March 11, 2014 by Electronic Information Exchange Administrative Judge Alex S. Karlin Administrative Judge Nicholas G. Trikouros Administrative Judge Paul B. Abramson Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Two White Flint North 11545 Rockville Pike Mail Stop: T-3F23 Rockville, MD 20852 In the Matter of PACIFIC GAS AND ELECTRIC COMPANY (Diablo Canyon Power Plant, Units 1 and 2)

Docket Nos. 50-275-LR and 50-323-LR RE: Status Report

Dear Administrative Judges:

As directed by the Licensing Board Order of June 7, 2011, Pacific Gas and Electric Company (PG&E) hereby provides its monthly report specifying its current best estimate of the dates on which it expects to complete milestones related to 3D seismic studies for Diablo Canyon Power Plant (DCPP) and the coastal zone consistency certification associated with NRC license renewal for DCPP.

The schedule for the seismic work is unchanged since PG&Es last submittal on February 11, 2014. PG&E will continue to provide specific dates in the monthly reports to the extent practicable, recognizing that these dates may be modified as more accurate information becomes available. PG&E wishes to assure the Licensing Board that it is making every effort to minimize the extent of the delay in the NRC license renewal process.

Executed in accord with 10 CFR 2.304(d),

/s/ signed electronically by Jennifer K. Post Attorney Pacific Gas and Electric Company 77 Beale St., B30A San Francisco, CA 94105 (415) 973-9809 jklm@pge.com

/s/ signed electronically by David A. Repka Winston & Strawn LLP 1700 K Street, NW Washington, DC 20006 (202) 282-5726 drepka@winston.com cc: Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Service List (via Electronic Information Exchange)

Pacific Gas and Electric Company Updated Best Estimate Schedule for Seismic Studies Description of Activity Current Estimate Shoreline Fault Submit Final Report to the NRC January 2011(a)

NRC Review Complete October 12, 2012(a)

Ocean Bottom Seismometer Study Permit Application Submitted to California State Lands May 6, 2011(a)

Commission (CSLC)

Permits Issued May 2013(a)

OBS System Installed August 2013(a)

OBS Equipment Repair and Adjustment November 2013(a) 2D/3D Low Energy Marine Studies Permits Issued N/A Surveys Complete October 2012(a)

Data Processing and Interpretation Complete October 2013(a) 2D Onshore High Energy Studies Permit Pre-Application Meeting May 4, 2011(a)

Use Permits Issued Not Required Surveys Complete December 2011(a) and December 2012(a)

Data Processing and Interpretation Complete June 2014 3D High Energy Marine Studies Permit Application Submitted to CSLC April 29, 2011(a)

CSLC Environmental Impact Report Scoping Meeting July 21, 2011(a)

Permits Denied November 14, 2012(a)

Issue Final Seismic Report to the NRC and ASLB June 2014 CZMA or Coastal Consistency File Coastal Development Permit TBD Coastal Consistency Issued TBD (a)

Note: - Actual Date Completed SF:349580.1