ML16127A518

From kanterella
Jump to navigation Jump to search
040_13 Initial Test and Operation
ML16127A518
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 04/11/2016
From:
Exelon Generation Co
To:
Office of Nuclear Reactor Regulation
Shared Package
ML16127A520 List: ... further results
References
TMI-16-035
Download: ML16127A518 (34)


Text

TMI-1 UFSAR CHAPTER 13 13-i REV. 18, APRIL 2006 FSAR Chapter 13 "Initial Tests and Operations" is a reprint of the original FSAR Chapter 13.

Initial startup and test results were submitted in a report to the NRC dated November 27, 1974.

FSAR Chapter 13 is provided for historical information purposes only

CHAPTER 13 - INITIAL TEST AND OPERATION TABLE OF CONTENTS

SECTION TITLE 13.0 INITIAL TESTS AND OPERATION

13.1 TEST PROGRAM DESCRIPTION 13.1.1 ADMINISTRATIVE PROCEDURES (TESTING) 13.1.1.1 TEST PROCEDURES 13.1.1.2 TEST INDEX 13.1.1.3 PREREQUISITE LISTS 13.1.1.4 TEST SCHEDULES 13.1.1.5 TEST MANNING ASSIGNMENTS 13.1.1.6 TEST PLAN 13.1.1.7 TEST INSTRUCTIONS 13.1.2 ADMINISTRATIVE PROCEDURES (MODIFICATIONS) 13.1.3 TEST OBJECTIVES AND PROCEDURES 13.1.3.1 CONSTRUCTION TEST PHASE 13.1.3.2 PREOPERATIONAL TEST PHASE 13.1.4 FUEL LOADING AND INITIAL OPERATION 13.1.5 ADMINISTRATIVE PROCEDURES (SYSTEM OPERATION)

13.2 AUGMENTATION OF APPLICANT'S STAFF FOR INITIAL TESTS AND OPERATIONS 13.2.1 ORGANIZATIONAL FUNCTIONS, RESPONSIBILITIES, AND AUTHORITIES 13.2.1.1 GPU SERVICE CORPORATION (GPUSC) 13.2.1.2 UNITED ENGINEERS AND CONSTRUCTORS (UE&C) 13.2.1.3 METROPOLITAN EDISON COMPANY (MET-ED) 13.2.1.4 GILBERT ASSOCIATES, INC. (GAI) 13.2.1.5 BABCOCK & WILCOX, INC. (B&W) 13.2.1.6 GENERAL ELECTRIC CO. (GE) 13.2.2 INTERRELATIONSHIPS AND INTERFACES 13.2.2.1 PLANT OPERATIONS REVIEW COMMITTEE (PORC) 13.2.2.2 TEST WORKING GROUP (TWG) 13.2.2.3 DESIGNER, OWNER, TESTER (DOT) 13.2.3 PERSONNEL FUNCTIONS, RESPONSIBILITIES, AND AUTHORITIES 13.2.3.1 GPU TEST SUPERINTENDENT 13.2.3.2 GPU ASSISTANT TEST SUPERINTENDENT 13.2.3.3 GPU SHIFT TEST ENGINEER (STE) 13.2.3.4 GPU TECHNICAL ENGINEER 13.2.3.5 GPU COGNIZANT TEST ENGINEER 13.2.3.6 MET-ED ASSISTANT STATION SUPERINTENDENT

TMI-1 UFSAR TABLE OF CONTENTS (cont'd)

SECTION TITLE CHAPTER 13 13-ii REV. 18, APRIL 2006 13.2.3.7 MET-ED SUPERVISOR OF OPERATIONS 13.2.3.8 MET-ED SHIFT FOREMAN 13.2.3.9 UE&C LEAD STARTUP ENGINEER 13.2.3.10 NSSS SITE OPERATIONS MANAGER 13.2.3.11 TURBINE GENERATOR SUPPLIER SITE REPRESENTATIVE 13.2.3.12 ARCHITECT ENGINEER - STARTUP TEST ENGINEER 13.2.3.13 MET-ED TEST AUDITOR

TMI-1 UFSAR CHAPTER 13 13-iii REV. 18, APRIL 2006 LIST OF TABLES

TABLE TITLE 13.1-1 LIST OF TEST INSTRUCTIONS

13.1-2 SAFETY RELATED TESTS TO BE PERFORMED DURING PREOPERATIONAL AND INITIAL STARTUP TEST PHASES

13.1-3 HOT FUNCTIONAL TESTS

13.1-4 POWER ESCALATION TESTING PROGRAM

TMI-1 UFSAR CHAPTER 13 13-iv REV. 18, APRIL 2006 LIST OF FIGURES

FIGURE TITLE 13.2-1 TEST PROGRAM ORGANIZATION

TMI-1 UFSAR CHAPTER 13 13.1-1 REV. 18, APRIL 2006 13.0 INITIAL TESTS AND OPERATIONS

This chapter provides historical information on the Three Mile Island Nuclear Station Unit 1 (TMI-1) initial test program for structures, sy stems, components, and design features for both the nuclear and non-nuclear portions of the plant. The information provided addresses major

phases of the test program, including pre-operational tests, initial fuel loading and initial

criticality, low power tests, and power ascension tests, which were all performed prior to placing

the plant in commercial operation. The initial testing and operation program was conducted by

and for Metropolitan Edison Company, Jersey Central Power and Light Company, and

Pennsylvania Electric Company, which were the owners at that time. TMI-1 was operated by Metropolitan Edison Company.

13.1 TEST PROGRAM DESCRIPTION

A comprehensive initial testing and operation program was conducted at TMI-1. This program was intended to provide adequate confidence that t he structures, systems, and components will perform satisfactorily in service and that adequate records are retained. The program accomplishes this objective by testing structur es, systems, and components in accordance with written procedures to demonstrate that they comply with their design codes and standards.

The Test Program applies to all unit structures, systems, and components necessary to conduct commercial operation, and is initiated when they are tu rned over for construction tests from the Construction Manager, and is concluded when the direct responsibility for the unit is transferred

from the GPU Project Manager to the Met-Ed Generation Department for normal commercial

operations.

The program's objectives are accomplished by us ing written test procedures to demonstrate that the unit's structures, systems, and components comply with applicable codes and standards and perform, both separately and collecti vely, in compliance with their design criteria for normal and safety related functions.

13.1.1 ADMINISTRATIVE PROCEDURES (TESTING)

The test program was conducted in a planned and systematic fashion and in accordance with

procedures and policies contained in the Three Mile Island Nuclear Generating Station Test

Manual and individual Test Instructions.

Testing of the unit's structures, systems, and components was conducted in accordance with written test procedures. The completed test procedures, including data sheets, shall be

retained as proof that the test results are satisfactory.

Changes to the test program shall be made as necessary to improve the program or to incorporate modifications to existing technical or regulatory requirements that affect testing.

Changes to the instruction shall be approv ed by organizations originally approving the instructions prior to implementing the changes.

Only tests listed in the Master Test Index (MTX) are to be performed as part of the test program and these tests will only be conducted when they are authorized by the approved Test Plan.

TMI-1 UFSAR CHAPTER 13 13.1-2 REV. 18, APRIL 2006 13.1.1.1 Test Procedures

Test procedures contain the technical content of the test program. Design requirements and

test requirements are translated into test procedures which are used to demonstrate the ability

of structures, systems, or components to com ply with the requirements. Design requirements and test requirements are contained in documents such as Architect Engineer (AE) or Nuclear Steam Supply System (NSSS) Test Specific ations, FSAR, commitments to the regulatory agencies, equipment technical manuals, and applicable codes and standards. Test results are

recorded in test procedures and are reviewed and approved to ensure that test requirements have been satisfactorily met. Changes or exc eptions to test procedures are reviewed and approved by individuals from the same organizat ions that originally approved the procedure.

Exceptions (i.e., procedure changes that do not change scope or intent of the procedure) are

recorded in the procedure and must be approved after the test has been performed. Any

changes that affect the scope or the intent of the procedure must be approved prior to test

performance. Four types of test procedures shall be used in the Unit 1 Test Program. Their descriptions are as follows:

a. Individual Test Procedures

These procedures are prepared especially to dem onstrate the system's or unit's ability to comply with test requirements. Data are recorded for evaluation and proof of

satisfactory test performance.

b. Functional Verification Procedures

These procedures are prepared to demonstrate the ability of certain systems and components to operate normally within es tablished parameters and to obtain required test data. Functional Verification Procedures use Met-Ed's operating procedures to

provide the necessary test steps. The Functional Verification Procedure may require

minor deviations from the operating procedure to allow tests of various features, such as hi-low level alarms and automatic switching.

c. Generic Test Procedures

These procedures are used to perform construction tests and checkouts. They may be used to develop checklists and procedures for inspection, alignment, checkout, and

preliminary operation of systems and components.

These procedures require that data be obtained for evaluation of test results.

d. Special Procedures

These procedures are used to perform tests and operations that are not contained in Generic Test Procedures, Individual Test Procedures, or Functional Verification

Procedures, e.g., chemical cleaning and charcoal filter testing.

13.1.1.2 Test Index

The Test Index contains a description of the start-up testing to be performed on Unit 1. The Test Index also contains the MTX that lists all the structures and systems and their assigned test procedures. The MTX assigns safety related classifications to the structures and systems TMI-1 UFSAR CHAPTER 13 13.1-3 REV. 18, APRIL 2006 and assigns a safety related category to the test procedures. Only tests that are listed in the MTX will be performed unless specifically authorized by the GPU Test Superintendent.

The Test Index shall also contain a section to provide scopes for individual test procedures.

The scope shall consist of a description of the test's objectives, the source of test requirements, and source of acceptance criteria.

13.1.1.3 Prerequisite Lists

The prerequisite list contains all items that must be satisfactorily completed or in an appropriate state of readiness to support the start of major events. As a minimum, a prerequisite list shall be prepared for each test program milestone event. The list shall be periodically updated and

reviewed prior to commencing the associated event.

13.1.1.4 Test Schedules

The test schedule provides the sequence for test performance over a certain designated period

of time. The schedule provides the means for conducting an orderly test program and for

keeping management informed of testing progress.

13.1.1.5 Test Manning Assignments

The Test Manning Assignments provide a listing of stations to be manned by appropriate personnel during the conduct of complex tests.

Test Manning Assignments during the conduct of complex tests remain in effect until released by the Shift Test Engineer in charge of the test.

13.1.1.6 Test Plan

The Test Plan provides a short-range schedule to authorize performance of specific tests. The

Test Plan is issued at various intervals deter mined by testing activity and shall state the period for which it is valid. A new test plan will nor mally be issued before the validation date is past in order to ensure a continuation of testing. Tests shall be performed when contained in the valid

test plan.

The Test Plan is reviewed and approved at scheduled Test Planning Meetings.

13.1.1.7 Test Instructions

Test Instructions provide procedures for the administr ative control of the Test Program. A list of Test Instructions is contained in Table 13.1-1

13.1.2 ADMINISTRATIVE PROCEDURES (MODIFICATIONS)

The administrative procedures used for incorpor ating system modifications or procedure changes are contained in the Test Instructions.

TMI-1 UFSAR CHAPTER 13 13.1-4 REV. 18, APRIL 2006 13.1.3 TEST OBJECTIVES AND PROCEDURES

The Test Program is divided into three test phases: (1) Construction, (2) Preoperational, and

(3) Fuel Loading and Initial Operation. A description of each phase and its objectives follows.

13.1.3.1 Construction Test Phase

The construction test phase starts when the system, or partial system, is turned over to the GPU Startup Engineer and is completed when all assigned construction tests have been satisfactorily performed and the system accepted by Met-Ed for tests, operations, and maintenance.

The objective of construction tests is to demons trate that structures, systems, and components comply with applicable engineering drawings, codes, and standards and to verify that the

installed systems and components operate properly and are ready to support further operations and testing.

Construction tests consist of:

a. Fluid System Hydrostatic Tests

These tests are performed to demonstrate that the system complies with the acceptance criteria contained in applicable codes and standards. b. Fluid System Cleanliness Flushes

The tests are performed to clean the syst em and to demonstrate that the cleanliness requirements have been satisfactorily obtained.

c. Electrical System Checkouts
1) Power Distribution

These checkouts demonstrate that t he electrical distribution system complies with applicable plans, specifications, codes, and standards.

2) Control Circuits and Systems

These checkouts demonstrate that the individual electrical control circuits and systems function as designed.

