery

open circuit voltage,

which the team

calculated to be 123.3 volts based

on the Exide

published data,

and is in fact lower due to the

initial load. on the battery during discharge.

For

example, for Battery "A" the team estimated that the

initial battery voltage is 119 volts,

based

on the

referenced

calculated battery load after one minute

and the Exide battery capacity curves.

On this basis

the average

duty cycle voltage is (105 + 119)/2 = 112

volts versus

117.6 volts calculated in Assumption

3. 1. a (where

105 represents

the voltage at the end of

the duty cycle).

The net result is 5X additional

load on the battery

on average

during discharge

due

to the increased

inverter load.

An incorrect inverter efficiency of 87X was utilized.

This is the efficiency at full load and 100K power

factor.

For the

same

load conditions

and with the

static transfer switch which is installed,

the rated

efficiency is 86K as stated in the Inverter Manual.

Apparently,

when the static transfer switch was

installed

on

DCP 10E-PN-013,

the calculation

was not

identified to be updated to reflect the revised

inverter efficiency.

Nevertheless,

the conservatism

10

utilized in stating the inverter load in the sizing

analysis for the battery (Inverters

A and

B were

considered

to be

lOOX loaded,

and Inverters

C and

D

were considered

to be

SOS loaded)

compensates

for the

error in inverter efficiency.

Also, the inverter efficiency utilized applies at

inverter full load and

lOOX power factor.

The

inverters are in fact operated at less

than full load

conditions (the team observed Inverter "B" at

approximately

30K load during

a plant walkdown),

and

less than

lOOX power factor (the licensee

assumed

90K

power factor in the calculation).

The operation of

the inverters at less

than full load results in

additional

design margin in the battery.

However,

the amount of margin was not established

since the

efficiency data

was not available for variations of.

load and power factor.

The team understood that this

data is being pursued

by the licensee with Elgar, the

manufacturer of the inverter.

The auxiliary relay cabinet

load was found by the

team to be understated.

The sizing calculation for

Battery "A" showed the steady state

load as

10

amperes for the auxiliary relay cabinets,

but the

single line diagram for the 125

VDC Distribution

Panel

E-PKA-E21 showed the load to just one (1) of

eight (8) auxiliary relay cabinets

as

10 amperes

(cabinet

E-ZJA-COl, 1250 VA).

Therefore,

the load

for seven

(7) auxiliary relay cabinets

was not

accounted for in the battery sizing analysis.

The team was provided with a preliminary draft of the

battery sizing reanalysis

on January

23,

1988, for

Batteries

"A" and "C," which are considered

to be the

worst case for each type of battery cell provided

(GN-23 and GN-13, respectively).

For Battery "A,"

for example,

the reanalysis

included

an increase

in

the average

inverter

load of 11.5 amperes

and an

increase

in the auxiliary relay cabinet

load of 70

amperes,for

the

2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> duty cycle.

Also, increased

first minute loads for the aforementioned

were

identified.

A similar increase

in the inverter load

for Battery "C" was identified; however,

no

additional auxiliary relay load was applicable for

this battery.

The results of the draft reanalysis

show that the

design margin capacity available in the batteries

was

decreased

from 36.6X to 10.8X for Battery "A," and

from 19.5X to 15. 1X for Battery "C."

The resulting

capacity margin available

in the batteries

was

acceptable,

especially since additional factors for

minimum battery cell operating temperature

and aging

11

factors

have also

been included in the battery sizing

analysis.

The team attributes

the errors in methodology

and

data to a lack of adequate

design verification.

This issue will remain

open pending confirmation from the

licensee that the subject calculation

has

been formally

revised

and supports

the plant's current design

configuration.

This is identified as inspection

item

50-528/88-01-07.

c.

Ade uac

of DC Volta e

'he

team reviewed the

DC cable sizing calculation to

verify the adequacy

of- the power cables

selected

to

provide adequate

voltage at equipment.

The team observed

weaknesses

in the verification of

assumptions

and results of the calculation,

and also

apparent

typographical

errors in a design equation

and

calculation tabulation headings.

Assumption

1 assumed that the first minute voltage of

the battery will be maintained at 125 volts.

125

volts is more than the

open circuit and

no load

battery terminal voltage,

123.3 volts.

This

assumption

also disagrees

with the analysis

provided

by Exide, for each of the Class

1E batteries,

as

found in Appendix

B of the calculation.

The Exide

calculations

indicate

a minimum first minute voltage

of illvolts.

Assumption

2 stated that in the absence

of vendor

data,

a minimbm of 80K of the rated voltage shall

be

assumed

to be needed at the load terminals during

starting.

On review of the equipment specification

for motors,

the team could not verify the adequacy of

this assumption.

The specification did not address

any requirement for DC motor starting at less

than

105 volts, which is 91.3X on a 115 volt base

(the

motor rated voltage base).

The motor feeder cable voltage

dr'op on full load and

starting for the Auxiliary Feedwater

Regulating Valve

J-AFC-HV-33 is calculated

as 4.6 and 28.41 volts,

respectively,

on sheet

12.

A 4.6 volt drop on full

load violates design criteria ¹2 which states

that

the voltage drop on full load shall not exceed

2.5X

of the rated

bus voltage (or 3.125 volts).

The 28.41

volt drop on starting deviates

from Assumption

2

which states

that the minimum voltage shall

be at

least

SO% (of rated

bus voltage,

125 VDC) or 100

volts.

125 volts (based

on Assumption 1) minus

12.

28.41 volts results in 96.59 volts at the motor

on

starting.

However, the team estimates

that

on motor

starting with the battery voltage at illvolts

(during the first minute

on

a design discharge)

the

voltage at the motor is 82.5 volts.

Since this

voltage

was significantly less

than specified,

and

also did not satisfy the assumed criteria, the

licensee

was requested

to provide justification for

the adequacy of the existing design,

including

confirmation of the required valve torque

and stroke

time on the reduced

motor voltage conditions.

The team

was given the results of a draft re-analysis,

which was prepared

by the licensee

during the inspection,

which indicated that the terminal voltage available at

eight (8)

DC motor operated

valves

was less than

105

volts.

For these

valves the voltage available

ranged

from

89.99 to 103.39 volts.

The licensee

also confirmed that

the resulting stroke time for each valve satisfied the

design

minimum requirement,

although in some

cases

by only

a very small margin.

In the draft analysis

the licensee

utilized the minimum battery voltage condition during

valve operation,

while considering

the actual battery load

as

a design basis.

Therefore,

the team noted that any

future load addition

on the battery requires

careful

consideration.

This issue wi'll remain

open pending confirmation from the

licensee that the subject calculation

has

been formally

revised

and supports

the plant's current design

configuration.

This is identified as inspection

item

50-528/88-01-08.

d.

Essential

S ra

Pond

S stem

SP

The SP, including the essential

spray pond,

serves

as the

ultimate heat sink for the Palo Verde Nuclear Generating

Station.

In the event of a postulated

design basis

loss

of coolant accident

(LOCA), containment

heat

loads

are

transfer red to the ultimate heat sink via the shutdown

cooling system

and

EW.

Upon initiation of post

LOCA sump

recirculation, the containment

heat

removal path consists

of:

Heat transfer from the containment

sump to the

EW via

the shutdown cooling heat exchanger;

Heat transfer from the

EW to the essential

spray pond

via the essential'ooling

water heat exchanger;

and

Heat dissipation to the environment via the essential

spray

pond and the evaporative

spray system.

13

The essential

spray pond contains sufficient inventory to

accommodate

accident heat loads,

reactor

decay heat,

and

auxiliary equipment

heat loads for up to 27 days.

The team reviewed Bechtel Calculation 13-NC-SP-007,

Revision 2, dated

September

25, 1986,

"Spray

Pond Thermal

Performance

Analysis."

The purpose of this calculation

was to confirm the thermal

performance of the spray pond

and the effect of SP bypass

flow on

EC heat exchanger

hot

side outlet temperature.

This calculation

documented

the

input, rationale,

assumptions,

and

summary of results for

a number of computer runs

as required to conduct this

analysis.

The design input indicated that all cases

assumed

an

overall heat transfer coefficient for both heat exchangers

which corresponded

to fouled conditions.

This assumption

may not always

be conservative

when all aspects

of the

total heat removal

system are considered.

The team found

that the analysis did not consider

cases

which could

result in higher essential

cooling water temperatures

and

higher spray pond temperatures.

Two other cases

must be

analyzed to adequately

envelope the total effect of heat

exchanger fouling on system performance

during

a

postulated

LOCA:

Case I.

Clean

shutdown cooling heat exchanger

and fouled

essential

cooling water heat exchanger.

This case

enhances

heat transfer to the

EM while degrading

heat transfer to the spray pond, thus maximizing hot side

essential

cooling water heat exchanger outlet temperature.

The resulting higher essential

cool,ing water temperatures

could exceed

the 125

F design limit imposed

on the system

to satisfy essential

chilled water requirements

for this

accident condition.

Higher chilled water temperatures

'ould affect the capability of the chilled water system to

provide adequate

room cooling to safety-related

equipment.

Case II.

Both shutdown cooling and essential

cooling

water heat exchangers

clean.

In this case

the total heat transfer path is at maximum

anticipated

heat rejection performance

thus maximizing

essential

spray

pond temperatures.

Since the spray pond

system supplies cooling water to the emergency

diesel

generator

equipment,

the resulting higher temperatures,

could exceed

the vendor

imposed 110'F design limit for

this equipment.

In response

to these

concerns,

Bechtel

developed

additional

analyses

addressing"these

cases.

The results

of the calculations

indicate that although cooling water

temperatures

were slightly increased,

design limits would

not be exceeded

in any case.

The team

had

no further

questions

on this issue.

Essential

Chilled Water

S stem

EC

Bechtel Calculation 13-MC-EC-252, Revision 1, is

a

calculation performed to establish

EC equipment sizes.

The team identified the following concerns with this

calculation:

Unverified and undocumented

assumptions;

No basis for design input, e.g., piping lengths,

equipment pressure

drops,

leakage,

system

volumes,

and

pump flow capacity;

and,

Chiller heat load not updated to as built conditions.

The team also reviewed Bechtel Calculation

13-MC-EC-451,

.

Revision 1, dated

September

19, 1984, which were pipe

sizing calculations.

However, this calculation determined

pipe sizes

based

on velocity limitations for the pipe size

selected.

No consideration

was given to the flow

distribution through the piping system to assure

that

component flow demands

could be achieved

based

on pressure

drops throughout the system

and the

pump flow capacity.

This. revision was

made to update the calculation to the

final "as built" piping configuration.

However, only the

line velocities were revised

based

on the "as built" pipe

diameters.

No attempt

was

made to determine

the actual

flows in the system

based

on a hydraulic network analysis

to confirm that design flow rates

could be achieved for

each

component supplied chilled water.

The team found

that the revisions

made were superficial relative to the

more significant update

which would confirm that design

requirements

had

been satisfied.

Neither of these calculations

determined

whether

pump

NPSH

requirements

had been

met.

The team could find no other

calculations

which determined that adequate

NPSH was

available to the essential

chilled water

pumps

under all

operating conditions.

In response

to the team's

concerns,

ANPP provided

preliminary evaluations

which confirmed adequate

NPSH to

the essential

chilled water pump.

The team also reviewed

the results of flow balancing tests for the

EC.

Test

results

demonstrated

that design flow requirements

to the

safety related coolers

were satisfied.

15

In addition,

ANPP:

Agreed that in order to modify the system, all or

portions of the calculation modeling the system will

be revised;

Added statements

to the cover sheet of the

calculation indicating the revisions

and updates

were

required

and must be made to the calculations prior

to performing any design modifications to the system;

and,

Will provide training to the engineering staff on

these

issues.

This is identified as inspection

item 50-528/88-01-09.

