ML12128A104
| ML12128A104 | |
| Person / Time | |
|---|---|
| Site: | Diablo Canyon (DPR-080, DPR-082) |
| Issue date: | 05/04/2012 |
| From: | Collins E Region 4 Administrator |
| To: | Halpin E Pacific Gas & Electric Co |
| References | |
| EA-12-075 IR-12-002 | |
| Download: ML12128A104 (30) | |
See also: IR 05000275/2012002
Text
May 4, 2012
EA 12-075
Mr. Edward D. Halpin
Senior Vice President and
Chief Nuclear Officer
Pacific Gas and Electric Company
Diablo Canyon Power Plant
P.O. Box 56, Mail Code 104/6
Avila Beach, CA 93424
Subject:
DIABLO CANYON POWER PLANT - NRC INTEGRATED INSPECTION
REPORT 05000275/2012002 AND 05000323/2012002 and NOTICE OF
VIOLATION
Dear Mr. Halpin:
On March 23, 2012, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection
at your Diablo Canyon Power Plant Units 1 and 2. The enclosed inspection report documents
the inspection findings, which were discussed on March 27, 2012, with Mr. James Becker, Site
Vice President, and other members of your staff.
The inspections examined activities conducted under your license as they relate to safety and
compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed
personnel.
In a conversation on April 26, 2012, Neil OKeefe of my staff informed you that the NRC was
considering escalated enforcement for an apparent violation involving the failure to provide
complete and accurate information to the NRC regarding control room habitability test results
conducted in 2005. Mr. OKeefe also informed you that we had sufficient information regarding
the apparent violation and your corrective actions to make an enforcement decision without the
need for a pre-decisional enforcement conference or a written response from you. You
indicated that Pacific Gas and Electric did not believe that a pre-decisional enforcement
conference or written response was needed.
Based on the information developed during the inspection, the NRC has determined that a
violation of NRC requirements occurred. The violation is cited in the enclosed Notice of
Violation (Notice) and the circumstances surrounding it are described in detail in the subject
inspection report.
The violation occurred on April 22, 2005, when Pacific Gas and Electric reported to the NRC
that control room habitability testing required by Generic Letter 2003-01, Control Room
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION IV
1600 EAST LAMAR BLVD
ARLINGTON, TEXAS 76011-4511
E. Halpin
- 2 -
Habitability, had confirmed that the main control room envelope did not have any unfiltered in-
leakage when performed in the most limiting configuration for operator dose (Pacific Gas and
Electric Letter DCL-05-042, April 22, 2005, Control Room Envelope In-Leakage Test Results
Relative to Generic Letter 2003-01, Control Room Habitability, ADAMS ML051260225). During
this inspection, inspectors identified that three of the four tests performed in January 2005 had
measured unfiltered control room in-leakage that were greater than both the values assumed in
the design basis and the values reported to the NRC in response to Generic Letter 2003-01,
and that the testing had not been performed in the most limiting configuration for operator dose.
On December 2, 2011, Pacific Gas and Electric issued a letter (ML113390057) to report that
incorrect information had been reported in their 2005 response to Generic Letter 2003-01. The
letter also provided the correct 2005 test results. The letter stated that a leakage path was
identified and corrected after the first three tests, and the fourth test (negative in-leakage) was
representative of the control room envelope. The licensee determined that human error (a
mindset that a pressurized control room should have zero in-leakage) affected the interpretation
of test results and led to the non-conservative determination of zero in-leakage in 2005. During
the period of the violation, both units spent time in operating and shutdown modes. The
licensee made an 8-hour notification on September 12, 2011, when the error was identified and
the control room was declared inoperable, and submitted a licensee event report and
supplement on November 14, 2011 and January 30, 2012, respectively.
The safety significance of this failure to provide complete and accurate information was very low
because the licensee was able to verify that emergency core cooling system leakage outside
containment was maintained sufficiently low so that control room operator dose would not have
exceeded 5 rem. This violation impacted the NRCs ability to perform its regulatory function
because the NRC relies on its licensees to provide complete and accurate information. The
staff has concluded that the NRC would have taken a different regulatory position or undertaken
substantial further inquiry had the correct test results been reported. Therefore, this violation
has been categorized in accordance with the NRC Enforcement Policy at Severity Level III.
In accordance with the NRCs Enforcement Policy, a base civil penalty of $70,000 is considered
for a Severity Level III violation. Because your facility has not been the subject of escalated
enforcement actions within the last 2 years, the NRC considered whether credit was warranted
for Corrective Action in accordance with the civil penalty assessment process in Section 2.3.4 of
the Enforcement Policy. Credit was given for the Corrective Action factor because you promptly
reported the erroneous report when you became aware of the problem and provided the correct
test results. You also implemented prompt compensatory measures and performed new tests.
Based on the civil penalty assessment process discussed above, the NRC will not propose a
civil penalty in this case. Additionally, it is recognized that this violation occurred more than 5
years ago, so it was beyond the normal statute of limitations.
You are required to respond to this letter and should follow the instructions specified in the
enclosed Notice when preparing your response. If you have additional information that you
believe the NRC should consider, you may provide it in your response to the Notice. The NRC
review of your response to the Notice will also determine whether further enforcement action is
necessary to ensure compliance with regulatory requirements.
Additionally, one NRC identified finding of very low safety significance (Green) was identified
during this inspection. This finding was determined to involve a violation of NRC requirements.
The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of
the Enforcement Policy.
E. Halpin
- 3 -
If you contest the non-cited violation, you should provide a response within 30 days of the date
of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory
Commission, ATTN: Document Control Desk, Washington, D.C. 20555-0001, with copies to the
Regional Administrator, Region IV; Director, Office of Enforcement, U.S. Nuclear Regulatory
Commission, Washington, D.C. 20555-0001; and the NRC Resident Inspector at the Diablo
Canyon Power Plant.
If you disagree with a cross-cutting aspect assigned in this report, you should provide a
response within 30 days of the date of this inspection report, with the basis for your
disagreement, to the Regional Administrator, Region IV, and the NRC Resident Inspector at the
Diablo Canyon Power Plant.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its
enclosure((s), and your response will be made available electronically for public inspection in
the NRC Public Document Room or from the NRCs document system (ADAMS), accessible
from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. To the extent possible,
your response should not include any personal privacy, proprietary, or safeguards information
so that it can be made available to the Public without redaction. If personal privacy or
proprietary information is necessary to provide an acceptable response, please provide a
bracketed copy of your response that identifies the information that should be protected and a
redacted copy of your response that deletes such information. If you request withholding of
such information, you must specifically identify the portions of your response that you seek to
have withheld and provide in detail the bases for your claim of withholding (e.g., explain why the
disclosure of information will create an unwarranted invasion of personal privacy or provide the
information required by 10 CFR 2.390(b) to support a request for withholding confidential
commercial or financial information). The NRC also includes significant enforcement actions on
its Web site at (http://www.nrc.gov/reading-rm/doc-collections/enforcement/actions/).
