Annual Post-Uprate Monitoring Report for Uprate Project. Part 4 of 18
ML15364A421
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 08/31/2014
From:
Ecology & Environment
To:
Office of New Reactors
Shared Package
ML15364A396 List:
References
L-2015-299, +reviewed
Download: ML15364A421 (8)


Text

FPL Turkey Point Annual Post-Uprate Monitoring Report for Units 3 & 4 Uprate Project - August 2014 Canal Extent of Saltwater Intrusion (USGS 2008)

Estimated Extent of Saltwater Intrusion USGS 2008 Note: 1) Avg =Average: Jun 2013 through May 2014;

2) Std Dev= Standani Deviation;
3) Samples Collected at 3 Depths (S: shallow; M: intermediate; D: deep)

Figure 2.1-18. Average and Standard Deviation of Salinity (PSS-78) for Groundwater Stations.

2-52 Section 2 9-2014

FPL Turkey Point Annual Post-Uprate Monitoring Report for Units 3 & 4 Uprate Project-August 2014

'E 90000 u

(i5 80000 2:

~ 70000 c:

(U t) 60000

t

~---~-----...---~---~

...Jr- ~~ ~~----------..-.---...-----!----..~~~~~~--!

~--;~

=....

.......;.:i.t-.

~-~~--~~---------

"C

~

§ 50000

(.)

u i;::::: 40000

  • c::;

~ 30000 Cl) 20000 10000 I

0 +--~~~~~~~~~~~~~~~--.~~~~~~~~~~~---+~~~~~~--.~--I 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c::::::J Interim Operating Period --TPGW-1 OS TPGW-11S -

TPGW-14S 27 0

~ 26 Cl)

I..

t -

(U I..

Cl)

Q.

E 25 Cl)

I-24 23 I

6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c...:J Interim Operating Period --TPGW-1 OS TPGW-11S -

TPGW-14S 100000

'E 90000 u

(i5 80000 2:

Cl) 70000 u

c:

(U - 60000 u

t "C c: 50000 0

(.)

u i;::::: 40000

  • c::;

~ 30000 Cl) 20000 10000

,._.--~-------------r-~

! i i Section2

~~'~-----~-------~..._.--.---;.~-----.......__

  • -~~---------:.::::=~=====:=;:==1

-::::=::::~~~~~*~~-::;S'.:!~~

.--',_ __ -:::::,...r-0 +-~~~~~~~~~~~~~~~---.~~~~~~~~~~~---+~~~~~~---.~--1 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c_J lnterim Operating Period --TPGW-100 TPGW-110 -

TPGW-140 28 I

27 I

l I

(.)

~ 26 Cl)

I..

t -

(U I..

Cl)

I I

I I

Q.

E 25 Cl)

I-I 24 23 I

6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 C_J lnterim Operating Period --TPGW-100 TPGW-110 -

TPGW-140 Figure 2.1-19. Comparison of Specific Conductance and Temperature in Biscayne Bay Shallow and Deep Wells TPGW-10, TPGW-11, and TPGW-14.

2-53

FPL Turkey Point Annual Post-Uprate Monitoring Report for Units 3 & 4 Uprate Project-August 2014 100000 ~--------------~----------~--------~

e :::::

~

-,.,.. __ _,,,., _ _,,,__,,__....-* *-+--~-------

(.)

~ 70000 Q)

~ 60000

~

... g 50000 "C

c: 8 40000

(.)

!E 30000

(.)

Q)

~ 20000 10000


~--*-----...J,__ --

0 -__,....s~~====;l!!5!!!5!!5~!!!!!!!=:~~~;o!55!!~~==::::~~~==:!~~~~~""""":::=;!!:!::::::.:=~==~===I 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c==i lnterim Operating Period --TPGW-14S TPGW-3S -

TPGW-13S -

TPGW-5S -

TPGW-7S 31 30 29

(.)

0 28 Q)...

J...

~

27 Q)

Q.

E 26 Q) 25 24 23 -t---~~~~~~~~~~~~~~~~~~~~~~~-----~~~~~~~--<

6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c_] Interim Operating Period --TPGW-14S TPGW-3S -

TPGW-13S -

TPGW-5S -

TPGW-7S Section2 100000 I

90000 e 80000,...

J.-"'---.:,

I :..,_.i......_,.... * -

I

  • ----r'L-4-*-1**

1~

(.)

~ 70000 Q) i 60000

... g 50000 "C

c: 8 40000

(.)

