Other: ML13098A396, ML13098A431, ML13098A511, ML13175A211, ML13295A222, ML13323A183, ML13323A186, ML13323A189, ML13323A190, ML13323A191, ML13338A165, NOC-AE-13003039, Corrections to Information Provided in Revised STP Pilot Submittal and Requests for Exemptions and License Amendment for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI)
|
MONTHYEARML13043A0132013-01-31031 January 2013 Pilot Submittal and Request for Exemption for a Risk-Informed Approach to Resolve Generic Safety Issue (GSI)-191 Project stage: Request ML13066A5192013-04-0101 April 2013 Supplemental Information Needed for Acceptance of Requested Licensing Action Request for Exemption for a Risk-Informed Approach to Resolve Generic Safety Issue 191 Project stage: Acceptance Review ML13098A3962013-04-0808 April 2013 Email Risk Informed GSI-191 Evaluation Project stage: Other ML13098A5112013-04-0808 April 2013 Corrosion/Head Loss Experiment Program Project stage: Other ML13098A4312013-04-0808 April 2013 Development of Chemical Effects Modules for Risk-Informed GSI-191 Resolution Project stage: Other ML13101A3142013-04-12012 April 2013 Notice of Meeting Via Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed Approach to Resolve Generic Safety Issue 191 for South Texas, Units 1 and 2 Project stage: Meeting NOC-AE-13002994, Schedule for Supplement to STP Pilot Submittal and Request for Exemption for a Risk-Informed Approach to Resolve Generic Safety Issue (GSI)-1912013-04-17017 April 2013 Schedule for Supplement to STP Pilot Submittal and Request for Exemption for a Risk-Informed Approach to Resolve Generic Safety Issue (GSI)-191 Project stage: Supplement ML13114A2552013-04-17017 April 2013 Schedule for Supplement to STP Pilot Submittal and Request for Exemption for a Risk-Informed Approach to Resolve Generic Safety Issue (GSI)-191 Project stage: Supplement ML13112A2522013-04-25025 April 2013 Approval of Extension to Submit Supplemental Information for Acceptance of Licensing Action; Request for Exemption for a Risk-Informed Approach to Resolve Generic Safety Issue 191 Project stage: Acceptance Review ML13119A0802013-04-30030 April 2013 Notice Meeting Via Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed Approach to Resolve Generic Safety Issue 191 for South Texas, Units 1 and 2 Project stage: Meeting ML13140A2562013-05-20020 May 2013 Licensee Slides for 5/23/13 Meeting - STP Pilot Submittal for Risk Informed Approach to Resolving GSI-191 Project stage: Meeting ML13140A2692013-05-20020 May 2013 NRC Slides for 5/23/13 Meeting Regarding Risk - Informed GSI-191 Pilot Application Initial Review Insights Project stage: Meeting ML13150A2162013-05-23023 May 2013 Licensee Slides for 5/23/13 Public Meeting Regarding GSI-191 Project stage: Meeting ML13161A1632013-06-14014 June 2013 5/23/13 Summary of Public Meeting Via Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed Approach to Resolve Generic Safety Issue 191 for South Texas, Units 1 and 2 Project stage: Meeting ML13175A2112013-06-19019 June 2013 Revised STP Pilot Submittal and Requests for Exemptions and License Amendment for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI)-191 Project stage: Other ML13168A1622013-06-26026 June 2013 Summary of Meeting Via Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed Approach to Resolve Generic Safety Issue 191 for South Texas, Units 1 and 2 Project stage: Meeting ML13214A0312013-08-13013 August 2013 Acceptance Review, Exemption Requests and License Amendment Request to Revise UFSAR for Resolution of Generic Safety Issue 191, Assessment of Debris Accumulation on PWR Sump Performance (TAC MF0613-MF0614; MF2400-09) Project stage: Acceptance Review ML13295A2222013-10-0303 October 2013 Corrections to Information Provided in Revised STP Pilot Submittal and Requests for Exemptions and License Amendment for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI) Project stage: Other NOC-AE-13003039, Corrections to Information Provided in Revised STP Pilot Submittal and Requests for Exemptions and License Amendment for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI)2013-10-0303 October 2013 Corrections to Information Provided in Revised STP Pilot Submittal and Requests for Exemptions and License Amendment for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI) Project stage: Other ML13323A1892013-10-22022 October 2013 Enclosure 4-2 - Risk-Informed Closure of GSI-191, Volume 2 Probabilistic Risk Analysis Project stage: Other ML13323A1912013-11-0606 November 2013 Enclosure 4-3 Risk-Informed Closure of GSI-191, Volume 3, Engineering (Casa Grande) Analysis, Page 212 of 1-122 Project stage: Other ML13323A1902013-11-0606 November 2013 Enclosure 4-3 Risk-Informed Closure of GSI-191, Volume 3, Engineering (Casa Grande) Analysis, Cover - Page 211 of 248 Project stage: Other ML13323A1862013-11-12012 November 2013 Enclosure 