Letter Sequence Other |
---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement
|
MONTHYEARL-09-086, License Amendment Request No. 08-027, Spent Fuel Pool Rerack2009-04-0909 April 2009 License Amendment Request No. 08-027, Spent Fuel Pool Rerack Project stage: Request ML0915201072009-06-0101 June 2009 Supplemental Information Needed for Acceptance of Requested Licensing Action Spent Fuel Pool Rerack Project stage: Acceptance Review L-09-162, Additional Technical Information Pertaining to License Amendment Request No. 08-0272009-06-15015 June 2009 Additional Technical Information Pertaining to License Amendment Request No. 08-027 Project stage: Request ML0917510672009-06-25025 June 2009 Acceptance of Requested Licensing Action Spent Fuel Pool Rerack Project stage: Acceptance Review ML0932809142009-12-0404 December 2009 Request for Additional Information Regarding Spent Fuel Pool Rerack License Amendment Project stage: RAI ML1003800022010-02-16016 February 2010 Request for Additional Information Spent Fuel Pool Rerack Amendment Project stage: RAI ML1001303452010-03-0505 March 2010 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for Hearing, and Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information Project stage: Other L-10-082, Response to NRC Staff Request for Additional Information Regarding Criticality Analyses Supporting a Spent Fuel Pool Re-rack2010-03-18018 March 2010 Response to NRC Staff Request for Additional Information Regarding Criticality Analyses Supporting a Spent Fuel Pool Re-rack Project stage: Request ML1007605842010-03-19019 March 2010 Request for Additional Information Spent Fuel Pool Rerack Round 3 Project stage: RAI ML1008407842010-04-15015 April 2010 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance L-10-121, Response to Request for Additional Information Related Spent Fuel Pool Rerack License Amendment Request2010-05-0303 May 2010 Response to Request for Additional Information Related Spent Fuel Pool Rerack License Amendment Request Project stage: Response to RAI L-10-151, Response to Request for Additional Information Related to Spent Fuel Pool Rerack License Amendment Request2010-05-21021 May 2010 Response to Request for Additional Information Related to Spent Fuel Pool Rerack License Amendment Request Project stage: Response to RAI L-10-130, Remainder of Responses to NRC Staff Request for Additional Information Regarding Unit 2 Spent Fuel Pool Rerack Criticality Analyses2010-06-0101 June 2010 Remainder of Responses to NRC Staff Request for Additional Information Regarding Unit 2 Spent Fuel Pool Rerack Criticality Analyses Project stage: Request ML1013805462010-06-11011 June 2010 Request for Additional Information Spent Fuel Pool Rerack License Amendment Project stage: RAI ML1017203652010-06-24024 June 2010 Impacts to the Review Schedule Regarding the Spent Fuel Pool Rerack License Amendment Request Project stage: Other L-10-235, Response to Request for Additional Information for License Amendment Request No. 08-027 Re Spent Fuel Pool Rerack2010-08-0909 August 2010 Response to Request for Additional Information for License Amendment Request No. 08-027 Re Spent Fuel Pool Rerack Project stage: Response to RAI ML1025107802010-09-14014 September 2010 Notice of Forthcoming Meeting with First Energy Nuclear Operating Company, Beaver Valley Power Station, Unit No. 2 & Holtec, Inc., to Discuss the Licensee'S Responses, Dated August 9, 2010 Project stage: Meeting L-10-282, Supplemental Response to Request for Additional Information Related to Spent Fuel Pool Rerack License Amendment Request2010-10-0707 October 2010 Supplemental Response to Request for Additional Information Related to Spent Fuel Pool Rerack License Amendment Request Project stage: Supplement L-10-275, License Amendment Request for Spent Fuel Pool Rerack2010-10-18018 October 2010 License Amendment Request for Spent Fuel Pool Rerack Project stage: Request ML1029404582010-10-18018 October 2010 Holtec Report No: HI-2084175, Licensing Report for Beaver Valley, Unit 2, Rerack. Project stage: Other ML1027903512010-10-18018 October 2010 Summary of Meeting with Firstenergy Nuclear Operating Company, on the Request for Additional Resposnses Regarding the Spent Fuel Rerack for Beaver Valley Power Station, Unit No. 2 Project stage: Meeting ML1035606612010-12-29029 December 2010 Summary of Beaver Valley Power Station, Unit 2 Public Conference Call Regarding Spent Fuel Pool Rerack LAR Draft RAI Responses Discussion Project stage: Draft RAI L-10-329, Supplemental Information for Spent Fuel Pool Rereack License Amendment Request2011-01-0505 January 2011 Supplemental Information for Spent Fuel Pool Rereack License Amendment Request Project stage: Supplement ML1102006022011-01-24024 January 2011 Request for Additional Information Spent Fuel Pool Rerack Amendment (ME1079) Project stage: RAI L-11-024, Chapters 5 and 7 of Holtec Licensing Report, in Support of License Amendment Request for Unit 2 Spent Fuel Pool Rerack2011-02-18018 February 2011 Chapters 5 and 7 of Holtec Licensing Report, in Support of License Amendment Request for Unit 2 Spent Fuel Pool Rerack Project stage: Request L-11-057, Responses to NRC Staff Request for Additional Information Regarding Unit No. 2 Spent Fuel Pool Rerack Criticality Analyses2011-02-18018 February 2011 Responses to NRC Staff Request for Additional Information Regarding Unit No. 2 Spent Fuel Pool Rerack Criticality Analyses Project stage: Request ML1107504782011-03-10010 March 2011 E-mail Summary of Clarification Phone Call Regarding the Beaver Valley 2 Spent Fuel Pool Rerack Amendment (ME1079) Project stage: Other ML1108001222011-03-18018 March 2011 Supplement to Spent Fuel Pool Rerack Amendment Request Project stage: Supplement L-11-101, Supplemental Information for Spent Fuel Pool Rerack License Amendment Request2011-03-21021 March 2011 Supplemental Information for Spent Fuel Pool Rerack License Amendment Request Project stage: Supplement ML1108005702011-03-21021 March 2011 Supplemental Information for Spent Fuel Pool Rerack License Amendment Request Project stage: Supplement ML1108908442011-04-29029 April 2011 Issuance of Amendment Regarding the Spent Fuel Pool Rerack Project stage: Approval 2010-05-21
[Table View] |
|
---|
Category:Letter
