ML13354B960

From kanterella
Jump to navigation Jump to search
2013, Dresden Initial License Exam, Proposed Admin JPMs
ML13354B960
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 11/25/2013
From: Walton R
NRC/RGN-III/DRS/OLB
To:
Walton R
References
Download: ML13354B960 (40)


Text

RO ADMIN JPM (K/A 2.1.25) Conduct of Operations - Determine Generator Operating Limits from Capability Curve.

I/Cs

  • U2 at 900 MWe and 200 MVARs
  • Regulator in Service (AUTO) - H 2 pressure is 58 PSIG Cue(s)
  • You are the BOP Operator.

Expected Actions

  • Obtain DOP 6400-08, 345 KV VOLTAGE CONTROL, and review prerequisites, etc.
  • Per Figure 4, determine that the TSO request can be performed within limits.
  • Adjust MVARs per step G.1.a (+ 20 MVARs) (Critical step - CS)
  • After MVARs adjusted, local operator informs you that the pressure regulator malfunctioned and H 2 pressure is now 44 PSIG.
  • Per Figure 4, determine that the current conditions are now not within limits. (CS)
  • As SRO, ask the applicant where he should leave MVARs, and verify his response is within the capability curve limits (JPM COMPLETE)

RO ADMIN JPM 2 K/A = 2.1.26 (Knowledge of industrial safety procedures)

Given the following Drywell conditions where work is being performed:

  • Dry Bulb Temperature = 110ºF
  • Wet Bulb Globe Temperature (WGBT) = 111ºF
  • Work Clothes/Scrubs are required.
  • Work = Inspections with moderate climbing Perform the following (SA-AA-111 may be used, if requested):
1. Classify the work environment conditions (CT). {Very High Temperature (VHT)}
2. Calculate the action time allowed (CT). {20 minutes (See Below)}
3. Calculate the rest time (the actual time to complete the job was 10 minutes)

(CT). {30 minutes (See Below)}

The action time (from Attachment 3) for WGBT = 111ºF and Moderate Work Rate = 20 minutes (from Attachment 4). Given that the job took 10 minutes, the rest time is 10min./20min. X 60 minutes = 30 minutes.

RO ADMIN 3 K/A = 2.2.14 (Knowledge of the process for controlling equipment configuration or status.)

Initial Conditions:

1. The plant is in Mode 1 GIVEN:
1. The process computer is NOT available,
2. The CRSP Unit Status sheet.
3. Provide plant data so that the value recorded in Step 4 OR 5 is GREATER THAN the Desired Setting per Operator Aid Unit 2(3) APRM/RBM Flow Converter Setting vs. Total Drive Flow, for WD% value recorded in Step 3, so the applicant contacts the QNE AND IMD to perform DIS 0700-02, APRM/RBM Flow Instrumentation Total Drive Flow Adjustment. (JPM COMPLETE)

CUE:

The US directs you, the extra RO, to perform an APRM FLOW BIAS CALIBRATION CHECK per DOS 0500-26.

CRITICAL TASKS (CTs):

1. Calculated Total Drive Flow (Step 1b)
2. Calculated Drive Flow % (Step 3)
3. Actions for Acceptance Criteria not met (Step 6a)

RO ADMIN JPM 5 K/A = 2.4.27 Knowledge of fire in the plant procedures.

I/Cs

  • A fire outside the protected area is occurring. (PROVIDE SOME ADDITIONAL DETAILS TO BE COMMUNICATED) - no explosion, hazmat or rescue required.
  • The Fire Brigade has been alerted and is attempting to combat the fire unsuccessfully.

Cue(s)

  • The US directs you to request outside assistance.
  • 911 is not working.
  • You are the BOP Operator.

