Other: ML13098A396, ML13098A431, ML13098A511, ML13175A211, ML13295A222, ML13323A183, ML13323A186, ML13323A189, ML13323A190, ML13323A191, ML13338A165, NOC-AE-13003039, Corrections to Information Provided in Revised STP Pilot Submittal and Requests for Exemptions and License Amendment for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI)
|
MONTHYEARML13043A0132013-01-31031 January 2013 Pilot Submittal and Request for Exemption for a Risk-Informed Approach to Resolve Generic Safety Issue (GSI)-191 Project stage: Request ML13066A5192013-04-0101 April 2013 Supplemental Information Needed for Acceptance of Requested Licensing Action Request for Exemption for a Risk-Informed Approach to Resolve Generic Safety Issue 191 Project stage: Acceptance Review ML13098A3962013-04-0808 April 2013 Email Risk Informed GSI-191 Evaluation Project stage: Other ML13098A5112013-04-0808 April 2013 Corrosion/Head Loss Experiment Program Project stage: Other ML13098A4312013-04-0808 April 2013 Development of Chemical Effects Modules for Risk-Informed GSI-191 Resolution Project stage: Other ML13101A3142013-04-12012 April 2013 Notice of Meeting Via Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed Approach to Resolve Generic Safety Issue 191 for South Texas, Units 1 and 2 Project stage: Meeting NOC-AE-13002994, Schedule for Supplement to STP Pilot Submittal and Request for Exemption for a Risk-Informed Approach to Resolve Generic Safety Issue (GSI)-1912013-04-17017 April 2013 Schedule for Supplement to STP Pilot Submittal and Request for Exemption for a Risk-Informed Approach to Resolve Generic Safety Issue (GSI)-191 Project stage: Supplement ML13114A2552013-04-17017 April 2013 Schedule for Supplement to STP Pilot Submittal and Request for Exemption for a Risk-Informed Approach to Resolve Generic Safety Issue (GSI)-191 Project stage: Supplement ML13112A2522013-04-25025 April 2013 Approval of Extension to Submit Supplemental Information for Acceptance of Licensing Action; Request for Exemption for a Risk-Informed Approach to Resolve Generic Safety Issue 191 Project stage: Acceptance Review ML13119A0802013-04-30030 April 2013 Notice Meeting Via Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed Approach to Resolve Generic Safety Issue 191 for South Texas, Units 1 and 2 Project stage: Meeting ML13140A2562013-05-20020 May 2013 Licensee Slides for 5/23/13 Meeting - STP Pilot Submittal for Risk Informed Approach to Resolving GSI-191 Project stage: Meeting ML13140A2692013-05-20020 May 2013 NRC Slides for 5/23/13 Meeting Regarding Risk - Informed GSI-191 Pilot Application Initial Review Insights Project stage: Meeting ML13150A2162013-05-23023 May 2013 Licensee Slides for 5/23/13 Public Meeting Regarding GSI-191 Project stage: Meeting ML13161A1632013-06-14014 June 2013 5/23/13 Summary of Public Meeting Via Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed Approach to Resolve Generic Safety Issue 191 for South Texas, Units 1 and 2 Project stage: Meeting ML13175A2112013-06-19019 June 2013 Revised STP Pilot Submittal and Requests for Exemptions and License Amendment for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI)-191 Project stage: Other ML13168A1622013-06-26026 June 2013 Summary of Meeting Via Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed Approach to Resolve Generic Safety Issue 191 for South Texas, Units 1 and 2 Project stage: Meeting ML13214A0312013-08-13013 August 2013 Acceptance Review, Exemption Requests and License Amendment Request to Revise UFSAR for Resolution of Generic Safety Issue 191, Assessment of Debris Accumulation on PWR Sump Performance (TAC MF0613-MF0614; MF2400-09) Project stage: Acceptance Review ML13295A2222013-10-0303 October 2013 Corrections to Information Provided in Revised STP Pilot Submittal and Requests for Exemptions and License Amendment for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI) Project stage: Other NOC-AE-13003039, Corrections to Information Provided in Revised STP Pilot Submittal and Requests for Exemptions and License Amendment for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI)2013-10-0303 October 2013 Corrections to Information Provided in Revised STP Pilot Submittal and Requests for Exemptions and License Amendment for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI) Project stage: Other ML13323A1892013-10-22022 October 2013 Enclosure 4-2 - Risk-Informed Closure of GSI-191, Volume 2 Probabilistic Risk Analysis Project stage: Other ML13323A1912013-11-0606 November 2013 Enclosure 4-3 Risk-Informed Closure of GSI-191, Volume 3, Engineering (Casa Grande) Analysis, Page 212 of 1-122 Project stage: Other ML13323A1902013-11-0606 