MONTHYEARML23109A1862023-04-19019 April 2023 and Turkey Point Acceptance of Requested Licensing Action Proposed Alternative to Asme Section XI Authorizing Implementation of Asme Code Case N-752-1 ML22067A0922022-03-0303 March 2022 State Consultation - Duane Arnold ISFSI-Only EP License Amendment ML22040A1162022-02-0808 February 2022 Email to G. Van Noordennen Zion and La Crosse Review Schedule Changes ML22027A3582022-01-26026 January 2022 DAEC: CY2022 Inspection Plan, Docket No: 05000331, License No: DPR-49 ML22007A3102022-01-0505 January 2022 State Consultation - Draft No Significant Hazards Determination Regarding a LAR for NextEra Energy Duane Arnold, LLC, Duane Arnold Energy Center ISFSI in Palo, Iowa ML22005A0862022-01-0404 January 2022 1-4-2022 Email Communication to Duane Arnold Regarding Its ISFSI Related Exemption Request on Supplemental Information Needed ML22005A0992022-01-0404 January 2022 Email from a Snyder to a Leek Re State Consultation - Draft No Significant Hazards Determination - License Amend. Req. for NextEra Energy, LLC, DAEC ISFSI in Palo, Iowa ML22005A1012022-01-0404 January 2022 Email from a Leek to a Snyder Re State Consultation - Draft No Significant Hazards Determination - License Amend. Req. for NextEra Energy, LLC, DAEC ISFSI in Palo Iowa ML22004A0122022-01-0303 January 2022 E-mail from M. Davis, NextEra, to A. Snyder, NRC, - Duane Arnold Energy Center - Supplement Information to Technical Specification Amendment Application ML21354A6722021-12-17017 December 2021 Email to State of Iowa - Draft EA on Duane Arnold Exemption ML21214A0482021-08-0101 August 2021 Acceptance of License Amendment Request to Adopt an ISFSI-Only Emergency Plan ML21214A0502021-08-0101 August 2021 Acceptance of License Amendment Request to Adopt an ISFSI-Only Physical Security Plan ML21165A1212021-06-10010 June 2021 E-mail from M. Davis, Duane Arnold, to M. Doell and R. Edwards, NRC - Duane Arnold Defueled Emergency Plan Implementation Confirmation ML21117A2752021-04-26026 April 2021 Acceptance of Updated Spent Fuel Management Plan ML21089A2092021-03-19019 March 2021 Spent Fuel Pattern Procedure ML21068A3352021-03-0707 March 2021 Acceptance of License Amendment Request to Adopt ISFSI-Only Technical Specifications ML21056A2172021-02-17017 February 2021 Acceptance of License Amendment Request to Revise the Physical Security Plan Requirements ML21032A1852021-02-0101 February 2021 Daec_ CY2021 Inspection Plan ML21006A4052021-01-0606 January 2021 NRR E-mail Capture - Final RAI - Duane Arnold - Post-Shutdown Decommissioning Activities Report ML20338A0032020-12-0101 December 2020 Letter from EPRI to Mr. Scott Wall, BWRVIP 2020-100, 288 Surveillance Capsule Test Results Report ML20316A0212020-11-10010 November 2020 NRR E-mail Capture - Final RAI - Duane Arnold - Duane Arnold Amendment for Proposed Defueled EP and EAL Scheme ML20289A3522020-10-14014 October 2020 NRR E-mail Capture - Duane Arnold Energy Center -Acceptance of Requested Licensing Action, One-Time Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Pandemic (EPID No. L-2020-LLE-01 ML20153A3772020-05-28028 May 2020 NRR E-mail Capture - Request for Additional Information - Duane Arnold Energy Center Quality Assurance Topical Report (FPL-3) - EPID L-2020-LLQ-0002) ML20154K6202020-05-27027 May 2020 COVID-19 Preparedness Assessments for FEMA Region VII Duane Arnold Energy Center (DAEC) and Quad Cities Generating Station (Qcgs) ML20141L8132020-05-19019 May 2020 NRR E-mail Capture - Request for