Expected Actions

  • Obtain DOA 0010-10, FIRE-EXPLOSION, and review prerequisites, etc.
  • Per Step D.2, obtain the phone number of the Coal City Fire Protection District per DOA 0010-S1, KEY PHONE NUMBERS FOR DOA 0010 BLOCK PROCEDURES (Critical step - CS)
  • Dial 815-942-0336 and communicate the details of the fire. (CS)
  • Notify Security Shift Supervisor that outside fire department will be responding AND request assistance in providing access to affected area if necessary. (JPM COMPLETE)

Exelon Nuclear Job Performance Measure Reportability Determination JPM Number: S-RD-03 Revision Number: 00 Date: 02/01/06 Developed By:

Instructor Date Validated By:

SME or Instructor Date Review By:

Operations Representative Date Approved By:

Training Department Date Page 1 of 9

Job Performance Measure (JPM)

JOB PERFORMANCE MEASURE VALIDATION CHECKLIST NOTE: All steps of this checklist should be performed upon initial validation. Prior to JPM usage, revalidate JPM using steps 8 through 11 below.

________ 1. Task description and number, JPM description and number are identified.

________ 2. Knowledge and Abilities (K/A) references are included.

________ 3. Performance location specified. (in-plant, control room, or simulator)

________ 4. Initial setup conditions are identified.

________ 5. Initiating and terminating cues are properly identified.

________ 6. Task standards identified and verified by SME review.

________ 7. Critical steps meet the criteria for critical steps and are identified with an asterisk (*).

________ 8. Verify the procedure referenced by this JPM matches the most current revision of that procedure:

Procedure Rev. _____ Date _____________

________ 9. Pilot test the JPM:

a. verify cues both verbal and visual are free of conflict, and
b. ensure performance time is accurate.

________ 10. If the JPM cannot be performed as written with proper responses, then revise the JPM.

________ 11. When JPM is revalidated, SME or Instructor sign and date JPM cover page.

SME/Instructor Date SME/Instructor Date SME/Instructor Date Page 2 of 9

Job Performance Measure (JPM)

Revision Record (Summary)

Revision 00 New JPM Page 3 of 9

Job Performance Measure (JPM)

SIMULATOR SETUP INSTRUCTIONS Any IC to accommodate other JPMs.

This is a table top JPM utilizing Simulator procedures.

Page 4 of 9

Job Performance Measure (JPM)

INITIAL CONDITIONS You are required to locate the appropriate procedures for this JPM.

You are the Unit Supervisor.

An event has occurred resulting in the following conditions:

Evaluator - Give examinee the attached condition sheet.

Evaluator copy is on next page.

INITIATING CUE Determine the Reportability requirements, including the Event Classification and the Time Limit of any Notifications or Reports.

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information for Evaluators Use:

UNSAT requires written comments on respective step.

  • Denotes CRITICAL steps.

Number any comments in the Comment Number column on the following pages. Then annotate that comment in the Comments section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps. These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

Page 5 of 9

Job Performance Measure (JPM)

You are required to locate the appropriate procedures for this JPM.

You are the Unit Supervisor.

An event has occurred resulting in the following conditions:

  • Unit 2 is at 95% power.
  • The seven-day Tech Spec time clock is about to expire for the Unit 2 EDG being degraded.
  • Unit 2 has initiated a shutdown since it is required to be in cold shutdown within the next 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Page 6 of 9

Job Performance Measure (JPM)

JPM Start Time: _________

UNSAT Comment #

PERFORMANCE CHECKLIST STANDARDS SAT

  • 1. Determines the event is Determines the event is reportable per SAF 1.2 reportable per SAF 1.2, Plant Shutdown Required by Technical Specifications
  • 2. Determines the time Determines the time limit to limit to report via ENS report via ENS as soon as as soon as practicable, practicable, and in all cases and in all cases within within four hour of initiating the four hour of initiating the shutdown that is required by shutdown that is TS.

required by TS.

Note The student might also indicate that a 60 day LER is required if the shutdown is completed.

END JPM Stop Time:_________

Page 7 of 9

Job Performance Measure (JPM)

Operators Name: ___________________________________

Job

Title:

NLO RO SRO STA SRO Cert JPM

Title:

Reportability Determination JPM Number: S-RD-01 Revision Number: 00 Task Number and

Title:

299L001, Determine Reportability requirements as outlined in station Reportability manual.