!E 30000

(.)

Q)

~ 20000 10000 0

I I -

r I

I I I

6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 1 Interim Operating Period --TPGW-1 40 TPGW TPGW-130 -

TPGW TPGW-70 31 30 I

29 I

0 0

28 Q)...

J...

~

27 Q)

Q.

E 26 Q)

I I I I I I

I I

I 25 24 I

i 23 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c==i Interim Operating Period --TPGW-140 TPGW TPGW-130 -

TPGW TPGW-70 Figure 2.1-20. Comparison of Specific Conductance and Temperature across the Landscape in Shallow and Deep Wells TPGW-14, TPGW-3, TPGW-13, TPGW-5, and TPGW 7.

2-54

FPL Turkey Point Annual Post-Uprate Monitoring Report for Units 3 & 4 Uprate Project-August 2014 100000 ~--------------~----------~--------~

90000 e 80000

~

~ 70000 Cl) g 60000 I'll -g 50000 "C

c: 8 40000 CJ i;:: 30000

'(j Cl)

~ 20000 10000 0 ---=;======r====T'====;======;======;;==-==;====;======r====o;=====;====;=====;=====;====;====-I 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c_] Interim Operating Period --TPGW-11 S --TPGW-13S -- TPGW-2S TPGW-4S -

TPGW-9S 31 30 29

(.)

0 28 Cl)...

J -

I'll 27 Cl) c.

E 26 Cl)

I-25

~

24 23 --,-----.--.---~---.-----,.----.----,-----.--.,.--~--T---.----.----,-----l 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c:::J lnterim Operating Period --TPGW-11S--TPGW-13S -

TPGW-2S TPGW-4S -

TPGW-9S 100000 90000 e 80000

~

~ 70000 Cl) g 60000 I'll -g 50000 "C

c: 8 40000 CJ i;:: 30000

'(j Cl)

~ 20000 10000 0

,~..,."'---'*"""t-I

........ ~-

I Section2

, ____,.,l~-...

1'""'

.......,. -~1~~-

4.-

I

,. I 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14

~ Interim Operating Period --TPGW-11 D --TPGW-13D --TPGW-2D TPGW-4D -

TPGW-9D 31 I

30 29

(.)

0 28 Cl)...

J I'll 27 Cl) c.

E 26 Cl)

I-25 I

24 ---

23 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c:::J Interim Operating Period --TPGW-11 D -

TPGW-13D --TPGW-2D TPGW-4D -

TPGW-9D Figure 2.1-21. Comparison of Specific Conductance and Temperature across the Landscape in Shallow and Deep Wells TPGW-11, TPGW-13, TPGW-2, TPGW-4, and TPGW-9.

2-55

FPL Turkey Point Annual Post-Uprate Monitoring Report for Units 3 & 4 Uprate Project-August 2014 100000 ~--------------~-------------------~

90000

'E 80000 u

cg_ 70000 Q) g 60000 IV -g 50000 "C

c: 8 40000 u

!E 30000 u

Q)

~ 20000 10000

---...-:----------------,_....__.., ____..:*-* -+-~ -....... __ _

I F-AF~'-----~~~r--__,..!

0 +-===:..::;::::::==::::::;===::::::;::::==::::::;::==::=;:====;:::::::==:;::::==::;::====:;====;====:;::====l;:====;====:;::===:::;::::====l 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 C-::J lnterim Operating Period --TPGW-11S --TPGW-13S TPGW-1S --TPGW-6S 31 30 29 u

~ 28 Q)...

I -

IV 27 Q)

Q.

E 26 Q) 25 24 23 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 C=:J lnterim Operating Period --TPGW-11S --TPGW-13S -- TPGW-1S --TPGW-6S 100000 90000

'E 80000 u

~ 70000 Q) g 60000 IV -g 50000 "C

c: 8 40000 u

!E 30000 u

Q)

~ 20000 10000 0

I

..)...-"---*

I :..,_Jo_.__L._ -

j.,

~

I

    • -~

I I

Section2 I

.-..... --r'L--l-..,........ 1**

1'--'

l i 1

I l l 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c

J Interim Operating Period TPGW-110 TPGW-130 TPGW-10 TPGW-60 31 30 I

29 u

~ 28 Q)...

I -

IV 27 Q)

Q.