Sincerely,
/RA KKennedy for/
Elmo E. Collins
Regional Administrator
Docket Nos.: 050000275, 050000323
Enclosures: (1) Notice of Violation
(2) Inspection Report 05000275/2012002 and 05000323/2012002
w/Attachment: Supplemental Information
E. Halpin
- 4 -
cc w/Enclosure: Electronic Distribution
Regional Administrator (Elmo.Collins@nrc.gov)
Deputy Regional Administrator (Art.Howell@nrc.gov)
DRP Director (Kriss.Kennedy@nrc.gov)
DRP Deputy Director (Troy.Pruett@nrc.gov)
Acting DRS Director (Tom.Blount@nrc.gov)
Acting DRS Deputy Director (Patrick.Louden@nrc.gov)
Senior Resident Inspector (Michael.Peck@nrc.gov)
Resident Inspector (Laura.Micewski@nrc.gov)
Branch Chief, DRP/B (Neil.OKeefe@nrc.gov)
Senior Project Engineer, DRP/B (Leonard.Willoughby@nrc.gov)
Project Engineer, DRP/B (Nestor.Makris@nrc.gov)
DC Administrative Assistant (Agnes.Chan@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Project Manager (Alan.Wang@nrc.gov)
Acting Branch Chief, DRS/TSB (Ryan.Alexander@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
OEMail Resource
ROPreports
W. A. Maier, RSLO (Bill.Maier@nrc.gov)
R. E. Kahler, NSIR (Robert.Kahler@nrc.gov)
RIV/ETA: OEDO (Michael.McCoppin@nrc.gov)
DRS/TSB STA (Dale.Powers@nrc.gov)
File located: R:\\_REACTORS\\_DC\\2012\\DC2012-02RP-msp.docx
SUNSI Rev Compl.
Yes No
Yes No
Reviewer Initials
Publicly Avail
Yes No
Sensitive
Yes No
Sens. Type Initials
RIV:RI:DRP/B
SRI:DRP/B
DRP/B
C:/DRS/PSB2
C:/DRS/EB1
LHMicewski
MSPeck
LWilloughby
GEWerner
TRFarnholtz
/RA via E/
/RA via E/
/RA/
/LRicketson for/
/RA/
5/2/12
5/2/12
5/2/12
5/2/12
5/2/12
C:/DRS/EB2
C:/DRS/PSB1
C:/DRS/OB
C:/DRS/TSB
C:/DRP/B
GMiller
MHay
MHaire
RAlexander
NFOKeefe
/RA/
/RA/
/RA via T/
/RA/
/RA/
5/2/12
5/2/12
5/2/12
5/2/12
5/3/12
C:/ORA/ACES
RC:ORA
D:/DRP
RKeller
KFuller
KMKennedy
/RA/
/RA/
/RA/
5/3/12
5/3/12
5/4/12
OFFICIAL RECORD COPY
T=Telephone E=E-mail F=Fax
- 1 -
Enclosure 1
Pacific Gas and Electric Company
Docket Nos. 050-275, 050-323
Diablo Canyon Power Plant
During an NRC inspection conducted between January 1, 2012 and March 23, 2012 a violation
of NRC requirements was identified. In accordance with the NRC Enforcement Policy, the
violation is listed below:
Title 10 CFR 50.9(a), Completeness and Accuracy of Information, requires, in part, that
information provided to the Commission by a licensee shall be complete and accurate in
all material respects.
Contrary to the above, on April 22, 2005, the licensee provided information to the
Commission that was not complete and accurate in all material respects. Specifically,
on April 22, 2005, the licensee stated to the NRC in their response to Generic Letter 2003-01 that: (1) test results confirmed that no unfiltered control room in-leakage
existed; and (2) tracer gas in-leakage testing was performed in the alignment that results
in the greatest consequence to the control room operator. However, the test results
from licensee Procedure PMT 23.39 PMT to Document Control Room Ventilation Test
to Satisfy Generic Letter 2003-01, conducted prior to the licensee response to Generic
Letter 2003-01, clearly indicated that the test identified unfiltered in-leakage greater than
the value assumed in design basis radiological analyses, and the in-leakage test was not
performed in the system alignment that resulted in the greatest consequence to the
control room operator. This was material because the staff would not have closed the
Generic Letter 2003-01 had the correct test results been reported.
This is a Severity Level III violation (Section 6.9).
Pursuant to the provisions of 10 CFR 2.201, Pacific Gas and Electric Company is hereby
required to submit a written statement or explanation to the U.S. Nuclear Regulatory
Commission, ATTN: Document Control Desk, Washington, DC 20555-0001 with a copy to the
Regional Administrator, Region IV, and a copy to the NRC Resident Inspector at the Diablo
Canyon Power Plant, within 30 days of the date of the letter transmitting this Notice of Violation.
This reply should be clearly marked as a "Reply to a Notice of Violation; EA-12-075" and should
include: (1) the corrective steps that have been taken and the results achieved, (2) the
corrective steps that will be taken, and (3) the results of your assessment of the cause of the
violation. Your response may reference or include previous docketed correspondence, if the
correspondence adequately addresses the required response. If an adequate reply is not
received within the time specified in this Notice, an order or a Demand for Information may be
issued as to why the license should not be modified, suspended, or revoked, or why such other
action as may be proper should not be taken. Where good cause is shown, consideration will
be given to extending the response time.
If you contest this enforcement action, you should also provide a copy of your response, with
the basis for your denial, to the Director, Office of Enforcement, United States Nuclear
Regulatory Commission, Washington, DC 20555-0001.
- 2 -
Enclosure 1
Because your response will be made available electronically for public inspection in the NRC
Public Document Room or from the NRCs document system (ADAMS), accessible from the
NRC Web site at http://www.nrc.gov/reading-rm/adams.html, to the extent possible, it should not
include any personal privacy, proprietary, or safeguards information so that it can be made
available to the public without redaction. If personal privacy or proprietary information is
necessary to provide an acceptable response, then please provide a bracketed copy of your
response that identifies the information that should be protected and a redacted copy of your
response that deletes such information. If you request withholding of such material, you must
specifically identify the portions of your response that you seek to have withheld and provide in
detail the bases for your claim of withholding (e.g., explain why the disclosure of information will
create an unwarranted invasion of personal privacy or provide information, required by 10
CFR 2.390(b), that supports a request to withhold confidential commercial or financial
information. If safeguards information is necessary to provide an acceptable response, please
provide the level of protection described in 10 CFR 73.21.
Dated this 4th day of May 2012
- 1 -
Enclosure 2
U.S. NUCLEAR REGULATORY COMMISSION
REGION IV
Docket:
05000275, 05000323
License:
Report:
Licensee:
Pacific Gas and Electric Company
Facility:
Diablo Canyon Power Plant, Units 1 and 2
Location:
7 1/2 miles NW of Avila Beach
Avila Beach, California
Dates:
January 1 through March 23, 2012
Inspectors:
M. Peck, Senior Resident Inspector
L. Micewski, Resident Inspector
L. Willoughby, Senior Project Engineer
N. Makris, Project Engineer
Approved By:
N. OKeefe, Chief, Project Branch B
Division of Reactor Projects
- 2 -
Enclosure 2
SUMMARY OF FINDINGS
IR 05000275/2012002, 05000323/2012002; 1/1/2012 - 3/23/2012; Diablo Canyon Power Plant,
Integrated Resident and Regional Report; Surveillance Testing; Other Activities
The report covered a 3-month period of inspection by resident inspectors. One Green non-cited
violation and one Severity Level III violation were identified. The significance of most findings is
indicated by their color (Green, White, Yellow, or Red) using Inspection Manual Chapter 0609,
Significance Determination Process. The cross-cutting aspect is determined using Inspection
Manual Chapter 0310, Components Within the Cross Cutting Areas. Findings for which the
significance determination process does not apply may be Green or be assigned a severity level
after NRC management review. The NRC's program for overseeing the safe operation of
commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process,
Revision 4, dated December 2006.
A.
NRC-Identified Findings and Self-Revealing Findings
Cornerstone: Mitigating Systems
Green. The inspectors identified a non-cited violation of 10 CFR, Part 50,
Appendix B, Criterion V, Instructions, Procedures, and Drawings, after operations
personnel declared diesel generator 2-3 operable after failing to meet all surveillance
test acceptance criterion. On December 22, 2011, diesel generator 2-3 did not meet
frequency acceptance criteria during technical specification surveillance testing.