K/A Number and Importance: 2.1.10 2.7 /3.9 Suggested Testing Environment: Simulator Actual Testing Environment: Simulator Plant Control Room Testing Method: Simulate Faulted: Yes No Perform Alternate Path: Yes No Time Critical: Yes No Estimated Time to Complete: 10 minutes Actual Time Used: _______minutes

References:

Reportability Manual, LS-AA-1110 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily? Yes No The operators performance was evaluated against the standards contained in this JPM, and has been determined to be: Satisfactory Unsatisfactory Comments:

Evaluators Name: ____________________________

(Print)

Evaluators Signature: ___________________________ Date: _________

Page 8 of 9

Job Performance Measure (JPM)

INITIAL CONDITIONS You are required to locate the appropriate procedures for this JPM.

You are the Unit Supervisor.

An event has occurred resulting in the following conditions:

  • Unit 2 is at 95% power.
  • The seven-day Tech Spec time clock is about to expire for the Unit 2 EDG being degraded.
  • Unit 2 has initiated a shutdown since it is required to be in cold shutdown within the next 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

INITIATING CUE Determine the Reportability requirements, including the Event Classification and the Time Limit of any Notifications or Reports.

Page 9 of 9

Exelon Nuclear Job Performance Measure DECLARE EDG OPERABLE AFTER SURVEILLANCE REVIEW JPM Number: A-N-c Revision Number: 00 Date: 03/22/2004 Developed By:

Instructor Date Approved By:

Facility Representative Date A-N-c Page 1 of 8

Job Performance Measure (JPM)

JOB PERFORMANCE MEASURE VALIDATION CHECKLIST NOTE: All steps of this checklist should be performed upon initial validation. Prior to JPM usage, revalidate JPM using steps 8 through 11 below.

________ 1. Task description and number, JPM description and number are identified.

________ 2. Knowledge and Abilities (K/A) references are included.

________ 3. Performance location specified. (in-plant, control room, or simulator)

________ 4. Initial setup conditions are identified.

________ 5. Initiating and terminating cues are properly identified.

________ 6. Task standards identified and verified by SME review.

________ 7. Critical steps meet the criteria for critical steps and are identified with an asterisk (*).

________ 8. Verify the procedure referenced by this JPM matches the most current revision of that procedure:

Procedure Rev. _____ Date _____________

________ 9. Pilot test the JPM:

a. verify cues both verbal and visual are free of conflict, and
b. ensure performance time is accurate.

________ 10. If the JPM cannot be performed as written with proper responses, then revise the JPM.

________ 11. When JPM is revalidated, SME or Instructor sign and date JPM cover page.

SME/Instructor Date SME/Instructor Date SME/Instructor Date A-N-c Page 2 of 8

Job Performance Measure (JPM)

Revision Record (Summary)

Revision 00, New JPM for ILT 03-1 NRC Exam A-N-c Page 3 of 8

Job Performance Measure (JPM)

SIMULATOR SETUP INSTRUCTIONS

1. Any IC to accommodate other JPMs.
2. This is a tabletop JPM utilizing simulator procedures.

A-N-c Page 4 of 8

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Unit 3 Unit Supervisor.
2. The Unit 3 NSO has completed DOS 6600-01, DIESEL GENERATOR SURVEILLANCE TESTS.
3. The Unit 3 EDG was run for a normal even month surveillance.
4. The Unit 3 NSO has completed the monthly EDG surveillance.

INITIATING CUE

1. Verify the Unit 3 EDG surveillance has been completed correctly.
2. Review the surveillance and determine the operability of the Unit 3 EDG. Report the outcome to the Shift Manager.

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information for Evaluators Use:

UNSAT requires written comments on respective step.

  • Denotes CRITICAL steps.

Number any comments in the Comment Number column on the following pages. Then annotate that comment in the Comments section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps. These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

A-N-c Page 5 of 8

Job Performance Measure (JPM)

JPM Start Time: _________

UNSAT Comment #

PERFORMANCE CHECKLIST STANDARDS SAT Note: If examinee identifies error and has NSO fix error, fix the problem with the number/solution provided by examinee.