Essential

Coolin

Water

S stem

EW

Calculation

13-MC-EW-200, Revision 1, dated

May 2, 1979,

is

a calculation performed to establish

the size of the

essential

cooling water surge tank.

However, the

calculation merely included

a statement

to use

one half

the size of the

Rancho

Seco

(SMUD) surge tank (apparently

a reference

to the Sacramento

Municipal UtilityDistrict

surge tank).

The volume of the tank was calculated

as 1/2

of 2000, i.e.,

1000 gallons,

where

2000 gallons

represented

the

SMUD tank'volume.

There were

no other

calculations to substantiate

the size of the surge tank

considering

thermal

expansion

and contraction,

leakage,

or

to develop operating level setpoints,

or high and low

level alarm 'setpoints.

ANPP submitted

a

new calculation developed

by Bechtel

in response

to the team's

concern to substantiate

the

surge tank size based

on coolant thermal

expansion

and

nitrogen pressurization.

However, there

was

no basis

provided in this analysis

(or any other

document) to

support the selected

level setpoints for the tank.

The

team was concerned that the tank relief valve might not be

, sized to accommodate

flows resulting from coolant thermal

expansion initiated at the level at which makeup supply is

turned off.

This setpoint could be too high to avoid

overpressurizing

the tank should the system

heat

up and

expand at this levels

Based

on preliminary calculations

performed

by ANPP I8C engineering,

the team concluded

that sufficient margin exists in the tank volume to bound

this condition.

However, this observation

remains

open

pending development of final level setpoint'calculations

for the tank.

This is identified as inspection

item

50-528/88-01"10..

Calculation 13-MC-EW-001, Revision 1, dated

September

6,

1985, is

a detailed hydraulic flow network analysis of the

16

EW.

The calculation did not determine

the

NPSH available

to the essential .cooling water

pumps or evaluate

whether

NPSH requirements

had been satisfied.

The licensee

was

unable to find any documented

evidence that this

evaluation

had been performed.

However, the team

independently

determined that sufficient

NPSH was

available to meet

pump requirements.

In general,

the team found that because

of the

use of

conservative

design,

none of the observations

identified as

related to calculations

were safety significant.

However,

these

observations

contributed to the team's

concern that the

depth of design verification is a weakness

in the performance

of design analyses

for Palo Verde safety systems.

Design

verification failed to identify inadequacies

in calculations

or

missing analyses

for all three

systems

selected for review.

Since these calculations

are

used in the development of plant

design modifications, the team was concerned that safety-

related

systems

might be modified in the future without the

foundation of an adequate

design basis to make these

changes.

(3)

Inconsistent

and Erroneous

Desi

n Documentation

ANPP has

developed

a number of documents

and drawings which

have

been identified as design

documents

to be used for design

at

PVNGS.

Examples

include system descriptions,

design

criteria documents,

P8 ID's, and system flow'diagrams.

System

descriptions

contain design basis information, design

parameters,

and

a description of the operational

aspects

of the

system.

Design criteria identify detailed design

requirements

related to each

system.

Flow diagrams

contain in'formation

related to operating pressures,

temperatures,

and flows for

various

modes of system operation.

Based

on conversations

with a number of ANPP engineering

personnel,

the team concluded that:

It is not clear to many engineering

personnel;which

documents

are to be used for design purposes.

Conflicting opinions exist

among

ANPP engineering

personnel

as to whether or not system descriptions

and

flow diagrams

are design

documents

which-may be used for

design.

In addition to this confusion concerning

design

documents,

the

team found a number of examples

where design

documents

contained

erroneous

design information.

For example:-

a

~

Essential

Chilled Water System Description,

Revision 3,

dated October ll, 1983.

Table

EC-2 lists 45

gpm as the minimum required

chilled water flow to the Channel

"A" ("8") DC

'17

Equipment

Room Essential

ACU 8HJA(B)-Z03.

However,

flow balancing

Procedure

No.

91GT-OXX99, Revision 0,

indicates

only 39

gpm was provided during testing

and

flow balancing.

Vendor data identifies

39

gpm as the

minimum required flow to this equipment.

ANPP has

issued

a System Description Revision Notice

(SDRN

149, dated February

12,

1988) to correct this error.

Appendix EC-A identifies the rated capacity of the

chiller as

235 tons with a chilled water flow rate of

400

gpm.

However, the vendor drawing indicates

a

flow of 435

gpm is required for rated conditions to

supply the required

44

F chilled water temperature

at

235 tons.

System flow balance testing confirmed the

435

gpm flow rate.

b.

Detailed Design Criteria for Essential

Cooling Water

System,

Revision 5, dated

November 3, 1983.

Section 1.6 indicates

the

EC interfaces with the safety

injection system

and provides cooling to the HPSI,

LPSI,

and containment

spray

pumps.

The team was advised that

this is incorrect.

ANPP has

issued

a Design Criteria

Revision Notice

(DCRN 1026,

dated January

14, 1988) to

delete

the HPSI,

LPSI,

and containment

spray

pumps

as

being directly cooled

by the

EW system.

c.

Essential

Spray

Pond System Description,

Revision 4, dated

September

27,

1984

'ection

2.6.2. 1 indicates

a Limiting Condition for

Operation

as

a spray pond average

water temperature

of

less

than or equal to 110 F.

However, current Technical

Specifications

(TS) indicate the temperature

is limited to

less

than or equal'o

89 F.

ANPP has

issued

a System

Description Revision Notice

(SDRN 150, dated

February 15,

1988) to correct this error.

d.

Essential

Chilled Water P810,

13-M-ECP-OOl, Revision 22.

Note

2 on this drawing indicates that valves

V228, V229,

V230,

and V231 are locked in their throttled position.

However, the team could find no record of the throttled

position required for these

valves.

The team

was advised

that the valves are locked open

and that the

P8ID is

incorrect.

Subsequently,

ANPP issued

a Drawing Change

Notice

(DCN 82) to the

P8 ID deleting this note.

These observations

are not safety significant since the team

could not identify any consequences

of the errors

made which

would impact safety.

However, the confusion concerning

use of

documents

for design

and the errors identified in design

documents

indicates

a weakness

in design basis

documentation.

Use of the erroneous

information in the development of plant

18

design modifications or procedures

could impact safety.

The

licensee

needs to identify actions to resolve ambiguities

between the design basis

documents

and specifically identify

. which documents

are the design basis

documents.

This item is

identified as inspection

item 50-528/88-01-11.

3.

Plant

Im lementation of Desi

n Basis

A.

Reactor

0 erations Activities

The team assessed

the implementation of a sample of design

parameters

and design parameter

changes

in the operations

area

as

well as

normal operation activities.

The specific operations

attribUtes

examined

included

an examination of operator

and

auxiliary operator training for the selected

systems

and design

changes

to the systems,

valve lineup controls,

knowledge of

operating procedures,

adequacy of the procedures,

auxiliary operator

round sheet

adequacy,

and the adequacy of observing

and reporting

plant deficiencies

by operations

personnel.

The examination of these

areas

and the findings are described

below:

(1)

Failure to Translate

Desi

n Features

Into 0 eratin

Procedures

The

EW consists

of two independent

and redundant

safety related.

flow trains.

Each flow train supplies cooling water to a

shutdown heat exchanger

and an essential

chiller during

emergency conditions or to shutdown the plant.

In the event

the nonsafety-related

nuclear cooling water system

(NCWS) is

not available, e.g.,

during a loss of offsite power, the

EW

supplies

cooling water flow to nonsafety-related

components

in

the

NCWS via cross

connecting piping between

each flow train.

The cross

connect valves

on Train A of the

EW are remotely

actuated

motor operated

valves

(MOVs), while those

on Train

B

are. manually operated,

locked cl.osed valves.

The crosstie piping between crosstie

valves

MOV UV 65 and 145,

and between

the manual crosstie

valves

HCV 66 or 146, is not

designed

to seismic Category I requirements.

Thus in the event

of a seismic disturbance

when the

EW is supplying the

NCWS, the

integrity of this piping cannot

be assured.

Failure of this

piping could result in draining the

EW coolant inventory and

a

loss of level in the

EW surge tank.

On a low water level in

the surge tank, the motor operated crosstie

valves are

automatically closed.

When the surge tank reaches

low-low

level, the tank makeup valve is closed (indicating a major

system leak).

Although high and low level in the tank is

alarmed,

there is no distinction made between the two alarms

(i.e., the alarm is a hi/lo level alarm).

For this case,

tank

low pressure

would be alarmed,

and

an operator dispatched

to

establish

the cause of the alarm.

Since the

EW pumps are rated at 14550

gpm,

a substantial

portion of the

EW inventory could be lost through the 14 inch

19

cross

connect line during the time required. to close the motor

operated isolation valves.

Further, if Train

B were selected

to supply the

NCWS, more inventory would be drained before the

manual

cross

connect isolation valves could be closed.

In response

to the team's

concern,

ANPP engineering

advised

that when the

EW system is cross

connected to the

NCMS, the

cross

connected

EW loop is declared

inoperable

in accordance

with TS 3.7.3.

This requires that two loops

be restored "to

OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least

HOT STANDBY

within the next

6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />."

ANPP engineering

also noted that

operating procedures

reflect this requirement.

The team reviewed Procedure

No.

410P-1EWOl,

Revision 5,

Essential

Cooling Mater System

(EW), Train A, which provides

instructions

and guidance to operators for the operation of the

EM.

However, the team found that Section 8.0 of the procedure

which is entitled

"PLACING EW SYSTEM TRAIN A IN SERVICE

ON THE

NUCLEAR COOLING WATER SYSTEM" contains

no directions or

instructions for the operators

to invoke the'required action

statement

under these conditions.

Although Section 9.0 does

include

a

CAUTION to "maintain

EW loops operable

in accordance

with TS 3.7.3," this section of the procedure is used for

removing Train

A from service

on the

NCWS.

The team concluded

that operators

did not have sufficient guidance to invoke

action statement

conditions

when the cross

connection is

initially made.

The licensee

committed to revise the procedure

to assure that operators

had acceptable

instructions for cross

connecting the two systems.

Further,

based

on conversations

with operations

personne],

the

team determined that operators

had differing opinions related

to

EW operability and were not clear

on declaring the system

inoperable

when the cross connection to the

NCWS is made.

However, in the review of operating history, the team did not

find any case

where the

EW system

(when required

by TS) had

been cross-connected

to

NCMS.

The licensee

in response

to this

concern

issued night orders to all operating

crews at Palo

Verde Units.

Subsequently,

the team discussed

with operators

their understanding

of the problem,

and the selected

operators

indicated that based

on the night order the

EM system would be

declared

inoperable if it was crosstied to

NCWS.

Inade uate

10 CFR 50.59 Evaluation

The essential

spray ponds

serve

as the ultimate heat sink for

the Palo Verde Nuclear Generating Station during emergency

conditions.

They provide sufficient inventory to supply

cooling water to the

SP for 27 days following a

LOCA.

Except

for the cleanup

and chemistry control portions of the system,

the

SP is designed, to seismic Category I requirements.

TMR No. 1-85-CI-377,

Revision 0, dated

September

27,

1985, is a

temporary modification to install tanks to supply hypochlorite

0

20

for the emergency

spray ponds.

The

TNR includes

a 10 CFR 50.59

Safety Evaluation for the temporary

change

which addresses

the

effects of this change related to the consequences

of tornado

generated

missiles.

The Saf'ety Evaluation concludes that the

risk associated

with missiles

which might be generated

by the

tank due to the effects of a tornado are lower than those

previously considered for the site.

However, the Safety

Evaluation did not consider the consequences

of a seismic event

which might result in the failure of the plastic tank or its

anchorage

and cause it to fall into the spray pond.

Further,

the

PVC piping to the spray

pond is not seismically anchored.

In the event of a seismic disturbance,

the potential exists for

the piping and the tank to fall into the pond,

where pieces

could break off the tank or its piping.