E 26 Q)

I I

I I

25 I

I 24 I

23 I

6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c_] lnterim Operating Period

--TPGW-110 --TPGW-130 --TPGW-10 -- TPGW-60 Figure 2.1-22. Comparison of Specific Conductance and Temperature across the Landscape in Shallow and Deep Wells TPGW-11, TPGW-13, TPGW-1, and TPGW-6.

2-56

FPL Turkey Point Annual Post-Uprate Monitoring Report for Units 3 & 4 Uprate Project-August 2014 100000 90000

'E 80000 u

cg_ 70000 Q) g 60000 I'll -g 50000 I.. -*

~-

I

  • -*,~T~--..-

"C c:

t-~'

I I

r-'-'

  • T-b 8 40000 u

~ 30000

  • c:;

Q)

~ 20000 10000 0

~,.

-w 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 C-:J lnterim Operating Period --TPGW-10S -- TPGW-12S --TPGW-13S --TPGW-6S 31 30 29 0

~ 28 Q)...

I -

I'll 27 Q)

Q, E

26 Q)

I-25 24 23 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c:=::i lnterim Operating Period --TPGW-10S --TPGW-1 2S --TPGW-13S --TPGW-6S 100000 90000

'E 80000 u

cg_ 70000 Q) g 60000 I'll -g 50000 "C c: 8 40000 u

~ 30000

  • c:;

Q)

~ 20000 10000 0

.J....-"--....:

. :..__1.-

Section2 I

- *---r'i.,.+."""'-1** 1'--'

f f i

-r--~

I I

I i

f 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14

~ Interim Operating Period

--TPGW-10D TPGW-12D

--TPGW-13D

--TPGW-6D I

I I

I I I 23 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 r

Interim Operating Period

--TPGW-10D --TPGW-12D --TPGW-13D --TPGW-6D Figure 2.1-23. Comparison of Specific Conductance and Temperature across the Landscape in Shallow and Deep Wells TPGW-10, TPGW-12, TPGW-13, and TPGW-6.

2-57

FPL Turkey Point Comprehensive Annual Report for Units 3 & 4 Uprate Project-August 2014 90000

'E 80000

~ 70000 "'~~--n\\~~~

Q)

~ 60000 Ill -g 50000 "C s 40000 ---------

(.)

~ 30000 0

~ 20000 en 10000 0 -+--------.--.....-----...... --....-----....... ----.--......--------.--..-----....... -----1

(.)

~

f

J cu...

Q) 0..

E Q)

I-6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 c:::J lnterim Operating Period

--TPGW-1S TPGW-3S TPGW-10S TPGW-12S TPGW-13S 30 29 28 27 26 25 24 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 TPGW-2S TPGW-11 S

-TPGW-14S 23 +---~-~--~-~-~--~-...,_-~-~--~-~-~--~-~-~------j 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12

---:::! Interim Operating Period

--TPGW-1S TPGW-3S TPGW-10S TPGW-1 2S TPGW-13S 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 TPGW-2S TPGW-11S TPGW-14S 6/1/14 Section2 100000 90000

'E 80000 *-

I

-..r--...-----r*~-,. 1 '""'----

0

~

~ 70000 Q) 0 60000 c:

Ill i

- r=c::

0 50000

J "C c: 40000 0

(.)

0 30000

!E 0

~ 20000 en 10000 0 -+--------.--..-----...... --....-----....... ----.--......--------.--..-----....... ~

-u

~

f

J cu...

Q) 0..

E Q)

I-6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 r..:::.:J Interim Operating Period

--TPGW-10 TPGW-30 TPGW-100 TPGW-12D TPGW-13S 30 29 28 27 26 25 24 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 E TPGW-20 TPGW-110

-TPGW-14S 23 +---~-~--~-~-~--~--T--~-~--~-~-~--~-~-~-

6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 Jlnterim Operating Period

--TPGW-10 TPGW-3D TPGW-10D TPGW-12D TPGW-13D 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 E TPGW-20 TPGW-11D TPGW-14D Figure 2.1-24. Comparison of Specific Conductance and Temperature across the Landscape in Shallow and Deep Wells Close to the CCS -TPGW-1, TPGW-2, TPGW-3, TPGW 10, TPGW-11, TPGW-12, TPGW-13, and TPGW-14.

2-58

FPL Turkey Point Annual Post-Uprate Monitoring Report for Units 3 & 4 Uprate Project-August 2014 Section2 Top view of probes in stilling well.

Biscayne Bay non-telemetry setup.

Figure 2.2-1. Automated Surface Water Stations.