  • 1. Verify A compressor Recognizes that the A starts > 220 psig. compressor started < 220 psig.
2. IF compressor A start/ Recognizes that compressor stop pressures are not A did NOT start within the within expected range, expected range (218 psig), the THEN contact System System Engineer needs to be Engineer. (Expected contacted. (Expected START range START 225 - range 225 - 240 psig) 240, STOP 250 - 260, _____ _____ _____

psig)

3. Notify System Engineer Notifies System Engineer that that A compressor did A compressor did not start at not start at the expected the expected band.

band. _____ _____ _____

  • 4. Declare D/G Operable Recognizes that the Acceptance Criteria for the Unit 3 EDG is met and determines the EDG is _____ _____ _____

operable.

5. Notify Shift Manager of Notifies Shift Manager of completion. discrepancies and EDG is now operable, but A compressor did not start within the required band and Engineering has been notified.

END JPM Stop Time:_________

A-N-c Page 6 of 8

Job Performance Measure (JPM)

Operators Name: _______________________________ ____

Job

Title:

RO SRO STA SRO Cert JPM

Title:

Verify Unit 3 EDG Surveillance JPM Number: A-N-c Revision Number: 00 Task Number and

Title:

264L009, Perform surveillance testing.

K/A Number and Importance: 2.2.12; 3.0 / 3.4 Suggested Testing Environment: Simulator Actual Testing Environment: Simulator Plant Control Room Testing Method: Simulate Faulted: Yes No Perform Alternate Path: Yes No Time Critical: Yes No Estimated Time to Complete: 15 minutes Actual Time Used: _______minutes

References:

DOS 6600-01 rev. 83 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily? Yes No The operators performance was evaluated against the standards contained in this JPM, and has been determined to be: Satisfactory Unsatisfactory Comments:

Evaluators Name: ____________________________

(Print)

Evaluators Signature: ___________________________ Date: _________

A-N-c Page 7 of 8

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Unit 3 Unit Supervisor.
2. The Unit 3 NSO has completed DOS 6600-01, DIESEL GENERATOR SURVEILLANCE TESTS.
3. The Unit 3 EDG was run for a normal even month surveillance.
4. The Unit 3 NSO has completed the monthly EDG surveillance.

INITIATING CUE

1. Verify the Unit 3 EDG surveillance has been completed correctly.
2. Review the surveillance and determine the operability of the Unit 3 EDG. Report the outcome to the Shift Manager.

A-N-c Page 8 of 8

Exelon Nuclear Job Performance Measure SELECT PERSONNEL FOR RADIATION WORK JPM Number: A-N-4-S Revision Number: NEW NEVER USED Date: 10/09 Developed By:

Instructor Date Approved By:

Facility Representative Date

Job Performance Measure (JPM)

Revision Record (Summary)

Revision 00 Modified A-N-4-S Page 2 of 10

Job Performance Measure (JPM)

SIMULATOR SETUP INSTRUCTIONS

1. This is a tabletop JPM utilizing simulator procedures.
2. No Simulator setup needed.

DOCUMENT PREPARATION

1. Markup a copy of an RWP for the Unit 3 RWCU Pump Room.
2. Markup a survey map for the Unit 3 RWCU Pump Room.
3. Clean copy of RP-AA-203.

A-N-4-S Page 3 of 10

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are a Unit Supervisor and will be briefing NLOs to perform a Clearance Order First Hang in the Unit 3 RWCU Pump Room under RWP 10004555.
2. Five NLOs are available this shift.
  • None of the five have received dose at any location other than Dresden Station.
  • None of the five have received dose since midnight on any RWPs other than 10004555.
3. The Radiation Protection Department has provided the attached Survey map, and the following dose history for the five NLOs to assist you in your planning:

DDE dose received on Annual TEDE dose Name RWP 10004555 Today To Date Alex 40 mrem 1550 mrem Dan 5 mrem 1950 mrem Mike 0 mrem 1920 mrem Sue 45 mrem 1850 mrem Tom 10 mrem 1750 mrem

4. The total expected stay time for each NLO will be 60 minutes. Based on past job history, it will breakdown as follows:
  • 45 minutes total in the area near the following two valves:

3-1201-138 RWCU Aux Pump Suction (at RWCU Aux Pump) 3-1201-139 RWCU Aux Pump Discharge (at RWCU Aux Pump)

  • 15 minutes total in the area near the following one valve:

3-1201-128A A RWCU Pump Suction (at A RWCU Pump)

INITIATING CUE

1. CALCULATE the expected dose for the work in RWCU Pump Room. DETERMINE which NLO(s) CAN and which NLO(s) CAN NOT be assigned to perform the task. EXPLAIN the basis for your determination.

