ML17192A175

From kanterella
Jump to navigation Jump to search

Plants, Units 1 and 2; Calvert Cliffs Independent Spent Fuel Storage Installation; Nine Mile Point Nuclear Station, Units 1 and 2; R. E. Ginna - Acceptance of License Amendment Request to Revise Emergency Action Level Schemes
ML17192A175
Person / Time
Site: Calvert Cliffs, Nine Mile Point, Ginna  Constellation icon.png
Issue date: 07/11/2017
From: Blake Purnell
Plant Licensing Branch III
To: Bryan Hanson
Exelon Generation Co
Purnell B A/301-415-1380
References
CAC MF9836, CAC MF9837, CAC MF9838, CAC MF9839, CAC MF9840
Download: ML17192A175 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 11, 2017 Mr. Bryan C. Hanson Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Officer (CNO)

Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

CALVERT CLIFFS NUCLEAR POWER PLANT, UNITS 1AND2; CALVERT CLIFFS INDEPENDENT SPENT FUEL STORAGE INSTALLATION; NINE MILE POINT NUCLEAR STATION, UNITS 1AND2; ANDRE. GINNA NUCLEAR POWER PLANT -ACCEPTANCE OF LICENSE AMENDMENT REQUEST TO REVISE EMERGENCY ACTION LEVEL SCHEMES (CAC NOS. MF9836-MF9840)

Dear Mr. Hanson:

By application dated May 31, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17164A149), Exelon Generation Company, LLC (Exelon, the licensee) submitted a license amendment request for Calvert Cliffs Nuclear Power Plant, Units 1 and 2; Nine Mile Point Nuclear Station, Units 1 and 2; and R. E. Ginna Nuclear Power Plant.

The amendments would revise the emergency plans by changing the emergency action level schemes for these facilities. The proposed changes are based on the Nuclear Energy lnstitute's (NEl's) guidance in NEI 99-01, Revision 6, "Development of Emergency Action Levels for Non-Passive Reactors," which was endorsed by the U.S. Nuclear Regulatory Commission (NRG) by letter dated March 28, 2013 (ADAMS Accession No. ML12346A463).

Exelon's application also included a request to amend the materials license for the Calvert Cliffs Independent Spent Fuel Storage Installation (ISFSI). There is not a separate emergency plan for the ISFSI, as it is included in the emergency plan for the Calvert Cliffs Nuclear Power Plant.

The NRC staff's review of changes to the Calvert Cliffs Nuclear Power Plant emergency plan will include a review of changes related to the ISFSI. An amendment to the materials license for the Calvert Cliffs ISFSI is not required.

The purpose of this letter is to provide the results of the NRC staff's acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

B. Hanson Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRG staff's ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.

Based on the information provided in your submittal, the NRG staff has estimated that the review of this licensing request will take approximately 700 hours29.167 days <br />4.167 weeks <br />0.959 months <br /> to complete. The NRC staff expects to complete this review by July 31, 2018. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRG staff's initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me at (301) 415-1380.

Sincerely, Blake Purnell, Project Manager Plant Licensing Branch Ill Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-317, 50-318, 72-8, 50-220, 50-410, 72-1036, 50-244, and 72-67 cc: Distribution via Listserv

, ML17192A175 *via email OFFICE LPL3/PM LPL3/LA NMSS/DSFM/SFLB/BC LPL3/BC LPL3/PM NAME BPurnell SRohrer JMcKirgan~ DWrona BPurnell DATE 07/11117 07/11/17 07111/17 07/11/17 07/11117