2-59

FPL Turkey Point Annual Post-Uprate Monitoring Report for Units 3 & 4 Uprate Project - August 2014 Canal Extent of Saltwater Intrusion (USGS 2008)

Estimated Extent of Saltwater Intrusion USGS 2008 Note: 1) Avg =Average: Jun 2013 through May 2014;

2) Std Dev= Standani Deviation;
3) Samples Collected at 3 Depths (S: shallow; M: intermediate; D: deep)

Figure 2.1-18. Average and Standard Deviation of Salinity (PSS-78) for Groundwater Stations.

2-52 Section 2 9-2014

FPL Turkey Point Annual Post-Uprate Monitoring Report for Units 3 & 4 Uprate Project-August 2014

'E 90000 u

(i5 80000 2:

~ 70000 c:

(U t) 60000

t

~---~-----...---~---~

...Jr- ~~ ~~----------..-.---...-----!----..~~~~~~--!

~--;~

=....

.......;.:i.t-.

~-~~--~~---------

"C

~

§ 50000

(.)

u i;::::: 40000

  • c::;

~ 30000 Cl) 20000 10000 I

0 +--~~~~~~~~~~~~~~~--.~~~~~~~~~~~---+~~~~~~--.~--I 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c::::::J Interim Operating Period --TPGW-1 OS TPGW-11S -

TPGW-14S 27 0

~ 26 Cl)

I..

t -

(U I..

Cl)

Q.

E 25 Cl)

I-24 23 I

6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c...:J Interim Operating Period --TPGW-1 OS TPGW-11S -

TPGW-14S 100000

'E 90000 u

(i5 80000 2:

Cl) 70000 u

c:

(U - 60000 u

t "C c: 50000 0

(.)

u i;::::: 40000

  • c::;

~ 30000 Cl) 20000 10000

,._.--~-------------r-~

! i i Section2

~~'~-----~-------~..._.--.---;.~-----.......__

  • -~~---------:.::::=~=====:=;:==1

-::::=::::~~~~~*~~-::;S'.:!~~

.--',_ __ -:::::,...r-0 +-~~~~~~~~~~~~~~~---.~~~~~~~~~~~---+~~~~~~---.~--1 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c_J lnterim Operating Period --TPGW-100 TPGW-110 -

TPGW-140 28 I

27 I

l I

(.)

~ 26 Cl)

I..

t -

(U I..

Cl)

I I

I I

Q.

E 25 Cl)

I-I 24 23 I

6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 C_J lnterim Operating Period --TPGW-100 TPGW-110 -

TPGW-140 Figure 2.1-19. Comparison of Specific Conductance and Temperature in Biscayne Bay Shallow and Deep Wells TPGW-10, TPGW-11, and TPGW-14.

2-53

FPL Turkey Point Annual Post-Uprate Monitoring Report for Units 3 & 4 Uprate Project-August 2014 100000 ~--------------~----------~--------~

e :::::

~

-,.,.. __ _,,,., _ _,,,__,,__....-* *-+--~-------

(.)

~ 70000 Q)

~ 60000

~

... g 50000 "C

c: 8 40000

(.)

!E 30000

(.)

Q)

~ 20000 10000


~--*-----...J,__ --

0 -__,....s~~====;l!!5!!!5!!5~!!!!!!!=:~~~;o!55!!~~==::::~~~==:!~~~~~""""":::=;!!:!::::::.:=~==~===I 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c==i lnterim Operating Period --TPGW-14S TPGW-3S -

TPGW-13S -

TPGW-5S -

TPGW-7S 31 30 29

(.)

0 28 Q)...

J...

~

27 Q)

Q.

E 26 Q) 25 24 23 -t---~~~~~~~~~~~~~~~~~~~~~~~-----~~~~~~~--<

6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c_] Interim Operating Period --TPGW-14S TPGW-3S -

TPGW-13S -

TPGW-5S -

TPGW-7S Section2 100000 I

90000 e 80000,...

J.-"'---.:,

I :..,_.i......_,.... * -

I

  • ----r'L-4-*-1**

1~

(.)

~ 70000 Q) i 60000

... g 50000 "C

c: 8 40000

(.)

!E 30000

(.)

Q)

~ 20000 10000 0

I I -

r I

I I I

6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 1 Interim Operating Period --TPGW-1 40 TPGW TPGW-130 -

TPGW TPGW-70 31 30 I

29 I

0 0

28 Q)...

J...