A-N-4-S Page 4 of 10

Job Performance Measure (JPM)

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluators Use:

UNSAT requires written comments on respective step.

  • Denotes critical steps.
  • Denotes critical elements of a critical step.

Number any comments in the Comment Number column on the following pages. Then annotate that comment in the Comments section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps.

These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

A-N-4-S Page 5 of 10

Job Performance Measure (JPM)

JPM Start Time: _________

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT NOTE:

Provide the examinee with the supplied copy of the RWP and survey map of the RWCU pump room and the supplied copy of RP-AA-203.

The following steps may be performed in any order.

1. Reviews Survey Maps to Reviews the survey maps determine area dose rates. and determines area dose rates to be 50 mr/hr for the first group of 2 valves and _____ _____ _____

160 mr/hr for the remaining valve.

NOTE:

The following calculations should be made:

2 valve clearance projected dose = 0.75 hr x 40 mr/hr = 30 mrem 1 valve clearance projected dose = 0.25 hr x 140 mr/hr = 35 mrem Total projected dose for the job = 40 mrem + 30 mrem = 65 mrem

  • 2. Calculates that the projected Determines the NLOs will dose that will be received for receive 30 mrem on the the task is 65 mrem. first 2 valves and 35 on the next valve. _____ _____ _____

CUE:

IF the candidate inquires whether or not any of the NLOs has received permission to exceed any dose limits, respond: None of the Non Licensed Operators have received permission to exceed any limits.

NOTE:

The following steps may be performed in any order.

  • 3. Determines that ALEX Alexs total daily dose on CAN NOT perform the job RWP 10004555 would be because he would exceed the 105 mrem.

80 mrem dose alarm on RWP _____ _____ _____

10004555.

A-N-4-S Page 6 of 10

Job Performance Measure (JPM)

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT

  • 4. Determines that Dan Dans total Annual dose CAN NOT perform the job would be 2015 mrem.

because he would exceed the 2000 mrem Exelon Annual _____ _____ _____

limit.

  • 5. Determines that Mike CAN Mikes total RWP daily perform the job because no dose and Annual dose will limits will be exceeded. remain below the limits. _____ _____ _____
  • 6. Determines that Sue Alexs total daily dose on CAN NOT perform the job RWP 10004555 would be because she would exceed 110 mrem. _____ _____ _____

the 80 mrem dose alarm on RWP 10004555.

  • 7. Determines that Tom CAN Toms total RWP daily perform the job because no dose and Annual dose will limits will be exceeded. remain below the limits.

END JPM Stop Time:_________

A-N-4-S Page 7 of 10

Job Performance Measure (JPM)

Operators Name:

Job

Title:

SRO JPM

Title:

SELECT PERSONEL FOR RADIATION WORK Revision Number: 00 JPM Number: A-N-4-S Task Number and

Title:

29900LK119, Discuss the items to be considered prior to work authorization K/A Number and Importance: Generic.2.3.4 3.2 / 3.7 Suggested Testing Environment: Simulator Actual Testing Environment: Simulator Control Room In-Plant Testing Method: Simulate Alternate Path: Yes No Perform SRO Only: Yes No Time Critical: Yes No Estimated Time to Complete: 10 minutes Actual Time Used: minutes

References:

RP-AA-203, rev 03 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily? Yes No The operators performance was evaluated against the standards contained in this JPM, and has been determined to be: Satisfactory Unsatisfactory Comments:

Evaluators Name (Print):

Evaluators Signature: Date:

A-N-4-S Page 8 of 10

Job Performance Measure (JPM)

KEY EVALUATOR: The candidate must determine that dose for the task will be 65 mrem and determine that only two NLOs can receive the dose, necessary to complete the task. They are Mike and Tom. See the table below for projected job dose, 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> total dose on RWP 10004555, and total Annual TEDE dose for each Operator.

