NRC 2013-0099, NextEra Energy Point Beach, LLC, Readiness for 95002 Supplemental Inspection

From kanterella
(Redirected from ML13303B690)
Jump to navigation Jump to search
NextEra Energy Point Beach, LLC, Readiness for 95002 Supplemental Inspection
ML13303B690
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 10/29/2013
From: Meyer L
Point Beach
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NRC 2013-0099
Download: ML13303B690 (2)


Text

NEXTera.

ENERGY~

~

October 29, 2013 NRC 2013-0099 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Point Beach Nuclear Plant, Units 1 and 2 Docket 50-266 and 50-301 Renewed License Nos. DPR-24 and DPR-27 NextEra Energy Point Beach, LLC, Readiness for 95002 Supplemental Inspection

References:

1. US Nuclear Regulatory Commission to NextEra Energy Point Beach, LLC, Final Significance Determination of a White Finding with Assessment Followup and Notice of Violation; NRC Inspection Report No. 05000266/2013012 and 05000301/2013012; Point Beach Nuclear Plant, Units 1 and 2, dated August 9, 2013 [ML13221A187]
2. US Nuclear Regulatory Commission to NextEra Energy Point Beach, LLC, Final Significance Determination of a White Finding with Assessment Followup and Notice of Violation; NRC Inspection Report No. 05000266/2012010; Point Beach Nuclear Plant, Unit 1, dated January 2, 2013 [ML13004A280]
3. US Nuclear Regulatory Commission to NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Unit 1- NRC 95001 Supplemental Inspection Report 05000266/2013009 and Assessment Follow-Up Letter, dated September 19, 2013 [ML13262A523]

The Nuclear Regulatory Commission (NRC) issued two greater than green findings in the Mitigating Systems Cornerstone to NextEra Energy Point Beach, LLC, for failure to implement external flooding wave run-up protection design features as described in the Final Safety Analysis Report (Reference 1) and failure of a turbine driven auxiliary feedwater pump (Reference 2). References 1 and 3 indicate the NRC will conduct an inspection using Inspection Procedure 95002, "Supplemental Inspection for One Degraded Cornerstone or Any Three White Inputs in a Strategic Performance Area," upon being notified of Point Beach's readiness for inspection.

NextEra Energy Point Beach, LLC, has completed investigations to determine the root and contributing causes of the individual and collective performance issues associated with the degraded cornerstone. The extent of condition and extent of cause of the individual and collective performance issues have also been evaluated, and a determination has been made whether safety culture components were causes of or contributors to the issues . Corrective actions have been developed to address the root and contributing causes and to prevent recurrence of the significant performance issues. NextEra believes the corrective actions taken and planned will address the issues and provide the basis for sustained, improved performance at Point Beach.

NextEra Energy Point Beach, LLC, 6610 Nuclear Road, Two Rivers, WI 54241

Document Control Desk Page 2 NextEra Energy Point Beach, LLC, is notifying the NRC of readiness for the 95002 Supplemental Inspection and is requesting the inspection to occur during the timeframe of December 2 - 20, 2013.

This letter contains no new regulatory commitments.

If you have any questions, please contact Mr. Michael Millen, Licensing Manager, at (920) 755-7845.

Very truly yours, NextEra Energy Point Beach, LLC

/~

arry fyleyer Si e--\hce President cc: Administrator, Region Ill, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC Project Manager, Point Beach Nuclear Plant, USNRC