3) Protective Devices

These checkouts demonstrate by operation under simulated conditions that the electrical system's protective devices function as designed.

d. Installed Instrumentation Checkouts

These checkouts demonstrate that the ins trumentation is properly aligned, calibrated, and capable of performing its designed function.

e. Preliminary Operation Tests TMI-1 UFSAR CHAPTER 13 13.1-5 REV. 18, APRIL 2006 The preliminary operational tests are performed to determine if there is any major deficiency in the systems or components.

This run-in period provides reasonable assurance that the system or component oper ates properly and is able to support further tests and operations. These tests and checkouts include items such as: lubrication, setting of limit switches, and setting of torque limiting devices.

13.1.3.2 Preoperational Test Phase

The preoperational test phase starts when a system, or partial system, is turned over to Met-Ed from the GPU Nuclear Start-up Engineer and ends at the start of initial fuel loading.

This phase consists of functional tests and verifications that demonstrate the component's

ability to perform its design function and of oper ational tests that demonstrate the system's ability to operate as designed under actual or simulated conditions. These tests are performed

on integrated systems or on an indiv idual system basis. Table 13.1-2 contains a listing of safety related tests that will be performed during preoperational and initial start-up test phases.

a. Hot Functional Testing

Hot functional tests will be performed during the preoperational phase. These tests demonstrate the ability of the Reactor Coolant System and associated auxiliary systems to operate properly at operating pressure and temperature. Table 13.1-3 contains a

listing of tests that will be performed during the hot functional test phase.

b. Vibration Surveillance Program

The first-of-a-kind reactor internals vibr ation surveillance program will be conducted on the prototype internals at Oconee. This pr ogram meets the requirements of Safety Guide No. 20 for Prototype Internals. The program includes vibration survey tests, analyses and description of forcing functions, v ibration analyses of the reactor internals, prediction of responses, vibration measur ements during hot functional testing, data analysis, acceptance criteria, and post-testing inspection of the reactor internals.

The TMI-1 vibration surveillance program will comply with the USNRC Reg. Guide No.

1.20 for Reactor Internals. The program consists of a detailed internals inspection both

prior to and following hot functional testing. In addition, the internals are subjected to at

least 10 7 cyclic stresses during HFT by running two or more reactor coolant pumps at hot, pressurized conditions for at least 278 hours0.00322 days <br />0.0772 hours <br />4.596561e-4 weeks <br />1.05779e-4 months <br />.

13.1.4 FUEL LOADING AND INITIAL OPERATION

The initial startup phase starts with initial fuel loading and ends upon completion of the power

escalation test program. Table 13.1-4 contains a list of tests that will be performed during the

initial startup phase. This phase consists of:

TMI-1 UFSAR CHAPTER 13 13.1-6 REV. 18, APRIL 2006

a. Initial Fuel Loading

Following the satisfactory completion and data evaluation of required preoperational tests and review of other initial fuel loading prerequisites, the Test Working Group will

allow fuel loading to commence.

An Initial Fueling Supervisor appointed by the GPU Project Manager will be responsible for supervising the initial fuel operations.

Fuel will be loaded into the reactor in accordance with a step-by-step written procedure.

This procedure, which contains a number of safety precautions and operating limitations, includes the following items:

1) A sequence of loading temporary detectors, sources, control rods, and fuel assemblies to maintain shutdown margin requirements.
2) Conditions under which fuel loading may continue after any step.
3) Identification of responsibility and authority.
4) During any reactivity changes, a m inimum of two detectors will be operating and indicating the neutron level after the source has been inserted. At all other times, at least one detector will indicate the neutron level.
5) Two completely independent plots of reciprocal neutron multiplications as a function of the parameter causing reactivity change will be maintained.
6) Reactivity effects for each fuel assembly addition will be checked before the fuel assembly is released by the fuel-handling grapple.
7) The reactivity effect for the next fuel addition will be estimated before the next fuel assembly is inserted.
8) The boron concentration in the reactor vessel, spent fuel pool, and Reactor Coolant System will be maintained at a v alue to ensure the required subcritical margin at all times.
9) The valve alignment of auxiliary syst ems connected to the Reactor Coolant System will be checked periodically to prevent dilution of the reactor coolant boron concentration.
10) Chemical analysis and water level monit oring will be conducted to ensure that inadvertent dilution of the boron concentration in the reactor coolant has not

occurred.

11) Communication between Control Room and fuel handling areas will be maintained.
12) Plant radiation monitoring systems as required for fuel loading will be in operation.

TMI-1 UFSAR CHAPTER 13 13.1-7 REV. 18, APRIL 2006

13) Health physics and chemistry m onitoring services will be provided.
14) Throughout the entire loading process, two persons, working independently, will verify fuel assembly identification and location within the core.
15) If an unexpected event or response occurs, loading will be suspended until the reason has been determined and an adequate evaluation made.
16) Two licensed Reactor Operators (one Senior Reactor Operator) as well as one additional experienced startup representative will be present at the facility

whenever fuel is moved into the reactor vessel.

b. Preparations for Initial Criticality

Upon completion of the initial fuel loading, pre-startup checks will be completed prior to the approach to initial criticality. Reactor Coolant Flow Test and Reactor Coolant Flow

Coastdown Test will be conducted under hot, pressurized reactor conditions to

determine the flow characteristics of the Reactor Coolant System after reactor core

installation.

c. Initial Criticality and Zero Power Physics Tests

A written procedure will be used as the controlling document for taking the primary system from a filled and vented condition following fuel loading through the zero power physics test program to a zero power, hot condition. This will be a step-by-step procedure that will list or reference all appropriate limits and precautions (including

technical specifications). It will incorporate or reference applicable steps in unit

operating procedures that have been modified and approved for use during the zero

power test program. The modified operating procedure steps will be blended with the

zero power test program to produce a preplanned, orderly, organized test sequence.

The step-by-step procedure ensures a safe, well-controlled test program. In cases

where performance of a particular step or ser ies of steps involves a significant safety consideration, a precautionary note will precede the step or steps.

d. Power Escalation Tests

TP 800/21, Unit Startup and Power Escalation Test Procedure, will be the controlling document for taking the unit from a zero power, hot condition through the various power

test plateaus up to commercial operation at licensed power. This will be a step-by-step

procedure that either incorporates or references applicable steps in normal approved unit operating procedures required to increase power from one test plateau to another

and maintain steady-state power at each te st plateau. The normal operating procedure steps will be blended with the power escalation test program to produce a preplanned, orderly, organized test sequence. The step-by-step procedure ensures a safe, well

controlled test program. All appropriate limits and precautions (including technical

specifications) will be listed or referenced in the applicable operating procedures, individual power escalation test procedures, or in the controlling document itself. In

cases where performance of a particular step or series of steps involves a significant safety consideration, a precautionary note will precede the step or steps in the

controlling document.

TMI-1 UFSAR CHAPTER 13 13.1-8 REV. 18, APRIL 2006 13.1.5 ADMINISTRATIVE PROCEDURES (SYSTEM OPERATION)

Upon acceptance of a system by Met-Ed for test and operations, the system will be operated in accordance with its normal operating procedure. The operating procedure will be revised as

necessary during this period and a final approved procedure issued.

Selected emergency operating procedures will be performed during the test program. Those

emergency procedures which are not possible to perform will be dry run by the station staff.

TMI-1 UFSAR CHAPTER 13 13.1-9 REV. 18, APRIL 2006 TABLE 13.1-1 (Sheet 1 of 1)

LIST OF TEST INSTRUCTIONS

TI-1 Repair Removal Authorization

TI-2 Test Plan

TI-3 Briefing and Dry Run

TI-4 Control of Test Records

TI-5 System Turnover

TI-6 Test Schedules

TI-7 GPU Startup Problem Report

TI-8 Unusual Occurrences

TI-9 Conduct of Test

TI-10 Prerequisite List

TI-11 Test Index

TI-12 Not used

TI-13 Test Interface Instructions

TI-14 Training and Qualifications of Test Personnel

TI-15 Not used

TI-16 Not used

TI-17 Shift Test Engineer's Log

TI-18 Test Procedure Documents

TI-19 Control of Test Equipment

TMI-1 UFSAR CHAPTER 13 13.1-10 REV. 18, APRIL 2006 TABLE 13.1-2 (Sheet 1 of 6)

SAFETY RELATED TESTS TO BE PERFORMED DURING PREOPERATIONAL AND INITIAL START-UP TEST PHASES

Test No. Title

SP 2 Filter Efficiency Tests MCP-15 Hanger Hot Setting Determination SP 53.10 Reactor Vessel Head Service Structure Temperature Profile Determination

SP 102.6 Fire Protection System Checkout TP 120/3 Fuel Handling System Integrated Functional Test TP 150/2 Reactor Building Structural Integrity Test TP 150/3 Initial Reactor Building Leak Rate Test (ILRT)

TP 150/4 Post Accident Hydrogen Purge System Functional Test TP 151/1 Reactor Building Isolation Valve Leak Test TP 153/3 Fluid Block System Functional Test TP 153/4 Fluid Block System Actuation Time Determination TP 154/3 Penetration Pressurization Operational Test TP 160/2 R. B. Emergency Cooling Water System TP 160/3 Reactor Building Purge System Functional Test TP 160/4 R. B. Fans Functional Test SP 166.2 Plant Test Panel Pre-op. Alignment TP 172/2A Control Building Ventilation Functional Test Part A - Compressed Air System

TP 172/2B Control Building Ventilation System Functional Test - Part B - Control Building Chilled Water System

TP 172/2C Control Building Ventilation System Functional Test Section C: Control Building Heating and Ventilation System

TP 180/3 Fire Service System Functional Test TP 200/1 Reactor Internals Vent Valve Inspection Test TP 200/4 Reactor Coolant System Hydrostatic Test TMI-1 UFSAR CHAPTER 13 13.1-11 REV. 18, APRIL 2006 TABLE 13.1-2 (Sheet 2 of 6)

SAFETY RELATED TESTS TO BE PERFORMED DURING PREOPERATIONAL AND INITIAL START-UP TEST PHASES

Test No. Title

TP 200/11A Reactor Coolant Pump Flow Test Part A - Cold, No Core TP 200/11C Reactor Coolant Pump Flow Test Part C - Hot, No Core TP 200/11D Reactor Coolant Pump Flow Test Part D - Hot, With Core TP 200/12A Reactor Coolant Flow Coastdown Test Part A - Cold, No Core TP 200/12B Reactor Coolant Flow Coastdown Test Part B - Cold, With Core TP 200/12C Reactor Coolant Flow Coastdown Test Part C - Hot, No Core TP 200/12D Reactor Coolant Flow Coastdown Test Part D - Hot, With Core TP 201/2 Core Flooding System Functional Test TP 201/5 Core Flood Flow Test SP 201.19 Reactor Coolant Pump Vibration Test TP 202/3 Makeup and Purification System Functional Test TP 202/7 Makeup and Purification System E. S. Test TP 203/1 Decay Heat Removal System B. W. S. T. Functional Test TP 203/4 Decay Heat Removal System Functional Test TP 203/7 Decay Heat Removal System E. S. Test TP 204/3 Reactor Building Spray System Functional Test TP 230/3 Liquid Waste Disposal System - Transfers To and From the Reactor Coolant and Miscellaneous Waste Evaporator Feed Tanks

TP 230/4 Liquid Waste Disposal System - Star t-up, Operation, and Transfers From the Reactor Coolant, and Miscellaneous Waste Evaporators

TP 230/8 Solid Waste Disposal System Test TP 231/3 Gaseous Waste Disposal System Functional Test TP 240/3 Intermediate Cooling System Functional Test TP 251/1 Reactor Building Sump, Auxiliary Building Sump and Compartment Leak Detector Functional Test

TMI-1 UFSAR CHAPTER 13 13.1-12 REV. 18, APRIL 2006 TABLE 13.1-2 (Sheet 3 of 6)

SAFETY RELATED TESTS TO BE PERFORMED DURING PREOPERATIONAL AND INITIAL START-UP TEST PHASES

Test No. Title SP 254.33 Turbine Generator Initial Operation TP 256/3 Instrument and Control Air System Functional Test TP 256/4 Loss of Instrument Air Test TP 263/4 Decay Heat River Water System Functional Test TP 264/4 Decay Heat Closed Cooling System Functional Test TP 266/4 Nuclear Service River Water Functional Test TP 267/4 Nuclear Service Closed Cooling Water System Functional Test TP 271/4 Main and Auxiliary Steam System Functional Test TP 273/3 Emergency Feedwater Turbine and Motor-Driven Pumps Functional Test TP 301/2 Nuclear Instrumentation Detector Cabling and Response Tests TP 301/3A Nuclear Instrumentation Pre-Op. Calibration (Source Range)

TP 301/3B Nuclear Instrumentation Pre-Op. Calibration (Intermediate Range)