Calculation:

2 valves clearance (at RWCU Aux Pump) projected dose = 0.75 hr x 40 mr/hr =

30mrem 1 valve clearance (at A RWCU Pump) projected dose = 0.25hr x 140 mr/hr =

35mrem 30mrem + 35 mrem = 65 mrem projected job dose for clearance order hanging DDE dose Annual TEDE Projected dose on Projected Annual TEDE Name received on RWP dose as of RWP 10004555 (including all dose from 10004555 today Midnight To Date for the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period last 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />)

(40 + 65 =) (1550 + 65 =)

Alex 40 mrem 1550 mrem 105 mrem 1615 mrem (5 + 65 =) (1950 + 65 =)

Dan 5 mrem 1950 mrem 70 mrem 2015 mrem (0 + 65 =) (1920 + 65 =)

Mike 0 mrem 1920 mrem 65 mrem 1985 mrem (45 + 65 =) (1850 + 65 =)

Sue 45 mrem 1850 mrem 110 mrem 1915 mrem (10 + 65 =) (1750 + 65 =)

Tom 10 mrem 1750 mrem 75 mrem 1815 mrem The bolded values in the table exceed the applicable Company, RWP, or 10CFR limit.

A-N-4-S Page 9 of 10

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are a Unit Supervisor and will be briefing NLOs to perform a Clearance Order First Hang in the Unit 3 RWCU Pump Room under RWP 10004555.
2. Five NLOs are available this shift.
  • None of the five have received dose at any location other than Dresden Station.
  • None of the five have received dose since midnight on any RWPs other than 10004555.
3. The Radiation Protection Department has provided the attached Survey map, and the following dose history for the five NLOs to assist you in your planning:

DDE dose received on Annual TEDE dose Name RWP 10004555 Today To Date Alex 40 mrem 1550 mrem Dan 5 mrem 1950 mrem Mike 0 mrem 1920 mrem Sue 45 mrem 1850 mrem Tom 10 mrem 1750 mrem

4. The total expected stay time for each NLO will be 60 minutes. Based on past job history, it will breakdown as follows:
  • 45 minutes total in the area near the following two valves:

3-1201-138 RWCU Aux Pump Suction (at RWCU Aux Pump) 3-1201-139 RWCU Aux Pump Discharge (at RWCU Aux Pump)

  • 15 minutes total in the area near the following one valve:

3-1201-128A A RWCU Pump Suction (at A RWCU Pump)

INITIATING CUE

1. CALCULATE the expected dose for the work in RWCU Pump Room.

DETERMINE which NLO(s) CAN and which NLO(s) CAN NOT be assigned to perform the task. EXPLAIN the basis for your determination.

A-N-4-S Page 10 of 10

Exelon Nuclear Job Performance Measure AUTHORIZE USE OF KI JPM Number: A-N-5-S Revision Number: 01 Date: 09/10 Developed By:

Instructor Date Approved By:

Facility Representative Date

Job Performance Measure (JPM)

Revision Record (Summary)

Revision 00 Bank JPM.

Revision 01 Revised for 2010 NRC exam.

A-N-5-S Page 2 of 9

Job Performance Measure (JPM)

SIMULATOR SETUP INSTRUCTIONS

1. This is a tabletop JPM utilizing simulator procedures.
2. No Simulator setup needed.

DOCUMENT PREPARATION

1. Two (2) marked up copies of EP-AA-113-F-02.
2. Blank copy of EP-AA-113.
3. Blank copy of EP-AA-113-F-03.

A-N-5-S Page 3 of 9

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Station Emergency Director.
2. A General Emergency has been declared.
3. There is an offsite release in progress.
4. A Loss of the Fuel Clad Barrier has occurred, together with a failure of the RCS.
5. Containment is currently being challenged.
6. The TSC has NOT been activated, but the appropriate EAL has been declared.
7. An Emergency life saving operation MUST be performed.
8. The operation will take between 15 and 20 minutes in a 200 R/hr field (CDE) with unknown fission product gas concentration in the room.
9. The operation requires two people to enter the field.
10. Clay Morrow, Employee ID# 123456 and Jax Teller Employee ID# 891011 have volunteered.
11. Clay and Jax have NEVER received an emergency exposure before.
12. Authorization for Emergency Exposure (EP-AA-113-F-02 forms) have been filled out for Clay and Jax.