Additional Information - Duane Arnold Energy Center (DAEC) - Exemption Request for Security Training Requirements Due to COVID-19 Pandemic - EPID L-2020-LLE-0042 to 45, L-2020-LLE-0051 ML20129J8282020-05-0606 May 2020 NRR E-mail Capture - LIC-109 Acceptance Review of Duane Arnold Request for Exemption from Portions of 10 CFR 50.47 and Appendix E - EPID L-2020-LLE-0023 ML20127H8662020-05-0505 May 2020 NRR E-mail Capture - Duane Arnold Energy Center (DAEC) - Request for Additional Information (RAI) - Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 1O CFR 50.75(h)(1)(iv) - EPID L-2020-LLE-0011 ML20122A1152020-04-30030 April 2020 NRR E-mail Capture - Duane Arnold Energy Center -Acceptance of Post-Shutdown Decommissioning Activities Report ML20087F2872020-03-26026 March 2020 NRR E-mail Capture - LIC-109 Acceptance Review of Duane Arnold Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) and 1O CFR 50.75(h)(1)(iv) - EPID L-2020-LLE-0011 ML20129J8322020-03-19019 March 2020 NRR E-mail Capture - (External_Sender) Teleconference with Nextra Energy - Duane Arnold Physical Security Plan LIC-109 Review Status ML20022A3602020-01-22022 January 2020 NRR E-mail Capture - Duane Arnold Energy Center - Acceptance of Requested Licensing Action, Proposed Partial Exemption from Record Retention Requirements ML19352G6872019-12-11011 December 2019 12-11-19 Email to FEMA: Response to FEMA Questions on Proposed DAEC Emergency Plan ML19302G3212019-10-29029 October 2019 LIC-109 Acceptance of Duane Arnold Energy Center (DAEC) - License Amendment Request (TSCR- 186) - Removal of License Condition 2.C.(3), Fire Protection Program - EPID L-2019-LLA-0211 ML19302G9732019-10-29029 October 2019 NRR E-mail Capture - LIC-109 Acceptance of Duane Arnold Energy Center (DAEC) - License Amendment Request (TSCR- 186): Removal of License Condition 2.C.(3), Fire Protection Program - EPID L-2019-LLA-0211 ML19280A0352019-10-0404 October 2019 NRR E-mail Capture - Final - RAI Related to License Amendment Request (TSCR-182) for Proposed Changes to the Emergency Plan for Permanently Defueled Conditions at Duane Arnold Energy Center (DAEC) - L-2019-LLA-0075 ML19206A2182019-07-25025 July 2019 NRR E-mail Capture - LIC-109 Acceptance of Duane Arnold Energy Center (DAEC) - License Amendment Request (TSCR-183) - Application to Revise Operating License and TS for Permanently Defueled Condition - EPID L-2019-LLA-0130 ML19183A0172019-06-26026 June 2019 NRR E-mail Capture - LIC-109 Acceptance of Request for Change in the BWRVIP Integrated Surveillance Program Test Schedule to Accommodate Early Closure of the Duane Arnold Energy Center - EPID L-2019-LRO-0042 ML19122A4882019-04-29029 April 2019 NRR E-mail Capture - LIC-109 Acceptance of License Amendment Request (TSCR-182) for Duane Arnold Energy Center (DAEC) - Proposed Changes to the Emergency Plan for Permanently Defueled Condition - EPID L-2019-LLA-0075 ML19086A3502019-03-27027 March 2019 NRR E-mail Capture - LIC-109 Acceptance of the Request for Exemption from 10 CFR 73.55(p)(1)(I) and 10 CFR 73.55(p)(1)(ii) for Duane Arnold Energy Center - EPID L-2019-LLE-0003 ML19064A2032019-03-0404 March 2019 NRR E-mail Capture - Results of LIC-109 Acceptance Review - Duane Arnold Energy Center - Request for Approval of Certified Fuel Handler Training Program, EPID L-2019-LLL-0003 ML18283B0522018-10-0909 October 2018 NRR E-mail Capture - Final Second Round - Request for Additional Information (RAI) - Duane Arnold Energy Center (DAEC) - LAR TSCR-166, Adoption