MONTHYEARML24025A0922024-01-25025 January 2024 Requalification Program Inspection L-23-267, Submittal of Discharge Monitoring Report (Npdes), Permit No. PA00256152023-12-18018 December 2023 Submittal of Discharge Monitoring Report (Npdes), Permit No. PA0025615 IR 05000334/20230112023-12-0404 December 2023 Age-Related Degradation Inspection Report 05000334/2023011 and 05000412/2023011 L-23-229, Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports2023-11-29029 November 2023 Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports IR 05000334/20233012023-11-27027 November 2023 Initial Operator Licensing Examination Report 05000334/2023301 L-23-247, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-11-17017 November 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 IR 05000334/20230032023-11-0606 November 2023 Integrated Inspection Report 05000334/2023003 and 05000412/2023003 L-23-227, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 20232023-10-20020 October 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 2023 ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23198A3592023-10-0202 October 2023 Issuance of Amendment Nos. 322 and 212 Analytical Methodology to the Core Operating Limits Report for a Full Spectrum Loss of Coolant Accident (EPID L-2022-LLA-0129) - Nonproprietary IR 05000334/20234022023-09-29029 September 2023 Security Baseline Inspection Report 05000334/2023402 and 05000412/2023402 (Cover Letter Only) ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure IR 05000334/20234012023-09-21021 September 2023 Cybersecurity Inspection Report 05000334/2023401 and 05000412/2023401 (Cover Letter Only) ML23263A0192023-09-20020 September 2023 Operator Licensing Examination Approval ML23243A9272023-09-19019 September 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report ML23249A1842023-09-18018 September 2023 Authorization and Safety Evaluation for Alternative Request No. 2-TYP-4-RV-06 L-23-208, Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA00256152023-09-14014 September 2023 Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA0025615 L-23-167, Twenty-Third Refueling Outage Inservice Inspection Summary Report2023-09-13013 September 2023 Twenty-Third Refueling Outage Inservice Inspection Summary Report L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments IR 05000334/20230052023-08-31031 August 2023 Updated Inspection Plan for Beaver Valley Power Station Units 1 and 2 (Report 05000334/2023005 and 05000412/2023005) L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual ML23129A1722023-08-25025 August 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2; Davis Besse Nuclear Power Station, Unit 1; and Perry Nuclear Power Plant, Unit 1 IR 05000334/20230022023-08-0909 August 2023 Integrated Inspection Report 05000334/2023002 and 05000412/2023002 ML23219A0592023-08-0707 August 2023 Steam Generator Inspection Reports - Spring 2023 Spring Refueling Outrage L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-179, Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA00256152023-07-18018 July 2023 Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA0025615 ML23188A0982023-07-17017 July 2023 Correction to the Safety Evaluation Issued Related to Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML23188A0672023-07-10010 July 2023 Project Manager Assignment L-23-165, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-06-26026 June 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-23-139, Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report2023-06-13013 June 2023 Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report ML23157A1072023-06-0707 June 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000334/2023011 and 05000412/2023011 ML23143A0272023-05-23023 May 2023 Licensed Operator Positive Fitness-For-Duty Test L-23-055, Submittal of the Updated Final Safety Analysis Report, Revision 342023-05-23023 May 2023 Submittal of the Updated Final Safety Analysis Report, Revision 34 ML23102A1472023-05-22022 May 2023 Issuance of Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report ML23135A7872023-05-19019 May 2023 Summary of Conference Calls Regarding the Spring 2023 Steam Generator Tube Inspections L-23-137, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-05-18018 May 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML23124A1742023-05-17017 May 2023 Energy Harbor Fleet Vistra License Transfer - Request for Withholding Information from Public Disclosure for Commance Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 L-23-125, Cycle 24 Core Operating Limits Report2023-05-17017 May 2023 Cycle 24 Core Operating Limits Report ML23124A3882023-05-16016 May 2023 Summary of Regulatory Audit in Support of License Amendment Request to Revise Technical Specification 5.6.3, Core Operating Limits Reports (COLR) and TS 4.2.1 Fuel Assemblies ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) L-23-132, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-10010 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations IR 05000334/20230012023-05-0808 May 2023 Integrated Inspection Report 05000334/2023001 and 05000412/2023001 L-23-129, Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations2023-05-0505 May 2023 Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations ML23118A3812023-04-28028 April 2023 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations L-23-115, Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological2023-04-27027 April 2023 Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological L-23-126, Discharge Monitoring Report (Npdes), Permit No. PA00256152023-04-22022 April 2023 Discharge Monitoring Report (Npdes), Permit No. PA0025615 CP-202300181, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-20020 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments ML23107A2502023-04-18018 April 2023 Requalification Program Inspection 2024-01-25
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 24, 2010 Mr. Paul A. Harden Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB 1 P.O. Box 4, Route 168 Shippingport, PA 15077
SUBJECT:
BEAVER VALLEY POWER STATION, UNIT NO.2-IMPACTS TO THE REVIEW SCHEDULE REGARDING THE SPENT FUEL POOL RERACK LICENSE AMENDMENT REQUEST (TAC NO. ME1079)
Dear Mr. Harden:
The purpose of this letter is to inform you of the factors that are impacting the Nuclear Regulatory Commission (NRC) staff's review schedule and to request a new proposed schedule for completion of the subject license amendment request (LAR).
