MONTHYEARGNRO-2023/00014, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-06-0606 June 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GNRO-2023/00015, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-06-0606 June 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors GNRO-2021/00037, 2021 Annual Report of Changes and Errors to 10 CFR 50.46 Analysis Grand Gulf Nuclear Station, Unit 12021-11-30030 November 2021 2021 Annual Report of Changes and Errors to 10 CFR 50.46 Analysis Grand Gulf Nuclear Station, Unit 1 GNRO-2021/00017, Notification of Readiness for Supplemental Inspection2021-06-22022 June 2021 Notification of Readiness for Supplemental Inspection GNRO-2021/00014, Inservice Testing Program Relief Request VRR-GGNS-2021-1 Pressure Isolation Valve Testing Frequency2021-06-0101 June 2021 Inservice Testing Program Relief Request VRR-GGNS-2021-1 Pressure Isolation Valve Testing Frequency GNRO-2021/00015, Annual Radioactive Effluent Release Report2021-04-28028 April 2021 Annual Radioactive Effluent Release Report GNRO-2021/00011, Revision of Original Report of 10CFR50.59 and Commitments Change Evaluations - July 1, 2018 Through May 21, 20202021-04-19019 April 2021 Revision of Original Report of 10CFR50.59 and Commitments Change Evaluations - July 1, 2018 Through May 21, 2020 GNRO-2021/00012, Annual Report of Individual Monitoring - NRC Form 5 for 2020 Per 10 CFR 20.22062021-04-13013 April 2021 Annual Report of Individual Monitoring - NRC Form 5 for 2020 Per 10 CFR 20.2206 GNRO-2020/00045, 2020 Report of Changes and Errors to 10 CFR 50.46 Analysis2020-12-16016 December 2020 2020 Report of Changes and Errors to 10 CFR 50.46 Analysis GNRO-2020/00034, Notification of Spent Fuel Cask Use2020-10-0808 October 2020 Notification of Spent Fuel Cask Use GNRO-2020/00033, Response to NRC Integrated Inspection Report 05000416/20200022020-09-10010 September 2020 Response to NRC Integrated Inspection Report 05000416/2020002 GNRO-2020/00029, Report of 10 CFR 72.48 Evaluations July 1, 2018 Through June 30, 20202020-08-18018 August 2020 Report of 10 CFR 72.48 Evaluations July 1, 2018 Through June 30, 2020 GNRO-2020/00022, Report of Technical Specification Bases Changes2020-07-21021 July 2020 Report of Technical Specification Bases Changes GNRO-2020/00027, Core Operating Limits Report (COLR) Cycle 23 Revision 1 for Grand Gulf Nuclear Station, Unit 1 (GGNS)2020-07-16016 July 2020 Core Operating Limits Report (COLR) Cycle 23 Revision 1 for Grand Gulf Nuclear Station, Unit 1 (GGNS) GNRO-2020/00023, Response to Request for Additional Information - License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies2020-06-26026 June 2020 Response to Request for Additional Information - License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies GNRO-2020/00020, Core Operating Limits Report (COLR) Cycle 23, and Pressure and Temperature Limits Report (PTLR) Update for Grand Gulf Nuclear Station, Unit 1 (GGNS)2020-05-0505 May 2020 Core Operating Limits Report (COLR) Cycle 23, and Pressure and Temperature Limits Report (PTLR) Update for Grand Gulf Nuclear Station, Unit 1 (GGNS) GNRO-2020/00018, Annual Radiological Effluent Release Report2020-04-30030 April 2020 Annual Radiological Effluent Release Report GNRO-2020/00016, Annual Report of Individual Monitoring -NRC Form 5 for 2019 Per 10 CFR 20.22062020-04-16016 April 2020 Annual Report of Individual Monitoring -NRC Form 5 for 2019 Per 10 CFR 20.2206 GNRO-2020/00015, Response to Request for Additional Information - License Amendment Request for One-Cycle Extension of Appendix J Type a Integrated Leakage Rate Test and Drywell Bypass Leakage Rate Test2020-04-0707 April 2020 Response to Request for Additional Information - License Amendment Request for One-Cycle Extension of Appendix J Type a Integrated Leakage Rate Test and Drywell Bypass Leakage Rate Test GNRO-2020/00007, Spent Fuel Storage Radioactive Effluent Release Report for 20192020-02-20020 February 2020 Spent Fuel Storage Radioactive Effluent Release Report for 2019 GNRO-2020/00006, License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies2020-02-19019 February 2020 License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies GNRO-2019/00052, Report of Changes and Errors to 10 CFR 50.46 Analysis2019-12-13013 December 2019 Report of Changes and Errors to 10 CFR 50.46 Analysis GNRO-2019/00051, Notification of Readiness of 92723 Inspection2019-12-11011 December 2019 Notification of Readiness of 92723 Inspection GNRO-2019/00045, Emergency Plan, Revision 792019-10-29029 October 2019 Emergency Plan, Revision 79 GNRO-2019/00037, Notification of Spent Fuel Cask Use2019-09-20020 September 2019 Notification of Spent Fuel Cask Use GNRO-2019/00036, Correction to Gnro 2019-00017 Emergency Plan Revision 782019-08-0808 August 2019 Correction to Gnro 2019-00017 Emergency Plan Revision 78 GNRO-2019/00027, Notification of Readiness of 95001 Supplemental Inspections2019-07-0303 July 2019 Notification of Readiness of 95001 Supplemental Inspections GNRO-2019/00031, Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.2206 - Corrected Report2019-06-25025 