Date: May 16, 2012 PRELIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE - PNO-I-12-002 This preliminary notification constitutes EARLY notice of events of POSSIBLE safety or public interest significance. Some of the information received may not yet be fully verified or evaluated by Region I staff. Facility Licensee Emergency Classification Entergy Nuclear Operations, Inc. ___ Notification of Unusual Event Pilgrim Nuclear Power Station ___ Alert Plymouth, MA ___ Site Area Emergency Docket: 50-293 ___ General Emergency

_X_ Not Applicable

SUBJECT:

CURRENT NRC ACTIONS DURING PILGRIM NUCLEAR POWER STATION UNION CONTRACT NEGOTIATIONS

As of May 16, 2012, members of the United Workers Union of America (UWUA) Local 369 have not accepted a new contract with Entergy. UWUA Local 369 includes members of the Maintenance, Radiation Protection, Chemistry and Operations organizations. The union contract expired at midnight on May 15, 2012.

The NRC has completed an inspection of Entergy's strike contingency plans per established inspection procedures (Inspection Procedure 92709, "Licensee Strike Contingency Plans"). The purpose of the inspection was to evaluate the adequacy of Pilgrim's strike contingency plan content to assure that public health and safety and security will be maintained during any possible strike period. As of 2:00 p.m., on May 16, 2012, there has been no formal call for a strike by the union.

On May 15, 2012, at 6:00 p.m., in anticipation of a strike, NRC resident inspectors, supplemented by regional inspectors, implemented 24-hour coverage at the site. The NRC Branch Chief responsible for Pilgrim Nuclear Power Station is also onsite to assist the resident and regional inspectors, and to observe Entergy's contingency plan implementation to ensure Pilgrim Nuclear Power Station meets its regulatory requirements. Barring an extension or a new contract agreement being reached between the parties, the NRC will continue its enhanced oversight to ensure the plant continues to be operated in a safe manner.

The information presented herein has been discussed with Pilgrim Nuclear Power Station and is current as of May 16, 2012 at 2:00 p.m. The NRC has kept the Commonwealth of Massachusetts informed. Region I Public Affairs is prepared to respond to media inquiries.

ADAMS Accession Number: ML 12137A552 Contact: DRP Branch Chief, Ronald Bellamy (610) 337-5200 DISTRIBUTION: (PN Recipient List) OWFN TWFN Chairman G. Jaczko NMSS Comm. K. Svinicki OIG Comm. G. Apostolakis RES Comm. W. Magwood Comm. W. Ostendorff OIP OCA OGC OPA EDO OE NRR SECY IRO ACRS NSIR NRO PDR RSLO Regional Offices

By Fax: DOT:Trans INPO NSAC RI Resident Office Licensee: Entergy Nuclear Operations, Inc.

DOCUMENT NAME: G:\DRP\BRANCH5\2-PG\2012 Strike Preparations\2012 Pilgrim Union Negotiations PN.docx After declaring this document "An Official Agency Record" it will be released to the Public.

To receive a copy of this document, indicate in the box:

" C" = Copy without attachment/enclosure " E" = Copy with attachment/enclosure " N" = No copy ADAMS Accession Number: ML12137A552 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP RI/PAO RI/SLO RI/DRP NAME TSetzer RBellamy DScrenci/TSC for NMcNamara/TSC for DRoberts DATE 05/16/12 05/16/12 05/16/12 05/12/12 05/16/12 OFFICE RI/ORA NAME DLew DATE 05/16/12 OFFICIAL RECORD COPY