By letters dated April 9, 2009 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML091210251) and June 15, 2009 (ADAMS Accession No. ML091680614), FirstEnergy Nuclear Operating Company (the licensee) submitted an LAR to modify the Beaver Valley Power Station, Unit NO.2 (BVPS-2) Technical Specifications (TSs).
The proposed amendment would modify TSs to support the installation of high density fuel storage racks in the BVPS-2 spent fuel pool, which will increase the total storage locations from 1,088 to 1,690.
The licensee requested approval of the LAR from the NRC by April 15, 2010. Per the licensee's request, the NRC staff expedited the review by contracting a technical reviewer from Oak Ridge National Laboratory for assistance.
By letters dated December 4,2009 (ADAMS Accession No. ML093280914), February 16 (ADAMS Accession No. ML100380002), March 19 (ADAMS Accession No. ML100760584), and June 11, 2010 (ADAMS Accession No. ML101380546), the NRC staff issued requests for additional information (RAls) to address several concerns. Of those concerns, the major technical issues were the following: (1) the use of non-conservative methodologies in the mechanical accident analyses without providing substantial technical justification, (2) the use of spent fuel pool concrete properties that are inconsistent with the BVPS-2 licensing basis, (3) the lack of adherence to NRC guidance with respect to the spent fuel pool rack structural loading combinations, (4) not incorporating the Haut Taux de Combustion critical experiment data in the criticality code validation as documented in NUREG/CR-6979 (ADAMS Accession No. ML082880452), (5) the use of non-bounding moderator temperatures for depletion, (6) the use of non-bounding axial burnup profiles, and (7) not incorporating the neutron absorber surveillance uncertainty in the criticality analysis.
P. Harden -2 In addition to issuing RAls and conducting several conference calls, the NRC staff conducted an audit to review supporting design documents, in an effort to resolve the technical issues. The licensee has been supportive in coordination of the conference calls and the audit. However, the NRC staff cannot continue its review without the revised Holtec Licensing Report, the remaining due RAI responses, and needed supplemental information to certain RAI responses, as seen in the table below.
Milestone Date Timeline NRC RAI Partial Final Supplement Current Status Response Response Needed 12/4/2009 1/18/2010 No The NRC staff received the complete response.
2/16/2010 3/18/2010 6/1/2010 Yes The licensee is going to supplement their original LAR with a revised copy of the Holtec Licensing Report.
3/19/2010 5/3/2010 5/21/2010 Yes The licensee is going to supplement their original LAR with a revised copy of the Holtec Licensing Report, as well as, provide supplemental information to some of the RAI responses.
6/11/2010 The licensee requested a 60-day response period.
To date, the NRC staff has completed a substantial portion of the review of the application. The original request for the completion of the review of the LAR was April 15, 2010. However, due to the delays associated with the RAI responses to the February 16 and March 19, 2010, RAI letters, the NRC staff has not been able to complete its review. We ask that you submit a new proposed schedule for your planned submittals and keep the NRC staff informed if this requested schedule should change or if any additional delays are foreseen. The NRC staff expects to complete its safety evaluation within 5 months of the final submittal from you.
However, this expected timeline assumes that there will be no additional RAls required.
If you have any questions regarding this issue, please contact me at (301) 415-1016.
Sincerely, Nadiyah S. Morgan, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-412 cc: Distribution via Listserv
.. ML101720365 *Via email OFFICE DORLILPLI-1/PM DOR LlLPLI-1 /LA DSS/SRXB/BC DE/EMCB/BC DOR LlLPLI-1 /BC NAME NMorgan SLittle* TUlses MKhanna NSalgado DATE 6/22/2010 6/22/2010 6/22/2010 6/22/2010 6/24/2010