MONTHYEARML16036A3072016-02-18018 February 2016 Regulatory Audit Plan in Support of the License Amendment Requests to Implement Risk-Informed Technical Specifications Initiative 4b Project stage: Other ML16105A4592016-04-14014 April 2016 NRR E-mail Capture - Request for Additional Information Re. Turkey Point 3 & 4 LAR-236 (CACs MF5455 & MF5456) Project stage: RAI ML16110A0042016-04-18018 April 2016 NRR E-mail Capture - Request for Additional Information - Turkey Point 3 & 4 LAR-236 (CACs MF5455 & MF5456) Project stage: RAI ML16154A3392016-06-0101 June 2016 NRR E-mail Capture - Request for Additional Information Re. Turkey Point 3 & 4 LAR-236 (CACs MF5455 & MF5456) Project stage: RAI L-2016-116, Response to Request for Additional Information Regarding License Amendment Request 236, Revision to TS to Adopt Risk Informed Completion Time TSTF-505, Revision 1,Provide Risk-Informed Extended Completion Times2016-06-16016 June 2016 Response to Request for Additional Information Regarding License Amendment Request 236, Revision to TS to Adopt Risk Informed Completion Time TSTF-505, Revision 1,Provide Risk-Informed Extended Completion Times Project stage: Response to RAI ML16154A0122016-06-21021 June 2016 Summary of NRC Audit of Turkey Point Nuclear Generating Unit Nos. 3 and 4 for License Amendment Request No. 236 Project stage: Other L-2016-136, Second Response to Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide.2016-08-11011 August 2016 Second Response to Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide. Project stage: Response to RAI L-2016-213, Response to Request for Additional Information Regarding License Amendment Request 245, Change to the Technical Specifications to Address an Inoperable Steam Supply for the Auxiliary Feedwater Pumps2016-11-15015 November 2016 Response to Request for Additional Information Regarding License Amendment Request 245, Change to the Technical Specifications to Address an Inoperable Steam Supply for the Auxiliary Feedwater Pumps Project stage: Response to RAI L-2017-006, Supplement to License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b2017-02-0909 February 2017 Supplement to License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b Project stage: Supplement ML17090A1252017-03-30030 March 2017 NRR E-mail Capture - Request for Additional Information Re. Turkey Point TSTF-505 LAR 236 (CACs MF5455 and MF5456) Project stage: RAI L-2017-063, Response to Third Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide .2017-04-27027 April 2017 Response to Third Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide . Project stage: Request ML17213A2102017-06-27027 June 2017 NRR E-mail Capture - Draft Request for Additional Information - Turkey Point 3 & 4 LAR-236 (CACs MF5455 & MF5456) Project stage: Draft RAI ML17222A2312017-07-18018 July 2017 NRR E-mail Capture - Draft Request for Additional Information - Turkey Point 3 & 4 LAR-236 (CACs MF5455 & MF5456) Project stage: Draft RAI ML17222A0042017-08-0303 August 2017 NRR E-mail Capture - Additional Draft RAI Related to the Turkey Point TSTF-505 LAR Project stage: Draft RAI ML17223A0612017-08-10010 August 2017 NRR E-mail Capture - Request for Additional Information - Turkey Point 3 & 4 LAR-236 (CACs MF5455 & MF5456) Project stage: RAI L-2017-168, Response to Fourth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed2017-10-30030 October 2017 Response to Fourth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed Project stage: Request L-2018-001, Supplement to Response to Fourth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide2018-02-15015 February 2018 Supplement to Response to Fourth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Project stage: Supplement ML18061A0172018-03-0101 March 2018 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4, Request