~

27 Q)

Q.

E 26 Q)

I I I I I I

I I

I 25 24 I

i 23 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c==i Interim Operating Period --TPGW-140 TPGW TPGW-130 -

TPGW TPGW-70 Figure 2.1-20. Comparison of Specific Conductance and Temperature across the Landscape in Shallow and Deep Wells TPGW-14, TPGW-3, TPGW-13, TPGW-5, and TPGW 7.

2-54

FPL Turkey Point Annual Post-Uprate Monitoring Report for Units 3 & 4 Uprate Project-August 2014 100000 ~--------------~----------~--------~

90000 e 80000

~

~ 70000 Cl) g 60000 I'll -g 50000 "C

c: 8 40000 CJ i;:: 30000

'(j Cl)

~ 20000 10000 0 ---=;======r====T'====;======;======;;==-==;====;======r====o;=====;====;=====;=====;====;====-I 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c_] Interim Operating Period --TPGW-11 S --TPGW-13S -- TPGW-2S TPGW-4S -

TPGW-9S 31 30 29

(.)

0 28 Cl)...

J -

I'll 27 Cl) c.

E 26 Cl)

I-25

~

24 23 --,-----.--.---~---.-----,.----.----,-----.--.,.--~--T---.----.----,-----l 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c:::J lnterim Operating Period --TPGW-11S--TPGW-13S -

TPGW-2S TPGW-4S -

TPGW-9S 100000 90000 e 80000

~

~ 70000 Cl) g 60000 I'll -g 50000 "C

c: 8 40000 CJ i;:: 30000

'(j Cl)

~ 20000 10000 0

,~..,."'---'*"""t-I

........ ~-

I Section2

, ____,.,l~-...

1'""'

.......,. -~1~~-

4.-

I

,. I 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14

~ Interim Operating Period --TPGW-11 D --TPGW-13D --TPGW-2D TPGW-4D -

TPGW-9D 31 I

30 29

(.)

0 28 Cl)...

J I'll 27 Cl) c.

E 26 Cl)

I-25 I

24 ---

23 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c:::J Interim Operating Period --TPGW-11 D -

TPGW-13D --TPGW-2D TPGW-4D -

TPGW-9D Figure 2.1-21. Comparison of Specific Conductance and Temperature across the Landscape in Shallow and Deep Wells TPGW-11, TPGW-13, TPGW-2, TPGW-4, and TPGW-9.

2-55

FPL Turkey Point Annual Post-Uprate Monitoring Report for Units 3 & 4 Uprate Project-August 2014 100000 ~--------------~-------------------~

90000

'E 80000 u

cg_ 70000 Q) g 60000 IV -g 50000 "C

c: 8 40000 u

!E 30000 u

Q)

~ 20000 10000

---...-:----------------,_....__.., ____..:*-* -+-~ -....... __ _

I F-AF~'-----~~~r--__,..!

0 +-===:..::;::::::==::::::;===::::::;::::==::::::;::==::=;:====;:::::::==:;::::==::;::====:;====;====:;::====l;:====;====:;::===:::;::::====l 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 C-::J lnterim Operating Period --TPGW-11S --TPGW-13S TPGW-1S --TPGW-6S 31 30 29 u

~ 28 Q)...

I -

IV 27 Q)

Q.

E 26 Q) 25 24 23 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 C=:J lnterim Operating Period --TPGW-11S --TPGW-13S -- TPGW-1S --TPGW-6S 100000 90000

'E 80000 u

~ 70000 Q) g 60000 IV -g 50000 "C

c: 8 40000 u

!E 30000 u

Q)

~ 20000 10000 0

I

..)...-"---*

I :..,_Jo_.__L._ -

j.,

~

I

    • -~

I I

Section2 I

.-..... --r'L--l-..,........ 1**

1'--'

l i 1

I l l 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c

J Interim Operating Period TPGW-110 TPGW-130 TPGW-10 TPGW-60 31 30 I

29 u

~ 28 Q)...

I -

IV 27 Q)

Q.

E 26 Q)

I I

I I

25 I

I 24 I

23 I

6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c_] lnterim Operating Period

--TPGW-110 --TPGW-130 --TPGW-10 -- TPGW-60 Figure 2.1-22. Comparison of Specific Conductance and Temperature across the Landscape in Shallow and Deep Wells TPGW-11, TPGW-13, TPGW-1, and TPGW-6.