If some of these

fragments

were sufficiently small, they could pass

through the

screens

protecting the

ESP

pumps

and become

lodged in the

ESP

pump running clearances,

bearings,

or packing.

There

was

no

analyses

to demonstrate

that failure of the tank and its

associated

plastic piping would not jeopardize

the safety

related

ESP pumps.

USNRC Regulatory Guide l.29, requires that those portions of

structures,

systems,

or components

whose continued function is

not required but whose failure could reduce the functioning of

safety related

systems

to an unacceptable

level should

be

designed

and constructed

so that the

SSE would not cause

such

failure.

In response

to this observation,

ANPP contacted

the

ESP

pump

vendor to confirm that

no damage to the

pump would be incurred

as

a result of small

PVC pieces

which might. enter the pump's

suction.

The vendor,

Bingham International, Inc., indicated

that it was unlikely that such fragments

would interrupt the

operation'of the pumps.

The team reviewed

ANPP's evaluation of

the effect on pump

NPSH and discovered that the failure of the

subject'temporary

modification would not adversely affect pump

NPSH requirements.

The inspection

team concerns

may be summarized

as follows:

Because

the subject temporary modification was installed

for over 24 years,

the effectiveness

of the licensee's

quarterly review program which authorized

the temporary

modifications

and continued implementations

should

be

evaluated.

A licensee

determination that other temporary modifications

currently installed meet the design basis

requirements

of

the associated

system,

structure.,or

component

should

be

considered.

A preliminary response

from the licensee

identified that

a specific type of electrical wiring used

in various temporary modifications in the containment

building are

21

not fire retardant,

and therefore,

do not meet design

requirements.

The licensee

should assure

that the current temporary

modification program will not result in changes

that

degrade

the design basis of the plant.

The team concl,uded that performance of 10 CFR 50.59 evaluation

for the temporary modification was inadequate.

This is a

potential violation and is identified as inspection

item

50-528/88-01-12.

Deficient Air Handl in

Unit

AHU

On January

7, 1988, the team noted

a significant deficient

.

condition on the Essential

AHU. for the motor driven auxiliary

feedwater

pump room.

The deficient condition was that an

inspection

access

panel

in the duct work between the chilled

water unit and the ventilation fan was missing.

The intent of

the

AHU is to draw room air across

the chilled water coils in

the unit (thus cooling the air) and then through the fan and

discharge

the cool air back into the

room to maintain

a

satisfactory

temperature

for the essential

equipment, in the

room.

The effect of having an access

panel

missing between the

fan and cooling coils is that

a significant portion of the

recirculated

room air would bypass

the cooling coils.

Consequently,

the cooling capacity of the

AHU is significantly

reduced.

The licensee

was informed of the condition of the Auxiliary

Feedwater

Motor Driven Pump

Room Essential Air Handling Unit

(Component

1M-HAB-Z04) on January

7, 1988, during the

room

examination.

The licensee

was requested

to determine if the

equipment

was in active maintenance

at that time and to take

appropriate

action if not.

Thirteen days later,

on January

20,

1988,

the licensee

declared

the motor driven auxiliary feedwater

pump inoperable

(due to

the missing access

panel

on the AHU).

The

AHU was'repaired

on

January

21,

1988,

(WR 206249)

and the auxiliary feedwater

pump

declared

operable.

The licensee,

subsequent

to the inspection,

through

an

Engineering Evaluation Request

and testing,

determined that the

AHU remained

operable with one access

panel missing.

However, the condition observed,

a missing access

door

on the

AHU, is contrary to 10 CFR 50, Appendix B, Criterion 5, which

states

in part that "Activities affecting quality shall

be

prescribed

by documented instructions,

procedures

or

drawings...and

shall

be accomplished

in accordance

with these

instructions,

procedures

and drawings."

The applicable

drawing

for the air handling unit is American Air Filter Company

4

22

Drawing No. MC-134-942G, Revision

G, which shows the

AHU Access

Doors installed.

The condition observed is

a potential violation, and is

identified as inspection

item 50-528/88-01-13.

The licensee

should include in his response

to the violation a

discussion

of the ancillary problems indicated

by this finding.

Specifically, what plant material condition controls should

have identified this problem earlier (e.g.,

walkdowns by

operator's,

system engineer

and plant management),

why the

declaration of inoperability of the auxiliary feedwater

pump

was delayed for 13 days,

and what corrective actions

are being

taken in these ancillary areas.

Observin

and

Re ortin

of Plant Deficiencies

The team performed walkdowns

and discussed

observed

deficiencies with plant personnel.

The team observed that the system

walkdown discrepancies

had

not been previously identified during the tours routinely

conducted

by operations

personnel

and system engineers.

(These

discrepancies

are

documented

throughout the report, e.g.,

missing

AHU access

panels.)

These discrepancies

were obvious,

but no maintenance

work requests

(MWRs) were prepared for these

items (preparation of a

MWR is the licensee's

normal

mechanism

for initiating corrective actions for discrepancies

found in

the plant).

The plant manager provided the team with a large

package

of MWRs that had been recently prepared

from

discrepancies

that were found by licensee

personnel

to show

that problems

were being identified.

The team acknowledged this effort, but noted that the

licensee's

program for identifying discrepancies

appeared

to be

not fully effective.

In particular,

there

was nothing readily

available to personnel

performing the tours to indicate what

equipment

had already

been identified as needing corrective

maintenance.

With the large

number of outstanding

MWRs, it

appeared

easy for personnel

to think that

a deficiency had

already

been entered into the system.

Also, it was easy for

people to become distracted

by other activities and forget to

write a

MWR.

This concern

was discussed

with the licensee

management

who indicated that they used "deficiency tags" to

identify discrepancies

through the construction

and startup

phases.

However, it was found that this method

had problems

and the program

was terminated.

However,

as

a result of the

team's

concern,

ANPP management

stated that they would evaluate

the effectiveness

of their present

program for identifying

deficienci'es.

The licensee

s evaluation will be reviewed in a

future inspection

and is identified as inspection

item

50-528/88-01-14.

23

(5)

0 eratin

Procedures

The team examined selected

operating procedures

for general

adequacy

and to determine if selected

design criteria (for the

systems

examined)

had been properly implemented in the

operating procedures.

In general,

the procedures

were found to be clearly written,

reasonably

structured for ease of use,

and contained

proper

verifications where applicable.

The particular procedures

examined

were operating procedures

for the three

systems,

SP,

EW, and

EC (including valve lineups)

and auxiliary operator

round sheets.

Certain positive

and negative findings were

made

as discussed

below:

a.

Procedure

Stren th

Re ardin

Procedure

Feedback

Re orts

The licensee

appears

to have

an effective,

easy to use

vehicle to allow plant personnel

to suggest

changes

to

procedures.

The licensee's

system,

called the "Procedure

Feedback

Reports," allows any member of plant staff to

formally suggest

a procedure

change,

have that suggestion

evaluated,

and receive

a disposition of his suggestion.

Procedure

change

suggestions

are evaluated

by the

procedure writing 'group (for operations,

The Operations

Standards

Group)

and implemented in all three units if

applicable.

b.

Procedure

and Hardware

Weakness

Re ardin

Annunciator

~Res

oose

Control

Room observations

by the team led to the

conclusion that operator

response

to nuisance

alarms

was

being performed inappropriately,

and further,

an

administrative procedure to describe

the proper response

expected of operators

did not exist.

As an item of background,

the number of annunciators

"in"

at a given time is a well discussed

issue with the

licensee,

has

been discussed

with licensee

management

at

several

regional

meetings

and the licensee's

corrective

actions regarding annunciator reduction are well

documented

and underway.

The team's

observation

did not

deal with this issue.

The team observed

10 to 12 annunciators

in "fast flash,"

but with no audible alarm.

The reason that this condition

is inappropriate is that each annunciator

window can and

usually does

have

more than

one input.

Four or five

inputs per window is typical.

At Palo Verde,

due to the

nature of the annunciator'wiring logic, when

an

annunciator

is in "f'ast flash" due to a

known recurring

I

24

nuisance

alarm (one input), it is nonetheless

precluded

from warning the operators

of an adverse

condition from

one of the other possible

inputs to the window.

That is,

fast flash precludes

other inputs from annunciating.

The annunciator circuitry at Palo Verde allows the

operator to acknowledge

the alarm partially by pushing

a

button which stops

the audible alarm.

This is a sensible

human factors feature which reduces

noise level but leaves

a flashing window to alert the operator that the condition

existed.

However, leaving the window in that condition

would blind the operator to further inputs to the

annunciator.

Nuisance

alarms

are

an occasional fact-of-life due to the

number

and complexity of alarm circuits.

It is equally

poor to have operators

spend their time continuously

answering

a spurious frequently occurring "alarm, diverting

them from other duties.

Therefore,

most sites

have

a method by which a single

nuisance

alarm input to an annunciator

window can be

removed from service until the problem is found and fixed,

but leaving the other inputs to the window active and able

to cause

a "reflash."

Palo Verde did not have

such

a

method at the time of inspection.

It should

be noted that the operators

are not totally

blinded to the other inputs to an annunciator in fast

flash.

They also

have

CRT displays which will print any

alarm coming in, and dependent

on the attentiveness

to

this screen,

the input could be noted.

However, this

screen

does not have

an audible alarm and consequently,

the'probability of rapid recognition of a

new input is

reduced.

In response

to the above observations,

the licensee

committed to examine other methods of dealing with

nuisance

alarms,

which wi 11 preserve

audible annunciation

of other inputs,

and to examine proceduralizing

the

expected

operator

actions in dealing with nuisance

alarms.

This item will be followed up in a future inspection

(inspection

item 50-528/88-01-15).

0 eratin

Procedures

Not In A r cement With Hi her Order

Desi

n Documents

The team examined selected

operating procedures

for

agreement

with higher order design

documents

to ensure

that design information was properly implemented in plant

procedures.

The design input documents

examined

were the

P8 IDs for the

SP,

EW, and

EC systems

and the vendor technical

manual for

25

the

for

Log

Essential

Chiller Units (Carrier Instruction Manual

19FA Hermetric Centrifugal Liquid Chillers - Bechtel

No.

13-10407-M723-213,

Revision 12).

The team identified several

instances

where design

document requirements

were not properly implemented in

procedures

and was informed by operations

standards

personnel

of an improper latitude taken

by the group to

change

procedures

in advance of having design

documents

changed.

Specific Examples of the above are:

S ra

Pond Crosstie

Valves

The normal operating position of spray pond crosstie

valves

HCV-207 and

HCV-208 were changed in operating

procedures

(e.g.,

410P-ISPOl)

from a normal position

of "open" to a normal position of "closed" in

Revision

1 to the procedures

issued

August 16,

1984.

The controlling design

document,

P8ID 13-M-SPP-001,-

was not likewise changed until much later,

specifically by

DCN 65 to 13-M-SPP-001,

Revision 16,

issued

December 8, 1987.

The

P8 ID should

have

been

changed

before the implementing operating procedures

were changed.

Ex ansion

Tank Water Level

Ga es Isolation Valve

Positions

Im ro er

P8ID drawing 01-M-ECP-001,

Revision 10,

a controlling

design

document for the

EC,

has

a note for expansion

tank level

gages

LG 19 and

20 that states,

"Open

LG

inst valves for test only."

This appears

to be an

appropriate

note since the

P8 ID shows that the level

gages

are non-seismic

attachments

to the seismically

designed

expansion

tank.

The team examined

these

valves

and found them to be open contrary to the

P8ID.

Fur ther, the operating procedures

41 OP-1

EC

Ol, 02 require these

valves to be normally open

(Appendix E) contrary to the

PAID.

During the inspection,

the licensee

examined the

situation

and determined that leaving the level

gage

isolation valves

open

was satisfactory

due to flow

restriction devices

and issued

DCN 81 to

13-M-ECP-001,

Revision 22,

on January

28,

1988, to

rectify the situation

by changing the PAID.

