Letter Sequence Acceptance Review |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement
|
MONTHYEARL-09-086, License Amendment Request No. 08-027, Spent Fuel Pool Rerack2009-04-0909 April 2009 License Amendment Request No. 08-027, Spent Fuel Pool Rerack Project stage: Request ML0915201072009-06-0101 June 2009 Supplemental Information Needed for Acceptance of Requested Licensing Action Spent Fuel Pool Rerack Project stage: Acceptance Review L-09-162, Additional Technical Information Pertaining to License Amendment Request No. 08-0272009-06-15015 June 2009 Additional Technical Information Pertaining to License Amendment Request No. 08-027 Project stage: Request ML0917510672009-06-25025 June 2009 Acceptance of Requested Licensing Action Spent Fuel Pool Rerack Project stage: Acceptance Review ML0932809142009-12-0404 December 2009 Request for Additional Information Regarding Spent Fuel Pool Rerack License Amendment Project stage: RAI ML1001918052010-01-18018 January 2010 Response to Request for Additional Information for License Amendment No. 08-027, Spent Fuel Pool Rerack Project stage: Response to RAI ML1003800022010-02-16016 February 2010 Request for Additional Information Spent Fuel Pool Rerack Amendment Project stage: RAI ML1001303452010-03-0505 March 2010 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for Hearing, and Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information Project stage: Other L-10-082, Response to NRC Staff Request for Additional Information Regarding Criticality Analyses Supporting a Spent Fuel Pool Re-rack2010-03-18018 March 2010 Response to NRC Staff Request for Additional Information Regarding Criticality Analyses Supporting a Spent Fuel Pool Re-rack Project stage: Request ML1007605842010-03-19019 March 2010 Request for Additional Information Spent Fuel Pool Rerack Round 3 Project stage: RAI ML1008407842010-04-15015 April 2010 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance L-10-121, Response to Request for Additional Information Related Spent Fuel Pool Rerack License Amendment Request2010-05-0303 May 2010 Response to Request for Additional Information Related Spent Fuel Pool Rerack License Amendment Request Project stage: Response to RAI L-10-151, Response to Request for Additional Information Related to Spent Fuel Pool Rerack License Amendment Request2010-05-21021 May 2010 Response to Request for Additional Information Related to Spent Fuel Pool Rerack License Amendment Request Project stage: Response to RAI L-10-130, Remainder of Responses to NRC Staff Request for Additional Information Regarding Unit 2 Spent Fuel Pool Rerack Criticality Analyses2010-06-0101 June 2010 Remainder of Responses to NRC Staff Request for Additional Information Regarding Unit 2 Spent Fuel Pool Rerack Criticality Analyses Project stage: Request ML1013805462010-06-11011 June 2010 Request for Additional Information Spent Fuel Pool Rerack License Amendment Project stage: RAI ML1017203652010-06-24024 June 2010 Impacts to the Review Schedule Regarding the Spent Fuel Pool Rerack License Amendment Request Project stage: Other L-10-038, Report of Facility Changes, Tests and Experiments2010-08-0909 August 2010 Report of Facility Changes, Tests and Experiments Project stage: Request L-10-235, Response to Request for Additional Information for License Amendment Request No. 08-027 Re Spent Fuel Pool Rerack2010-08-0909 August 2010 Response to Request for Additional Information for License Amendment Request No. 08-027 Re Spent Fuel Pool Rerack Project stage: Response to RAI ML1025107802010-09-14014 September 2010 Notice of Forthcoming Meeting with First Energy Nuclear Operating Company, Beaver Valley Power Station, Unit No. 2 & Holtec, Inc., to Discuss the Licensees Responses, Dated August 9, 2010 Project stage: Meeting L-10-282, Supplemental Response to Request for Additional Information Related to Spent Fuel Pool Rerack License Amendment Request2010-10-0707 October 2010 Supplemental Response to Request for Additional Information Related to Spent Fuel Pool Rerack License Amendment Request Project stage: Supplement L-10-275, License Amendment Request for Spent Fuel Pool Rerack2010-10-18018 October 2010 License Amendment Request for Spent Fuel Pool Rerack Project stage: Request ML1029404582010-10-18018 October 2010 Report No: HI-2084175, Licensing Report for Beaver Valley, Unit 2, Rerack Project stage: Other ML1027903512010-10-18018 October 