of EAL Scheme Pursuant to NEI 99-01 - EPID L-2017-LLA-0420 ML18255A2922018-09-11011 September 2018 NRR E-mail Capture - Draft Second Round - Request for Additional Information (RAI) - Duane Arnold Energy Center (DAEC) - LAR TSCR-166, Adoption of EAL Scheme Pursuant to NEI 99-01 - EPID L-2017-LLA-0420 ML18166A2982018-06-15015 June 2018 NRR E-mail Capture - Draft Request for Additional Information (RAI) - Duane Arnold Energy Center (DAEC) - LAR TSCR-166, Adoption of EAL Scheme Pursuant to NEI 99-01 - EPID L-2017-LLA-0420 ML18108A3102018-04-12012 April 2018 NRR E-mail Capture - Audit at NextEra Headquarters, Juno Beach, Florida - April 24, 2018 Through April 26, 2018 - 50.69 LARs for Duane Arnold Energy Center (Daec), and Point Beach Nuclear Plant (Pbnp), Units 1 and 2 - EPIDs L-2017-LLA-0283/ ML18088A0102018-03-28028 March 2018 NRR E-mail Capture - Final RAI for Duane Arnold (DAEC) 5th-10 Year ISI (RR-05) ML18037B0032018-02-0606 February 2018 NRR E-mail Capture - Draft Request for Additional Information - Duane Arnold Energy Center (DAEC) - License Amendment Request (TSCR-170), Revision to Technical Specification 3.5.1, ECCS-Operating - EPID L-2017-LLA-0288 ML18025A2362018-01-24024 January 2018 NRR E-mail Capture - Resent - LIC-109 Acceptance - Duane Arnold LAR (TSCR-166) - Adoption of Emergency Action Level (EAL) Scheme Pursuant to NEI 99-01, Revision 6, Development of EALs for Non-Passive Reactors ML18023A0752018-01-22022 January 2018 NRR E-mail Capture - LIC-109 Acceptance - Duane Arnold License Amendment Request (LAR) (TSCR-179) - Application to Add Technical Specification 3.2.3, Linear Heat Generation Rate - EPID: L-2017-LLA-0436 ML18019A0732018-01-18018 January 2018 NRR E-mail Capture - LIC-109 Acceptance - Duane Arnold License Amend Request (LAR)(TSCR-178) - Application to Reduce the Required Number of Operable Suppression Chamber-to-Drywell Vacuum Breakers ML17355A0132017-12-20020 December 2017 NRR E-mail Capture - LIC-109 Acceptance of Duane Arnold LAR TSCR-177, Application to Revise Tech Spec to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements - EPID: L-2017-LLA-0385 2023-04-19
[Table view] |
Text
NRR-PMDA-ECapture Resource From: Feintuch, Karl Sent: Wednesday, February 08, 2012 3:56 PM To: Feintuch, Karl; McConnell, Matthew; Byrne, Thomas
Subject:
Duane Arnold Energy Center -Pre-application conference call to plan for processing a change to TS 3.8.4 DC Sources <ae>
Attachments: oledata.mso; TS 3.8.4 markup.pdf The conference call started at 3:30 PM and ended at 3:45 PM ET on 2/8/2012 Attending were:
For NRC: Feintuch, McConnell For DAEC: Thomas Byrne, Dennis Pint, Steve Catron Contemplated changes were discussed (see notes below). For planning purposes, DAEC (Byrne) will notify Karl Feintuch of the projected date of issuance of the amendment application.
Karl Feintuch USNRC 301-415-3079 From: Feintuch, Karl Sent: Wednesday, February 08, 2012 1:00 PM To: 'Thomas.Byrne@nexteraenergy.com' Cc: McConnell, Matthew
Subject:
Pre-Application review - Notes for TS 3.8.4 DC Sources - TS change discussion Based on our (Catron, Byrne, Feintuch) phone conversation on 2/6/2012, I prepared these notes for Reviewer McConnell. They would color his perceptions in participating in the call scheduled for today. Please review them with the objective of clarifying or correcting what I wrote so all parties accurately understand what your are attempting. An accurate version of the notes will be a record of the call. (Undetected errors remain mine.)