Plant operators declared the diesel operable after applying an engineering
evaluation. The inspectors identified that the evaluation was not appropriate to the
conditions of the failed test. The licensees corrective actions included corrective
maintenance, re-performance of the surveillance test, and entering the condition into
the corrective action program as Notifications 50449027 and 50449504.
The failure of operations personnel to recognize that diesel generator surveillance
results indicated that the system was not fully operable was a performance
deficiency. This finding was more than minor because the licensees engineering
evaluation created a reasonable doubt that the system was operable, similar to
Example 3.k in Inspection Manual Chapter 0612, Appendix E, Examples of Minor
Issues. The inspectors concluded that the finding was of very low safety
significance (Green) because the finding was not a design or qualification deficiency,
did not result in the loss of operability or functionality of a single train for greater than
the technical specification outage time, did not represent an actual loss of safety
function, and was not potentially risk significant due to a seismic, flooding, or severe
weather event. The most significant contributor to this performance deficiency was
that operators did not review and understand the diesel generator surveillance
results sufficiently to recognize that the condition did not match the previously-
evaluated condition that was used to conclude the diesel generator remained
operable. Therefore, this finding had a cross-cutting aspect in the area of problem
identification and resolution, associated with the corrective action program
component P.1(c) (Section 1R22).
- 3 -
Enclosure 2
Cornerstone: Barrier Integrity
SL-III. The inspectors identified a Green finding and Severity Level III violation of
10 CFR 50.9, Completeness and Accuracy of Information, after Pacific Gas and
Electric failed to submitted complete and accurate information in response to Generic
Letter 2003-01, Control Room Habitability. Generic Letter 2003-01 requested that
the licensee submit information demonstrating that the control room habitability
system was in compliance with the current licensing and design bases. The licensee
was specifically requested to verify that the most limiting unfiltered in-leakage into
the control room envelope was no more than the value assumed in the design basis
radiological analyses for control room habitability. On April 22, 2005, the licensee
reported to the NRC that testing performed in the most limiting configuration for
operator dose demonstrated that there was no unfiltered in-leakage into the control
room envelope. This was material because the NRC used this information to close
out Generic Letter 2003-01. In September 2011, the inspectors identified that the
control room test results were greater than the value assumed in the design basis
radiological analysis and that the licensees testing was not performed in the most
limiting configuration for operator dose. Using the actual control room in-leakage
rates, the inspectors concluded that the resultant operator dose could have
exceeded the limit established by current licensing and design bases during an
accident.
The inspectors concluded that the failure of Pacific Gas and Electric to provide
complete and accurate information in response to Generic Letter 2003-01 was a
performance deficiency. The finding was more than minor because the information
was material to the NRCs decision making processes. The inspectors screened the
issue through the Reactor Oversight Process because the finding included a
performance deficiency that was reasonably within the licensees ability to control.
The inspectors concluded that the finding was of very low safety significance (Green)
because only the radiological barrier function of the control room was affected. The
inspectors also screened the issue through the traditional enforcement process
because the violation impacted the regulatory process. The inspectors concluded
that the violation was a Severity Level III because had the licensee provided
complete and accurate information in their letter dated April 22, 2005, the NRC would
have likely reconsidered a regulatory position or undertaken a substantial further
inquiry. The inspectors did not identify a cross-cutting aspect because the
performance deficiency was not reflective of present performance (Section 40A5).
B.
Licensee-Identified Violations
None
- 4 -
Enclosure 2
REPORT DETAILS
Summary of Plant Status
Pacific Gas and Electric Company (PG&E) was operating both units at full power at the
beginning of the inspection period. On February 13, 2012, plant operators reduced Unit 2 to
50 percent power following ocean debris fouling of the condenser cooling system. On
February 17, 2012, the licensee cleared the debris and returned the unit to full power. Both
units operated at full power for the remainder of the inspection period.
1.
REACTOR SAFETY
Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, and Emergency
Preparedness
1R04 Equipment Alignments (71111.04)
.1
Partial Walkdown
a.
The inspectors performed partial system walkdowns of the following risk-significant
systems:
Inspection Scope
Unit 1, Emergency diesel generator train 1-2, January 4, 2012
Unit 2, Residual heat removal pump train 2-2, January 10, 2012
Unit 2, Centrifugal charging pump train 2-2, January 17, 2012
Unit 1, Component cooling water train 1-1, February 29, 2012
The inspectors selected these systems based on their risk significance relative to the
reactor safety cornerstones at the time they were inspected. The inspectors attempted
to identify any discrepancies that could affect the function of the system, and, therefore,
potentially increase risk. The inspectors reviewed applicable operating procedures,
system diagrams, Final Safety Analysis Report Update (FSARU), technical specification
requirements, administrative technical specifications, outstanding work orders, condition
reports, and the impact of ongoing work activities on redundant trains of equipment in
order to identify conditions that could have rendered the systems incapable of
performing their intended functions. The inspectors also inspected accessible portions
of the systems to verify system components and support equipment were aligned
correctly and operable. The inspectors examined the material condition of the
components and observed operating parameters of equipment to verify that there were
no obvious deficiencies. The inspectors also verified that the licensee had properly
identified and resolved equipment alignment problems that could cause initiating events
or impact the capability of mitigating systems or barriers and entered them into the
corrective action program with the appropriate significance characterization.
These activities constitute completion of four partial system walkdown samples as
defined in Inspection Procedure 71111.04-05.
b.
No findings were identified.
Findings
- 5 -
Enclosure 2
.2
Complete Walkdown
a.
On March 22, 2012, the inspectors performed a complete system alignment inspection
of the Unit 1 auxiliary feedwater system to verify the functional capability of the system.
The inspectors selected this system because it was considered both safety significant
and risk significant in the licensees probabilistic risk assessment. The inspectors
inspected the system mechanical and electrical equipment line ups, electrical power
availability, system pressure and temperature indications, as appropriate, component
labeling, component lubrication, component and equipment cooling, hangers and
supports, operability of support systems, and to ensure that ancillary equipment or
debris did not interfere with equipment operation. The inspectors reviewed a sample of
past and outstanding work orders to determine whether any deficiencies significantly
affected the system function. In addition, the inspectors reviewed the corrective action
program database to ensure that system equipment alignment problems were being
identified and appropriately resolved. Specific documents reviewed during this
inspection are listed in the attachment.
Inspection Scope
These activities constitute completion of one complete system walkdown sample as
defined in Inspection Procedure 71111.04-05.
b.
No findings were identified.
Findings
1R05 Fire Protection (71111.05)
Quarterly Fire Inspection Tours
a.
The inspectors conducted fire protection walkdowns that were focused on availability,
accessibility, and the condition of firefighting equipment in the following risk-significant
plant areas:
Inspection Scope
January 12, 2012, Unit 1, Fire Area FB-1, spent fuel handing floor
January 31, 2012, Unit 2, Fire Zone 19-E, component cooling water heat
exchanger room
February 1, 2012, Unit 1, Fire Zones 11-A-1, 11-B-1 and 11-C-1, emergency
diesel generator rooms 1-1, 1-2, and 1-3
February 1, 2012, Unit 1, Fire Zones 11-A-2, 11-B-2, and 11-C-2, emergency
diesel generator radiator rooms
February 7, 2012, Units 1 and 2, Fire Zones 8-B-4, and 8-B-3, control room
ventilation equipment rooms
- 6 -
Enclosure 2
The inspectors reviewed areas to assess if licensee personnel had implemented a fire
protection program that adequately controlled combustibles and ignition sources within
the plant; effectively maintained fire detection and suppression capability; maintained
passive fire protection features in good material condition; and had implemented
adequate compensatory measures for out of service, degraded or inoperable fire
protection equipment, systems, or features, in accordance with the licensees fire plan.