for Additional Information Regarding License Amendment Request 256 (CAC Nos. MF5455 and MF5456; EPID L-2014-0002) Project stage: RAI L-2018-061, Response to Fifth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed....2018-03-22022 March 2018 Response to Fifth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed.... Project stage: Request L-2014-000, Response to Fifth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed..2018-03-22022 March 2018 Response to Fifth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed.. Project stage: Request ML18138A0002018-04-19019 April 2018 NRR E-mail Capture - Draft Request for Additional Information - Turkey Point 3 and 4 LAR 236 (CAC Nos. MF5455 and MF5456; EPID L-2014-0002) Project stage: Draft RAI ML18138A4652018-05-17017 May 2018 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4, Request for Additional Information Regarding License Amendment Request 236 (CAC Nos. MF5455 and MF5456; EPID L-2014-0002) Project stage: RAI L-2018-118, Response to Sixth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed2018-06-12012 June 2018 Response to Sixth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed Project stage: Request ML18151A4342018-06-14014 June 2018 Summary of NRC Audit Regarding License Amendment Request to Adopt Risk-Informed Completion Times in Technical Specifications (CAC Nos. MF5372 and MF5373; EPID L-2014-LLA-0002) Project stage: Other ML18303A2432018-10-26026 October 2018 NRR E-mail Capture - (External_Sender) NRC Notification of State of Florida Regarding Turkey Point 3 and 4 License Amendments - Regarding the Addition of Risk-Informed Completion Times Project stage: Other ML18270A4292018-12-0303 December 2018 Issuance of Amendments Nos. 284 and 278 Regarding Adoption of Risk-Informed Completion Times in Technical Specifications (CAC Nos. MF5455 and MF5456; EPID L-2014-LLA-0002) Project stage: Approval 2017-06-27
[Table View] |
Text
UNITED ST ATES NUCLEAR REGULATORY COMMISSION Mr. Mano Nazar President and Chief Nuclear Officer Nuclear Division NextEra Energy P.O. Box 14000 Juno Beach, FL 33408-0420 WASHINGTON, D.C. 20555-0001 June 21, 2016
SUBJECT:
SUMMARY
OF NRC AUDIT OF TURKEY POINT NUCLEAR GENERATING UNIT NOS. 3 AND 4 FOR LICENSE AMENDMENT REQUEST NO. 236 (CAC NOS. MF5455 AND MF5456)
Dear Mr. Nazar:
By letter L-2014-369 dated December 23, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15029A297), Florida Power & Light Company submitted License Amendment Request (LAR) No. 236 to revise the Turkey Point Nuclear Generating Unit Nos. 3 and 4 (Turkey Point) Technical Specifications to adopt risk-informed completion times in accordance with the Technical Specifications Task Force (TSTF)
Traveler-505, Revision 1, "Provide Risk-Informed Extended Completion Times - RITSTF
[Risk Informed TSTF] Initiative 4b" (ADAMS Accession No. ML111650552).
On February 24 and 25, 2016, the U.S. Nuclear Regulatory Commission (NRC) staff and its contractors from the Pacific Northwest National Laboratory participated in a regulatory audit of Turkey Point at the NextEra Energy Offices in Juno Beach, Florida. The purpose of the audit was to understand what information the NRC staff needed to support its review of the LAR and to develop requests for additional information, as needed. The NRC staff will request any additional information needed to support its review in accordance with NRC Office of Nuclear Reactor Regulation, Office Instruction LIC-101, "License Amendment Review Procedures" (ADAMS Accession No. ML113200053). provides the schedule of activities during the audit. Enclosure 2 provides the list of audit participants. Enclosure 3 contains a list of documents reviewed by the team.
If you have any questions regarding this issue, please contact me at (301) 415-0489 or by e-mail at Audrey.Klett@nrc.gov.