A similar situation

was noted by the team

and

corrected

on the Essential

Cooling Water expansion

tank level

gage isolation valves, by

DCN 39 to drawing

13-M-EWP-006, Revision 14, issued

January

28,

1988.

The operating procedures

should not have

been

issued with

requirements

different than those

shown

on the

P8 ID.

The

responsible

procedures

group personnel

and supervision

indicated to the team that changing

implementing

procedures

prior to requesting

engineering

approval to

P8 IDs is not uncommon.

The procedures

group indicated

that engineering

concurrence

can sometimes

take

up to a

year to obtain.

The team discussed

the need to have

a

clearly understood

and implemented

design

document

hierarchy

and that changes

to implementing procedures

without clear documented

engineering

approval

was

inappropriate.

Licensee

actions

in this regard will be

reported in a future inspection report.

This is

identified as inspection

item

50-, 528/88-01-16.

d.

Essential

Chiller Sum

Oil Tem eratures

Im ro er

The team examined

the vendor technical

manual for the

essential

chi llers.'hese

are large self-contained

refrigeration units which provide chilled water for

essential

room cooling.

The team also examined the auxiliary operator

round sheets

in the areas pertaining to the chiller units to verify

that operators

were indeed checking operating

parameter

values

recommended

by the vendor (or officially changed).

The team found that the chiller oil

sump temperatures

were

not being checked for the'roper

temperature

values.

The vendor

recommends

a

sump oil temperature

of 140-

150'F maintained

by electric heaters

when the unit is in

standby conditions.

However, the auxiliary operator log

sheets

check that

sump oil temperature

is 130 - 170 F,

which is not in agreement with the vendor recommendations.

Hi

h Oil Tem erature

At the close of the inspection,

the licensee

committed to change

the Operating

Department

Guideline

(ODG) No.

15 to reflect the proper

high oil

temperature

value

(150

F vs 170 F).

The licensee's

tracking of this item is considered sufficient and

further

NRC tracking does

not appear warranted.

Operations

personnel

stated that high oil temperature

had not been

a problem (i.e.,

above

150 F).

Additionally, the chiller operating procedure for

manual start

(410D) contains

the proper values for

sump oil temperature.

27

Low Oil Tem erature

Although the auxiliary operator

round sheets

(ODG-15)

required the operator to check that the

sump oil

temperature

was greater

than 130~F,

whereas

the

vendor required 140'F, the licensee

demonstrated

that

they had processed

a change (after contact with the

vendor) to authorize the change.

Specifically,

Engineering Evaluation Request

EER 87-EC-007

was

initiated February

28, 1987,

and approved July 17,

1987, which recommended

the

ODG-15 change.

However, in reviewing the supporting information, the

team noted that the vendor's letter of response

to

the licensee

dated

June

30, 1987, stated that they

had "no problem" with the licensee's

change,

but added

"however, with the cooler startup temperatures,

oil

foaming could become

a problem, this in turn will

cause

the chiller to trip on oil pressure

during

these startups."

The team discussed

this apparent

di,sclaimer

by the vendor with the system engineer.

The system engineer

considered that Palo Verde had

sufficient operating experience with their essential

and non-essential

chillers to show that low oil

pressure trips

on starting would not be

a problem.

Im ro er 50.59 Review of Oil Tem erature

Chan

e

In view of the vendors

apparent disclaimer,

the team

reviewed the

10 CFR 50.59 evaluation

done for EER

87-EC-007

on July 8, 1987.

That review requires'he

engineer to determine if the "probability of. a

malfunction of equipment

important to safety

be

increased.""

In this case,

the engineer

checked

"no"

and thus precluded the licensee's

Plant Review Board

(PRB) from agreeing

or disagreeing with this

decision.

The licensee

committed to further resolve with

the vendor. whether

an increased probability of low

oil pressure trips on starts is an actual

concern

and to have that decision properly reviewed by the

PRB.

This is an unresolved

inspection

item

50-528/88-01-17.

Weaknesses

in Precise

Acce tance

Values

on Round Sheets

Although operator

round sheets

were structured to tell the

operator

specific parameters

to be checked with the

acceptance

values,

several

examples

were noted where the

information was not precise.

In accompanying

an auxiliary

operator

on rounds,

the team determined that the required

values

were not clearly understood

and assumptions

were

made.

28

Although no operability questions

were raised

from further

examination,

the licensee

committed to revise the round

sheets

to describe

more precisely the parameters

required

to be checked.

Examples of lack of preciseness

are:

Freon level, in X of sightglass,

was given only for

the high level (75K); no value

was given for low

level.

Compressor oil level, in X of sightglass

was given as

25 to 50K, whereas

there is no sightglass

installed

but rather two bullseyes.

The operator explained

what 25 to 50K "probably meant."

In view of the licensee's

commitment,

no specific

NRC

'follow-up of this item is considered

warranted.

(6)

0 erations Trainin

on Desi

n Chan

es

The area of operations training has

been previously examined at

Palo Verde and is the subject of ongoing actions for

improvement.

For this inspection,

the narrow subject of design

change

implementation training was examined.

Specifically, for

selected

design

changes,

were operations

personnel

trained

on

the changes prior to operating

changed

systems.

Two DCPs were selected

dealing with changes

in alarm setpoints

for the Spray

Pond Level

and Temperature, i.e.,

PCP

85-01-,SP-037-00

and

PCP 85-01-SP-025-00.

The 1985 design

changes

were completed

and accepted

on November 18,

1986 and

January

7, 1986, respectively,

indicating all work was done,

testing completed

and necessary

procedures

changed.

The team reviewed the most recent training lesson plan for the

subject.

That was

Lesson Title Essential

Cooling Water and

Spray

Ponds

(NLC 22-00-RC-013-0A),

Revision A, dated July 19,

1987.

The team found that the training lesson plan (revised at least

seven

months after the design

change

acceptance)

did not

reflect the proper alarm setpoint for spray pond temperature

(Reference training plan page

27, Item B. l.a., "Instrumentation

and Alarms" ).

The training plan referenced

the spray

pond

temperature

high alarm as 95'F whereas

the technical

specification limits the temperature

to 89~F and 'the design

change

had lowered the alarm setpoint to 87 F.

However, the

same training plan described

an "administrative limit of" 89'F

(reference training plan

Page

2 Objective E014).

Further investigation revealed that the training department

administrative control method for factoring in design

change

information to training is described

in Procedure

No.

29

8I718.07.05,

Revision 0, dated July 28,

1986,

"Updating

ANPP

Training."

For design

changes

the system

depends

on a member

of the training department,

the training auditor, to review all

design

changes

and determine if the information is pertinent

for training.

In the case of the two design

changes

examined,

the team found

that the training auditor had reviewed the changes

on

January

29,

1986 and October 29, 1985, respectively,

and

determined that there

was

no impact

on the training program,

procedures,

or activities.

This apparently

erroneous

decision

was discussed

with the training auditor who stated that

he

understood

the setpoints

were not taught in training.

Based

on

that decision,

he did not .forward the design

changes

to

training personnel

for incorporation in lesson plans.

The training manager

committed to strengthen

the design

change

review process.

The tr'aining manager also indicated that the

training department

does not generally review design

changes

for training changes until after they are completed.

He

further indicated that in the case of operations,

the

operations

department is depended

on to provide the information

to the operators

in a timely way,

and that training may take

several

months to factor in and administer training on changes.

The operations

department

manager for Unit 1 indicated that

pertinent. information was passed

on to the operators

in several

forms, specifically night notes

and incident reports.

Additionally, he stated that procedure

changes

are required to

be read

and initialled but that

no systematic training on

design

changes

was performed,

but was probably largely covered

by the procedure

change

reviews.

The licensee

committed to examine the training given in regards

to design

changes,

with'mphasis

on

a systematic

method of

ensuring

necessary

information is provided to operations

personnel

when changes

are

made to the systems

they are

operating.

The area will be examined during

a future

inspection.

This is identified as inspection

item

50-528/88-01-18.

B.

Maintenance Activities

The team reviewed the licensee's

corrective

and preventive

maintenance

programs.

This was accomplished

by performance of

system walkdowns,

review of equipment configuration control, review

of the role of system engineers

in the maintenance

process,

observation of maintenance activities,

and

a review of maintenance

data.

In addition, the team reviewed selected

portions of the

licensee's

operating

experience

review program

as it related to

specific maintenance activities.

30

(1)

S stem Walkdowns

The team conducted

walkdowns of the

EC Train A, the

EW Train B,

and various other peripheral

mechanical

and electrical

components,

such

as electrical

panels

and terminal

boxes which

supply power to components

in these

systems.

The purpose of

.

these

walkdowns

was to compare the as-built status of the plant

to the design drawings,

review the cleanliness

of the system

components

and areas,

and to determine

the operability of the

systems

from a maintenance

standpoint.

In general,

the components,

systems,

and areas

inspected

appeared

satisfactory

from a housekeeping

standpoint.

However,

during these tours,

numerous

discrepancies

were found.

An.

example of these

discrepancies

was temperature

elements

EW

TE 154 and 156,

and their respective

terminal box,

1MEWNPOlBT,

for the bearings

on,the "B" Train

EW pump.

These

showed signs

of internal corrosion

due to excessive

water leakoff from the

bearings

on the

pump.

This in-leakage

appeared

to have

been

occurring for quite

a long time.

Discussions

with the system

engineer indicated that the bearing leakoff had, at times,

been

extreme.

It was obvious that

no effective corrective action

had been

implemented

due to the amount of corrosion within

these

components.

The system engineer stated that

a design

change

had recently been submitted to change to a mechanical

seal

on the

pump (this change

should preclude

leakage of water

into these

components).

Other examples of deficiencies

consisted of dirt, debris,

and construction

acceptance

tags

found in junction boxes

and breaker enclosures..

More

noteworthy discrepancies

are discussed

in the paragraphs

below.

All discrepancies

found during the system walkdowns were

identified to the licensee for corrective action.

(2)

E ui ment Confi uration Control

During the performance of system walkdowns, the team noted

a

number of equipment configuration control problems.

The team

toured the

EC and

EW system

rooms in addition to the vital

battery, battery charger,

and static inverter rooms.

The

problems identified to the licensee

were

as follows:

Electrical

Panels

Missin

Bolts

Several

panels

and breaker enclosures

were found to have

missing cover bolts.

In particular, vital static inverter

1-E-PND-N14 was missing

9 of the

19 cover bolts

and vital

static inverter 1-E-PKD-N44 was missing

12 of the

19 panel

cover bolts.

This configuration was not in accordance

with drawing 543-201-4.

The team questioned

the licensee

as .to the ability of panel

1-E-PND-N14 to withstand

a

seismic event under 'this configuration.

This item is an

additional

example of a potential violation, inspection

item 50-528/88-01-19.

31

b.

Vital Batteries

The team found that the 120

VDC Class

1E vital batteries

were installed in accordance

with the vendor

recommended

design

and design

drawings with one exception.

The one

case identified was the lack of, the cylindrical plastic

spacers

which were required to be located

between

some

battery jars in accordance

with drawing 13-10407

EA-15467,

Sheet

3 of 6,

and drawing E050-86,

Sheets

1 and 2.

In

particular, vital battery "A" was missing two spacers,

vital battery "D" was missing two spacers,

and vital

battery "B" was missing three spacers.

The team discussed

the requirements

for these

spacers

to be installed with a

battery manufacturer

representative.

These discussions

revealed that the spacers

were inserted

between the jars

during initial installation of the batteries.

They were

required for alignment only and serve

no other purpose

such

as seismic restraint.

However, the team

was

concerned that these

spacers

were

somehow

removed

and

design

drawings were not updated to show this

configuration chang'e.

The lack of control over the

configuration of these

components

is a further example of

a potential violation and is identified as inspection

item

50-528/88-01-20.

c.