June 2019 Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.2206 - Corrected Report GNRO-2019/00028, Supplement to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation.2019-06-13013 June 2019 Supplement to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation. GNRO-2019/00026, Response to Requests for Additional Information Regarding Relief Request Number GG-ISI-023, Inservice Inspection Impracticality - Limited Coverage Examinations During the Third 10-Year Inservice Inspection Interval2019-05-0606 May 2019 Response to Requests for Additional Information Regarding Relief Request Number GG-ISI-023, Inservice Inspection Impracticality - Limited Coverage Examinations During the Third 10-Year Inservice Inspection Interval GNRO-2019/00024, Annual Radioactive Effluent Release Report2019-04-30030 April 2019 Annual Radioactive Effluent Release Report GNRO-2019/00020, Annual Radiological Operating Report (AREOR)2019-04-30030 April 2019 Annual Radiological Operating Report (AREOR) GNRO-2019/00022, Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.22062019-04-22022 April 2019 Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.2206 GNRO-2019/00017, Emergency Plan, Revision 782019-03-14014 March 2019 Emergency Plan, Revision 78 GNRO-2019/00014, Snubber Testing Program for Fourth Inspection Interval2019-03-13013 March 2019 Snubber Testing Program for Fourth Inspection Interval GNRO-2019/00012, Internal Events Probabilistic Risk Assessment (PRA) Sensitivity Study Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program2019-03-0606 March 2019 Internal Events Probabilistic Risk Assessment (PRA) Sensitivity Study Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program GNRO-2019/00016, Spent Fuel Storage Radioactive Effluent Release Report for 20182019-02-21021 February 2019 Spent Fuel Storage Radioactive Effluent Release Report for 2018 GNRO-2019/00003, Application to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation2019-01-23023 January 2019 Application to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation GNRO-2018/00057, Submittal of Revision 17 to the Grand Gulf Nuclear Station Physical Security, Safeguards Contingency, and Training and Qualification Plan2018-12-0404 December 2018 Submittal of Revision 17 to the Grand Gulf Nuclear Station Physical Security, Safeguards Contingency, and Training and Qualification Plan GNRO-2018/00055, Response to Request for Additional Information for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a ...2018-11-30030 November 2018 Response to Request for Additional Information for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a ... GNRO-2018/00054, Relief Request No. GG-ISI-023, Inservice Inspection Impracticality: Limited Coverage Examination During the Third 10-Year Inservice Inspection Interval2018-11-30030 November 2018 Relief Request No. GG-ISI-023, Inservice Inspection Impracticality: Limited Coverage Examination During the Third 10-Year Inservice Inspection Interval GNRO-2018/00052, License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis - Partial Response to Request for Additional Information and Extension of Response to Request for Additional Information2018-10-24024 October 2018 License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis - Partial Response to Request for Additional Information and Extension of Response to Request for Additional Information GNRO-2018/00051, Supplement to Revise Technical Specifications to Adopt Technical Specification Task Force Traveler TSTF-542, Reactor Pressure Vessel Water Inventory Control2018-10-23023 October 2018 Supplement to Revise Technical Specifications to Adopt Technical Specification Task Force Traveler TSTF-542, Reactor Pressure Vessel Water Inventory Control GNRO-2018/00046, Submittal of 2018 Report of Changes and Errors to 10CFR50.462018-10-16016 October 2018 Submittal of 2018 Report of Changes and Errors to 10CFR50.46 GNRO-2018/00047, Submittal of 2018 Inservice Inspection Summary Report2018-10-16016 October 2018 Submittal of 2018 Inservice Inspection Summary Report GNRO-2018/00048, Response to Request for Additional Information License Amendment Request, Adoption of Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 62018-10-10010 October 2018 Response to Request for Additional Information License Amendment Request, Adoption of Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 6 GNRO-2018/00042, Core Operating Limits Report Cycle 22, Revision 12018-09-18018 September 2018 Core Operating Limits Report Cycle 22, Revision 1 GNRO-2018/00043, Revised Offsite Dose Calculation Manual2018-09-18018 September 2018 Revised Offsite Dose Calculation Manual GNRO-2018/00039, Report of Technical Specification Bases Changes2018-08-20020 August 2018 Report of Technical Specification Bases Changes GNRO-2018/00040, Report of 10CFR50.59 Evaluations and Commitment Change Evaluations - July 1, 2016 Through June 30, 20182018-08-20020 August 2018 Report of 10CFR50.59 Evaluations and Commitment Change Evaluations - July 1, 2016 Through June 30, 2018 2023-06-06
[Table view] |
Text
'"":P Entergy Operations, Inc.