INITIATING CUES

1. Execute section 4.4 of EP-AA-113.

A-N-5-S Page 4 of 9

Job Performance Measure (JPM)

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluators Use:

UNSAT requires written comments on respective step.

  • Denotes critical steps.
  • Denotes critical elements of a critical step.

Number any comments in the Comment Number column on the following pages. Then annotate that comment in the Comments section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps.

These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

A-N-5-S Page 5 of 9

Job Performance Measure (JPM)

JPM Start Time: _________

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT NOTE:

Provide the Examinee the provided copies of:

EP-AA-113-F-02, EP-AA-113, and EP-AA-113-F-03

1. Applicant determines need for Emergency action is emergency action. needed per initiating cue.

CUE:

If asked, Clay and Jax do NOT have any adverse reactions to KI.

2. Applicant recognizes per the Recognizes that initiating cue that authorization to take KI authorization to take KI must must also be completed.

also be completed prior to the _____ _____ _____

emergency workers entering the space.

  • 3. Determines there is or has Determines KI must be been a Loss of Fuel Clad issued.

Barrier (based on initiating cues). Determines from step 4.4.1.B, condition 1, that workers will be entering an unknown radiological atmosphere that is suspected to have a high iodine concentration. Determines KI must be issued.

  • 4. Documents the decision to BOTH individuals being issue KI using THYROID authorized for KI and BLOCKING AGENT entering the space must be AUTHORIZATION Form listed with their correct (EP-AA-113-F-03). names and employee ID numbers:
  • Clay Morrow _____ _____ _____

123456

  • Jax Teller 891011 A-N-5-S Page 6 of 9

Job Performance Measure (JPM)

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT NOTE:

If asked for Radiation Protection Manager to sign and date EP-AA-113-F-03, enter name as TIG TRAGER and todays date in the appropriate blanks.

5. Notifies Occupational Health Examinee states that (Medical) Services he/she would notify OHS.

Department promptly that KI _____ _____ _____

is to be issued to Exelon Nuclear personnel or contractors.

NOTE:

JPM is complete when applicant notifies OHS of KI use.

END JPM Stop Time:_________

A-N-5-S Page 7 of 9

Job Performance Measure (JPM)

Operators Name:

Job

Title:

SRO JPM

Title:

AUTHORIZE USE OF KI Revision Number: 01 JPM Number: A-N-5-S Task Number and

Title:

29900LK150, Discuss the responsibilities of the Shift Manager regarding Reportability determination and event notifications.

K/A Number and Importance: Generic.2.4.40 2.7 / 4.5 Suggested Testing Environment: Simulator Actual Testing Environment: Simulator Control Room In-Plant Testing Method: Simulate Alternate Path: Yes No Perform SRO Only: Yes No Time Critical: Yes No Estimated Time to Complete: 20 minutes Actual Time Used: minutes

References:

EP-AA-113, rev B; EP-AA-113-F-03, rev D; EP-AA-113, rev 10 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily? Yes No The operators performance was evaluated against the standards contained in this JPM, and has been determined to be: Satisfactory Unsatisfactory Comments:

Evaluators Name (Print):

Evaluators Signature: Date:

A-N-5-S Page 8 of 9

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Station Emergency Director.
2. A General Emergency has been declared.
3. There is an offsite release in progress.
4. A Loss of the Fuel Clad Barrier has occurred, together with a failure of the RCS.
5. Containment is currently being challenged.
6. The TSC has NOT been activated, but the appropriate EAL has been declared.
7. An Emergency life saving operation MUST be performed.
8. The operation will take between 15 and 20 minutes in a 200 R/hr field (CDE) with unknown fission product gas concentration in the room.
9. The operation requires two people to enter the field.
10. Clay Morrow, Employee ID# 123456 and Jax Teller Employee ID# 891011 have volunteered.
11. Clay and Jax have NEVER received an emergency exposure before.
12. Authorization for Emergency Exposure (EP-AA-113-F-02 forms) have been filled out for Clay and Jax.

INITIATING CUES

1. Execute section 4.4 of EP-AA-113.

A-N-5-S Page 9 of 9