TP 301/3C Nuclear Instrumentation Pre-Op. Calibration (Power Range)

TP 301/3D Determination and Setting of Detector Voltages TP 305/1A Reactor Protection System Initial Power Application TP 305/1B Reactor Protection System Preoperational Calibration TP 305/2 Reactor Protection System Response Time SP 330/1 Control Rod Drive Pre-Op. Calibration TP 330/2 CRD Control System Operational Test TP 330/3 Control Rod Drive Mechanism Functional Test TP 330/3A Post Core Load CRDM Functional Test TP 330/4 Integrated CRD System Test TP 330/5 CRD Trip Test TP 360/1A Process Radiation Monitor Calib. and Functional Test for Portable Atmospheric Monitors TMI-1 UFSAR CHAPTER 13 13.1-13 REV. 18, APRIL 2006 TABLE 13.1-2 (Sheet 4 of 6)

SAFETY RELATED TESTS TO BE PERFORMED DURING PREOPERATIONAL AND INITIAL START-UP TEST PHASES

Test No. Title TP 360/1B Process Radiation Monitor Calibration and Functional Test for Fixed Atmospheric Monitors TP 360/1C Process Radiation Monitor C alibration and Functional Test for Liquid Monitors

TP 360/2 Area Radiation Monitoring Calibration and Functional Test TP 401/1 Diesel Generator Startup Test TP 401/3 Station Battery Discharge and Charge Test TP 500/3 Initial Radiochemistry Test TP 600/1 Unit Heatup Test TP 600/3 Soluble Poison Concentration Control Test TP 600/4 Makeup and Purification System Operational Procedure TP 600/5 Nuclear Chemical Addition and Sampling System Operational Test TP 600/6A Liquid Waste Disposal System Operational Test TP 600/7 Intermediate Cooling System Operational Test TP 600/10 RCS Hot Leakage Test TP 600/11 Emergency Feed System and OTSG Level Control Test TP 600/13 Pressurizer Operation and Spray Flow Test TP 600/14 Pipe and Component Hanger Hot Deflection and Inspection Test TP 600/15 Non-Nuclear Instrumentation Hot Operation and Calibration TP 600/17 Control Rod Drive Operational Test TP 600/20 Loss of Electrical Power Test (Without E. S.)

TP 600/21 Integrated E. S. Actuation Test TP 600/23 Reactor Protection System Functional Test TP 600/24 Unit Cooldown Test

TMI-1 UFSAR CHAPTER 13 13.1-14 REV. 18, APRIL 2006 TABLE 13.1-2 (Sheet 5 of 6)

SAFETY RELATED TESTS TO BE PERFORMED DURING PREOPERATIONAL AND INITIAL START-UP TEST PHASES

Test No. Title TP 600/28 Controlling Procedure for HFT TP 600/29 Reactor Coolant System Thermal Expansion Functional Test TP 600/30 HFT Checkpoints TP 710/1 Zero Power Test SP 710/2 Controlling Procedure for Post Fuel Load Precritical Testing TP 800/2 NI Calibration at Power TP 800/3 Biological Shield Survey TP 800/5 Reactivity Coefficients at Power TP 800/6 Turbine Bypass System Test TP 800/7 Feedwater System Operation and Testing TP 800/8 ICS Tuning at Power TP 800/9 Turbine Generator Operational Testing TP 800/11 Core Power Distribution TP 800/12 Unit Load Steady State Test TP 800/14 Turbine/Reactor Trip Test TP 800/16 Reactivity Depletion vs Burnup TP 800/17 Unit Acceptance Test TP 800/18 Power Imbalance Detector Correlation Test TP 800/20 Rod Reactivity Worth Measurement TP 800/21 Unit Startup and Power Escalation Test TP 800/22 NSS Heat Balance TP 800/23 Unit Load Transient Test TP 800/24 Incore Detector Testing TP 800/30 Power Escalation Check Points

TMI-1 UFSAR CHAPTER 13 13.1-15 REV. 18, APRIL 2006 TABLE 13.1-2 (Sheet 6 of 6)

SAFETY RELATED TESTS TO BE PERFORMED DURING PREOPERATIONAL AND INITIAL START-UP TEST PHASES

Test No. Title TP 800/31 Pseudo Dropped Rod TP 800/32 Loss of Offsite Power Test TP 800/33 Pseudo Rod Ejection Test TP 800/34 Generator Trip Test TP 800/35 Effluent and Effluent Monitoring System Test TP 800/36 Shutdown From Outside the Control Room as Modified for Hot Functional Testing F 1104/6 Spent Fuel Cooling System Functional Verification F 1104/24B Screen House Ventilation Functional Verification (Including River Water)

F 1104/29A Liquid Waste Disposal System Functional Verification (Reactor Coolant Cleanup Processes)

F 1104/29D Liquid Waste Disposal System Functional Verification - Part D - Decay Heat Water Cleanup Process

F 1104/29E Liquid Waste Disposal System Functional Verification - Part E - Bleed and Feed Processes

F 1104/29I Liquid Waste Disposal System Functional Verification - Part I - Transfer From Reactor Coolant Drain Tank

F 1104/29J Liquid Waste Disposal System Functional Verification - Part J - Transfers Through Reactor Drain Pump

F1104/29Y Liquid Waste Disposal System Functional Verification - Part Y - Operation and Use of the Precoat Filters

TMI-1 UFSAR CHAPTER 13 13.1-16 REV. 18, APRIL 2006 TABLE 13.1-3 (Sheet 1 of 2)

HOT FUNCTIONAL TESTS

Test No. Title

MCP-15 Hanger Hot Setting Determination SP 53.10 Reactor Vessel Head Service Structure Temperature Profile Determination

SP 166.2 Plant Test Panel Pre-op. Alignment TP 200/1 Reactor Internals Vent Valve Inspection Test TP 200/11C Reactor Coolant Pump Flow Test Part C - Hot, No Core TP 200/12C Reactor Coolant Flow Coastdown Test Part C - Hot, No Core SP 201.19 Reactor Coolant Pump Vibration Test TP 202/7 Makeup and Purification System E. S. Test TP 203/7 Decay Heat Removal E. S. Test SP 254.33 Turbine Generator Initial Operation TP 271/4 Main and Auxiliary Steam System Functional Test TP 330/3 Control Rod Drive Mechanism Functional Test TP 330/4 Integrated CRD System Test TP 500/3 Initial Radiochemistry Test TP 600/1 Unit Heatup Test TP 600/3 Soluble Poison Concentration Control Test TP 600/4 Makeup and Purification System Operational Procedure TP 600/5 Nuclear Chemical Addition and Sampling System Operational Test TP 600/6A Liquid Waste Disposal System Operational Test TP 600/7 Intermediate Cooling System Operational Test TP 600/10 RCS Hot Leakage Test TP 600/11 Emergency Feed System and OTSG Level Control Test TP 600/13 Pressurizer Operation and Spray Flow Test TP 600/14 Pipe and Component Hanger Hot Deflection and Inspection Test

TMI-1 UFSAR CHAPTER 13 13.1-17 REV. 18, APRIL 2006 TABLE 13.1-3 (Sheet 2 of 2)

HOT FUNCTIONAL TESTS

Test No. Title

TP 600/15 Non-Nuclear Instrumentation Hot Operation and Calibration TP 600/17 Control Rod Drive Operational Test TP 600/20 Loss of Electrical Power Test (Without E. S.)

TP 600/21 Integrated E. S. Actuation Test TP 600/23 Reactor Protection System Functional Test TP 600/24 Unit Cooldown Test TP 600/28 Controlling Procedure for HFT TP 600/29 Reactor Coolant System Thermal Expansion Functional Test TP 600/30 HFT Checkpoints TP 800/36 Shutdown From Outside the Control Room as Modified for Hot Functional Testing TMI-1 UFSAR CHAPTER 13 13.1-18 REV. 18, APRIL 2006 TABLE 13.1-4 (Sheet 1 of 6)

POWER ESCALATION SEQUENCE TABLE

Test Procedure No.

POWER LEVEL (%) TP 500/3 TP 710/1 SP 710/2 TP 800/2 TP 800/3

0 - 15 (ZPPT) (ZPPT) (Pre-ZPPT) X (ZPPT) 15 X

15-25 25 DAILY

30 35 40 X X

50 60 70 76 X

85 95 100 X X

Test No. Title

TP 500/3 Initial Radiochemistry Test TP 710/1 Zero Power Test SP 710/2 Controlling Procedure for Post Fuel Load Pre-critical Testing TP 800/2 NI Calibration at Power TP 800/3 Biological Shield Survey

TMI-1 UFSAR CHAPTER 13 13.1-19 REV. 18, APRIL 2006 TABLE 13.1-4 (Sheet 2 of 6)

POWER ESCALATION SEQUENCE TABLE

Test Procedure No.

POWER LEVEL (%) TP 800/5 TP 800/6 SP 800/7 TP 800/8 TP 800/9

0 - 15 X X 15 X X X 15-25 X

25 30 X

35 40 X X X X

50 60 70 76 X X X X

85 95 100 X X X X X

Test No. Title

TP 800/5 Reactivity Coefficients at Power TP 800/6 Turbine Bypass System Test SP 800/7 Feedwater System Operation and Testing TP 800/8 ICS Tuning at Power TP 800/9 Turbine-Generator Operational Testing

TMI-1 UFSAR CHAPTER 13 13.1-20 REV. 18, APRIL 2006 TABLE 13.1-4 (Sheet 3 of 6)

POWER ESCALATION SEQUENCE TABLE

Test Procedure No.

POWER LEVEL (%) TP 800/11 TP 800/12 TP 800/14 TP 800/16 TP 800/17

0 - 15 X 20, 30, 40 and 15 X X 50 effective 15-25 full power days 25 X

30 X T

35 X

40 X X X R

50 X

60 X

70 X

76 X X

85 X

95 X

100 X X X

Test No. Title

TP 800/11 Core Power Distribution TP 800/12 Unit Load Steady State Test SP 800/14 Turbine/Reactor Trip Test TP 800/16 Reactivity Depletion vs. Burnup TP 800/17 Unit Acceptance Test

TMI-1 UFSAR CHAPTER 13 13.1-21 REV. 18, APRIL 2006 TABLE 13.1-4 (Sheet 4 of 6)

POWER ESCALATION SEQUENCE TABLE Test Procedure No.

POWER LEVEL (%) TP 800/18 TP 800/20 TP 800/21 TP 800/22 TP 800/23

0 - 15 X X

15 X X

15-25 X

25 X X X

30 X

35 X X

40 X X X X X

50 X X

60 X X

70 X X

76 X X X X X

85 X X

95 X X

100 X X X X

Test No. Title

TP 800/18 Power Imbalance Detector Correlation Test TP 800/20 Rod Reactivity Worth Measurement SP 800/21 Unit Startup and Power Escalation Test TP 800/22 NSS Heat Balance TP 800/23 Unit Load Transient Test

TMI-1 UFSAR CHAPTER 13 13.1-22 REV. 18, APRIL 2006 TABLE 13.1-4 (Sheet 5 of 6)

POWER ESCALATION SEQUENCE TABLE Test Procedure No.

POWER LEVEL (%) TP 800/24 TP 800/30 TP 800/31 TP 800/32 TP 800/33

0 - 15

15 X X X 1

15-25

25 X

30

35 X

40 X X X X

50

60

70

76 X X

85

95

100 X

Test No. Title

TP 800/24 Incore Detector Testing TP 800/30 Power Escalation Check Points SP 800/31 Pseudo Dropped Rod TP 800/32 Loss of Offsite Power Test TP 800/33 Pseudo Rod Ejection Test

TMI-1 UFSAR CHAPTER 13 13.1-23 REV. 18, APRIL 2006 TABLE 13.1-4 (Sheet 6 of 6)

POWER ESCALATION SEQUENCE TABLE Test Procedure No.

POWER LEVEL (%) TP 800/34 TP 800/35 TP 800/36 MCP-15

0 - 15 15 (ZPPT) (X) X 1 X 15 - 25 25 30 35 40 X X

50 60 70 76 X X

85 95 100 X X X

Test No. Title TP 800/34 Generator Trip TP 800/35 Effluent and Effluent Monitoring System Test SP 800/36 Shutdown from Outside Control Room As Modified for Hot Functional Testing MCP-15 Hanger Hot Setting Determination

Where (ZPPT) = During zero power physics test and X = 10 percent generator output

X 1 = turbine trip X

T = reactor trip

Note: Major power plateaus are 15, 40, 76 and 100 percent full power

TMI-1 UFSAR CHAPTER 13 13.2-1 REV. 18, APRIL 2006 13.2 AUGMENTATION OF APPLICANT'S STAFF FOR INITIAL TESTS AND OPERATIONS

Met-Ed, a subsidiary of GPU, is the responsible owner and applicant for TMI-1. Met-Ed, via a

service agreement, is utilizing the services of t he GPU Service Corporation, which is the agent for the owners. The Design and Construction Division of the GPU Service Corporation, acting

for Met-Ed, is responsible for conduct of the test program until the unit is declared commercial.