Karl Feintuch USNRC 301-415-3079
========== begin notes =====
Below is a challenge from Duane Arnold.
I requested this summary (below and attached) as the result of a call from Duane Arnolds licensing manager (Steve Catron) this afternoon. They have a project to increase the number of battery cells for the Division 1 and 2 -125 VDC batteries. However, their assigned project team did not complete the necessary calculation to support a licensing amendment until after the deadline for our one year metric, relative to their next refueling outage. Now it is a matter of practicality to accomplish the needed licensing amendment within our resources.
I will list the constraints below that I drew from this first conversation and suggest a follow-up conversation to see if we can be responsive.
Details follow as I know them at this time. I can open a pre-application review TAC if a cursory review of the licensees impending application is encouraging.
1 - TS Changes to be requested: See attached TS pages 3.8-17, 3.8-18, and 3.8-19, as marked by hand.
2 - Reason for change: Increase capacity for Design Basis Accident and Fukushima response.
3 - Physical change: Add two cells to each 125 VDC source.
1
4 - Physical change schedule: Add cells during fall refueling outage (nominal 10/06/2012 to 12/06/2012);
physically install the cell but not connect them without the amendment.
5 - Amendment issuance requested by: First week in December 2012 (corresponding to nominal 12/06/2012 end of outage.)
6 - Planned date to submit application: mid to late February 2012.
7 - Inferred [by PM] SE to PM date for issuance in Dec.2012: Late October to Early November 2012 [
We (DORL) typically need 6 weeks to issue the letter, and I am presuming seasonal stresses due to confluence of holidays, excess leave to be taken, rush because of end-of-year deadlines - kdf]
8 - Effective number of full months for Tech Branch to produce SE Memorandum: 8 months = full March thru most of, or full, October 2012.
9 - Implementing strategy for issuance of SE Memorandum within 8 full months:
A - Apply LIC-109 processes such that (1) the application is perfect (no RAI items are needed - for the entire project) or (2) RAI cycle time(s) are 7 calendar days throughout the entire project. These accelerated cycle times would be the as mutually agreed times that supersede the default 30 day intervals. [Make allowance for other compelling circumstances.- kdf 2/8/2012]
B - Recommend an OGC Reviewer very experienced with TS 3.8.4 reviews.
C - Perceived benefit-to-cost: Benefit = Application of 9A and 9B can save about 2 months of processing time; if this strategy is practical for EEEB, then we brief the licensee on the Benefit to Cost considerations for achieving project goals.
The licensee is expediting the application effort at this time. I believe that EEEB and ITSB are the only cognizant Technical Branches for this TS change.
Karl Feintuch
==== begin Duane Arnold TS 3.8.4 change executive summary ==========
From: Byrne, Thomas [1]
Sent: Monday, February 06, 2012 3:17 PM To: Feintuch, Karl Cc: Catron, Steve
Subject:
DAEC Summary of Amendment Request for TS 3.8.4, DC Sources Karl:
The proposed amendment we discussed today would revise the DAEC TS by modifying existing Surveillance Requirements (SRs) regarding the battery terminal and charger voltages and amperage provided in SR 3.8.4.1 and SR 3.8.4.6. This amendment also deletes the one-time allowance provided in Amendment 247 (granted in 2002) to allow for online battery replacement. I figured I'd clean up the TS by removing this one-time allowance. See the attached pages for a markup of what will change. We're interested in getting approval by the first week of December 2012 if possible. Let me know if you require further information.
Tom Thomas R. Byrne Thomas.Byrne@nexteraenergy.com Senior Licensing Engineer Duane Arnold Energy Center (319) 851-7929
==== end Duane Arnold TS 3.8.4 change executive summary ======