Docket Nos. 50-250 and 50-251
Enclosures:
- 1. Audit Schedule
- 2. Audit Participants
- 3. Audit Documents cc w/enclosures: Distribution via Listserv Sincerely, Audrey L. Klett, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Schedule of Activities Wednesday, February 24, 2016 8:30 AM 11:30 AM 12:30 PM 4:00 PM
Introductions
Presentation on Risk-Informed Completion Time (RICT) Program Overview Discussion of license amendment request and RICT Program Discussion on how external events are considered for the RICT Discussion on how risk management actions are determined and implemented Lunch Presentation on Probabilistic Risk Assessment (PRA) functional definition, development, and use (PRA Request for Additional Information (RAI) 10)
Discussion of other RAls - PRA, Instrumentation and Control, and Technical Specifications End of the Day Briefings Thursday. February 25, 2016 8:30 AM 11 :30 AM 12:30 PM 4:00 PM 5:00 PM Presentation on Configuration Risk Management Program (CRMP) demonstration (including presentation of user interface for evaluations)
Discussion of reviews and acceptance testing of the CRMP model Discussion on how the CRMP is maintained consistent with baseline PRA model Discussion of other RAls - PRA, Instrumentation and Control, and Technical Specifications Lunch Presentation on Walkthrough sample RICT calculations Discussion of reviews and acceptance testing of the CRMP model Discussion on how cumulative risk will be evaluated and tracked End of the Day Briefings End of day debriefs were canceled based on travel from the plant walkdowns
List of Participants U.S. Nuclear Regulatory Commission Team Stacey Rosenberg, Branch Chief Leslie Fields, Audit Team Leader Perry Buckberg, Licensing Project Manager Jonathan Evans, Technical Reviewer Stephen Dinsmore, Technical Reviewer Norbert Carte, Technical Reviewer*
Margaret Chernoff, Technical Reviewer*
Audrey Klett, Licensing Project Manager*
- phone participant Pacific Northwest National Laboratory Team Garill Coles, Risk Analyst Steve Short, Risk Analyst Florida Power & Light Company/NextEra Energy Company Mahmoud Heiba
- Anil Julka Loren Heistard Jake Porterfield Mark Averett Richard Turcotte Larry Nicholson William Cross Florida Power & Light Company/NextEra Energy Company Contractor Andrew Howe, JBC Nuclear, Inc., Consultant
List of Documents Reviewed
- 1.
Hurricane Procedure
- 2.
Configuration Management
- 3.
Risk-Informed Completion Time (RICT) Calculations
- 4.
Configuration Risk Management Program Procedure
- 5.
Protected Train Procedure
- 6.
NextEra Energy Audit Kick-Off Presentation (Presentation)
- 7.
Turkey Point Risk-Managed Technical Specifications Overview (Presentation)
- 8.
Overview of NextEra Energy License Amendment Request (Presentation)
- 9.
Electric Power Research Institute Phoenix Risk Monitor Implementation Overview (Presentation)
- 10.
Turkey Point Sample RICT Calculations (Presentation)
If you have any questions regarding this issue, please contact me at (301) 415-0489 or by e-mail at Audrey.Klett@nrc.gov.
Docket Nos. 50-250 and 50-251
Enclosures:
- 1. Audit Schedule
- 2. Audit Participants
- 3. Audit Documents cc w/enclosures: Distribution via Listserv DISTRIBUTION:
PUBLIC LPL2-2 R/F LFields, NRR RidsNrrDorlLpl2-2 RidsNrrLABClayton RidsNrrPMTurkeyPoint ADAMS A ccess1on N o.: ML16154A012 OFFICE DORL/LPL2-2/PM DORL/LPL2-2/LA NAME AKlett BClayton DATE 6/17/16 6/17/16 Sincerely, IRA/
Audrey L. Klett, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation RidsRgn2MailCenter RidsACRS_MailCTR RidsNrrDraApla RidsNrrDssStsb PBuckberg, NRR JEvans, NRR
1y memoran um ORA/AP LA/BC*
DORL/LPL2-2/BC (A)
DORL/LPL2-2/PM SRosenberg TOrf A Klett 4/21/16 6/21/16 6/21/16 OFFICIAL RECORD COPY