The Test Program Organization for TMI-1 is shown on Figure 13.2-1.

13.2.1 ORGANIZATIONAL FUNCTIONS, RESPONSIBILITIES, AND AUTHORITIES

13.2.1.1 GPU Service Corporation (GPUSC)

a. GPU Startup and Test Department (GPU Engineering)

The GPU Startup and Test Department is responsible for the administrative and technical content of the test program. The Start-up and Test Department has assigned a

Test Superintendent to the Three Mile Island nuclear project to administer the test

program and act as chairman of the Test Working Group.

b. GPU Projects

GPU Projects is responsible for the overall conduct of the project, including the test program. This responsibility is carried out by the GPU Test Superintendent for the GPU

Project Manager, Three Mile Island.

c. GPU Quality Assurance Department

The GPU Quality Assurance Department is responsible for the administration of the GPUSC Startup and Test Quality Assurance Plan.

13.2.1.2 United Engineers And Constructors (UE&C)

a. Construction Division (Construction Manager)

UE&C as Construction Manager is responsible for the construction of the unit in accordance with drawings and specifications. This responsibility includes the

completion of the systems, or partial system s, in a sequence that will allow efficient and orderly testing. The Construction Division provides craft support for tests and to correct

deficiencies.

b. Startup Department

The UE&C Startup Department is responsible for preparation and conduct of construction-related tests and checkouts and subsequent turnover of systems/equipment to Met-Ed. The Startup Department assigns a Lead Startup Engineer and staff to

conduct construction tests and checkouts under the technical and operational direction

of the GPU Test Superintendent.

TMI-1 UFSAR CHAPTER 13 13.2-2 REV. 18, APRIL 2006

c. Field Quality Control Group

The UE&C Field Quality Control Group is responsible for performing the required inspection of construction tests and checkouts in accordance with Quality Control

procedures and checklists.

13.2.1.3 Metropolitan Edison Company (MET-ED)

a. Station Supervisory Staff

The station supervisory staff is responsible for the operation and maintenance of systems and equipment after acceptance from the UE&C Startup Department. This responsibility includes operating systems in accordance with test procedures to perform

preoperational and initial startup tests. Met-Ed assigns a voting representative to the

Test Working Group.

b. Met-Ed System Engineering

Met-Ed System Engineering is responsible for the control of tests, checkouts, and the acceptance of results for all protective relays, substations, and switchgear. System

Engineering is also responsible for the design review of the substation switchyards.

13.2.1.4 Gilbert Associates, Inc. (GAI)

Gilbert Associates, Inc. is the AE for Unit 1. As the AE, they are responsible for the entire

design of the unit, except those portions designed by the owner, the turbine generator supplier, and the NSSS supplier. This responsibility includes incorporating those items required to

support the NSSS and the Turbine Generator System. The AE assigns a voting representative to the Test Working Group.

13.2.1.5 Babcock And Wilcox, Inc. (B&W)

B&W is the NSSS supplier for Unit 1. B&W is responsible for the design and delivery of the

NSSS and assigns a voting representative to the Test Working Group.

13.2.1.6 General Electric Co. (GE)

General Electric Co. supplies the turbine generator for Unit 1. They are responsible for the

design and delivery of the turbine generating unit and pr ovide a site representative to concur in test procedures for tests of the turbine generator and associated equipment and systems.

13.2.2 INTERRELATIONSHIPS AND INTERFACES

13.2.2.1 Plant Operations Review Committee (PORC)

PORC reviews safety related test procedures.

This review is coordinated through the Met-Ed Station Superintendent's Test Working Group representative. A complete description of the

duties and responsibilities of PORC is contained in Chapter 15 (Technical Specifications).

TMI-1 UFSAR CHAPTER 13 13.2-3 REV. 18, APRIL 2006 13.2.2.2 Test Working Group (TWG)

The TWG is the coordinating body for the Start-up Test Program. The TWG functions in such a

manner as to assure that all safety related testing is conducted properly and that all test

requirements are satisfactorily met. All appr ovals by the TWG will be indicated by all voting members' signatures.

The TWG's responsibilities include the following items:

. Approval of milestone and prerequisite lists.

. Approval of project test sequence.

. Conduct of review and approval of safety related test procedures.

. Approval of changes to safety related test procedures.

. Review and approval of test results of safety related test procedures.

. Review and approval of the scope of the test program contained in the Test Index.

The TWG membership shall consist of one member and at least one alternate member from the

following organizations: GPU Startup and Test, B&W, Gilbert Associates, and Met-Ed Station

Supervisory Staff. The Met-Ed Generation D epartment assigns a nonvoting member to the TWG to act as Test Auditor. The following is a list of the TWG membership, qualifications, requirements, and a brief description of their duties and responsibilities.

a. GPU Startup and Test Representative

The GPU Test Superintendent is the TWG chairman and a voting member. As chairman, he is responsible to convene and conduct TWG meetings, as necessary, and

to achieve agreement of its voting members for the technical and administrative content of the test program.

b. Architect Engineer Representative

A senior Startup and Test Engineer and alternate shall be assigned by the AE as a TWG voting member.

He shall be responsible for the technical content of testing for that portion of the unit designed by the AE. The AE member of the TWG has received his M.S. degree in

Nuclear Engineering from the University of Washington and has had eight years of experience in the commercial nuclear power field. Four of those years he was Project

Engineer on a 450-MWe pressurized water reactor which involved equipment

specification and procurement, fluid system design, and startup and test program resolution of design deficiencies. This also included the startup and testing of a second

pressurized water reactor in Japan. The remaining four years have been spent on the

TMI project in the following areas: obtaining AE design completions for startup; obtaining

AE resolution for system design deficiencies; obtaining data for AE engineering TMI-1 UFSAR CHAPTER 13 13.2-4 REV. 18, APRIL 2006 evaluations; approving field changes; coordinating design interfaces with NSSS and turbine generator vendor; and functioning as a TWG member.

c. Nuclear Steam Supply System Representative

The B&W Site Operations Manager and his alternate are assigned as a TWG voting member. He is responsible for the technical content of testing for the NSSS.

d. Met-Ed Station Supervisory Staff Representative

The Assistant Station Superintendent and alternate are assigned as TWG voting members for Unit 1. He represents the utility owner and is responsible for the proper

operation of the unit. His signature, when associated with TWG approval of test

procedures for safety related systems, indicat es that the PORC review is complete and their comments are satisfactorily resolv ed. His qualifications are contained in Chapter

12.
e. Med-Ed Generation Department

The Met-Ed Generation Department shall assign a test auditor to provide independent evaluation of the action taken by the TWG. He is not a voting member, and his

signature is not required on TWG test documents. His primary responsibilities are to

assure that the actions taken by the TWG do not cause a deviation from the Test

Manual, the technical specifications, or other requirements contained in the FSAR, warranties, or design documents. He shall report results of his review to the GPU

Project Manager, GPU Startup and Testing Manager, and Met-Ed Manager -

Generation.

13.2.2.3 Designer, Owner, Tester (DOT)

This group is established to review and approve the technical content of test procedures that

are not appropriate for TWG approval. This group cons ists of representatives from GPU Startup and Test, the designer (B&W or GAI), and the Met-Ed Station Supervisory staff. DOT-approved

test procedures do not require PORC review.

The DOT representatives' duties and responsibilities for non safety related systems are similar to those assigned to TWG members for safety related systems.

13.2.3 PERSONNEL FUNCTIONS, RESPONSIBILITIES, AND AUTHORITIES

13.2.3.1 GPU Test Superintendent

He is responsible to the GPU Startup and Test Manager for technical content and to the TMI

Project Manager for the administration of the test program. He is chairman of DOT and TWG.

He assigns a representative of GPU Start-up and Test to be a voting member of Test Planning

Meetings.

TMI-1 UFSAR CHAPTER 13 13.2-5 REV. 18, APRIL 2006 13.2.3.2 GPU Assistant Test Superintendent

He is responsible to the GPU Test Superintendent for planning, scheduling, and conducting all

preoperational and initial start-up testing. Other duties are assigned by the GPU Test

Superintendent.

13.2.3.3 GPU Shift Test Engineer (STE)

He is responsible to the GPU Assistant Test Superintendent for conduct and inspection of

preoperational and initial startup tests in accordance with test instructions and test procedures.

He directs the conduct of tests through the Met-Ed Shift Foreman.

13.2.3.4 GPU Technical Engineer

He is responsible to the GPU Test Superintendent for the preparation of all test procedures, except construction tests. This includes sc heduling the review and approval of procedures to support the test schedule.

13.2.3.5 GPU Cognizant Test Engineer

He is responsible to the GPU Technical Engineer for preparation of test procedures in

accordance with test instructions and applicable test requirements. He may assist the Shift Test

Engineers in conducting tests.

13.2.3.6 Met-Ed Assistant Station Superintendent

He is responsible to the Met-Ed Station Superintendent for the proper operation and

maintenance of the unit during the preoperational and initial startup test phase. He has been

designated as the Met-Ed member of the TWG and DOT for Unit 1. He shall assign a member

of the station staff to be a voting member of test planning meetings.

13.2.3.7 Met-Ed Supervisor Of Operations

The Supervisor of Operations for Unit 1 is responsible to the Met-Ed Assistant Station

Superintendent for the operation of the unit during the preoperational and initial startup phase.

He is responsible to operate systems and co mponents in accordance with approved operating procedures and perform tests in accordance with approved test procedures.

3.2.3.8 Met-Ed Shift Foreman

He is responsible to the Met-Ed Supervisor of Operations for directing the operation of systems

and equipment after acceptance by the utility owner. He directs the operation of unit systems and equipment in accordance with approved operating and test procedures. He orders test

steps contained in approved test procedures to be performed when requested by the GPU Shift Test Engineer during performance of preoperational and initial startup testing.

TMI-1 UFSAR CHAPTER 13 13.2-6 REV. 18, APRIL 2006 13.2.3.9 UE&C Lead Start-up Engineer

He is responsible to the GPU Test Superintendent for preparation of construction test

procedures and conduct of construction tests and checkouts, in accordance with those

procedures. He is responsible for scheduling construction tests to provide a consistent interface

sequence with the preoperational test phase and assigns a Start-up Engineer to attend and

participate as a voting member in the test planning meetings. He acts as test program liaison

with the Construction Manager for providing craft support of test and correction of deficiencies.

13.2.3.10 NSSS Site Operations Manager

He provides advice and consultation for test and test-related matters for the NSSS and is the

B&W Project Manager's onsite representative for test-related matters. His responsibilities

include the following:

a. Provision of test specifications prepared by B&W to GPU and preparation of designated test procedures as requested by the GP U Project Manager, and providing them to the GPU Test Superintendent for incorporation into the test program.
b. Responsibility for the technical content of testing relating to the NSSS.
c. Scheduling technical assistance from within the NSSS or its vendors, as required.
d. Attending and participating as a voting member of the Test Planning Meeting.
e. Attending and participating as a voting member of the TWG and DOT.
f. Coordinating the implementation of approved B&W related field changes with the GPU Test Superintendent for systems under test control.
g. Responsibility for obtaining resolution of design and operational problems associated with testing or operation of systems and equipment within the NSSS scope of supply.

13.2.3.11 Turbine Generator Supplier Site Representative

He provides test requirements for test procedures associated with the turbine generator and

concurs with those procedures prior to test performance.

13.2.3.12 Architect Engineer - Startup Test Engineer

He provides engineering liaison service for the te st program and that portion of the unit designed by the AE. In addition, he shall have the following responsibilities:

a. Provides test procedures as requested by GPU Project Manager and submits them to the GPU Test Superintendent for incorporation into the test program.
b. Responsible for the technical content of balance-of-plant testing.
c. Attends and participates as a voting member in test planning meetings.

TMI-1 UFSAR CHAPTER 13 13.2-7 REV. 18, APRIL 2006

d. Participates as a voting member of TWG and DOT.
e. Responsible for obtaining resolutions of design problems associated with the test and operation of systems within the AE's design scope. When requested by the GPU Test

Superintendent, he also obtains resolutions for design problems associated with test and

operation of equipment purchased to specifications provided by the AE.

f. Coordinates the implementation of approved AE related field changes with the GPU Test Superintendent for systems under test control.