Batter

E ewash Stations

During the tours, the team noted that the licensee

had

installed permanently

mounted battery

eyewash stations

in

the vital battery

rooms.

The team questioned

the ability

of the mounting configuration to withstand

a seismic event

from a position retention standpoint (licensee's

seismic

category

9 requirement).

The team requested

the

calculations/documentation

for the eyewash station's

qualification.

The licensee

reviewed existing

documentation

and found that the calculation isometric

drawings did not show the existing configuration for the

eyewash stations.

Therefore,

the licensee

performed

an

engineering

evaluation of the existing eyewash

configuration to satisfy the team's

concerns.

The results

were documented

in engineering evaluation

request

(EER)

88-DS-001

and 88-DS-002.

In these

documents,

the licensee identified that the

existing configuration met seismic category

9

requirements.

However, the licensee

also identified that

there were discrepancies

between the as-built

configuration and the design

drawings for all

3 Units.

The discrepancy

was that the existing drawings only showed

the main header

up to the work point (first couple of pipe

supports) for the emergency

shower

and eyewash stations.

The last

10 feet of piping was field installed,

but the

calculation isometric drawing,

13-MC-DS-511,

was not

revised to show the arrangement

of the eyewash stations.

32

As a result,

the actual

mounting arrangement

could vary in

distance

from the wall or in height of the station.

This

would alter the actual

loading to some degree.

Also, one

of the eyewash stations

only had one pipe support.

The

remaining three stations

had two.

The calculations

were

based

on

a standard configuration which was different than

the actual installed configuration.

Therefore,

the

calculations

had to be re-performed to verify that the

stations

met seismic category

9 requirements.

Again, the team

w'as concerned that the missing battery spacers

and

the missing bolts from the static inverters

had not been previously

identified and, indicated

an inadequate

thoroughness

in work

completion by maintenance

personnel,

and closeout verification by

gC.

Tours were conducted

on

a routine basis

by operations

personnel

and system engineers,

in addition to the performance of preventive

maintenance

and surveillance activities

on these

components

by

personnel.

The team considered that in addition to an evaluation

of the effectiveness

of their program for performing system

walkdowns, the licensee

should evaluate

the tr aining that

maintenance

and surveillance

personnel

receive

on restoration of

equipment to its original configuration.

The licensee's

program for

restoration of equipment will be further evaluated.

The lack of'icensee

controls over the configuration of these

components

is another

example of a potential violation and is

identified as inspection

item 50-528/88-01-21.

(3)

Observations

and Review of Maintenance Activities

The team reviewed Preventive

Maintenance activities

(PMs) for

selected

pumps, valves,

and instruments

in the essential

cooling water, essential

chilled water,

and spray

pond systems.

The team also reviewed

PMs and surveillances for the vital and

emergency lighting batteries

and observed

maintenance

in-

progress

on other components.

This was

done in order to

determine if the equipment

had been properly maintained

and

vendor

requirements

were reflected in the licensee's

programs.

The observed

PM and corrective maintenance activities were

on

the stuck control element

assembly, vital and emergency

lighting batteries,

and the battery charger.

The team verified

that the required administrative approvals

had been obtained

prior.to initiation of work, that independent verification

requirements

were established

and performed

(when required),

that the craft identified discrepancies

and anomalies properly,

and that corrective actions

were initiated when discrepancies

were found.

a.

Emer enc

Li htin

Batteries

During a tour, the team identified a substantial

amount of

negative plate degradation

in the Unit 1 and

2 emergency

33

lighting batteries.

This was evidenced

by negative plate

material that formed a sediment at the bottom of the

battery jars.

This sediment

was attracted to the positive

plates

and formed an internal discharge

flowpath (short

circuit) within the jars.

The team identified this

concern to the licensee

for the Unit 1 batteries,

1E-QDN-F01 and QDN-F02.

Coincidentally, the annual

burn

(capacity) test for these batteries

was

due in February

1988.

The licensee

conducted

the test

and fouhd the

batteries

to satisfactorily meet their capacity

requirements

established

in

WO 00273899

Task No.

054992.

The requirements

established

a voltage

minimum of 107

VDC

and

an illumination minimum of 6 foot candles for lights

in the control

room horseshoe

area.

Upon completion of

the test,

the licensee

attempted to perform an equalizing

charge to restore

the batteries

to their fully charged

state.

However, the batteries

could not be recharged

after the test because

of the significant degradation

which was apparently

due to float charging at too high a

voltage

or other

unknown factors.

In 1986, the licensee identified in licensee

event report

(LER) 86-59 and Supplement

1 to the

LER, that

PMs had not

been performed

on batteries

lE-QDN-F01 and QDN-F02.

In

this

LER, the licensee identified corrective actions to be

taken to ensure that these batteries

were tested at

required frequencies.

Since then,

ANPP had been

performing

PMs on these batteries,

but nobody had

evaluated

the results of those

PMs to determine if a

negative trend was in progress.

For additional corrective actions of a generic nature,

the

licensee identified in a memorandum

dated

June

17, 1987,

that they had evaluated

the adequacy of the testing

programs for other

non

TS components.

The team reviewed

this memorandum

and noted that the licensee

only

identified that

PMs existed for these

non

TS items.

They

did not verify that the

PMs were in fact being performed

at the required frequencies.

The team noted that

procedure

30AC-9ZZ02, Revision 4, "Preventive

Maintenance,"

allows for waiving non

TS related

and

non

licensing commitment related

PMs

up to 3 consecutive

times

by the planner coordinator.

The team did not find any

evidence that this information

(PM waiver) was supplied to

the system engineer or any central point of contact.

As a

result,

the team

was concerned that

a valuable

source of

trending data could be waived without responsible

engineering

personnel

being aware.

Review of the

licensee's

PM program with regards

to the practices of not

trending maintenance

and test results

and of waiving PMs,

in particular, with respect to batteries

lE-QDN-FOl and

QDN-F02, will be reviewed in a future inspection effort

and is identified as inspection

item 50-528/88-01-22..

0

34

120

VDC Vital Batteries

The team verified that proper survei llances

were performed

for the

120

VDC vital batteries

in accordance

with

IEEE-450.

In addition, the team verified that these

batteries

were maintained in accordance

with the

manufacturer's

recommendations

with one exception.

The

team found that the licensee

had

no criteria for selecting

battery pilot cells.

The vendor

recommended that pilot

cells (used to monitor average battery jar performance)

be

selected

based

on certain criteria and changed yearly.

The yearly change of cells was

recommended

in order to

prevent

removal of too much electrolyte which could effect

the jar performance

and

skew surveillance results.

The

team found that nobody

knew how the pilot cells were

selected.

Apparently during startup,

the engineer

established criteria and selected

the pilot cells.

However, after the plant was licensed,

the. responsibility

for performance

of tests

was switched to the surveillance

program.

At that time, the criteria for selecting pilot

cells was

removed

from the surveillance test.

As a

result,

the

same cells

have

been

used

as pilot cells since

then.

The team identified this concern to the licensee.

The licensee

committed to update their program to assure

acceptable pilot cell selection.

No further followup is

necessary:

The team

was concerned that the vital batteries

may be

susceptible. to similar degradation

of the plates

as

was

found on the emergency lighting batteries

because

of the

high float voltage that the vital batteries

experience.

The licensee

set the float voltage criteria at 134 to 136

volts.

This was

done in response

to electrolyte

stratification that

had been experienced

at lower float

voltages.

The reason for this stratification was never,

identified.

For corrective action,

ANPP obtained

vendor

concurrence

to operate

the batteries at the higher float

voltage.

However, operating the batteries at.a higher

float voltage could have impact on their operable lifetime

and

any deleterious

effects of operating at this higher

range would go unnoticed in the absence

of a formal

trending program.

The licensee

responded

to the team's

concern

by stating that they would evaluate

the

possibility of operating the batteries

in a lower float

voltage range.

In addition, the licensee

indicated that

they were in the process

of gathering information from the

system engineers

to further

advance

the status

of the

trending program.

The fact that the maintenance

department,

the surveillance

department,

or the system engineer did not know how or

who

selected

the pilot cells or that nobody was concerned

about the

state of the emergency lighting batteries until the

NRC raised

0

35

a question,

were examples of the poor coordination

between the

various organizations.

Data

Base

Reviews

The team reviewed the outstanding

maintenance

work request

and

maintenance

work order list for Unit 1.

The licensee

was

generating

MMRs at the rate of about

120 to 150 per week for

Unit 1 only.

Thus, there were

a substantial

amount of

outstanding

items.

Most of the items reviewed

by the team

seemed to be minor in nature.

The licensee

indicated that

these

would be worked as time permitted.

However, the backlog

of maintenance

items

has

been

a continuing source of concern

within Region

V.

The team reviewed the implementation status of the nuclear

plant reliability data

system

(NPRDS).

As of this inspection

pe'riod,

the licensee

had completed the data

base for all three

Units.

The Institute for Nuclear

Power Operations

(INPO) had

accepted

99K of the data

base for Unit 1, with the other

two

Units to follow.

The licensee

was in the process

of inputting

the failure analysis for the three Units.

ANPP had the ability

to retrieve information on failures at other sites.

However,

the team noted that they were not retrieving this information

on a systematic

basis

since the

NPRDS utilization had not been

initiated as of this inspection.

0 eratin

Ex erience

Review Pro

ram

The team attempted

a review of the licensee's

program for

maintenance

and surveillance of system

manual isolation valves.

However, the team found that the licensee

did not have

a

program to perform surveillances

(e.g., stroking) or

PMs (e.g.,

stem lubrication) of these

type valves.

Examples of these

were

the spray pond cross

connect valves

and locked manual

system

isolation valves.

Discussions

with the licensee

indicated

that they only check valve position of these

valves.

This issue

was discussed

in IE Notice 86-61, "Failure of

Auxiliary Feedwater

Manual Isolation Valve," which was issued

July 28,

1986.

This IE Notice discussed

the failure of manual

isolation valves (in particular,

an auxiliary feedwater

(AFM)

manual isolation valve)

due to the lack of a preventive

maintenance

program.

In this case, it resulted in the valve

being inadequately

lubricated which caused

the valve to seize.

This item was also discussed

in NUREG-1195, Section 5.3.

The team questioned

the licensee to determine

what actions

they had taken to address

the concerns identified in IE Notice

86-61.

In this case,

the Licensing Department which was

responsible for tracking the item,

and the independent

safety

engineering

group (ISEG), which was responsible for initial

review of the Operating

Experience

Review item, sent this

Notice to the Maintenance

Department

and requested

that

a

36

review be

made to determine if corrective actions

were

required.

However,

as of this inspection period,

no response

had been sent to Licensing.

The team reviewed procedure

ES05.03,

Revision 0, "Operating Experience

Review,"

and noted

that, in the case of major concerns,

responses

were required to

be sent back to Licensing within 30 days.

Major concerns

were

considered

to be IE Bulletins or high priority IE Notices.

Discussions

with the licensee

indicated that actions

on the

information provided in this Notice were considered

to be

of'ow

priority.

The team did not dispute this, but was concerned

that more than

a year

and

a half had elapsed

since the issuance

of this Notice without -any corrective actions identified (not

even

a response

from the responsible

organization).

The

licensee

stated that informal discussions

had taken place.

It

was believed that this was

a problem that was unique to the

site identified in the IE Notice; but, it was not a problem at

Palo Verde.

In addition, it appeared

that

no final decisions

were

made

and that nobody was quite sure

when these

informal

discussions

had taken place.

As a result of the team's

concerns,

the licensee

indicated that

they would review this item to determine if and

how a program

'should

be implemented to perform

PMs and/or surveillances

on

system

manual isolation valves.

The licensee's

evaluation will

be reviewed

and is identified as inspection

item

50-528/88-01-23.