2-56

FPL Turkey Point Annual Post-Uprate Monitoring Report for Units 3 & 4 Uprate Project-August 2014 100000 90000

'E 80000 u

cg_ 70000 Q) g 60000 I'll -g 50000 I.. -*

~-

I

  • -*,~T~--..-

"C c:

t-~'

I I

r-'-'

  • T-b 8 40000 u

~ 30000

  • c:;

Q)

~ 20000 10000 0

~,.

-w 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 C-:J lnterim Operating Period --TPGW-10S -- TPGW-12S --TPGW-13S --TPGW-6S 31 30 29 0

~ 28 Q)...

I -

I'll 27 Q)

Q, E

26 Q)

I-25 24 23 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 c:=::i lnterim Operating Period --TPGW-10S --TPGW-1 2S --TPGW-13S --TPGW-6S 100000 90000

'E 80000 u

cg_ 70000 Q) g 60000 I'll -g 50000 "C c: 8 40000 u

~ 30000

  • c:;

Q)

~ 20000 10000 0

.J....-"--....:

. :..__1.-

Section2 I

- *---r'i.,.+."""'-1** 1'--'

f f i

-r--~

I I

I i

f 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14

~ Interim Operating Period

--TPGW-10D TPGW-12D

--TPGW-13D

--TPGW-6D I

I I

I I I 23 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 r

Interim Operating Period

--TPGW-10D --TPGW-12D --TPGW-13D --TPGW-6D Figure 2.1-23. Comparison of Specific Conductance and Temperature across the Landscape in Shallow and Deep Wells TPGW-10, TPGW-12, TPGW-13, and TPGW-6.

2-57

FPL Turkey Point Comprehensive Annual Report for Units 3 & 4 Uprate Project-August 2014 90000

'E 80000

~ 70000 "'~~--n\\~~~

Q)

~ 60000 Ill -g 50000 "C s 40000 ---------

(.)

~ 30000 0

~ 20000 en 10000 0 -+--------.--.....-----...... --....-----....... ----.--......--------.--..-----....... -----1

(.)

~

f

J cu...

Q) 0..

E Q)

I-6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 c:::J lnterim Operating Period

--TPGW-1S TPGW-3S TPGW-10S TPGW-12S TPGW-13S 30 29 28 27 26 25 24 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 6/1/14 TPGW-2S TPGW-11 S

-TPGW-14S 23 +---~-~--~-~-~--~-...,_-~-~--~-~-~--~-~-~------j 6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12

---:::! Interim Operating Period

--TPGW-1S TPGW-3S TPGW-10S TPGW-1 2S TPGW-13S 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 TPGW-2S TPGW-11S TPGW-14S 6/1/14 Section2 100000 90000

'E 80000 *-

I

-..r--...-----r*~-,. 1 '""'----

0

~

~ 70000 Q) 0 60000 c:

Ill i

- r=c::

0 50000

J "C c: 40000 0

(.)

0 30000

!E 0

~ 20000 en 10000 0 -+--------.--..-----...... --....-----....... ----.--......--------.--..-----....... ~

-u

~

f

J cu...

Q) 0..

E Q)

I-6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 r..:::.:J Interim Operating Period

--TPGW-10 TPGW-30 TPGW-100 TPGW-12D TPGW-13S 30 29 28 27 26 25 24 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 E TPGW-20 TPGW-110

-TPGW-14S 23 +---~-~--~-~-~--~--T--~-~--~-~-~--~-~-~-

6/1/10 9/1/10 12/1/10 3/1/11 6/1/11 9/1/11 12/1/11 3/1/12 6/1/12 9/1/12 Jlnterim Operating Period

--TPGW-10 TPGW-3D TPGW-10D TPGW-12D TPGW-13D 12/1/12 3/1/13 6/1/13 9/1/13 12/1/13 3/1/14 E TPGW-20 TPGW-11D TPGW-14D Figure 2.1-24. Comparison of Specific Conductance and Temperature across the Landscape in Shallow and Deep Wells Close to the CCS -TPGW-1, TPGW-2, TPGW-3, TPGW 10, TPGW-11, TPGW-12, TPGW-13, and TPGW-14.

2-58

FPL Turkey Point Annual Post-Uprate Monitoring Report for Units 3 & 4 Uprate Project-August 2014 Section2 Top view of probes in stilling well.

Biscayne Bay non-telemetry setup.

Figure 2.2-1. Automated Surface Water Stations.

2-59