13.2.3.13 Met-Ed Test Auditor

He is responsible for auditing and reporting action taken by TWG as discussed in Item e. of

Subsection 13.2.2.2.

TMI-1 UFSAR CHAPTER 13 13-i REV. 18, APRIL 2006 FSAR Chapter 13 "Initial Tests and Operations" is a reprint of the original FSAR Chapter 13.

Initial startup and test results were submitted in a report to the NRC dated November 27, 1974.

FSAR Chapter 13 is provided for historical information purposes only

CHAPTER 13 - INITIAL TEST AND OPERATION TABLE OF CONTENTS

SECTION TITLE 13.0 INITIAL TESTS AND OPERATION

13.1 TEST PROGRAM DESCRIPTION 13.1.1 ADMINISTRATIVE PROCEDURES (TESTING) 13.1.1.1 TEST PROCEDURES 13.1.1.2 TEST INDEX 13.1.1.3 PREREQUISITE LISTS 13.1.1.4 TEST SCHEDULES 13.1.1.5 TEST MANNING ASSIGNMENTS 13.1.1.6 TEST PLAN 13.1.1.7 TEST INSTRUCTIONS 13.1.2 ADMINISTRATIVE PROCEDURES (MODIFICATIONS) 13.1.3 TEST OBJECTIVES AND PROCEDURES 13.1.3.1 CONSTRUCTION TEST PHASE 13.1.3.2 PREOPERATIONAL TEST PHASE 13.1.4 FUEL LOADING AND INITIAL OPERATION 13.1.5 ADMINISTRATIVE PROCEDURES (SYSTEM OPERATION)

13.2 AUGMENTATION OF APPLICANT'S STAFF FOR INITIAL TESTS AND OPERATIONS 13.2.1 ORGANIZATIONAL FUNCTIONS, RESPONSIBILITIES, AND AUTHORITIES 13.2.1.1 GPU SERVICE CORPORATION (GPUSC) 13.2.1.2 UNITED ENGINEERS AND CONSTRUCTORS (UE&C) 13.2.1.3 METROPOLITAN EDISON COMPANY (MET-ED) 13.2.1.4 GILBERT ASSOCIATES, INC. (GAI) 13.2.1.5 BABCOCK & WILCOX, INC. (B&W) 13.2.1.6 GENERAL ELECTRIC CO. (GE) 13.2.2 INTERRELATIONSHIPS AND INTERFACES 13.2.2.1 PLANT OPERATIONS REVIEW COMMITTEE (PORC) 13.2.2.2 TEST WORKING GROUP (TWG) 13.2.2.3 DESIGNER, OWNER, TESTER (DOT) 13.2.3 PERSONNEL FUNCTIONS, RESPONSIBILITIES, AND AUTHORITIES 13.2.3.1 GPU TEST SUPERINTENDENT 13.2.3.2 GPU ASSISTANT TEST SUPERINTENDENT 13.2.3.3 GPU SHIFT TEST ENGINEER (STE) 13.2.3.4 GPU TECHNICAL ENGINEER 13.2.3.5 GPU COGNIZANT TEST ENGINEER 13.2.3.6 MET-ED ASSISTANT STATION SUPERINTENDENT

TMI-1 UFSAR TABLE OF CONTENTS (cont'd)

SECTION TITLE CHAPTER 13 13-ii REV. 18, APRIL 2006 13.2.3.7 MET-ED SUPERVISOR OF OPERATIONS 13.2.3.8 MET-ED SHIFT FOREMAN 13.2.3.9 UE&C LEAD STARTUP ENGINEER 13.2.3.10 NSSS SITE OPERATIONS MANAGER 13.2.3.11 TURBINE GENERATOR SUPPLIER SITE REPRESENTATIVE 13.2.3.12 ARCHITECT ENGINEER - STARTUP TEST ENGINEER 13.2.3.13 MET-ED TEST AUDITOR

TMI-1 UFSAR CHAPTER 13 13-iii REV. 18, APRIL 2006 LIST OF TABLES

TABLE TITLE 13.1-1 LIST OF TEST INSTRUCTIONS

13.1-2 SAFETY RELATED TESTS TO BE PERFORMED DURING PREOPERATIONAL AND INITIAL STARTUP TEST PHASES

13.1-3 HOT FUNCTIONAL TESTS

13.1-4 POWER ESCALATION TESTING PROGRAM

TMI-1 UFSAR CHAPTER 13 13-iv REV. 18, APRIL 2006 LIST OF FIGURES

FIGURE TITLE 13.2-1 TEST PROGRAM ORGANIZATION

TMI-1 UFSAR CHAPTER 13 13.1-1 REV. 18, APRIL 2006 13.0 INITIAL TESTS AND OPERATIONS

This chapter provides historical information on the Three Mile Island Nuclear Station Unit 1 (TMI-1) initial test program for structures, sy stems, components, and design features for both the nuclear and non-nuclear portions of the plant. The information provided addresses major

phases of the test program, including pre-operational tests, initial fuel loading and initial

criticality, low power tests, and power ascension tests, which were all performed prior to placing

the plant in commercial operation. The initial testing and operation program was conducted by

and for Metropolitan Edison Company, Jersey Central Power and Light Company, and

Pennsylvania Electric Company, which were the owners at that time. TMI-1 was operated by Metropolitan Edison Company.

13.1 TEST PROGRAM DESCRIPTION

A comprehensive initial testing and operation program was conducted at TMI-1. This program was intended to provide adequate confidence that t he structures, systems, and components will perform satisfactorily in service and that adequate records are retained. The program accomplishes this objective by testing structur es, systems, and components in accordance with written procedures to demonstrate that they comply with their design codes and standards.

The Test Program applies to all unit structures, systems, and components necessary to conduct commercial operation, and is initiated when they are tu rned over for construction tests from the Construction Manager, and is concluded when the direct responsibility for the unit is transferred

from the GPU Project Manager to the Met-Ed Generation Department for normal commercial

operations.

The program's objectives are accomplished by us ing written test procedures to demonstrate that the unit's structures, systems, and components comply with applicable codes and standards and perform, both separately and collecti vely, in compliance with their design criteria for normal and safety related functions.

13.1.1 ADMINISTRATIVE PROCEDURES (TESTING)

The test program was conducted in a planned and systematic fashion and in accordance with

procedures and policies contained in the Three Mile Island Nuclear Generating Station Test

Manual and individual Test Instructions.

Testing of the unit's structures, systems, and components was conducted in accordance with written test procedures. The completed test procedures, including data sheets, shall be

retained as proof that the test results are satisfactory.

Changes to the test program shall be made as necessary to improve the program or to incorporate modifications to existing technical or regulatory requirements that affect testing.

Changes to the instruction shall be approv ed by organizations originally approving the instructions prior to implementing the changes.

Only tests listed in the Master Test Index (MTX) are to be performed as part of the test program and these tests will only be conducted when they are authorized by the approved Test Plan.

TMI-1 UFSAR CHAPTER 13 13.1-2 REV. 18, APRIL 2006 13.1.1.1 Test Procedures

Test procedures contain the technical content of the test program. Design requirements and

test requirements are translated into test procedures which are used to demonstrate the ability

of structures, systems, or components to com ply with the requirements. Design requirements and test requirements are contained in documents such as Architect Engineer (AE) or Nuclear Steam Supply System (NSSS) Test Specific ations, FSAR, commitments to the regulatory agencies, equipment technical manuals, and applicable codes and standards. Test results are

recorded in test procedures and are reviewed and approved to ensure that test requirements have been satisfactorily met. Changes or exc eptions to test procedures are reviewed and approved by individuals from the same organizat ions that originally approved the procedure.

Exceptions (i.e., procedure changes that do not change scope or intent of the procedure) are

recorded in the procedure and must be approved after the test has been performed. Any

changes that affect the scope or the intent of the procedure must be approved prior to test

performance. Four types of test procedures shall be used in the Unit 1 Test Program. Their descriptions are as follows:

a. Individual Test Procedures

These procedures are prepared especially to dem onstrate the system's or unit's ability to comply with test requirements. Data are recorded for evaluation and proof of

satisfactory test performance.

b. Functional Verification Procedures

These procedures are prepared to demonstrate the ability of certain systems and components to operate normally within es tablished parameters and to obtain required test data. Functional Verification Procedures use Met-Ed's operating procedures to

provide the necessary test steps. The Functional Verification Procedure may require

minor deviations from the operating procedure to allow tests of various features, such as hi-low level alarms and automatic switching.

c. Generic Test Procedures

These procedures are used to perform construction tests and checkouts. They may be used to develop checklists and procedures for inspection, alignment, checkout, and

preliminary operation of systems and components.

These procedures require that data be obtained for evaluation of test results.

d. Special Procedures

These procedures are used to perform tests and operations that are not contained in Generic Test Procedures, Individual Test Procedures, or Functional Verification

Procedures, e.g., chemical cleaning and charcoal filter testing.

13.1.1.2 Test Index

The Test Index contains a description of the start-up testing to be performed on Unit 1. The Test Index also contains the MTX that lists all the structures and systems and their assigned test procedures. The MTX assigns safety related classifications to the structures and systems TMI-1 UFSAR CHAPTER 13 13.1-3 REV. 18, APRIL 2006 and assigns a safety related category to the test procedures. Only tests that are listed in the MTX will be performed unless specifically authorized by the GPU Test Superintendent.

The Test Index shall also contain a section to provide scopes for individual test procedures.

The scope shall consist of a description of the test's objectives, the source of test requirements, and source of acceptance criteria.

13.1.1.3 Prerequisite Lists

The prerequisite list contains all items that must be satisfactorily completed or in an appropriate state of readiness to support the start of major events. As a minimum, a prerequisite list shall be prepared for each test program milestone event. The list shall be periodically updated and

reviewed prior to commencing the associated event.

13.1.1.4 Test Schedules

The test schedule provides the sequence for test performance over a certain designated period

of time. The schedule provides the means for conducting an orderly test program and for

keeping management informed of testing progress.

13.1.1.5 Test Manning Assignments

The Test Manning Assignments provide a listing of stations to be manned by appropriate personnel during the conduct of complex tests.

Test Manning Assignments during the conduct of complex tests remain in effect until released by the Shift Test Engineer in charge of the test.

13.1.1.6 Test Plan

The Test Plan provides a short-range schedule to authorize performance of specific tests. The

Test Plan is issued at various intervals deter mined by testing activity and shall state the period for which it is valid. A new test plan will nor mally be issued before the validation date is past in order to ensure a continuation of testing. Tests shall be performed when contained in the valid

test plan.

The Test Plan is reviewed and approved at scheduled Test Planning Meetings.

13.1.1.7 Test Instructions

Test Instructions provide procedures for the administr ative control of the Test Program. A list of Test Instructions is contained in Table 13.1-1

13.1.2 ADMINISTRATIVE PROCEDURES (MODIFICATIONS)

The administrative procedures used for incorpor ating system modifications or procedure changes are contained in the Test Instructions.

TMI-1 UFSAR CHAPTER 13 13.1-4 REV. 18, APRIL 2006 13.1.3 TEST OBJECTIVES AND PROCEDURES

The Test Program is divided into three test phases: (1) Construction, (2) Preoperational, and

(3) Fuel Loading and Initial Operation. A description of each phase and its objectives follows.

13.1.3.1 Construction Test Phase

The construction test phase starts when the system, or partial system, is turned over to the GPU Startup Engineer and is completed when all assigned construction tests have been satisfactorily performed and the system accepted by Met-Ed for tests, operations, and maintenance.

The objective of construction tests is to demons trate that structures, systems, and components comply with applicable engineering drawings, codes, and standards and to verify that the

installed systems and components operate properly and are ready to support further operations and testing.

Construction tests consist of:

a. Fluid System Hydrostatic Tests

These tests are performed to demonstrate that the system complies with the acceptance criteria contained in applicable codes and standards. b. Fluid System Cleanliness Flushes

The tests are performed to clean the syst em and to demonstrate that the cleanliness requirements have been satisfactorily obtained.

c. Electrical System Checkouts
1) Power Distribution

These checkouts demonstrate that t he electrical distribution system complies with applicable plans, specifications, codes, and standards.

2) Control Circuits and Systems

These checkouts demonstrate that the individual electrical control circuits and systems function as designed.

3) Protective Devices

These checkouts demonstrate by operation under simulated conditions that the electrical system's protective devices function as designed.

d. Installed Instrumentation Checkouts

These checkouts demonstrate that the ins trumentation is properly aligned, calibrated, and capable of performing its designed function.

e. Preliminary Operation Tests TMI-1 UFSAR CHAPTER 13 13.1-5 REV. 18, APRIL 2006 The preliminary operational tests are performed to determine if there is any major deficiency in the systems or components.