The Licensing Department indicated that, in general,

long

overdue

responses

to the licensing commitment tracking system

(LCTS) are flagged to the responsible

organization.

Flagging

of this particular item to the responsible

organization

was not

verified by the team.

The team

had several

additional

concerns

over the licensee's

operating experience

review program:

(1)

the program allows

an infinite amount of time for the

responsible

organization to make

a response

on non high

priority items,

(2) the long lack of a response

was not

identified to the next higher level of management

for

resolution,

(3) the licensee

did not review this Notice with

sufficient detail to determine if it was applicable to Palo

Verde and,

(4) the seriousness

of the loss of ability to

operate

a system

manual isolation valve was apparently

not

considered.

The team identified these

concerns

to the licensee

for evaluation.

This evaluation will be reviewed

and is

identified as inspection

item 50-528/88-01-24.

(6)

Motor 0 crated Valve Testin

Discussions

with ANPP personnel

indicated that several

motor

operated

valve

(MOV) motors were found to be marginally sized

to perform their function.

These

motor operators for MOVs

SI-604 and SI-,609, in the safety injection system for all

3

Units, were subsequently

replaced.

The improper sizing was

found during performance of motor operated

valve analysis

and

testing

(MOVATs) of these

valves.

The team discussed

the

37

licensee's

program for performing testing of motor operated

valves.

The valves required to be tested

by IE Bulletin 85-03,

"Motor Operated

Valve Common

Mode Failures

During Plant

Transients

Due To Improper Switch Settings,"

have

been

completed.

However, the team questioned

the licensee

to

determine if they planned to extend their valve testing program

to all safety-related

valves.

This was

due to the team's

concern that marginally sized motors or associated

problems

with other safety-related

valves could exist.

The licensee

stated that they were evaluating the

need to extend the

MOVATs

program to other valves.

The licensee',s

evaluation will be

reviewed in the future.

This is identified as inspection

item

50-528/88-01-25.

Surveillances

Instrument Calibration

and Monitorin

Pro

rams

(1)

Surveillance

Pro

ram

The licensee's

surveillance

programs for the

EW, the

EC,

and

the

SP were reviewed to determine their conformance with, the

plant

TS surveillance

requirements.

The following procedures

were examined

by the team:

Procedure

73AC-9ZZ04, "Surveillance Testing"

Procedure

73AC-1ZZ24, "Technical Specifications

Surveillance

Requirements

Cross-Reference

- Unit 1"

The first procedure

describes

the methodologies

and

responsibilities

requisite to the administration

and

implementation of the surveillance

testing program.

The second

procedure

provides

a complete cross-reference

of the Unit 1

standard

TS surveillance

requirements

and associated

test

procedures.

The following TS surveillance

requirements

were reviewed along

with the licensee's

implementing

and surveillance

procedures:

TS Section 4.0.5, "Surveillance

Requirements

for Inservice

Inspection

and Testing of ASME Class

1,

2 and

3

Components"

The team discussed

the

NDE program with the lead ISI

engineer

and examined the following two procedures

which

are applicable to the three Class

3 systems

(EW,

EC,

and

SP) under inspection:

Procedure

No. 73TI-9ZZ13, "Visual Examination for

Leakage"

t

Procedure

No. 73TI-9ZZ18, "Visual Examination of

Support

Components"

38

The NDE'rogram requires

a visual examination for leaks

during a functional/pressure

testing of Class

3 piping

systems

every ten years.

Welded attachment

and pipe

supports/hangers

on piping systems

greater

than

4 inches

in diameter shall also

be inspected

every ten years.

One-third of the Class

3 piping systems

and supports

are-

inspected

in a three

and

a half year period.

Since Unit 1

is still in its first three

and

a half year period,

no

inspections

of the

EW,

EC,

and

SP systems

have

been

made.

The inspection effort to date

has

been devoted to the

Class

1 and Class

2 piping systems.

The team examined the programs

for functionally testing

pumps

and valves

as described

in Procedure

73AC-OZZ30,

"Inservice Testing of Safety Related

Pumps

and Valves."

Pumps

and check valves are functionally tested quarterly

(every 90 days)

under the following surveillance test

procedures:

41ST-1EC02,

"Essential

Chilled Water

Pump

Operability"

41ST-1EW02,

"Essential

Cooling Mater

Pump

Oper abi 1 ity"

41ST-lSP02,

"Essential

Spray

Pond

Pump Operability"

73ST-1ZZ05, "Section XI Check Valve Operability,

Normal Operations"

Some twenty-seven surveillance

records for pumps

and check

val.ves performed over the past two years in the three

systems

under inspection

were examined to verify

compliance with TS requirements.

The records

appeared

to

satisfy the

TS requirements

and conformed to the

surveillance

procedures.

The relief valves are off-line set

and pressure

verified

every five years in accordance

with Procedure

73ST-9ZZ20,

"Section XI PSV Off-Line Pressure Verification."

During

the first refueling outage,

three relief valves

SPAPSV-0029,

SPBPSV-0030,

and

SPAPSV-0141

on the

ESP

system were set

and pressure

verified.

These

are the only

relief valves of the systems

under inspection tested to

date.

The surveillance test

packages

for these

valves

were examined

and found to conform to the above procedure.

The following TS surveillance

requirements

with the

applicable

implementing procedures

were inspected

by

examining the appropriate

procedures

and reviewing past

surveillance

records:

TS 4.7.6. 1, "...demonstrate

two

ECW loops operable

every

31 days

by verifying positions of those valves

39

(manual,

power operated,

or automatic) -- not locked,

sealed

or otherwise

secured

in position."

This

surveillance

requirement was.performed

under

procedure

41ST-lECOl, "Essential

Chilled Water Valve

Ver ificati on. "

The following surveillance

requirements

were

performed under surveillance

procedure

40AC-OZZ06,

"Locked Valve and Breaker Control."

"Once per

18 months during shutdown, verify that

each valve (manual,

power-operated,

or

automatic) servicing safety-related

equipment

that -is locked, sealed,

or otherwise

secured

in

position, is in its correct position for:"

TS 4.7.3.d

Two independent

essential

cooling

water loops.

TS 4.7.4.2

Two independent

essential

spray

pond loops.

TS 4.7.6.2

Two independent

essential

chilled

water loops.

"At least

once per 31 days

by verifying that

each valve (manual,

power-operated,

or

automatic) servicing safety-related

equipment

that is not locked, sealed,

or otherwise

secured

in position, is in its. correct position."

TS 4.7.3.a

Two independent

essential

cooling

water

loops.

TS 4.7.4. 1

Two independent

essential

spray

pond loops.

TS 4.7.5

TS 4.7.3.C-

"The ultimate heat sink shall

be

determined

OPERABLE at least

once per

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />

by verifying the average

water temperature

and water depth to

be within their limits for each

essential

spray pond."

This

surveillance

requirement

was performed

under procedure

41ST-1ZZ16,

"Routine

Surveillance Daily Midnight Logs."

"At least

two essential

cooling water

loops shall

be demonstrated

OPERABLE:

At least

once per 18 months duiring

shutdown

by verifying that the

essential

cooling water

pumps start

on

an SIAS test signal."

This'urveillance

was performed for "B"

40

train under

procedure

73ST-lDG02,

"Class

IE Diesel Generator

and

Integrated

Safeguards

Surveillance

Test - Train B."

The different procedures

for the various

TS surveillances

appeared

to be adequate

and the surveillances

test records

were complete in their content.

Of the many surveillance

records

sampled

(over sixty) for the- above

TS, all were

readily recovered

from the files, and none were missing.

Surveillances for 4160 Volt and 480 Volt Switch ear

and Motor

Control Centers

The surveillances for 4160 Volt switchgear relays are

described

in "Guideline for Frequency of Relay Testing,"

No. 14-3-1,

dated

December

14,

1981.

The 4160 Volt switchgear relays

are calibrated

and tested

on four year intervals.

The calibration

and test records

performed in August 1984 for the relays of circuit

breakers for two

EW pumps,

two SP pumps,

and two

EC

chillers were examined

and appeared

to be in order.

The periodic testing of trip settings for 480 Volt

switchgear

and motor control center circuit breakers

are

accomplished

under preventive

maintenance

(PM) work orders

as described

in Procedure

30AC-9ZZ02, "Preventive

Maintenance

(PM)."

The testing of circuit breakers

is

accomplished

during the regular

PM of the circuit

breakers,

at three year intervals during refueling.

However,

no

PM was performed

on any 480 Volt circuit

breakers

a'ssociated

with the three

systems

under

inspection during the first refueling outage,

which was

completed during January

1988.

The licensee's

surveillance

program appeared

to be

conducted in accordance

with the licensee

approved

procedures

and appears

to satisfy the requirements

of the

FSAR and the

TS requirements.

(2)

Calibration and

NOTTE Pro

rams

a 0

Instrument Calibration Pro

ram

The licensee's

instrument calibration program

was examined

by reviewing procedure

30AC-9ZZ02, "Preventive

Maintenance,"

the controlling procedure for instrument

calibration.

Instrument calibration schedules

were

reviewed.

Instrument calibration records for nine

instrument loops for the three

systems

(EW,

ECW, and

ESP)

under inspection

were examined.

This involved

approximately thirty-five instruments

in the three

systems.

Samples of history records for these

instruments

were also reviewed.

The history record included

a

chronology of calibrations,

maintenance,

and repairs for

the instrument.

The calibration

and history records

were

found to be in order

and complete.

The documentation

reviewed

and examined

supports

the conclusion that the

instrument calibration program appears

to operate

in

accordance

with the controlling procedure

and appears

to

be adequate.

b.

Measurin

and Test

E ui ment

(M&TE) Pro

ram

The licensee's

program for measuring

and testing equipment

(M&TE) was inspected to determine whether procedures

were

established

and implemented to assure that tools,

gauges,

instruments,

and other measuring

and testing

equipment

used in activities affecting safety are properly

controlled, calibrated

and adjusted to maintain precision

and accuracy within specified limits.

The following procedures

were examined to evaluate

the

implementation of the

M&TE program:

34PR-OZZ01

34AC-.OZZ03

Measuring

and test equipment

(M&TE)

control program

Control of nonconforming

M&TE and

calibration standards

34AC-OZZ04

Control of automated

M&TE calibration

program

34AC-OZZ05

Control of procurement,

shipping,

packing and receiving inspection of

M&TE

34AC-OZZ06

Calibration requirements

for M&TE and

calibration standards

34AC-9ZZ07

34AC-9ZZ08

M&TE users administrative

requirements

M&TE work control

34TI-OZZ01

-

Receipt inspection of M&TE and

calibration standards

Two audit reports,86-019

and 87-027, of audits

conducted

in the area of measuring

and test equipment

were examined

with the following items noted:

The finding of audit 86-019 (performed June 16-30,

1986) identified a backlog of approximately

200

out-of-tolerance

notices

(OTNs), including four

dating back to 1984.

42

This situation

was previously identified to

management

in audit report 85-018 with no significant

improvement noted to date

(June 1986).

Corrective action report

(CAR) CA86-0163

was written

September

30,

1986, after the

same findings had been

identified during an

INPO evaluation,

to correct the

findings of audit 86-019.

CAR CA86-0163 was closed in May 1987 with this

statement:

"Since the issuance

of .this

CAR, the

program for OTN evaluations

has

shown significant

improvements

and can

be considered

to be in

conformance with the intent of ANSI N18.7-1976,

Para.

5. 2. 16."

The findings of audit 87-027 (performed July 6-23,

1987) again identified problems

such

as not

completing out-of-tolerance

evaluations

in the

required sixty (60) day time period, delinquent

M&TE

(overdue for calibration) not being returned to the

Metrology Laboratory,

excessive

amounts of MTE being

lost/stolen in a sixteen

(16) month period,

inadequate justifications

on out-of-tolerance

evaluation replies,

etc.