November 2013 Enclosure 4-3 Risk-Informed Closure of GSI-191, Volume 3, Engineering (Casa Grande) Analysis, Cover - Page 211 of 248 Project stage: Other ML13323A1862013-11-12012 November 2013 Enclosure 4-1 - Risk-Informed Closure of GSI-191, Volume 1 Project stage: Other ML13323A1832013-11-13013 November 2013 To Revised STP Pilot Submittal and Requests for Exemptions and License Amendment for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI)-191 Project stage: Other ML13323A1922013-11-13013 November 2013 Enclosure 5 - Response to NRC Supplemental Information Items Project stage: Supplement NOC-AE-13003043, Enclosure 5 - Response to NRC Supplemental Information Items2013-11-13013 November 2013 Enclosure 5 - Response to NRC Supplemental Information Items Project stage: Supplement NOC-AE-13003054, Supplement 1 to Revised STP Pilot Submittal for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI)-191 to Supersede and Replace the Revised Pilot Submittal2013-11-21021 November 2013 Supplement 1 to Revised STP Pilot Submittal for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI)-191 to Supersede and Replace the Revised Pilot Submittal Project stage: Supplement ML13338A1652013-11-21021 November 2013 To Revised STP Pilot Submittal for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI)-191 to Supersede and Replace the Revised Pilot Submittal Project stage: Other ML13330B7152013-11-26026 November 2013 RAI from the Mechanical & Civil Engineering Branch Re. Revise STP Submittal and Request for Exemptions and License Amendment for a Risk-information Approach to Resolving Generic Safety Issues (GSI)-191 Project stage: RAI 2013-04-12
[Table View] |
Text
Risk-Informed GSI-191 Pilot Application Initial Review Insights Initial Review Insights May 23, 2013 y
Objective:
Provide high level review insights regarding the risk-informed portion of STPs pilot submittal, consistent with the intent of Regulatory Guide 1 200 with the intent of Regulatory Guide 1.200.
2
Review Area Regulatory Guidance
- 1. Risk-informed applications should include a complete list of changes made to the PRA in support of an application RG 1.174 states that data, methods, and assessment criteria used to support regulatory decisionmaking must be well support of an application, including but not limited to:
- Changes to basic event values decisionmaking must be well documented and available for public review.
- Changes to mission times
- Application-specific Human Reliability Analysis (HRA) summary summary
- Key Assumptions 3
Review Area Regulatory Guidance
- 2. Risk-informed applications should include a summary of all Facts and Observations (F&Os) identified by full or focused scope Modified PRA should meet guidance in Regulatory Guide 1.200.
identified by full or focused scope peer reviews and their resolution.
4
Review Area Regulatory Guidance
- 3. Risk-informed applications should address all hazard groups (e.g., seismic) and operational modes Regulatory Guide 1.174 states that the risk from a hazard group may be treated qualitatively if the licensee can demonstrate that the modes.
A technical justification should be provided if a particular hazard licensee can demonstrate that the risk contributions from the hazard group would not affect the decision.
group or operating mode is not germane to the application.
Regulatory Guide 1.200, Section 1.2.5 provides acceptable methods for screening seismic methods for screening seismic and other external hazards from further analysis.
5
Review Area Regulatory Guidance
- 4. Risk-informed applications LIC-101 states that NRC staff pp should clearly identify and describe all methods that have not been previously reviewed and accepted by the NRC must obtain all relevant information needed to make a regulatory decision on a license amendment request that is fully accepted by the NRC.
Documents referenced in a submittal but not previously amendment request that is fully informed, technically correct, and legally defensible.
reviewed and approved by the NRC staff should be submitted.
6
References 1.
An Approach for Using Probabilistic Risk Assessment in Risk-Informed Decisions on Plant-Specific Changes to the Licensing Basis. Regulatory Guide 1 174 Revision 2 May 2011 Guide 1.174, Revision 2. May 2011.
(ML100910006) 2.
An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk-Informed Activities Regulatory Guide 1 200 Assessment Results for Risk-Informed Activities. Regulatory Guide 1.200, Revision 2. March 2009.
(ML090410014) 3 NRR License Amendment Review Procedures LIC-101 Revision 4 May 3.
NRR License Amendment Review Procedures. LIC 101, Revision 4. May 2012.
(ML113200053) 7