The inspectors selected fire areas based on their overall contribution to internal fire risk
as documented in the plants Individual Plant Examination of External Events with later
additional insights, their potential to affect equipment that could initiate or mitigate a
plant transient, or their impact on the plants ability to respond to a security event. Using
the documents listed in the attachment, the inspectors verified that fire hoses and
extinguishers were in their designated locations and available for immediate use; that
fire detectors and sprinklers were unobstructed; that transient material loading was
within the analyzed limits; and fire doors, dampers, and penetration seals appeared to
be in satisfactory condition. The inspectors also verified that minor issues identified
during the inspection were entered into the licensees corrective action program.
Specific documents reviewed during this inspection are listed in the attachment.
These activities constitute completion of five quarterly fire-protection inspection samples
as defined in Inspection Procedure 71111.05-05.
b.
No findings were identified.
Findings
1R06 Flood Protection Measures (71111.06)
a.
The inspectors reviewed the FSARU, the flooding analysis, and plant procedures to
assess susceptibilities involving internal flooding; reviewed the corrective action program
to determine if licensee personnel identified and corrected flooding problems; inspected
underground bunkers/manholes to verify the adequacy of sump pumps, level alarm
circuits, cable splices subject to submergence, and drainage for bunkers/manholes; and
verified that operator actions for coping with flooding can reasonably achieve the desired
outcomes. The inspectors also inspected the areas listed below to verify the adequacy
of equipment seals located below the flood line, floor and wall penetration seals,
watertight door seals, common drain lines and sumps, sump pumps, level alarms, and
control circuits, and temporary or removable flood barriers. Specific documents
reviewed during this inspection are listed in the attachment.
Inspection Scope
February 1, 2012, Unit 1, residual heat removal pumps rooms
These activities constitute completion of one flood protection measures inspection
sample as defined in Inspection Procedure 71111.06-05.
b.
No findings were identified.
Findings
- 7 -
Enclosure 2
1R11 Licensed Operator Requalification Program and Licensed Operator Performance
(71111.11)
.1
a.
Quarterly Review of Licensed Operator Requalification Program
On January 17, 2012, the inspectors observed a crew of licensed operators in the plants
simulator to verify that operator performance was adequate, evaluators were identifying
and documenting crew performance problems and training was being conducted in
accordance with licensee procedures. The inspectors assessed the following areas:
Inspection Scope
Licensed operator performance
The ability of the licensee to administer the evaluations and the quality of the
training provided
The modeling and performance of the control room simulator
The quality of post-scenario critiques
Follow-up actions taken by the licensee for identified discrepancies
These activities constitute completion of one quarterly licensed operator requalification
program sample as defined in Inspection Procedure 71111.11.
b.
No findings were identified.
Findings
.2
Quarterly Observation of Licensed Operator Performance
a.
On March 8, 2012, the inspectors observed the performance of on-shift licensed
operators in the plants main control room. At the time of the observations, the plant was
in a period of heightened activity due to diesel generator testing, reactivity
manipulations, and operability issues associated with defective Rosemont transmitters.
Inspection Scope
In addition, the inspectors assessed the operators adherence to plant procedures,
including Procedure OP1.DC10, Conduct of Operations, and other operations
department policies.
These activities constitute completion of one quarterly licensed-operator performance
sample as defined in Inspection Procedure 71111.11.
b.
No findings were identified.
Findings
- 8 -
Enclosure 2
1R12 Maintenance Effectiveness (71111.12)
a.
The inspectors evaluated degraded performance issues involving the following risk
significant systems:
Inspection Scope
Containment isolation valves, Notification 64054266
230kV preferred offsite power maintenance, Notification 50286581
The inspectors reviewed events such as where ineffective equipment maintenance has
resulted in valid or invalid automatic actuations of engineered safeguards systems and
independently verified the licensee's actions to address system performance or condition
problems in terms of the following:
Implementing appropriate work practices
Identifying and addressing common cause failures
Scoping of systems in accordance with 10 CFR 50.65(b)
Characterizing system reliability issues for performance monitoring
Charging unavailability for performance monitoring
Trending key parameters for condition monitoring
Ensuring proper classification in accordance with 10 CFR 50.65(a)(1) or -(a)(2)
Verifying appropriate performance criteria for structures, systems, and
components classified as having an adequate demonstration of performance
through preventive maintenance, as described in 10 CFR 50.65(a)(2), or as
requiring the establishment of appropriate and adequate goals and corrective
actions for systems classified as not having adequate performance, as described
in 10 CFR 50.65(a)(1)
The inspectors assessed performance issues with respect to the reliability, availability,
and condition monitoring of the system. In addition, the inspectors verified maintenance
effectiveness issues were entered into the corrective action program with the appropriate
significance characterization. Specific documents reviewed during this inspection are
listed in the attachment.
These activities constitute completion of two quarterly maintenance effectiveness
sample as defined in Inspection Procedure 71111.12-05.
b.
No findings were identified.
Findings
- 9 -
Enclosure 2
1R13 Maintenance Risk Assessments and Emergent Work Control (71111.13)
a.
The inspectors reviewed licensee personnel's evaluation and management of plant risk
for the maintenance and emergent work activities affecting risk-significant and safety-
related equipment listed below to verify that the appropriate risk assessments were
performed prior to removing equipment for work:
Inspection Scope
Unit 2, planned maintenance and testing of the vital batteries, January 23, 2012
Units 1 and 2, removal of Morro Bay 230 kV Bus E from service for maintenance,
January 26 and 27, 2012
Unit 2, planned maintenance of emergency diesel generator 2-3 and condensate
booster pump 2-1, February 22, 2012
Unit 1, unplanned maintenance work window extension for emergency diesel
generator 1-3, February 27, 2012
Unit 2, residual heat removal train 2-2 maintenance work window,
February 28, 2012
The inspectors selected these activities based on potential risk significance relative to
the reactor safety cornerstones. As applicable for each activity, the inspectors verified
that licensee personnel performed risk assessments as required by 10 CFR 50.65(a)(4)
and that the assessments were accurate and complete. When licensee personnel
performed emergent work, the inspectors verified that the licensee personnel promptly
assessed and managed plant risk. The inspectors reviewed the scope of maintenance
work, discussed the results of the assessment with the licensee's probabilistic risk
analyst or shift technical advisor, and verified plant conditions were consistent with the
risk assessment. The inspectors also reviewed the technical specification requirements
and inspected portions of redundant safety systems, when applicable, to verify risk
analysis assumptions were valid and applicable requirements were met. Specific
documents reviewed during this inspection are listed in the attachment.
These activities constitute completion of five maintenance risk assessments and
emergent work control inspection samples as defined in Inspection
Procedure 71111.13-05.
b.
No findings were identified.
Findings
1R15 Operability Evaluations (71111.15)
a.