CAR CA87-0091 written July 30, 1987, to correct the

deficiencies of'udit 87-027 contains this statement:

"Based

on the following adverse

conditions,

the

implementation of the present

measuring

and test

equipment

program is ineffective in controlling

nonconforming

METE, lost and stolen

M8TE; evaluation

of nonconforming items in a timely manner

and

recalibration of METE at specified intervals, to meet

,the intent of ANSI N18.7 and to minimize any

potential

adverse

impact on the operability of

safety-related

systems,

structures

or components."

, The licensee

as

a result of their

own preliminary self

evaluation (prior to the performance of audit 87-027

and

the issue of CAR CA87-0091)

had enlisted of an outside

industrial contractor

i'n conducting

a detailed in-depth

study of distributed

METE Responsibilitiesat

ANPP.

This

.

self-evaluation identified the

same

scope of concerns

as

those in CAR No.

CA87-0091.

Upon completion of this

study,

a final report will be issued

and (if applicable)

a

proposal for changes

to enhance

the program at ANPP.

The

licensee

has established

a target date of April 30, 1988,

to implement

recommended

changes

(determined to be

appropriate

and practical) identified at the conclusion of

. the study.

It is concluded that the licensee's

program for the

control of measuring

and test equipment is deficient in

43'everal

respects

as identified in CAR CA87-0091.

It

appears

that'actions

taken in the past to correct these

recurring deficiencies

have

been

inadequate.

This item

remains

as

an unresolved

item pending

a review by the

licensee

to determine whether

or not any of the

out-of-calibration instruments

were used in surveillances

of safety systems.

This is identified as inspection

item

50-528/88-01-26.

(3)

Monitorin

Pro

rams

a.

Heat Exchan er Monitorin

Pro

ram

The Palo Verde

FSAR Section 9.2. 1.4 indicates that an

important design basis is that the Spray

Pond

System

pressure

at the Essential

Cooling Mater Heat Exchanger is

maintained

higher than the

EW pressure.

This is to ensure

that in the event of a tube leak in the heat exchanger,

potentially radioactive water in the

EW would not be

injected into the Spray

Pond System where it would be

released

to the atmosphere.

The team found no evidence that the licensee

had

implemented

a proceduralized,

periodic assessment

of this

design parameter.

The team noted that

no pressure

gages

were in place at the heat exchanger

on the Essential

Cooling Mater side although they were in place

on the

Spray

Pond System side.

The team verified, by document

review, that the parameter

had been

measured

and found

satisfactory in preoperational

testing.

The licensee, installed

gages

and conducted

a test

on

January

18, 1988, in response

to the

NRC concern

and

verified that the spray pond system pressure

was indeed

higher than the

EM pressure.

The licensee's

surveillance

program for heat

exchangers

was discussed

with the lead performance

engineer

for

balance of plant,

and it was learned that at this time no

program

has

been

implemented.

The licensee

committed to

initiate a proceduralized periodic verification of this

design parameter.

The licensee's

implementation of this

commitment will be examined during

a future inspection.

This is identified as inspection

item 50-528/88-01-27.

b.

S ra'ond

Performance

Monitorin

Pro

ram

The licensee

has established

a program for monitoring

monthly (every 31 days) spray pond performance,

under

Administrative Procedure

73AC-9SPOl,

"Spray

Pond Piping

Integrity Verification."

The spray pond nozzle

performance is monitored under this monthly program.

In

reviewing this-program with the

EWs engineer,

nozzle

performance

was 'examined.

A drop as slight as

one tenth.

44

pound in nozzle discharge

pressure

indicates

a loss of two

square

inches in nozzle capacity.

Documentation of the

testing of spray

pond capacity

and effects of removal of

nozzles

on spray pond performance

conducted

during startup

testing prior to initial operation of Unit'

was examined.

It is concluded that the spray pond performance

and nozzle

.monitoring program is adequate.

4.

Desi

n Basis

Documentation

and

En ineerin

Efforts

A.

Technolo

Transfer

Pro

ram

The technology transfer

program was originated

by ANPP to establish

the methodology associated

with its receipt

and control of the

design basis

documents

from the original architect-engineer.

The

purpose of this turnover is to ensure that

ANPP is in total control

of the design;

however, it does

not imply that the utility is

independent

from the

need of architect-engineer

services.

The

current utility staffing assumes

that 50K of the design

changes will

be done in-house

and the remaining

50X will be contracted.

Further,

the utility is proceeding to be in the position of either doing the

design

change itself or have the option to select

an architect-

engineer for the task.

The selection will be based

on which option

is most advantageous

to the project for a specific design

change.

As stated in ANPP instruction

No. 7I414.00. 17, Revision 0, dated

March 27,

1987, entitled,

"Engineering Turnover Documentation

Instruction," the technology transfer

program was'intended

to enable

ANPP to reassess

the completeness

and acceptability of the design

input and output documentation

required to support the operation

of.

the plant and any related engineering,

licensing,

and maintenance

activities.

In accordance

with the aforementioned

instruction, the

corporate

engineers

are required to review the turnover packages

in

accordance

with a three-page

checklist that requires

a

random'ampling

of drawings, calculations,

and components.

Also, the

reviewers

were to determine if certain

randomly selected

calculations

had assumptions

that were properly described,

justified, and correct.

Also, they were to determine if the

turnover package

was complete.

The

NRC inspection

team identified that the technology transfer

program failed to identify as missing several

calculations

associated

with the systems

reviewed, that

a properly implemented

program should

have identified.

These missing calculations

are

required to support the following systems:

design pressure/temperature

ratings of systems,

chilled water system flow balance,

the surge tank relief valve is sized for a failed open,

upstream regulator valve for the essential

chilled and cooling

water systems,

45

vertical cable supports capability to withstand seismic

event'ver

life of plant,

battery

room minimum temperature

resulting from LOP.

Also, contrary to the guidelines of the Engineering Turnover

Documentation Instruction's checklist where reviewers

were to

randomly select calculations to verify assumptions,

the

NRC

inspection .team identified that

ANPP had not adequately

reviewed the

calculation assumptions.

Specifically, for the three

systems

reviewed

by the

NRC inspection

team,

the technology transfer

program

did not identify the unjustified assumptions

in the following

calculations:

Essential

chilled water surge tank sizing calculation

Chiller sizing calculation

Spray pond's capability to reject heat from clean heat

exchangers

Battery/charger

sizing calculation

DC cable sizing calculation

DG load study calculation

Battery room

HVAC calculation

The team concluded that the root cause of the technology transfer

program not identifying the missing calculations

is a lack of

in-house

design experience,

e.g., architect-engineer

experience.

The team notes that

ANPP management

had previously identified the

need to augment their staff with experienced

design engineers,

but

the final staffing has not yet been

completed.

With regard to the

technology transfer

program fai ling to identify unjustified

assumptions

even though

such actions

were required

on a sampling

basis,

the

NRC team concluded the root cause to be

a lack of

management

involvement and commitment to ensure that the subject

'-programmatic instructions

were effectively implemented.

Another aspect of the technology transfer

program was the

establishment

of the design basis

manual.

This manual is intended

to provide

ANPP a reference

to the design basis

documents.

It is

being prepared

by in-house architect-engineer

personnel

(Bechtel)

under the direction of ANPP management.

It is also reviewed by ANPP

via a five-page checklist to ensure that the information required to

maintain the design basis is referenced,

and that the referenced

documentation

has

been received.

For the three

systems

reviewed by

the

NRC inspection

team,

none of these

had

a design basis

manual

which had been finally approved

by ANPP.

However,

a review of the

ANPP comments

revealed that they had not identified the missing

calculations that the

NRC had identified and their comments

could be

characterized

as editorial.

Clearly,

ANPP had hot performed the

46

type of review necessary

to accomplish their stated

purpose of

ensuring that the information required to maintain the design basis

-is referenced.

The final aspect of the technology transfer

program is the

performance of a detailed review of the engineering turnover

documentation

associated

with two safety-related

systems.

At the

time of the

NRC inspection,

ANPP had not yet started this review of

two selected

systems,

but it was scheduled

to be completed

by April

1988 and it is to include

a detailed review of calculations.

These

concerns will be followed as

an unresolved

item, pending

ANPP's review and assurance

that acceptable

design basis

documents

have

been established

(Inspection

Item 50-528/88-01-28).

Trainin

Pro

rams for ANPP Cor orate

En ineers

The normal training program for ANPP corporate

engineers

is

described

in ANPP instruction

No. 8I718.00.01,

Revision 1, dated

March 5, 1987, entitled,

"Nuclear Engineering Indoctrination and

Training Program."

This program intends to define the initial and

continuous training requirements

for ANPP corporate

personnel

performing quality-related design,

engineering

and other technical

activities.

Elements of this program include an orientation reading

list, general

design requirements

training (e.g.,

reading

FSAR,

design criteria manual,

NRC rules

and regulations, etc.),

system

design training (review in detail specifications,

drawings,

design

calculations,

etc.)

and finally administrative controls training.

This program also provides for the preparation of individual

training plans which identify the training considered

necessary

by

management

and

may include in-house

and out-of-house training.

The

cornerstone

of the identification of the

need of training is the

skills inventory matrix which is prepared for an individual by the

immediate discipline supervisor.

The skills inventory matrix is a

comprehensive

listing of rating factors associated

with an

individual's knowledge of work, quality of work, quantity of work,

interpersonal

effectiveness,

planning

and job control.

Individuals

are rated against

performance

standards

established

by the

engineering

manager for that particular engineering discipline.

Once the skills matrix has

been completed, it is used

by management

to identify individuals'trengths

and weaknesses.

Where weaknesses

are identified for a rating factor that is applicable to the

original work of the individual, the supervisor

has the option of

specifying the type of training required.

Additional design training is attained

by the

ANPP corporate

engineers

as

a result of the process

used to approve

DCPs.

Every

design

change

independent

of the initiating organization

must be

presented

to the

ANPP design review board by the responsible

corporate

engineer.

The design review board is comprised in part by

the engineering discipline supervisors

in accordance

with ANPP

Procedure

No. 7I4I2.01.09,

Revision 0, dated August 5, 1987,

entitled,

"Design Review Board."

All members of the design review

board

have

10 years of relevant

power plant experience,

5 years of

47

which is related to power plant design.

The responsible

engineer

must verbally present

the design

change to the design review board

and convince

them that it is necessary

and technically justified.

Thus, this process

causes

the responsible

engineer to understand

the

associated

design

change

even if it was prepared

by another

organization.

Training received

by the

ANPP corporate

engineers

as

a part of the

technology transfer

program

was through courses

by Bechtel

and

on-the-job training from Bechtel.

For more than

one year,

ANPP has

been the recipient of various technical

courses

being conducted

by

Bechtel senior engineers.

In total, there were 38 courses

scheduled

with an average

length of classroom instruction of 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br />.

Examples of the courses

include support design,

earthquake

engineering,

qualifications of equipment, electrical physical

design,

overcurrent protection principles, pipe stress,

ASME Codes,

control valve'fundamentals,

flow measurement,

etc.

Where

applicable,

standard calculational

methods

were reviewed

as part of

the classroom training.

Most of the courses

had been

conducted

by

December

1987, with a few remaining to be taught in the first half

of 1988.

In addition to the courses,

ANPP has

had Bechtel provide

on-the-job training to the corporate

engineers.

Bechtel senior

engineers

are currently working in the

ANPP offices to assist

the

licensee's

personnel

in becoming familiar with the design

and

architect-engineer

methods.

It is noted

by the team that Bechtel

personnel

are working in accordance

with ANPP procedures.

The

NRC inspection

team reviewed

ANPP's training program for

corporate

engineers,

the individual training records of one randomly

selected

ANPP corporate

engineer

and the architect engineer

design

experience

for corporate

engineers

in the electrical

and mechanical

disciplines.

Based

upon this review, the team believes that an

adequate

training program is in place.