This run-in period provides reasonable assurance that the system or component oper ates properly and is able to support further tests and operations. These tests and checkouts include items such as: lubrication, setting of limit switches, and setting of torque limiting devices.

13.1.3.2 Preoperational Test Phase

The preoperational test phase starts when a system, or partial system, is turned over to Met-Ed from the GPU Nuclear Start-up Engineer and ends at the start of initial fuel loading.

This phase consists of functional tests and verifications that demonstrate the component's

ability to perform its design function and of oper ational tests that demonstrate the system's ability to operate as designed under actual or simulated conditions. These tests are performed

on integrated systems or on an indiv idual system basis. Table 13.1-2 contains a listing of safety related tests that will be performed during preoperational and initial start-up test phases.

a. Hot Functional Testing

Hot functional tests will be performed during the preoperational phase. These tests demonstrate the ability of the Reactor Coolant System and associated auxiliary systems to operate properly at operating pressure and temperature. Table 13.1-3 contains a

listing of tests that will be performed during the hot functional test phase.

b. Vibration Surveillance Program

The first-of-a-kind reactor internals vibr ation surveillance program will be conducted on the prototype internals at Oconee. This pr ogram meets the requirements of Safety Guide No. 20 for Prototype Internals. The program includes vibration survey tests, analyses and description of forcing functions, v ibration analyses of the reactor internals, prediction of responses, vibration measur ements during hot functional testing, data analysis, acceptance criteria, and post-testing inspection of the reactor internals.

The TMI-1 vibration surveillance program will comply with the USNRC Reg. Guide No.

1.20 for Reactor Internals. The program consists of a detailed internals inspection both

prior to and following hot functional testing. In addition, the internals are subjected to at

least 10 7 cyclic stresses during HFT by running two or more reactor coolant pumps at hot, pressurized conditions for at least 278 hours0.00322 days <br />0.0772 hours <br />4.596561e-4 weeks <br />1.05779e-4 months <br />.

13.1.4 FUEL LOADING AND INITIAL OPERATION

The initial startup phase starts with initial fuel loading and ends upon completion of the power

escalation test program. Table 13.1-4 contains a list of tests that will be performed during the

initial startup phase. This phase consists of:

TMI-1 UFSAR CHAPTER 13 13.1-6 REV. 18, APRIL 2006

a. Initial Fuel Loading

Following the satisfactory completion and data evaluation of required preoperational tests and review of other initial fuel loading prerequisites, the Test Working Group will

allow fuel loading to commence.

An Initial Fueling Supervisor appointed by the GPU Project Manager will be responsible for supervising the initial fuel operations.

Fuel will be loaded into the reactor in accordance with a step-by-step written procedure.

This procedure, which contains a number of safety precautions and operating limitations, includes the following items:

1) A sequence of loading temporary detectors, sources, control rods, and fuel assemblies to maintain shutdown margin requirements.
2) Conditions under which fuel loading may continue after any step.
3) Identification of responsibility and authority.
4) During any reactivity changes, a m inimum of two detectors will be operating and indicating the neutron level after the source has been inserted. At all other times, at least one detector will indicate the neutron level.
5) Two completely independent plots of reciprocal neutron multiplications as a function of the parameter causing reactivity change will be maintained.
6) Reactivity effects for each fuel assembly addition will be checked before the fuel assembly is released by the fuel-handling grapple.
7) The reactivity effect for the next fuel addition will be estimated before the next fuel assembly is inserted.
8) The boron concentration in the reactor vessel, spent fuel pool, and Reactor Coolant System will be maintained at a v alue to ensure the required subcritical margin at all times.
9) The valve alignment of auxiliary syst ems connected to the Reactor Coolant System will be checked periodically to prevent dilution of the reactor coolant boron concentration.
10) Chemical analysis and water level monit oring will be conducted to ensure that inadvertent dilution of the boron concentration in the reactor coolant has not

occurred.

11) Communication between Control Room and fuel handling areas will be maintained.
12) Plant radiation monitoring systems as required for fuel loading will be in operation.

TMI-1 UFSAR CHAPTER 13 13.1-7 REV. 18, APRIL 2006

13) Health physics and chemistry m onitoring services will be provided.
14) Throughout the entire loading process, two persons, working independently, will verify fuel assembly identification and location within the core.
15) If an unexpected event or response occurs, loading will be suspended until the reason has been determined and an adequate evaluation made.
16) Two licensed Reactor Operators (one Senior Reactor Operator) as well as one additional experienced startup representative will be present at the facility

whenever fuel is moved into the reactor vessel.

b. Preparations for Initial Criticality

Upon completion of the initial fuel loading, pre-startup checks will be completed prior to the approach to initial criticality. Reactor Coolant Flow Test and Reactor Coolant Flow

Coastdown Test will be conducted under hot, pressurized reactor conditions to

determine the flow characteristics of the Reactor Coolant System after reactor core

installation.

c. Initial Criticality and Zero Power Physics Tests

A written procedure will be used as the controlling document for taking the primary system from a filled and vented condition following fuel loading through the zero power physics test program to a zero power, hot condition. This will be a step-by-step procedure that will list or reference all appropriate limits and precautions (including

technical specifications). It will incorporate or reference applicable steps in unit

operating procedures that have been modified and approved for use during the zero

power test program. The modified operating procedure steps will be blended with the

zero power test program to produce a preplanned, orderly, organized test sequence.

The step-by-step procedure ensures a safe, well-controlled test program. In cases

where performance of a particular step or ser ies of steps involves a significant safety consideration, a precautionary note will precede the step or steps.

d. Power Escalation Tests

TP 800/21, Unit Startup and Power Escalation Test Procedure, will be the controlling document for taking the unit from a zero power, hot condition through the various power

test plateaus up to commercial operation at licensed power. This will be a step-by-step

procedure that either incorporates or references applicable steps in normal approved unit operating procedures required to increase power from one test plateau to another

and maintain steady-state power at each te st plateau. The normal operating procedure steps will be blended with the power escalation test program to produce a preplanned, orderly, organized test sequence. The step-by-step procedure ensures a safe, well

controlled test program. All appropriate limits and precautions (including technical

specifications) will be listed or referenced in the applicable operating procedures, individual power escalation test procedures, or in the controlling document itself. In

cases where performance of a particular step or series of steps involves a significant safety consideration, a precautionary note will precede the step or steps in the

controlling document.

TMI-1 UFSAR CHAPTER 13 13.1-8 REV. 18, APRIL 2006 13.1.5 ADMINISTRATIVE PROCEDURES (SYSTEM OPERATION)

Upon acceptance of a system by Met-Ed for test and operations, the system will be operated in accordance with its normal operating procedure. The operating procedure will be revised as

necessary during this period and a final approved procedure issued.

Selected emergency operating procedures will be performed during the test program. Those

emergency procedures which are not possible to perform will be dry run by the station staff.

TMI-1 UFSAR CHAPTER 13 13.1-9 REV. 18, APRIL 2006 TABLE 13.1-1 (Sheet 1 of 1)

LIST OF TEST INSTRUCTIONS

TI-1 Repair Removal Authorization

TI-2 Test Plan

TI-3 Briefing and Dry Run

TI-4 Control of Test Records

TI-5 System Turnover

TI-6 Test Schedules

TI-7 GPU Startup Problem Report

TI-8 Unusual Occurrences

TI-9 Conduct of Test

TI-10 Prerequisite List

TI-11 Test Index

TI-12 Not used

TI-13 Test Interface Instructions

TI-14 Training and Qualifications of Test Personnel

TI-15 Not used

TI-16 Not used

TI-17 Shift Test Engineer's Log

TI-18 Test Procedure Documents

TI-19 Control of Test Equipment

TMI-1 UFSAR CHAPTER 13 13.1-10 REV. 18, APRIL 2006 TABLE 13.1-2 (Sheet 1 of 6)

SAFETY RELATED TESTS TO BE PERFORMED DURING PREOPERATIONAL AND INITIAL START-UP TEST PHASES

Test No. Title

SP 2 Filter Efficiency Tests MCP-15 Hanger Hot Setting Determination SP 53.10 Reactor Vessel Head Service Structure Temperature Profile Determination

SP 102.6 Fire Protection System Checkout TP 120/3 Fuel Handling System Integrated Functional Test TP 150/2 Reactor Building Structural Integrity Test TP 150/3 Initial Reactor Building Leak Rate Test (ILRT)

TP 150/4 Post Accident Hydrogen Purge System Functional Test TP 151/1 Reactor Building Isolation Valve Leak Test TP 153/3 Fluid Block System Functional Test TP 153/4 Fluid Block System Actuation Time Determination TP 154/3 Penetration Pressurization Operational Test TP 160/2 R. B. Emergency Cooling Water System TP 160/3 Reactor Building Purge System Functional Test TP 160/4 R. B. Fans Functional Test SP 166.2 Plant Test Panel Pre-op. Alignment TP 172/2A Control Building Ventilation Functional Test Part A - Compressed Air System

TP 172/2B Control Building Ventilation System Functional Test - Part B - Control Building Chilled Water System

TP 172/2C Control Building Ventilation System Functional Test Section C: Control Building Heating and Ventilation System

TP 180/3 Fire Service System Functional Test TP 200/1 Reactor Internals Vent Valve Inspection Test TP 200/4 Reactor Coolant System Hydrostatic Test TMI-1 UFSAR CHAPTER 13 13.1-11 REV. 18, APRIL 2006 TABLE 13.1-2 (Sheet 2 of 6)

SAFETY RELATED TESTS TO BE PERFORMED DURING PREOPERATIONAL AND INITIAL START-UP TEST PHASES

Test No. Title

TP 200/11A Reactor Coolant Pump Flow Test Part A - Cold, No Core TP 200/11C Reactor Coolant Pump Flow Test Part C - Hot, No Core TP 200/11D Reactor Coolant Pump Flow Test Part D - Hot, With Core TP 200/12A Reactor Coolant Flow Coastdown Test Part A - Cold, No Core TP 200/12B Reactor Coolant Flow Coastdown Test Part B - Cold, With Core TP 200/12C Reactor Coolant Flow Coastdown Test Part C - Hot, No Core TP 200/12D Reactor Coolant Flow Coastdown Test Part D - Hot, With Core TP 201/2 Core Flooding System Functional Test TP 201/5 Core Flood Flow Test SP 201.19 Reactor Coolant Pump Vibration Test TP 202/3 Makeup and Purification System Functional Test TP 202/7 Makeup and Purification System E. S. Test TP 203/1 Decay Heat Removal System B. W. S. T. Functional Test TP 203/4 Decay Heat Removal System Functional Test TP 203/7 Decay Heat Removal System E. S. Test TP 204/3 Reactor Building Spray System Functional Test TP 230/3 Liquid Waste Disposal System - Transfers To and From the Reactor Coolant and Miscellaneous Waste Evaporator Feed Tanks

TP 230/4 Liquid Waste Disposal System - Star t-up, Operation, and Transfers From the Reactor Coolant, and Miscellaneous Waste Evaporators

TP 230/8 Solid Waste Disposal System Test TP 231/3 Gaseous Waste Disposal System Functional Test TP 240/3 Intermediate Cooling System Functional Test TP 251/1 Reactor Building Sump, Auxiliary Building Sump and Compartment Leak Detector Functional Test

TMI-1 UFSAR CHAPTER 13 13.1-12 REV. 18, APRIL 2006 TABLE 13.1-2 (Sheet 3 of 6)

SAFETY RELATED TESTS TO BE PERFORMED DURING PREOPERATIONAL AND INITIAL START-UP TEST PHASES

Test No. Title SP 254.33 Turbine Generator Initial Operation TP 256/3 Instrument and Control Air System Functional Test TP 256/4 Loss of Instrument Air Test TP 263/4 Decay Heat River Water System Functional Test TP 264/4 Decay Heat Closed Cooling System Functional Test TP 266/4 Nuclear Service River Water Functional Test TP 267/4 Nuclear Service Closed Cooling Water System Functional Test TP 271/4 Main and Auxiliary Steam System Functional Test TP 273/3 Emergency Feedwater Turbine and Motor-Driven Pumps Functional Test TP 301/2 Nuclear Instrumentation Detector Cabling and Response Tests TP 301/3A Nuclear Instrumentation Pre-Op. Calibration (Source Range)

TP 301/3B Nuclear Instrumentation Pre-Op. Calibration (Intermediate Range)

TP 301/3C Nuclear Instrumentation Pre-Op. Calibration (Power Range)