2010 Summary of Meeting with Firstenergy Nuclear Operating Company, on the Request for Additional Resposnses Regarding the Spent Fuel Rerack for Beaver Valley Power Station, Unit No. 2 Project stage: Meeting ML1035606612010-12-29029 December 2010 Summary of Beaver Valley Power Station, Unit 2 Public Conference Call Regarding Spent Fuel Pool Rerack LAR Draft RAI Responses Discussion Project stage: Draft RAI L-10-329, Supplemental Information for Spent Fuel Pool Rereack License Amendment Request2011-01-0505 January 2011 Supplemental Information for Spent Fuel Pool Rereack License Amendment Request Project stage: Supplement ML1102006022011-01-24024 January 2011 Request for Additional Information Spent Fuel Pool Rerack Amendment (ME1079) Project stage: RAI L-11-024, Chapters 5 and 7 of Holtec Licensing Report, in Support of License Amendment Request for Unit 2 Spent Fuel Pool Rerack2011-02-18018 February 2011 Chapters 5 and 7 of Holtec Licensing Report, in Support of License Amendment Request for Unit 2 Spent Fuel Pool Rerack Project stage: Request L-11-057, Responses to NRC Staff Request for Additional Information Regarding Unit No. 2 Spent Fuel Pool Rerack Criticality Analyses2011-02-18018 February 2011 Responses to NRC Staff Request for Additional Information Regarding Unit No. 2 Spent Fuel Pool Rerack Criticality Analyses Project stage: Request ML1107504782011-03-10010 March 2011 E-mail Summary of Clarification Phone Call Regarding the Beaver Valley 2 Spent Fuel Pool Rerack Amendment (ME1079) Project stage: Approval ML1108001222011-03-18018 March 2011 Supplement to Spent Fuel Pool Rerack Amendment Request Project stage: Supplement L-11-101, Supplemental Information for Spent Fuel Pool Rerack License Amendment Request2011-03-21021 March 2011 Supplemental Information for Spent Fuel Pool Rerack License Amendment Request Project stage: Supplement ML1108005702011-03-21021 March 2011 Supplemental Information for Spent Fuel Pool Rerack License Amendment Request Project stage: Supplement ML1108908442011-04-29029 April 2011 Issuance of Amendment Regarding the Spent Fuel Pool Rerack Project stage: Approval 2010-04-15
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 25, 2009 Mr. Peter P. Sena III Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB1 P.O. Box 4, Route 168 Shippingport, PA 15077
SUBJECT:
BEAVER VALLEY POWER STATION, UNIT NO.2 - ACCEPTANCE OF REQUESTED LICENSING ACTION RE: SPENT FUEL POOL RERACK (TAC NO. ME1079)
Dear Mr. Sena:
By letter dated April 9, 2009, FirstEnergy Nuclear Operating Company submitted a license amendment for Beaver Valley Power Station, Unit NO.2 (BVPS-2). The proposed amendment would modify Technical Specifications (TSs) to support the installation of high density fuel storage racks in the BVPS-2 spent fuel pool. The purpose of this letter is to provide the results of the Nuclear Regulatory Commission (NRC) staff's acceptance review of this amendment request. The acceptance review is performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review.
The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the TSs) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the NRC staff to complete its technical review, you will be advised by separate correspondence.
P.Sena
- 2 If you have any questions, please contact me at (301) 415-1016.
Sincerely, Nadiyah S. Morgan, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-412 cc: Distribution via Listserv
P.Sena
- 2 If you have any questions, please contact me at (301) 415-1016.
Sincerely, IRA!
Nadiyah S. Morgan, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-412 cc: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsNrrDssSrxb Resource Branch Reading File KWood RidsAcrsAcnw_MailCTR Resource RidsNrrDeEmcb Resource RidsNrrDorl Resource MHartzman RidsNrrDorlDpr Resource RidsNrrDssSbpb Resource RidsNrrDorlLpl1-1 Resource SJones RidsNrrLASLittle Resource MHamm RidsNrrPMNMorgan Resource EWong RidsOgcRp Resource GLapinsky RidsRgn1 MailCenter Resource DWerkheiser RidsNrrDciCsgb Resource RidsNrrDirsltsb Resource ADAMS Accession No*.. ML091751067
- Via email OFFICE DORLlLPL1-1/PM DORULPL1-1/LA DIRS/IOLB/BC DCI/CSGB DIRS/ITSB/BC DE/EMCB/BC NAME NMorgan SUttle NSalgado MGavriias REIliot MKhanna DATE 6/25/09 6/25/09 5/19/2009 5/1/2009 5/18/2009 6/19/2009 OFFICE DSS/SBPB/BC (A)
DSS/SRXB/BC DORULPL1-1/BC NAME GPurciarelio GCranston NSalgado DATE 6/19/2009 6/22/2009 6/25/09 OFFICIAL RECORD COpy