P.o. Box 756 Port Gibson, Mississippi 39150 James J. Nadeau Manager, Regulatory Assurance Grand Gulf Nuclear Station 601-437-2103 GNRO-2016/00060 November 15, 2016 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
SUBJECT:
Supplemental Report of 10CFR50.59 Evaluations - July 1, 2012 through June 30, 2014 Grand Gulf Nuclear Station, Unit No. 1 Docket No. 50-416 License No. NPF-29
REFERENCE:
- 1. Letter to NRC, GNRO-2014/00065, "Report of 10CFR50.59 Evaluations and Commitment Changes July 1, 2012 through June 30, 2014," dated September 30, 2014.
Dear Sir or Madam:
In review of Reference 1, it was identified that certain 50.59 Evaluations were not included in the Reference 1, Attachment 1, 10CFR50.59 Summary Report. In response, Entergy Operations, Inc. (Entergy) is submitting a supplement to Reference 1, Attachment 1. The Attachment to this letter, Supplemental 10CFR50.59 Summary Report, will replace Attachment 1, 10CFR50.59 Summary Report, of Reference 1.
Pursuant to 10CFR50.59(d)(2), Entergy Operations, Inc. hereby submits a supplemental summary of 50.59 Evaluations for the period of July 1, 2012 through June 30, 2014 in this letter. The Attachment to this letter contains the Supplemental 10CFR50.59 Summary Report.
This letter does not contain any new commitments. If you have any questions or require additional information, please contact James Nadeau at 601-437-2103.
JJN/tmm
GNRO 2016-00060 Page 2 of 2
Attachment:
Supplemental 10CFR50.59 Summary Report cc:
NRC Senior Resident Inspector Grand Gulf Nuclear Station Port Gibson, MS 39150 U.S. Nuclear Regulatory Commission ATTN: Kriss M. Kennedy (w/2)
Region Administrator, Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 U. S. Nuclear Regulatory Commission ATTN: Jim Kim, NRR/DORL (w/2)
Mail Stop OWFN 8 B1 Rockville, MD 20852-2738
Attachment to GNRO 2016-00060 Supplemental 10CFR50.59 Summary Report
GNRO-2016/00060 Page 1 of 1 Grand Gulf Nuclear Station Supplemental 10CFR50.59 Summary Report Initiating Document 50.59 Summary EC38371, LBDCR2012-0034 Engineering Change EC-38371, "Cycle 19 EPU COLR."
EC38230 Engineering Change EC-38230, "EC 38230 as modified by EC 38798."
EC 38885 Engineering Change EC-38885, "The Loss of Coolant Accident, Main Steam Line Break Outside Containment, and Control Rod Drop Accident dose analyses apply the alternative source term from 10 CFR 50.67 to determine the offsite and control room doses associated with these design basis accidents. These dose analyses are revised to reflect implementation of the Extended Power Uprate."
EC41518 Engineering Change EC-41518, "New Strategy for Protecting PMP External Doors 1X701D308, 1X701D312,1X701D309,1X701D310,1Y401M110, 2Y402M110, 2Y402M111 and SZ100C313 From PMP Hazard."
EC43421 Engineering Change EC-43421, "Evaluation of ESF Switchgear Room 1A309 Temperature with room cooler 1T46B003A out of service."
EC43958 Engineering Change EC-43958, "Evaluation of ESF Switchgear Room 1A308 Temperature with room cooler 1T46B003B out of service."
EC44293 Engineering Change EC-44293, "Evaluation to allow ESF Room Coolers 1T46B001B and 1T46B002B to be out of service (at different times) per TRM 6.7.1."
EC48003 Engineering Change EC-48003, "Evaluation to allow ESF Room Cooler 1T46B003A to be out of service per TRM LCO 6.7.1 Action C3."
EC48407 Engineering Change EC-48407, "Evaluation to allow ESF Room Cooler 1T46B002A to be out of service per TRM LCO 6.7.1 Action C3."
EC49291,LBDCR2014-004 Engineering Change EC-49291, "Cycle 20 COLR."
EC49891 Engineering Change EC-49891, "This change is to substitute Beta calibration units to manually perform the automatic function of the turbine first stage pressure transmitters."
EC42886 Engineering Change EC-42886, "Evaluation of ESF Switchgear Room 1A219 Temperature with room cooler 1T46B002A out of service."