L-10-038, Report of Facility Changes, Tests and Experiments

From kanterella
Jump to navigation Jump to search
Report of Facility Changes, Tests and Experiments
ML102250057
Person / Time
Site: Beaver Valley
Issue date: 08/09/2010
From: Harden P
FirstEnergy Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
L-10-038
Download: ML102250057 (1)


Text

FENOC ~P.O.

Beaver Valley Power Station Box 4 FirstEnergyNuclear OperatingCompany Shippingport,PA 15077 PaulA. Harden 724-682-5234 Site Vice President Fax: 724-643-8069 August 9, 2010 L-1 0-038 10 CFR 50.59(d)(2)

ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

SUBJECT:

Beaver Valley Power Station, Unit No. 1 Docket No. 50-334, License No. DPR-66 Report of Facility Changes, Tests and Experiments In accordance with 10 CFR 50.59(d)(2), which requires reporting of changes, tests, and experiment descriptions, FirstEnergy Nuclear Operating Company reports that there were no evaluations completed pursuant to 10 CFR 50.59 during the reporting period of October 25, 2007 through July 16, 2010 for the Beaver Valley Power Station, Unit No. 1.

There are no regulatory commitments contained in this letter. If there are any questions or if additional information is required, please contact Mr. Thomas A. Lentz, Manager -

Fleet Licensing, at (330) 761-6071.

Sincerely, Paul A. Harden cc: NRC Region I Administrator NRC Resident Inspector NRR Project Manager Director BRP/DEP Site BRP/DEP Representative