The inspectors reviewed the following issues:
Inspection Scope
- 10 -
Enclosure 2
Unit 1, systems and process notification (SAPN) 50450980, January 8, 2012,
high vibration on containment fan cooler 1-4
Unit 2, SAPN 50454298, January 26, 2012, failure of the control rod position
switch
Units 1 and 2, SAPN 50455814, February 6, 2012, degraded control room
habitability system
Units 1 and 2, SAPN 50461051, weld cracks in emergency diesel generator
turbocharger supports, February 27, 2012
The inspectors selected these potential operability issues based on the risk significance
of the associated components and systems. The inspectors evaluated the technical
adequacy of the evaluations to ensure that technical specification operability was
properly justified and the subject component or system remained available such that no
unrecognized increase in risk occurred. The inspectors compared the operability and
design criteria in the appropriate sections of the technical specifications and FSARU to
the licensee personnels evaluations to determine whether the components or systems
were operable. Where compensatory measures were required to maintain operability,
the inspectors determined whether the measures in place would function as intended
and were properly controlled. The inspectors determined, where appropriate,
compliance with bounding limitations associated with the evaluations. Additionally, the
inspectors also reviewed a sampling of corrective action documents to verify that the
licensee was identifying and correcting any deficiencies associated with operability
evaluations. Specific documents reviewed during this inspection are listed in the
attachment.
These activities constitute completion of four operability evaluations inspection samples
as defined in Inspection Procedure 71111.15-05.
b.
No findings were identified.
Findings
1R19 Post-maintenance Testing (71111.19)
a.
The inspectors reviewed the following post-maintenance activities to verify that
procedures and test activities were adequate to ensure system operability and functional
capability:
Inspection Scope
Unit 2, work order 64071682-0100, preventive maintenance of residual heat
removal pump 2-1, January 11, 2012
Unit 2, work orders 64050461 and 64024569, preventive and corrective
maintenance of vital battery charger 2-3-2, January 25, 2012
Unit 2, work order 64031217-5000, preventive and corrective maintenance of
emergency diesel generator 2-2, January 30, 2012
- 11 -
Enclosure 2
Unit 2, work order 640438384, kV vital bus H undervoltage relay preventive
maintenance and calibration, January 30, 2012
The inspectors selected these activities based upon the structure, system, or
component's ability to affect risk. The inspectors evaluated these activities for the
following (as applicable):
The effect of testing on the plant had been adequately addressed; testing was
adequate for the maintenance performed
Acceptance criteria were clear and demonstrated operational readiness; test
instrumentation was appropriate
The inspectors evaluated the activities against the technical specifications, the FSARU,
10 CFR Part 50 requirements, licensee procedures, and various NRC generic
communications to ensure that the test results adequately ensured that the equipment
met the licensing basis and design requirements. In addition, the inspectors reviewed
corrective action documents associated with post-maintenance tests to determine
whether the licensee was identifying problems and entering them in the corrective action
program and that the problems were being corrected commensurate with their
importance to safety. Specific documents reviewed during this inspection are listed in
the attachment.
These activities constitute completion of four post-maintenance testing inspection
samples as defined in Inspection Procedure 71111.19-05.
b.
No findings were identified.
Findings
1R22 Surveillance Testing (71111.22)
a.
Inspection Scope
The inspectors reviewed the FSARU, procedure requirements, and technical
specifications to ensure that the surveillance activities listed below demonstrated that the
systems, structures, and/or components tested were capable of performing their
intended safety functions. The inspectors either witnessed or reviewed test data to
verify that the significant surveillance test attributes were adequate to address the
following:
Preconditioning
Evaluation of testing impact on the plant
Acceptance criteria
Test equipment
Procedures
- 12 -
Enclosure 2
Jumper/lifted lead controls
Test data
Testing frequency and method demonstrated technical specification operability
Test equipment removal
Restoration of plant systems
Fulfillment of ASME Code requirements
Updating of performance indicator data
Engineering evaluations, root causes, and bases for returning tested systems,
structures, and components not meeting the test acceptance criteria were correct
Reference setting data
Annunciators and alarms setpoints
The inspectors also verified that licensee personnel identified and implemented any
needed corrective actions associated with the surveillance testing.
Unit 2, routine surveillance test of centrifugal charging pump 2-1,
January 17, 2012
Unit 2, inservice test of turbine driven auxiliary feedwater pump 2-1,
January 26, 2012
Units 1 and 2, reactor coolant leakage surveillance test, January 26, 2012
Unit 2, in-service testing surveillance of containment isolation valve FCV-698,
January 27, 2012
Unit 1, routine surveillance test of 4kv vital bus F undervoltage relay calibration,
February 22, 2012
Specific documents reviewed during this inspection are listed in the attachment.
These activities constitute completion of five surveillance testing inspection samples as
defined in Inspection Procedure 71111.22-05.
b.
Findings
Inadequate Operability Evaluation
Introduction. The inspectors identified a green noncited violation of 10 CFR, Part 50,
Appendix B, Criterion V, Instructions, Procedures, and Drawings, when operations
- 13 -
Enclosure 2
personnel declared diesel generator 2-3 operable after failing to meet all surveillance
test acceptance criterion.
Description. On December 22, 2011, plant operators completed diesel generator 2-3
technical specification surveillance testing using Procedure STP M-9A, Diesel Engine
Generator Routine Surveillance Test, Revision 90. Plant operators concluded that the
test acceptance criterion were met and declared the diesel generator operable.
Procedure ST M-9A, Step 12.3.9, required the operator to verify that the generator
frequency stabilized between 59.5 and 60.5 cycles per second within 13 seconds
following a start signal. During the test the frequency stabilized above this range at
60.6 cycles per second. Procedure STP M-9A, Step 6.1, Acceptance Criteria, required
that the test frequency be within the acceptance range before the diesel generator could
be considered operable. Also, Administrative Procedure AD13.ID1, Conduct of Plant
and Equipment Tests, Revision 12, Section 5.7, Test Review, required the licensee to
first revise the surveillance test acceptance criteria prior to accepting test results outside
of the existing acceptance range.
The inspectors concluded that the most significant contributor to the finding was a less
than adequate operability evaluation. Plant operators concluded the diesel generator
was operable based on an engineering evaluation described in Action Request 056731.
This evaluation stated that the diesel generator could be considered operable if the
frequency failed to stabilize within 13 seconds provided that the generator voltage had
stabilized within 13 seconds. On December 23, 2011, the inspectors identified that this
engineering evaluation was not applicable to the failed surveillance test because the
evaluation did not address frequency stabilization outside of the acceptance range.
Following discussions with the inspectors, the licensee declared diesel generator 2-3
inoperable and performed maintenance on the motor operated potentiometer controlling
generator frequency. Plant operators subsequently re-performed the surveillance test
and all acceptance criteria were met. The licensee entered the condition into the
corrective action program as Notifications 50449027 and 50449504.
Analysis. The failure of operations personnel to recognize that diesel generator
surveillance results indicated that the system was not fully operable was a performance
deficiency. The performance deficiency was similar to the more than minor example 3.k
in Inspection Manual Chapter 0612, Appendix E, Examples of Minor Issues, because
the inadequate evaluation resulted in a reasonable doubt of diesel generator operability.
The inspectors concluded that the finding affected the mitigating systems cornerstone
because the performance deficiency was related to diesel generator availability. The
inspectors used Inspection Manual Chapter 609, Attachment 4, Phase 1 - Initial
Screening and Characterization of Findings, to analyze the significance of the finding.
The inspectors concluded that the finding was of very low safety significance (Green)
because the finding was not a design or qualification deficiency, did not result in the loss
of operability or functionality of a single train for greater than the Technical Specification
outage time, did not represent an actual loss of safety function for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />,
and was not potentially risk significant due to a seismic, flooding, or severe weather
initiating event. The most significant contributor to this performance deficiency was that
operators did not review and understand the diesel generator surveillance results
sufficiently to recognize that the condition did not match the previously-evaluated
condition that was used to conclude the diesel generator remained operable. Therefore,
this finding had a cross-cutting aspect in the area of problem identification and
resolution, associated with the corrective action program component P.1(c).