4-1 - Risk-Informed Closure of GSI-191, Volume 1 Project stage: Other ML13323A1832013-11-13013 November 2013 To Revised STP Pilot Submittal and Requests for Exemptions and License Amendment for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI)-191 Project stage: Other ML13323A1922013-11-13013 November 2013 Enclosure 5 - Response to NRC Supplemental Information Items Project stage: Supplement NOC-AE-13003043, Enclosure 5 - Response to NRC Supplemental Information Items2013-11-13013 November 2013 Enclosure 5 - Response to NRC Supplemental Information Items Project stage: Supplement NOC-AE-13003054, Supplement 1 to Revised STP Pilot Submittal for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI)-191 to Supersede and Replace the Revised Pilot Submittal2013-11-21021 November 2013 Supplement 1 to Revised STP Pilot Submittal for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI)-191 to Supersede and Replace the Revised Pilot Submittal Project stage: Supplement ML13338A1652013-11-21021 November 2013 To Revised STP Pilot Submittal for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI)-191 to Supersede and Replace the Revised Pilot Submittal Project stage: Other ML13330B7152013-11-26026 November 2013 RAI from the Mechanical & Civil Engineering Branch Re. Revise STP Submittal and Request for Exemptions and License Amendment for a Risk-information Approach to Resolving Generic Safety Issues (GSI)-191 Project stage: RAI 2013-04-12
[Table View] |
Text
From:
Bartlett, Matthew Sent:
Tuesday, November 26, 2013 10:54 AM awharrison@stpegs.com To:
Cc:
Sebrosky, Joseph
Subject:
RAI from the Mechanical & Civil Engineering Branch Mr. Harrison, The U.S. Nuclear Regulatory Commission (NRC) staff's Chief, Mechanical & Civil Engineering Branch (EMCB) has reviewed your application dated June 19, 2013 (Agencywide Documents Access and Management System (ADAMS), Accession No. ML13175A211) and supplements dated October 3, 2013 (ADAMS Accession No. ML13295A222) and October 31, 2013 (ADAMS Accession No. ML13323A673). Attached below is an RAI regarding your license amendment request for the GSI-191. Please provide your response to the attached RAI by January 17, 2014 in order to support the review schedule.
Thanks.
Sincerely, Matt Bartlett NRRIDORULPLIV (Rotation)
(301) 415-1577 REQUEST FOR ADDITIONAL INFORMATION (RAI)
REGARDING LICENSE AMENDMENT FOR RISK-INFORMED APPROACH TO RESOLVING GENERIC SAFETY ISSUE (GSI) 191
References:
SOUTH TEXAS NUCLEAR OPERATING COMPANY (STPNOC)
SOUTH TEXAS PROJECT (STP), UNITS 1 AND 2 DOCKET NOS. 50-498 AND 50-499 (TAC NOs MF2400 and MF2401)
- 1. Enclosure to Letter From William H. Ruland, Director, Division of Safety Systems, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, to Anthony Pietrangelo, Vice President, Regulatory Affairs, Nuclear Energy Institute, "Revised Content Guide for Generic Letter 2004-02 Supplemental Responses." November 21, 2007. (ADAMS Accession No. ML073110389)
- 2. Letter No. NOC-AE-08002372, From David W. Rencurrel, Site Vice President, South Texas Nuclear Operating Company, to U.S. Nuclear Regulatory Commission, Document Control Desk, "Supplement 4 to the Response to Generic Letter 2004-02," December 11, 2008. (Accession No. ML083520326)
- 3. Letter No. NOC-AE-13002986, From D. W. Rencurrel, Senior Vice President, Operations, South Texas Nuclear Operating Company, to U.S. Nuclear Regulatory Commission, Document Control Desk, "Revised STP Pilot Submittal and Requests for Exemptions and License Amendment for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI)-191,"June 19, 2013. (Accession No. ML13175A211)
- 4. Letter No. NOC-AE-13003043, From G. T. Powell, Site Vice President, South Texas Nuclear Operating Company, to U.S. Nuclear Regulatory Commission, Document Control Desk, "Supplement 1 to 1
Revised STP Pilot Submittal and Requests for Exemptions and License Amendment for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI)-191," November 13, 2013.
(Accession No. ML13323A183)
Mechanical and Civil Engineering Branch (EMCB)
STP-GSI-191-EMCB-RAI-1 Item 3.k of Reference 1 requested licensees to summarize the structural qualification results and design margins for various components of the sump strainer structural assembly. In Reference 2, STPNOC, the licensee, provided a qualitative response regarding the structural analysis without any supporting quantitative data. Additional information is needed regarding actual and allowable stresses and design margins for the various components of the sump strainer structural assembly to clarify the inherent level of conservatism employed in the design. This information was not STPNOC submittals (References 3 and 4).
Please summarize the structural qualification results, including the actual and allowable stresses, and design margins for the various components of the sump strainer structural assembly.