TP 301/3D Determination and Setting of Detector Voltages TP 305/1A Reactor Protection System Initial Power Application TP 305/1B Reactor Protection System Preoperational Calibration TP 305/2 Reactor Protection System Response Time SP 330/1 Control Rod Drive Pre-Op. Calibration TP 330/2 CRD Control System Operational Test TP 330/3 Control Rod Drive Mechanism Functional Test TP 330/3A Post Core Load CRDM Functional Test TP 330/4 Integrated CRD System Test TP 330/5 CRD Trip Test TP 360/1A Process Radiation Monitor Calib. and Functional Test for Portable Atmospheric Monitors TMI-1 UFSAR CHAPTER 13 13.1-13 REV. 18, APRIL 2006 TABLE 13.1-2 (Sheet 4 of 6)

SAFETY RELATED TESTS TO BE PERFORMED DURING PREOPERATIONAL AND INITIAL START-UP TEST PHASES

Test No. Title TP 360/1B Process Radiation Monitor Calibration and Functional Test for Fixed Atmospheric Monitors TP 360/1C Process Radiation Monitor C alibration and Functional Test for Liquid Monitors

TP 360/2 Area Radiation Monitoring Calibration and Functional Test TP 401/1 Diesel Generator Startup Test TP 401/3 Station Battery Discharge and Charge Test TP 500/3 Initial Radiochemistry Test TP 600/1 Unit Heatup Test TP 600/3 Soluble Poison Concentration Control Test TP 600/4 Makeup and Purification System Operational Procedure TP 600/5 Nuclear Chemical Addition and Sampling System Operational Test TP 600/6A Liquid Waste Disposal System Operational Test TP 600/7 Intermediate Cooling System Operational Test TP 600/10 RCS Hot Leakage Test TP 600/11 Emergency Feed System and OTSG Level Control Test TP 600/13 Pressurizer Operation and Spray Flow Test TP 600/14 Pipe and Component Hanger Hot Deflection and Inspection Test TP 600/15 Non-Nuclear Instrumentation Hot Operation and Calibration TP 600/17 Control Rod Drive Operational Test TP 600/20 Loss of Electrical Power Test (Without E. S.)

TP 600/21 Integrated E. S. Actuation Test TP 600/23 Reactor Protection System Functional Test TP 600/24 Unit Cooldown Test

TMI-1 UFSAR CHAPTER 13 13.1-14 REV. 18, APRIL 2006 TABLE 13.1-2 (Sheet 5 of 6)

SAFETY RELATED TESTS TO BE PERFORMED DURING PREOPERATIONAL AND INITIAL START-UP TEST PHASES

Test No. Title TP 600/28 Controlling Procedure for HFT TP 600/29 Reactor Coolant System Thermal Expansion Functional Test TP 600/30 HFT Checkpoints TP 710/1 Zero Power Test SP 710/2 Controlling Procedure for Post Fuel Load Precritical Testing TP 800/2 NI Calibration at Power TP 800/3 Biological Shield Survey TP 800/5 Reactivity Coefficients at Power TP 800/6 Turbine Bypass System Test TP 800/7 Feedwater System Operation and Testing TP 800/8 ICS Tuning at Power TP 800/9 Turbine Generator Operational Testing TP 800/11 Core Power Distribution TP 800/12 Unit Load Steady State Test TP 800/14 Turbine/Reactor Trip Test TP 800/16 Reactivity Depletion vs Burnup TP 800/17 Unit Acceptance Test TP 800/18 Power Imbalance Detector Correlation Test TP 800/20 Rod Reactivity Worth Measurement TP 800/21 Unit Startup and Power Escalation Test TP 800/22 NSS Heat Balance TP 800/23 Unit Load Transient Test TP 800/24 Incore Detector Testing TP 800/30 Power Escalation Check Points

TMI-1 UFSAR CHAPTER 13 13.1-15 REV. 18, APRIL 2006 TABLE 13.1-2 (Sheet 6 of 6)

SAFETY RELATED TESTS TO BE PERFORMED DURING PREOPERATIONAL AND INITIAL START-UP TEST PHASES

Test No. Title TP 800/31 Pseudo Dropped Rod TP 800/32 Loss of Offsite Power Test TP 800/33 Pseudo Rod Ejection Test TP 800/34 Generator Trip Test TP 800/35 Effluent and Effluent Monitoring System Test TP 800/36 Shutdown From Outside the Control Room as Modified for Hot Functional Testing F 1104/6 Spent Fuel Cooling System Functional Verification F 1104/24B Screen House Ventilation Functional Verification (Including River Water)

F 1104/29A Liquid Waste Disposal System Functional Verification (Reactor Coolant Cleanup Processes)

F 1104/29D Liquid Waste Disposal System Functional Verification - Part D - Decay Heat Water Cleanup Process

F 1104/29E Liquid Waste Disposal System Functional Verification - Part E - Bleed and Feed Processes

F 1104/29I Liquid Waste Disposal System Functional Verification - Part I - Transfer From Reactor Coolant Drain Tank

F 1104/29J Liquid Waste Disposal System Functional Verification - Part J - Transfers Through Reactor Drain Pump

F1104/29Y Liquid Waste Disposal System Functional Verification - Part Y - Operation and Use of the Precoat Filters

TMI-1 UFSAR CHAPTER 13 13.1-16 REV. 18, APRIL 2006 TABLE 13.1-3 (Sheet 1 of 2)

HOT FUNCTIONAL TESTS

Test No. Title

MCP-15 Hanger Hot Setting Determination SP 53.10 Reactor Vessel Head Service Structure Temperature Profile Determination

SP 166.2 Plant Test Panel Pre-op. Alignment TP 200/1 Reactor Internals Vent Valve Inspection Test TP 200/11C Reactor Coolant Pump Flow Test Part C - Hot, No Core TP 200/12C Reactor Coolant Flow Coastdown Test Part C - Hot, No Core SP 201.19 Reactor Coolant Pump Vibration Test TP 202/7 Makeup and Purification System E. S. Test TP 203/7 Decay Heat Removal E. S. Test SP 254.33 Turbine Generator Initial Operation TP 271/4 Main and Auxiliary Steam System Functional Test TP 330/3 Control Rod Drive Mechanism Functional Test TP 330/4 Integrated CRD System Test TP 500/3 Initial Radiochemistry Test TP 600/1 Unit Heatup Test TP 600/3 Soluble Poison Concentration Control Test TP 600/4 Makeup and Purification System Operational Procedure TP 600/5 Nuclear Chemical Addition and Sampling System Operational Test TP 600/6A Liquid Waste Disposal System Operational Test TP 600/7 Intermediate Cooling System Operational Test TP 600/10 RCS Hot Leakage Test TP 600/11 Emergency Feed System and OTSG Level Control Test TP 600/13 Pressurizer Operation and Spray Flow Test TP 600/14 Pipe and Component Hanger Hot Deflection and Inspection Test

TMI-1 UFSAR CHAPTER 13 13.1-17 REV. 18, APRIL 2006 TABLE 13.1-3 (Sheet 2 of 2)

HOT FUNCTIONAL TESTS

Test No. Title

TP 600/15 Non-Nuclear Instrumentation Hot Operation and Calibration TP 600/17 Control Rod Drive Operational Test TP 600/20 Loss of Electrical Power Test (Without E. S.)

TP 600/21 Integrated E. S. Actuation Test TP 600/23 Reactor Protection System Functional Test TP 600/24 Unit Cooldown Test TP 600/28 Controlling Procedure for HFT TP 600/29 Reactor Coolant System Thermal Expansion Functional Test TP 600/30 HFT Checkpoints TP 800/36 Shutdown From Outside the Control Room as Modified for Hot Functional Testing TMI-1 UFSAR CHAPTER 13 13.1-18 REV. 18, APRIL 2006 TABLE 13.1-4 (Sheet 1 of 6)

POWER ESCALATION SEQUENCE TABLE

Test Procedure No.

POWER LEVEL (%) TP 500/3 TP 710/1 SP 710/2 TP 800/2 TP 800/3

0 - 15 (ZPPT) (ZPPT) (Pre-ZPPT) X (ZPPT) 15 X

15-25 25 DAILY

30 35 40 X X

50 60 70 76 X

85 95 100 X X

Test No. Title

TP 500/3 Initial Radiochemistry Test TP 710/1 Zero Power Test SP 710/2 Controlling Procedure for Post Fuel Load Pre-critical Testing TP 800/2 NI Calibration at Power TP 800/3 Biological Shield Survey

TMI-1 UFSAR CHAPTER 13 13.1-19 REV. 18, APRIL 2006 TABLE 13.1-4 (Sheet 2 of 6)

POWER ESCALATION SEQUENCE TABLE

Test Procedure No.

POWER LEVEL (%) TP 800/5 TP 800/6 SP 800/7 TP 800/8 TP 800/9

0 - 15 X X 15 X X X 15-25 X

25 30 X

35 40 X X X X

50 60 70 76 X X X X

85 95 100 X X X X X

Test No. Title

TP 800/5 Reactivity Coefficients at Power TP 800/6 Turbine Bypass System Test SP 800/7 Feedwater System Operation and Testing TP 800/8 ICS Tuning at Power TP 800/9 Turbine-Generator Operational Testing

TMI-1 UFSAR CHAPTER 13 13.1-20 REV. 18, APRIL 2006 TABLE 13.1-4 (Sheet 3 of 6)

POWER ESCALATION SEQUENCE TABLE

Test Procedure No.

POWER LEVEL (%) TP 800/11 TP 800/12 TP 800/14 TP 800/16 TP 800/17

0 - 15 X 20, 30, 40 and 15 X X 50 effective 15-25 full power days 25 X

30 X T

35 X

40 X X X R

50 X

60 X

70 X

76 X X

85 X

95 X

100 X X X

Test No. Title

TP 800/11 Core Power Distribution TP 800/12 Unit Load Steady State Test SP 800/14 Turbine/Reactor Trip Test TP 800/16 Reactivity Depletion vs. Burnup TP 800/17 Unit Acceptance Test

TMI-1 UFSAR CHAPTER 13 13.1-21 REV. 18, APRIL 2006 TABLE 13.1-4 (Sheet 4 of 6)

POWER ESCALATION SEQUENCE TABLE Test Procedure No.

POWER LEVEL (%) TP 800/18 TP 800/20 TP 800/21 TP 800/22 TP 800/23

0 - 15 X X

15 X X

15-25 X

25 X X X

30 X

35 X X

40 X X X X X

50 X X

60 X X

70 X X

76 X X X X X

85 X X

95 X X

100 X X X X

Test No. Title

TP 800/18 Power Imbalance Detector Correlation Test TP 800/20 Rod Reactivity Worth Measurement SP 800/21 Unit Startup and Power Escalation Test TP 800/22 NSS Heat Balance TP 800/23 Unit Load Transient Test

TMI-1 UFSAR CHAPTER 13 13.1-22 REV. 18, APRIL 2006 TABLE 13.1-4 (Sheet 5 of 6)

POWER ESCALATION SEQUENCE TABLE Test Procedure No.

POWER LEVEL (%) TP 800/24 TP 800/30 TP 800/31 TP 800/32 TP 800/33

0 - 15

15 X X X 1

15-25

25 X

30

35 X

40 X X X X

50

60

70

76 X X

85

95

100 X

Test No. Title

TP 800/24 Incore Detector Testing TP 800/30 Power Escalation Check Points SP 800/31 Pseudo Dropped Rod TP 800/32 Loss of Offsite Power Test TP 800/33 Pseudo Rod Ejection Test

TMI-1 UFSAR CHAPTER 13 13.1-23 REV. 18, APRIL 2006 TABLE 13.1-4 (Sheet 6 of 6)

POWER ESCALATION SEQUENCE TABLE Test Procedure No.

POWER LEVEL (%) TP 800/34 TP 800/35 TP 800/36 MCP-15

0 - 15 15 (ZPPT) (X) X 1 X 15 - 25 25 30 35 40 X X

50 60 70 76 X X

85 95 100 X X X

Test No. Title TP 800/34 Generator Trip TP 800/35 Effluent and Effluent Monitoring System Test SP 800/36 Shutdown from Outside Control Room As Modified for Hot Functional Testing MCP-15 Hanger Hot Setting Determination

Where (ZPPT) = During zero power physics test and X = 10 percent generator output

X 1 = turbine trip X

T = reactor trip

Note: Major power plateaus are 15, 40, 76 and 100 percent full power

TMI-1 UFSAR CHAPTER 13 13.2-1 REV. 18, APRIL 2006 13.2 AUGMENTATION OF APPLICANT'S STAFF FOR INITIAL TESTS AND OPERATIONS

Met-Ed, a subsidiary of GPU, is the responsible owner and applicant for TMI-1. Met-Ed, via a

service agreement, is utilizing the services of t he GPU Service Corporation, which is the agent for the owners. The Design and Construction Division of the GPU Service Corporation, acting

for Met-Ed, is responsible for conduct of the test program until the unit is declared commercial.