- 14 -
Enclosure 2
Enforcement. Title 10 CFR, Part 50, Appendix B, Criterion V, Instructions, Procedures,
and Drawings, requires in part that activities affecting quality be accomplished in
accordance with procedures. Procedure STP M-9A, Diesel Engine Generator Routine
Surveillance Test, Revision 90, stated that the diesel generator shall be considered
operable when frequency stabilizes within the acceptance range within 13 seconds
following a start signal. Contrary to the above, on December 22, 2011, plant personnel
concluded that diesel generator 2-3 was operable after the frequency failed to stabilize
within the required acceptance range within 13 seconds following a start signal without
an adequate technical basis. Because this finding was of very low safety significance
and was entered into the corrective action program as Notifications 50449027
and 50449504, this violation is being treated as a noncited violation, consistent with
Section 2.3.2 of the NRC Enforcement Policy: NCV 05000323/2012002-01, Inadequate
4.
OTHER ACTIVITIES
Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency
Preparedness, Public Radiation Safety, Occupational Radiation Safety, and
Security
4OA1 Performance Indicator Verification (71151)
.1
Data Submission Issue
a.
The inspectors performed a review of the performance indicator data submitted by the
licensee for the fourth quarter 2011performance indicators for any obvious
inconsistencies prior to its public release in accordance with Inspection Manual
Chapter 0608, Performance Indicator Program.
Inspection Scope
This review was performed as part of the inspectors normal plant status activities and,
as such, did not constitute a separate inspection sample.
b.
No findings were identified.
Findings
.2
Unplanned Scrams per 7000 Critical Hours (IE01)
a.
The inspectors sampled licensee submittals for the unplanned scrams per 7000 critical
hours performance indicator for Units 1 and 2 for the period from the first quarter 2011
through the fourth quarter 2011. To determine the accuracy of the performance indicator
data reported during those periods, the inspectors used definitions and guidance
contained in NEI Document 99-02, Regulatory Assessment Performance Indicator
Guideline, Revision 6. The inspectors reviewed the licensees operator narrative logs,
issue reports, event reports, and NRC integrated inspection reports for the period of
January 2011 through December 2011 to validate the accuracy of the submittals. The
inspectors also reviewed the licensees issue report database to determine if any
Inspection Scope
- 15 -
Enclosure 2
problems had been identified with the performance indicator data collected or
transmitted for this indicator and none were identified.
These activities constitute completion of two unplanned scrams per 7000 critical hours
samples as defined in Inspection Procedure 71151-05.
b.
No findings were identified.
Findings
.3
Unplanned Power Changes per 7000 Critical Hours (IE03)
a.
The inspectors sampled licensee submittals for the unplanned power changes per
7000 critical hours performance indicator for Units 1 and 2 for the period from the first
quarter 2011 through the fourth quarter 2011. To determine the accuracy of the
performance indicator data reported during those periods, the inspectors used definitions
and guidance contained in NEI Document 99-02, Regulatory Assessment Performance
Indicator Guideline, Revision 6. The inspectors reviewed the licensees operator
narrative logs, issue reports, event reports, and NRC integrated inspection reports for
the period of January 2011 through December 2011 to validate the accuracy of the
submittals. The inspectors also reviewed the licensees issue report database to
determine if any problems had been identified with the performance indicator data
collected or transmitted for this indicator and none were identified.
Inspection Scope
These activities constitute completion of two unplanned transients per 7000 critical hours
samples as defined in Inspection Procedure 71151-05.
b.
No findings were identified.
Findings
.4
Unplanned Scrams with Complications (IE04)
a.
The inspectors sampled licensee submittals for the unplanned scrams with
complications performance indicator for Units 1 and Unit 2 for the period from the
first quarter 2011 through the fourth quarter 2011. To determine the accuracy of the
performance indicator data reported during those periods, the inspectors used definitions
and guidance contained in NEI Document 99-02, Regulatory Assessment Performance
Indicator Guideline, Revision 6. The inspectors reviewed the licensees operator
narrative logs, issue reports, event reports, and NRC integrated inspection reports for
the period of January 2011 through December 2011 to validate the accuracy of the
submittals. The inspectors also reviewed the licensees issue report database to
determine if any problems had been identified with the performance indicator data
collected or transmitted for this indicator and none were identified.
Inspection Scope
These activities constitute completion of two unplanned scrams with complications
samples as defined in Inspection Procedure 71151-05.
- 16 -
Enclosure 2
b.
No findings were identified.
Findings
4OA2 Identification and Resolution of Problems (71152)
.1
Routine Review of Identification and Resolution of Problems
a.
As part of the various baseline inspection procedures discussed in previous sections of
this report, the inspectors routinely reviewed issues during baseline inspection activities
and plant status reviews to verify that they were being entered into the licensees
corrective action program at an appropriate threshold, that adequate attention was being
given to timely corrective actions, and that adverse trends were identified and
addressed. The inspectors reviewed attributes that included: the complete and
accurate identification of the problem; the timely correction, commensurate with the
safety significance; the evaluation and disposition of performance issues, generic
implications, common causes, contributing factors, root causes, extent of condition
reviews, and previous occurrences reviews; and the classification, prioritization, focus,
and timeliness of corrective actions. Minor issues entered into the licensees corrective
action program because of the inspectors observations are included in the attached list
of documents reviewed.
Inspection Scope
These routine reviews for the identification and resolution of problems did not constitute
any additional inspection samples. Instead, by procedure, they were considered an
integral part of the inspections performed during the quarter and documented in
Section 1 of this report.
b.
No findings were identified.
Findings
.2
Daily Corrective Action Program Reviews
a.
In order to assist with the identification of repetitive equipment failures and specific
human performance issues for follow-up, the inspectors performed a daily screening of
items entered into the licensees corrective action program. The inspectors
accomplished this through review of the stations daily corrective action documents.
Inspection Scope
The inspectors performed these daily reviews as part of their daily plant status
monitoring activities and, as such, did not constitute any separate inspection samples.
b.
No findings were identified.
Findings
- 17 -
Enclosure 2
.3
Selected Issue Follow-up Inspection
a.
During a review of items entered in the licensees corrective action program, the
inspectors recognized a corrective action item documenting:
Inspection Scope
SAPN 50459801, Operating experience at Byron Nuclear Plant, impact of open
circuit on offsite power system, February 16, 2012
SAPN 50455065, Availability of the emergency diesel generators during
surveillance testing
These activities constitute completion of two in-depth problem identification and
resolution samples as defined in Inspection Procedure 71152-05.
b.
No findings were identified.
Findings
4OA5 Other Activities
.1
(Closed) Unresolved Item 05000275; 05000323/2011004-02: Inconsistent Control Room
In-Leakage Test Results Reported to the NRC
The inspectors reviewed information submitted by the licensee in response to Generic
Letter 2003-01, Control Room Habitability, and completed a review of circumstances,
extent of condition, and causes related to incorrect information reported to the NRC
following control room envelope trace gas testing. The results of this review are
documented in Section 4OA5.2. This URI is closed.
.2
Failure to Submit Complete and Accurate Information in Response to Generic
Letter 2003-01, Control Room Habitability
Introduction. The inspectors identified a Green finding and Severity Level III violation of
10 CFR 50.9, Completeness and Accuracy of Information, after Pacific Gas and
Electric failed to provide complete and accurate information in response Generic
Letter 2003-01, Control Room Habitability.