However, the team is

concerned that the training program is not being vigorously

implemented.

The basis for 'this observation

is that the corporate

engineers

have not reviewed in detail

any of the calculations

associated

with the systems

reviewed

by the

NRC team.

This is

contrary to the

ANPP procedure,8I718. 00. 01 which requires

system

design training to include

a detailed review of system calculations.

Additionally, the team is concerned that the corporate

engineers

lack appreciable

design experience,

e.g., architect-engineer

experience.

However, the team notes that

ANPP had identified in its

1987 staffing and training requirements

the

need to hire "qualified

engineers

with previous design experience

at an operating facility

to avoid extensive training."

The team reviewed the qualifications

of the last six employees

hired into the mechanical

and electrical

disciplines collectively.

The results of this review indicate that

4 of the

6 had architect engineer

design experience

and that

ANPP

management

was appropriately acting

upon

a weakness it had

identified.

The team encourages

the continued augmentation of ANPP

staff with engineers

with applicable

design experience.

In-summary

ANPP needs

to fully implement the training program it has

in place

and continue to augment the current staff with engineers

48

having significant nuclear design experience,

e. g., architect-

engineer

experience.

C.

Site

S stem

En ineerin

The team discussed

system design

and design basis,

and performance

monitoring and trending with various site system engineers,

as well

as training and responsibilities,

throughout the course of the

inspection.

Desi

n Basis

In the area of system design the system engineers

were

generally

knowledgeable

of how their systems

operate.

However,

when discussions

and walkdowns lead into the design basis,

the

site systems

engineers

lacked specific knowledge in several

areas,

e. g., various interface. functions with other systems

and

EW surge tank level setpoints.

This finding is of concern,

in

that, the site system engineers

may not be able to effectively

discharge their responsibilities

and assure

continued function

of the system without a clear understanding

of the design

basis.

During the system walkdowns,

NRC team identified significant

problems with various

systems

and components

discussed

in other

sections of this report.

The team concluded that most of these

problems

should

have

been identified by site system engineers

in their walkdowns;

and the fai lure of system engineers

to

identify the problems

may be attributed to a lack of

understanding

of design basis

and/or

walkdown functions.

The

team also recognized that the problem is compounded

by a

difficult to use plant problem reporting program,

which is

discussed

in another section of this report.

(2)

,S stem Performance

Monitorin

and Trendin

The team reviewed

and discussed

the system

engineers'esponsibilities

related to system performance

monitoring and

trending.

This included monitoring and trending of equipment

history (corrective maintenance),

testing (surveillances,

operational verifications,

and preventive

maintenance

with

emphasis

on verification of design basis),

and

use of industry

experience

(NRC Information Notices

and Bulletins,

and INPO's

Nuclear Plant Reliability Data System

and Significant Operating

Experience

Reports).

With regards to equipment history, the licensee's

program

currently consists

of:

a corporate

engineering

computerized

sort of equipment history which identified components

with a

number of failures beyond

an acceptance

criteria;

and

a review

of this computerized sort by the site system engineers

or their

supervision to determine if additional evaluation of component

or system performance is required.

In reviewing the status

of

this program,

the team found that the corporate sort

had been

C-

4

49

completed,

but this sort

had not been

reviewed by selected site

system engineers

or their supervision.

The team's

review of

the computerized sort information found that for'he selected

systems,

one component with a number of failures

beyond the

acceptance criteria had not been

reviewed by the site

engineering

department.

Engineering

management

indicated that

other work (Unit 1 outage related activities)

had taken

priority over equipment history review.

Also with regard to "equipment history monitoring, the team

determined that there

was

no formalized policy to assure that

system engineers

were kept apprised of significant mai,ntenance

or testing activities

on their related

systems

on a real time

basis.

Licensee

management

indicated that a program to route

all work orders through site system engineers

has

been planned

(this program is to include

a review of b'acklogged

work orders

and prioritization).

An example

of'

situation where system

testing should

have

been reviewed

by the system

engineer

was

the delay of an annual test committed to in LER 86-59 on the

emergency lighting (this problem is discussed

in detail in

another section of this report).

In the area of monitoring and trending of testing,

the licensee

was developing

a surveillance

test trending program.

The

status of this program

was that the system engineers

were

providing a list of parameters

required to adequately

monitor

system performance.

Licensee

management

indicated, this was to

be

a plant-wide integrated effort to utilize not only

surveillance tests,

but also operations verification,

preventive maintenance,

and engineering tests (for example,

ISI, IST).

With regard to verifying key system design basis

parameters,

the licensee's

program to verify heat exchanger

performance for

the

SSFI systems

was reviewed.

The team found that the

licensee

had not developed

a plan to monitor heat

exchanger

heat transfer capability.

Also, the licensee

had not verified

that

SP pressure

was higher than

EW pressure

at the

EW heat

exchanger to assure

no potential radioactive

leakage to the

environment (the licensee

has subsequently verified this

function and established

a rationale

and process

to assure this

important design. parameter).

However, these findings are again

indicative that site system engineers

may lack an adequate

design basis

understanding

to assure

testing

and verification

of important design functions.

(3)

~Tra i ni n

The team reviewed recently issued

documents

related to training

for site system engineers.-

The training document

lacked

sufficient specificity to assure that system engineers

were

fami liar with applicable

TSs,

design criteria,

FSAR sections,

technical

manuals,

surveillance tests,

and operational,

.emergency

and maintenance

procedures.

Also, the training

50

document did not specify techniques

to assure

adequacy

and

retention of training, nor did it assure that system engineers

would be knowledgeable

of changes

related to their system.

Licensee

management

has discussed

a plan to address

these

concerns.

(4)

Res onsibi lities

The current site systems

engineer responsibilities,

document

(EEDG-034, Revision') specified

a set of duties for site

system engineers.

These duties include

a knowledge of system

design

and operational

requirements,

trending

and monitoring of

system performance,

review of design

changes,

assistance

to

operations

and maintenance

organizations,

root cause failure

analysis,

and

many others.

The team verified that most system

engineers

were responsible for a number of different systems

(3

to 7, dependent

on system complexity).

Also, the team

determined

from the review of the aforementioned

duties that

the system engineers

have not been able to fulfillall their

responsibilities,

e. g., trending of system performance.

Further,

the team observed that there is extensive

use of

overtime

among the system engineers.

The inspection

team concluded that licensee

management

has not taken

a

proactive role in the definition and monitoring of, the site system

engineer

program.

This conclusion

was based

on the findings related to

the lack of system engineer

knowledge of design basis,

system

engineers'ailure

to identify problems that the team identified, failure of the

engineering

department to monitor and trend key equipment

performance

conditions,

the lack of specific training criteria and verification, and

a fai lure to assure that all system engineer responsibilities

were

appropriately discharged.

Discussions

with licensee

management

concluded

that they plan to re-evaluate

system engineers'esponsibilities,

training,

and workloads, to assure that management's

expectations

are

clearly defined

and attainable.

This is identified as inspection

item

50-528/88-01-29.

5.

Unresolved

Item

Unresolved

items are matters

about which more information is required to

determine

whether they are acceptable

or

may involve violations or

deviations.

The licensee is requested

to provide additional information

on these

items,

as noted in the forwarding letter to this report.

6.

Exit Interview

On February

12,

1988,

an exit interview was conducted with the licensee

representatives

identified in paragraph

1.

The team reviewed the scope

of the inspection

and findings as described

in the

Summary of Significant

Inspection

Findings section of this report.

Enclosure

1

PERSONS

CONTACTED

Arizona Nuclear

Power Pro ect

ANPP)

5'E

)kJ

)hJ*J

"W.

R

A'

I.

  • J

)kE

D.

F.

B.

J.

J.

C

  • T

B.

D.

L.

C.

R.

,R ~

J.

D.

p.

R.

R.

G.

8 ~

M.

S.

R.

B.

  • W.

D.

T.

L.

T.

L.

N.

K.

R.

W.

R.

M.

n Support

er

ervisor

rvisor

Van Brunt, Jr.,

Executive Vice President

Allen, Director, Engineering

and Construction

Haynes,

Vice President;

Nuclear Production

Kirby, Director, Site Services

guinn, Director, Nuclear Safety and Licensing

Papworth, Director, guality Assurance

Allen, Unit 1 Plant Manager

Zeringue, Unit 3 Plant Manager

Driscoll, Assistant Vice President,

Nuclear Productio

Butler, Director, Standards

and Technical

Support

Sterling,

Engineering

Manager

Fasnacht,

Construction

Manager

Godwin,

Records

Management

Manager

Fernow, Training Manager

Vorees,

Nuclear Safety Manager

Lo Cicero,

Independent

Safety Engineering

Group Manag

Rogers,

Licensing Manager

Shriver,

Compliance

Manager

Craig, guality Systems

and Engineering

Manager

Fowler,

Procurement

equality

Manager

Souza,

equality Audits and Monitoring Manager

Russo, guality Control Manager

Younger, Operations

Manager

Beecken,

Maintenance

Manager

Dennis,

Work Control Manager

Blackson,

WRF Manager

Brandjes,

Outage

Management

Manager

Nelson,

Central

Maintenance

Manager

Adney, Plant Standards

and Control Manager

Sowers,

Engineering Evaluations

Manager

Berg, Protection Relaying and Control Maintenance

Sup

Powell, Unit 1, Electrical Supervisor

Karimi, Compliance

Engineer

Kropp, Technical

Support

McCaskey, Surveillance

Program Coordinator Supervisor

Simko,

Lead Mechanical

Engineer

Hansen,

Lead ISI Engineer

Weber,

Lead Technical

Engineer

Perea,

Lead Performance

Engineer

Hall, Lead NSSS/Radwaste

Engineer

Trouy, Technician,

Technical

Support

Hallas,

System Engineer,

EW System

Cutler,

I8C Standards

Supervisor

Page,

I8C Support Supervisor

Goodman,

Lead Metrology Technician

Vallely, Senior Reactor Operator Shift Supervisor

Zerkel, Senior Reactor Operator,

Assistant Shift Supe

D.

)kR

A'p

"W.

)hJ

M.

M.

H.

M.

J.

A.

D.

W.

R.

F.

M.

AJ

S.

"A.

p.

F.

J.

Hackbert,

qual ity Audit Super visor

Rouse,

Compliance

Engineer

Coffin, Compliance

Engineer

Jump,

Outage

Manager

Juan,

Licensing Engineer

Hodge,

Mechanical/Chemical

Engineer

Radoccia,

Lead Mechanical/Chemical

Engineer

Riley,

Lead Mechanical/Chemical

Engineer

Winsor,

Lead Mechanical/Chemical

Engineer

Deluca,

Mechanical/Chemical

Engineer

Amr, Mechanical/Chemical

Engineer

Bhasin,

Mechanical/Chemical

Engineer

Phalen,

Mechanical/Chemical

Engineer

Kershaw,

Lead Instrumentation

and Controls Engineer

Prawlocki,

Lead Methods

and Training Engineer

Hypse, Electric Engineer

Barrow, Electrical Engineering Supervisor

Kesler,

Lead Electrical

Engineer

Demlong, Electrical Engineer

Mueller, Electrical Engineer

Horner, Mechanical/Chemical

Engineer

Clarke, Operations,,Technical

Support

2.

Other Personnel

"S..Terrigino,.Participant

SVCS, Coordinator

"M. Wharton,

Southern California Edison Co., Assistant Technical

Manager

NRC Personnel

In addition to the inspection

team,

the following NRC Regional Office

Managers

and Supervisors participated in the inspection activity and/or

attended

the associated

management

meeting:

J. Martin, Regional Administrator

"D. Kirsch, Director, Division of Reactor Safety

and Projects

"R. Pate,

Chief, Reactor Safety Branch

"E. Imbro, Chief, TIAD Section,

NRR

"Denotes

those

personnel

in attendance

at an exit meeting

on February 12,

1988.