The Test Program Organization for TMI-1 is shown on Figure 13.2-1.

13.2.1 ORGANIZATIONAL FUNCTIONS, RESPONSIBILITIES, AND AUTHORITIES

13.2.1.1 GPU Service Corporation (GPUSC)

a. GPU Startup and Test Department (GPU Engineering)

The GPU Startup and Test Department is responsible for the administrative and technical content of the test program. The Start-up and Test Department has assigned a

Test Superintendent to the Three Mile Island nuclear project to administer the test

program and act as chairman of the Test Working Group.

b. GPU Projects

GPU Projects is responsible for the overall conduct of the project, including the test program. This responsibility is carried out by the GPU Test Superintendent for the GPU

Project Manager, Three Mile Island.

c. GPU Quality Assurance Department

The GPU Quality Assurance Department is responsible for the administration of the GPUSC Startup and Test Quality Assurance Plan.

13.2.1.2 United Engineers And Constructors (UE&C)

a. Construction Division (Construction Manager)

UE&C as Construction Manager is responsible for the construction of the unit in accordance with drawings and specifications. This responsibility includes the

completion of the systems, or partial system s, in a sequence that will allow efficient and orderly testing. The Construction Division provides craft support for tests and to correct

deficiencies.

b. Startup Department

The UE&C Startup Department is responsible for preparation and conduct of construction-related tests and checkouts and subsequent turnover of systems/equipment to Met-Ed. The Startup Department assigns a Lead Startup Engineer and staff to

conduct construction tests and checkouts under the technical and operational direction

of the GPU Test Superintendent.

TMI-1 UFSAR CHAPTER 13 13.2-2 REV. 18, APRIL 2006

c. Field Quality Control Group

The UE&C Field Quality Control Group is responsible for performing the required inspection of construction tests and checkouts in accordance with Quality Control

procedures and checklists.

13.2.1.3 Metropolitan Edison Company (MET-ED)

a. Station Supervisory Staff

The station supervisory staff is responsible for the operation and maintenance of systems and equipment after acceptance from the UE&C Startup Department. This responsibility includes operating systems in accordance with test procedures to perform

preoperational and initial startup tests. Met-Ed assigns a voting representative to the

Test Working Group.

b. Met-Ed System Engineering

Met-Ed System Engineering is responsible for the control of tests, checkouts, and the acceptance of results for all protective relays, substations, and switchgear. System

Engineering is also responsible for the design review of the substation switchyards.

13.2.1.4 Gilbert Associates, Inc. (GAI)

Gilbert Associates, Inc. is the AE for Unit 1. As the AE, they are responsible for the entire

design of the unit, except those portions designed by the owner, the turbine generator supplier, and the NSSS supplier. This responsibility includes incorporating those items required to

support the NSSS and the Turbine Generator System. The AE assigns a voting representative to the Test Working Group.

13.2.1.5 Babcock And Wilcox, Inc. (B&W)

B&W is the NSSS supplier for Unit 1. B&W is responsible for the design and delivery of the

NSSS and assigns a voting representative to the Test Working Group.

13.2.1.6 General Electric Co. (GE)

General Electric Co. supplies the turbine generator for Unit 1. They are responsible for the

design and delivery of the turbine generating unit and pr ovide a site representative to concur in test procedures for tests of the turbine generator and associated equipment and systems.

13.2.2 INTERRELATIONSHIPS AND INTERFACES

13.2.2.1 Plant Operations Review Committee (PORC)

PORC reviews safety related test procedures.

This review is coordinated through the Met-Ed Station Superintendent's Test Working Group representative. A complete description of the

duties and responsibilities of PORC is contained in Chapter 15 (Technical Specifications).

TMI-1 UFSAR CHAPTER 13 13.2-3 REV. 18, APRIL 2006 13.2.2.2 Test Working Group (TWG)

The TWG is the coordinating body for the Start-up Test Program. The TWG functions in such a

manner as to assure that all safety related testing is conducted properly and that all test

requirements are satisfactorily met. All appr ovals by the TWG will be indicated by all voting members' signatures.

The TWG's responsibilities include the following items:

. Approval of milestone and prerequisite lists.

. Approval of project test sequence.

. Conduct of review and approval of safety related test procedures.

. Approval of changes to safety related test procedures.

. Review and approval of test results of safety related test procedures.

. Review and approval of the scope of the test program contained in the Test Index.

The TWG membership shall consist of one member and at least one alternate member from the

following organizations: GPU Startup and Test, B&W, Gilbert Associates, and Met-Ed Station

Supervisory Staff. The Met-Ed Generation D epartment assigns a nonvoting member to the TWG to act as Test Auditor. The following is a list of the TWG membership, qualifications, requirements, and a brief description of their duties and responsibilities.

a. GPU Startup and Test Representative

The GPU Test Superintendent is the TWG chairman and a voting member. As chairman, he is responsible to convene and conduct TWG meetings, as necessary, and

to achieve agreement of its voting members for the technical and administrative content of the test program.

b. Architect Engineer Representative

A senior Startup and Test Engineer and alternate shall be assigned by the AE as a TWG voting member.

He shall be responsible for the technical content of testing for that portion of the unit designed by the AE. The AE member of the TWG has received his M.S. degree in

Nuclear Engineering from the University of Washington and has had eight years of experience in the commercial nuclear power field. Four of those years he was Project

Engineer on a 450-MWe pressurized water reactor which involved equipment

specification and procurement, fluid system design, and startup and test program resolution of design deficiencies. This also included the startup and testing of a second

pressurized water reactor in Japan. The remaining four years have been spent on the

TMI project in the following areas: obtaining AE design completions for startup; obtaining

AE resolution for system design deficiencies; obtaining data for AE engineering TMI-1 UFSAR CHAPTER 13 13.2-4 REV. 18, APRIL 2006 evaluations; approving field changes; coordinating design interfaces with NSSS and turbine generator vendor; and functioning as a TWG member.

c. Nuclear Steam Supply System Representative

The B&W Site Operations Manager and his alternate are assigned as a TWG voting member. He is responsible for the technical content of testing for the NSSS.

d. Met-Ed Station Supervisory Staff Representative

The Assistant Station Superintendent and alternate are assigned as TWG voting members for Unit 1. He represents the utility owner and is responsible for the proper

operation of the unit. His signature, when associated with TWG approval of test

procedures for safety related systems, indicat es that the PORC review is complete and their comments are satisfactorily resolv ed. His qualifications are contained in Chapter

12.
e. Med-Ed Generation Department

The Met-Ed Generation Department shall assign a test auditor to provide independent evaluation of the action taken by the TWG. He is not a voting member, and his

signature is not required on TWG test documents. His primary responsibilities are to

assure that the actions taken by the TWG do not cause a deviation from the Test

Manual, the technical specifications, or other requirements contained in the FSAR, warranties, or design documents. He shall report results of his review to the GPU

Project Manager, GPU Startup and Testing Manager, and Met-Ed Manager -

Generation.

13.2.2.3 Designer, Owner, Tester (DOT)

This group is established to review and approve the technical content of test procedures that

are not appropriate for TWG approval. This group cons ists of representatives from GPU Startup and Test, the designer (B&W or GAI), and the Met-Ed Station Supervisory staff. DOT-approved

test procedures do not require PORC review.

The DOT representatives' duties and responsibilities for non safety related systems are similar to those assigned to TWG members for safety related systems.

13.2.3 PERSONNEL FUNCTIONS, RESPONSIBILITIES, AND AUTHORITIES

13.2.3.1 GPU Test Superintendent

He is responsible to the GPU Startup and Test Manager for technical content and to the TMI

Project Manager for the administration of the test program. He is chairman of DOT and TWG.

He assigns a representative of GPU Start-up and Test to be a voting member of Test Planning

Meetings.

TMI-1 UFSAR CHAPTER 13 13.2-5 REV. 18, APRIL 2006 13.2.3.2 GPU Assistant Test Superintendent

He is responsible to the GPU Test Superintendent for planning, scheduling, and conducting all

preoperational and initial start-up testing. Other duties are assigned by the GPU Test

Superintendent.

13.2.3.3 GPU Shift Test Engineer (STE)

He is responsible to the GPU Assistant Test Superintendent for conduct and inspection of

preoperational and initial startup tests in accordance with test instructions and test procedures.

He directs the conduct of tests through the Met-Ed Shift Foreman.

13.2.3.4 GPU Technical Engineer

He is responsible to the GPU Test Superintendent for the preparation of all test procedures, except construction tests. This includes sc heduling the review and approval of procedures to support the test schedule.

13.2.3.5 GPU Cognizant Test Engineer

He is responsible to the GPU Technical Engineer for preparation of test procedures in

accordance with test instructions and applicable test requirements. He may assist the Shift Test

Engineers in conducting tests.

13.2.3.6 Met-Ed Assistant Station Superintendent

He is responsible to the Met-Ed Station Superintendent for the proper operation and

maintenance of the unit during the preoperational and initial startup test phase. He has been

designated as the Met-Ed member of the TWG and DOT for Unit 1. He shall assign a member

of the station staff to be a voting member of test planning meetings.

13.2.3.7 Met-Ed Supervisor Of Operations

The Supervisor of Operations for Unit 1 is responsible to the Met-Ed Assistant Station

Superintendent for the operation of the unit during the preoperational and initial startup phase.

He is responsible to operate systems and co mponents in accordance with approved operating procedures and perform tests in accordance with approved test procedures.

3.2.3.8 Met-Ed Shift Foreman

He is responsible to the Met-Ed Supervisor of Operations for directing the operation of systems

and equipment after acceptance by the utility owner. He directs the operation of unit systems and equipment in accordance with approved operating and test procedures. He orders test

steps contained in approved test procedures to be performed when requested by the GPU Shift Test Engineer during performance of preoperational and initial startup testing.

TMI-1 UFSAR CHAPTER 13 13.2-6 REV. 18, APRIL 2006 13.2.3.9 UE&C Lead Start-up Engineer

He is responsible to the GPU Test Superintendent for preparation of construction test

procedures and conduct of construction tests and checkouts, in accordance with those

procedures. He is responsible for scheduling construction tests to provide a consistent interface

sequence with the preoperational test phase and assigns a Start-up Engineer to attend and

participate as a voting member in the test planning meetings. He acts as test program liaison

with the Construction Manager for providing craft support of test and correction of deficiencies.

13.2.3.10 NSSS Site Operations Manager

He provides advice and consultation for test and test-related matters for the NSSS and is the

B&W Project Manager's onsite representative for test-related matters. His responsibilities

include the following:

a. Provision of test specifications prepared by B&W to GPU and preparation of designated test procedures as requested by the GP U Project Manager, and providing them to the GPU Test Superintendent for incorporation into the test program.
b. Responsibility for the technical content of testing relating to the NSSS.
c. Scheduling technical assistance from within the NSSS or its vendors, as required.
d. Attending and participating as a voting member of the Test Planning Meeting.
e. Attending and participating as a voting member of the TWG and DOT.
f. Coordinating the implementation of approved B&W related field changes with the GPU Test Superintendent for systems under test control.
g. Responsibility for obtaining resolution of design and operational problems associated with testing or operation of systems and equipment within the NSSS scope of supply.

13.2.3.11 Turbine Generator Supplier Site Representative

He provides test requirements for test procedures associated with the turbine generator and

concurs with those procedures prior to test performance.

13.2.3.12 Architect Engineer - Startup Test Engineer

He provides engineering liaison service for the te st program and that portion of the unit designed by the AE. In addition, he shall have the following responsibilities:

a. Provides test procedures as requested by GPU Project Manager and submits them to the GPU Test Superintendent for incorporation into the test program.
b. Responsible for the technical content of balance-of-plant testing.
c. Attends and participates as a voting member in test planning meetings.

TMI-1 UFSAR CHAPTER 13 13.2-7 REV. 18, APRIL 2006

d. Participates as a voting member of TWG and DOT.
e. Responsible for obtaining resolutions of design problems associated with the test and operation of systems within the AE's design scope. When requested by the GPU Test

Superintendent, he also obtains resolutions for design problems associated with test and

operation of equipment purchased to specifications provided by the AE.

f. Coordinates the implementation of approved AE related field changes with the GPU Test Superintendent for systems under test control.

13.2.3.13 Met-Ed Test Auditor

He is responsible for auditing and reporting action taken by TWG as discussed in Item e. of

Subsection 13.2.2.2.