Description. The NRC issued Generic Letter 2003-01, Control Room Habitability, to
ensure that the applicable regulatory requirements and the design bases were met for
control room habitability systems. The generic letter specifically requested Pacific Gas
and Electric to verify that the most limiting unfiltered in-leakage into the control room
envelope was no more than the value assumed in the design basis radiological analyses
for control room habitability. FSARU Section 15.5.17.10, Post-Accident Control Room
Exposures, stated that the control room design bases limited post-accident operator
radiation exposure to 5 rem equivalent for the duration of the most severe accident,
consistent with General Design Criteria 19, Control Room, of 10 CFR, Part 50,
Appendix A. The habitability system limited operator radiation exposure by filtering and
pressurizing the air in control room envelope. The licensee used Calculation STA-195,
Design Bases Dose Consequences and Recirculation Loop Margin Leakage Rates,
- 18 -
Enclosure 2
Revision 0, to demonstrate that this design basis requirement was met.
Calculation STA-195 showed that 10 cubic feet minute (cfm) unfiltered in-leakage into
the envelope would result in control room operators receiving 5 rem equivalent dose.
In response to Generic Letter 2003-01, Pacific Gas and Electric reported to the NRC that
testing performed in January 2005 confirmed that the control room envelope did not
have any unfiltered in-leakage (Pacific Gas and Electric Letter DCL-05-042,
April 22, 2005, Control Room Envelope In-Leakage Test Results Relative to Generic
Letter 2003-01, Control Room Habitability, ADAMS ML051260225). The licensee
stated that the testing was performed in the most limiting configuration for operator dose
consistent with Regulatory Guide 1.197, Demonstrating Control Room Envelope
Integrity at Nuclear Power Reactors, Section 2.2, Alignment, Operation, and
Performance. In 2006, the NRC concluded that the licensees responses and described
actions needed for Generic Letter 2003-01 were complete because the licensee had
reported that in-leakage was not greater than assumed in the design basis radiological
analyses (Diablo Canyon Power Plant , Units 1 and 2 - RE: Response to Generic
Letter 2003-01, Control Room Habitability TAC Nos. MB9797 and MB9798, ADAMS
In September 2011, the inspectors identified that the control room in-leakage test results
had been greater than both the values reported to the NRC in response to the generic
letter and the values assumed in the design basis radiological analyses. Procedure
PMT 23.39, PMT to Document Control Room Ventilation Test to Satisfy Generic
Letter 2003-01, tested the control room habitability system in four configurations and
had measured unfiltered in-leakage rates described in Table 1.
Table 1 - PMT 23.29 Control Room Unfiltered In-Leakage
Date
Configuration
Unfiltered In-Leakage
(CFM)
January 22, 2005
Supply Fan S-99 in operation
59
January 22, 2005
Supply Fan S-98 in operation
44
January 22, 2005
Supply Fan S-97 in operation
19
January 22, 2005
Supply Fan S-96 in operation
-10
The inspectors also identified that the licensee had not performed the trace gas in-
leakage test in the most limiting configuration for operator dose consistent with
Regulatory Guide 1.197. The licensee had performed the 2005 tests with components
of both control room habitability trains in operation. Technical Specification Basis 3.7.10,
Control Room Ventilation System (CRVS), stated that each individual ventilation train
was required to limit operator dose to 5 rem equivalent. In November 2011, the licensee
re-performed the in-leakage tests in the most limiting configuration for operator dose and
measured about 800 CFM unfiltered in-leakage into the control room envelope. Plant
operators subsequently declared the habitability system inoperable and implemented
compensatory actions.
The inspectors concluded that the violation resulted in potential safety consequences.
By failing to recognize and report the unfiltered in-leakage, the licensee did not take
corrective actions necessary to ensure that the control room habitability system would
- 19 -
Enclosure 2
meet the radiological analysis for in-leakage into the control room envelope. The
analysis assumed 10 cfm in-leakage and concluded that the control room operators
would receive the 5 rem equivalent regulatory limit established by 10 CFR Part 50, Appendix A, General Design Criteria 19, Control Room. Based on the results of the
2005 control room in-leakage test, control room operators would have had the potential
to exceed the 5 rem equivalent regulatory limit during an accident with a release. The
inspectors concluded that no actual consequences occurred as a result of the violation
because there were no adverse radiological conditions that challenged this function.
Analysis. The inspectors concluded that the failure of Pacific Gas and Electric to provide
complete and accurate information in response to Generic Letter 2003-01 was a
performance deficiency. The inspectors screened the issue through the Reactor
Oversight Process because the finding included a performance deficiency that was
reasonably within the licensees ability to control. The inspectors also screened the
issue through the traditional enforcement process because the violation impacted the
regulatory process. The purpose of the generic letter was to collect information to
determine if additional regulatory action was required. Title 10 CFR 50.9(a) required that
the requested information, when provided, must be complete and accurate in all material
respects. The finding was more than minor because the information was material to the
NRCs decision making processes. Specifically, the information requested by Generic
Letter 2003-01 was to enable NRC staff to determine whether the applicable regulatory
requirements identified in the generic letter (10 CFR Part 50, Appendix A, General
Design Criteria 1, 3, 4, and 19; and 10 CFR Part 50, Appendix B, Criterion XI), were
being met in regard to the operational readiness of the control room habitability system.
The inspectors concluded that the finding was associated with the Barrier Integrity
Cornerstone because the control room habitability system was affected. Using
Inspection Manual Chapter 0609, Attachment 4, Phase 1 - Initial Screening and
Characterization of Findings, the inspectors concluded that the finding was of very low
safety significance (Green) because only the radiological barrier function of the control
room was affected. The inspectors used the NRC Enforcement Policy to evaluate the
traditional enforcement violation. The inspectors concluded that the violation was a
Severity Level III because had the licensee provided complete and accurate information
in their letter dated April 22, 2005, the NRC would not have closed Generic Letter 2003-01. The staff considered whether a civil penalty was warranted. The licensee has
not been the subject of escalated enforcement actions within the last 2 years; Credit was
given for the Corrective Action factor because the licensee promptly reported the
erroneous report when they became aware of the problem and provided the correct test
results; Prompt compensatory measures were taken and new tests were performed.
Based on the civil penalty assessment process, the NRC will not propose a civil penalty
in this case. Additionally, it is recognized that this violation occurred more than 5 years
ago, so it was beyond the normal statute of limitations.
The inspectors did not identify a cross-cutting aspect because the performance
deficiency was not reflective of present performance.
Enforcement. Title 10 CFR 50.9(a), Completeness and Accuracy of Information,
requires, in part, information provided to the Commission by a licensee shall be
complete and accurate in all material respects. Contrary to the above, on April 22, 2005,
the licensee provided information to the Commission that was not complete and
accurate in all material respects. Specifically, on April 22, 2005, the licensee stated to
- 20 -
Enclosure 2
the NRC in their response to Generic Letter 2003-01 that: (1) test results confirmed that
no unfiltered in- leakage existed; and (2) tracer gas in-leakage testing was performed in
the alignment that results in the greatest consequence to the control room operator.
However, the test results from licensee Procedure PMT 23.39, PMT to Document
Control Room Ventilation Test to Satisfy Generic Letter 2003-01, conducted prior to the
licensee response to Generic Letter 2003-01, clearly indicated that the test identified
unfiltered in-leakage greater than the value assumed in design basis radiological
analyses, and the in-leakage test was not performed in the system alignment that
resulted in the greater consequence to the control room operator. This was material
because the staff would not have closed the generic letter, had the correct test results
been reported: NOV 05000275;05000323/2012002-02, Incomplete and Inaccurate
Information Provided to the NRC in Response to Generic Letter 2003-01, Control Room
Habitability.
4OA6 Meetings
Exit Meeting Summary
On March 27, 2012, the inspectors presented the inspection results to Mr. James Becker, Site
Vice President, and other members of the licensee staff. The licensee acknowledged the issues
presented. The inspectors asked the licensee whether any materials examined during the
inspection should be considered proprietary. No proprietary information was identified.
A-1
Attachment
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
J. Becker, Site Vice President
J. Welsch, Station Director
J. Nimick, Director, Operations Services
S. David, Director, Site Services
T. Baldwin, Manager, Regulatory Services
P. Gerfen, Manager, Operations
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Opened and Closed 05000323-2012002-01
Inadequate Operability Determination (Section 1R22)
Opened 05000323-2012002-01
Incomplete and Inaccurate Information Provided to the NRC
in Response to Generic Letter 2003-01, Control Room
Habitability. (Section 4OA5)
Closed
05000275;05000323/2011004-02
Inconsistent Control Room In-Leakage Test Results
Reported to the NRC (Section 4OA5)
LIST OF DOCUMENTS REVIEWED
Section 1R04: Equipment Alignments
PROCEDURES
NUMBER
TITLE
REVISION
DCM S-21
Diesel Engine System
21A
DCM S-10
Residual Heat Removal System
16B
DCM S-9
Safety Injection System
27
DRAWINGS
NUMBER
TITLE
REVISION
106703
Sheet 3, AFW System
76
106703
Sheet 4, Aux Feedwater and Chemical Injection
75
A-2
Attachment
Section 1R05: Fire Protection
PROCEDURES
NUMBER
TITLE
REVISION
OM8.ID1
Fire Loss Prevention
22
OM8.ID2
Fire System Impairment
16
OM8.ID4
Control of Flammable and Combustible Materials
19
STP M-70A
Inspection of Fire Barrier and HELB Penetration Seals
6
STP M-70D
Inspection of Fire Barriers, Rated Enclosures, Credited Cable
Tray Fire Stops, and Equipment Hatches
13
ECG 18.7
Fire Rated Assemblies
7
DRAWINGS
NUMBER
TITLE
REVISION
515573
Fire Barriers for Unit 2, Turbine Building, 85 Elevation, Sht. 1
19
Section 1R06: Flood Protection Measures
DOCUMENTS
NUMBER
TITLE
REVISION
PG&E PRA Calculation File No. F4 PRA Internal Floods
Analysis
1
Section 1R11: Licensed Operator Requalification Program
PROCEDURES
NUMBER
TITLE
REVISION
Exam115E1-1
17
OP1.DC10
Conduct of Operations
30
Section 1R12: Maintenance Effectiveness
PROCEDURES
NUMBER
TITLE
REVISION
MA1.ID17
Maintenance Rule Monitoring Program
23
NOTIFICATIONS
50369577
50439888
50408740
A-3
Attachment
DOCUMENTS
Maintenance Rule Expert Panel Meeting 185, March 22, 2012
Section 1R13: Maintenance Risk Assessments and Emergent Work Control
PROCEDURES
NUMBER
TITLE
REVISION
MA1.ID17
Maintenance Rule Monitoring Program
24
AD7.DC6
On-Line Risk Management
19A
DOCUMENTS
NUMBER
TITLE
DATE
Switching Log
12-0112
Removal of Morro Bay Bus 1 Section e and CB 582
Dec. 28, 2011
Switching Log
12-0113
Removal of Morro Bay Bus 1 Section e and CB 582 T-Tap
Dec. 28, 2011
Unit 1, Risk Assessment 09-15, DEG 2-3 (M-75F) and Condensate Booster Pump 2-1 MOW
Section 1R15: Operability Evaluations
PROCEDURES
NUMBER
TITLE
REVISION
OM7.ID12
22
AD13.1D
Control of Plant and Equipment Tests
12
AD.13
Test Control,
3
AD13.DC1
Control of the Surveillance Test Program,
37
NOTIFICATIONS
50460853
50461614
50464320
DOCUMENTS
NUMBER
TITLE
REVISION /
DATE
Operational Decision Making Report, Unit 2 Rod Control Jan. 28, 2012
PG&E Letter DCL 88-
090
Deletion of Reactor Trip on turbine Trip Below 50
Percent Power
Apr. 18, 1988
OP1.DC10
Conduct of Operations
Rev. 30
Diesel Generator 13 Turbo-Charger Vibration Report,
Data Collect 12/04/03
A-4
Attachment
Input Data sent to MPR Associates for analysis
Operability write up, SAPN 50460853 Task 6, Cracked
Welds on Support Bracket for EDG Turbocharger
CALCULATIONS
D21.1-3
Diesel Generator System
Rev. 0
D21.1-2
Diesel Generator System
Rev. 0
SAP 9000041323-001-00 Legacy Calc. No.: SQE-024.14
Rev. 1
Section 1R19: Post-maintenance Testing
PROCEDURES
NUMBER
TITLE
REVISION
STP P-RHR-21
Routine Surveillance Test of RHR Pump 2-1
23
STP M-12B
Battery Charger Performance Test
15
MP E-64.1B
Molded Case Circuit Breaker Exercise and Maintenance
12
MP E-67.3C
Maintenance of Solid State Controls 400A vital Station
Battery Chargers
8
MP E-57.15
Maintenance and Calibrations of Ammeters Voltmeters,
Frequency Meters & tachometers
13
MP E-50.30B
Agastat Type ETR Timing Relay Maintenance
17
MP E-50.62
Basler BE1-GPS100 Relay Maintenance
5
MP E-50.33A
Type SSV-T One Unit Voltage Relay Maintenance
11
MP E-50.61
Basler type BE1-27 Medium Inverse Undervoltage Relay
Maintenance
5
STP M-75H
4 kV Vital Bus H Undervoltage relay Calibration
1
NOTIFICATIONS
50455065
Section 1R22: Surveillance Testing
PROCEDURES
NUMBER
TITLE
REVISION
STP P-CCP-21
Routine Surveillance Test of Centrifugal Charging Pump 2-1
22
STP I-1B
Routine Daily Checks required by Licenses U1
121
STP V-3T4
Exercising of Containment Atmosphere Sample Post LOCA
Valves
12
STP I-1B
Routine Daily Checks required by Licenses U2
102
A-5
Attachment
STP P-AFW-21
Routine Surveillance test of Turbine-Driven Auxiliary
Feedwater Pump 2-1
25
STP M-75F
4kv Vital Bus F Undervoltage Relay Calibration
1A
MP E-50.61
Basler Type BE1-27 Medium Inverse Undervoltage Relay
Maintenance
5
STP M-9A
Diesel engine Generator Routine Surveillance Test
90
AD13.1D
Control of Plant and Equipment Tests
12
AD.13
Test Control,
3
AD13.DC1
Control of the Surveillance Test Program,
37
Section 4OA2: Identification and Resolution of Problems
PROCEDURES
NUMBER
TITLE
REVISION
OM7.ID13
Technical Evaluation
1
DOCUMENTS
Pre-NIEP Self-Assessment of Diablo Canyon Quality Program Implementation,
February 4, 2012
Section 4OA5: Other Activities
DOCUMENTS
Drawing 437621 Startup Bus Control Power Schematic
Drawing 437666 Startup Bus Control Power Schematic
Drawing 437664 Startup Bus Control Power Schematic
Drawing 437625 Startup Bus Control Power Schematic
Drawing 437665, 4 KV Diesel Generators and Associated Circuit Breakers Schematic
Drawing 458863 4160 Volt Bus Section F Automatic Transfer Logic Diagram
A-6
Attachment
LIST OF ACRONYMS
Agencywide Document Access and Management System
alternative dispute resolution
cubic feet per minute
control room ventilation system
FSARU
Final Safety Analysis Report Update
non-cited violation
NRC
Nuclear Regulatory Commission
PEC
Pre-decisional Enforcement Conference
SAPN
systems applications process notification